Bid Tabulations for Timber Trail Guardrail Construction

This document is a bid tabulation report for Marion County, Oregon's Timber Trail Guardrail Construction project (PW1859-26), an invitation to bid (ITB) released on October 12, 2026, with bids opening on November 4, 2026. The project scope encompasses removal of existing guardrail and installation of new guardrail in accordance with the Plans and Specifications, along with incidental work as directed by the Engineer. The bid tabulation includes 22 line items detailing various construction components, including mobilization, temporary traffic control, flaggers, erosion control, sediment barriers, survey work, site clearing, aggregate base, guardrail materials (Midwest Guardrail System Type 2A), guardrail terminals and end pieces, post hole work in rock, permanent seeding, mailbox supports, and sign removal and reinstallation. Quantities range from single units to 820 units for sediment barriers and 470 linear feet for guardrail material. Two bids were received from Mid Valley Excavation, LLC and Coral Construction.

The bid tabulation reflects significant price variance between the two bidders across most line items. Mid Valley Excavation, LLC submitted a total bid of $125,500.00, while Coral Construction's total bid was $145,777.00, representing a difference of $20,277.00. Notable price variations include temporary signs ($3.00 versus $20.00 per square foot), flaggers ($90.00 versus $60.00 per hour), and aggregate base ($33.50 versus $80.00 per ton). The estimated project cost range of $100,000 to $250,000 provided in the ITB documentation encompasses both submitted bids. Individual line item pricing demonstrates competitive bidding across mobilization, labor, materials, and specialized guardrail components.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract TIMBER TRAIL GUARDRAIL CONSTRUCTION - Bid Abstract Report Date Bid Release Bid Opening

11/4/2026 10/12/2026 2026-11-03T22:00:00.000Z

Line Number Description Unit Quantity Average Price Average Total Price Total Price Total 1 0210-0100 MOBILIZATION LS 1 13464.25 13464.25 $12,351.50 $12,351.50 $14,577.00 $14,577.00 2 0221-0100 TEMPORARY PROTECTION AND DIRECTION OF TRAFFIC LS 1 5875 5875 $3,750.00 $3,750.00 $8,000.00 $8,000.00

3 0222-0102 TEMPORARY SIGNS SQFT 232 11.5 2668 $3.00 $696.00 $20.00 $4,640.00

4 0223-0168 FLAGGERS HOUR 256 75 19200 $90.00 $23,040.00 $60.00 $15,360.00

5 0280-0100 EROSION CONTROL LS 1 882.5 882.5 $750.00 $750.00 $1,015.00 $1,015.00

6 0280-0115 SEDIMENT BARRIER, TYPE 3 EACH 820 6 4920 $1.00 $820.00 $11.00 $9,020.00 7 0290-0100 POLLUTION CONTROL PLAN LS 1 625 625 $250.00 $250.00 $1,000.00 $1,000.00 8 0305-0100 CONSTRUCTION SURVEY WORK LS 1 3250 3250 $2,000.00 $2,000.00 $4,500.00 $4,500.00 9 0310-0106 REMOVAL OF STRUCTURES AND OBSTRUCTIONS LS 1 4030 4030 $5,000.00 $5,000.00 $3,060.00 $3,060.00

10 0320-0100 CLEARING AND GRUBBING LS 1 3250 3250 $4,000.00 $4,000.00 $2,500.00 $2,500.00 11 0641-0102 AGGREGATE BASE TON 475 56.75 26956.25 $33.50 $15,912.50 $80.00 $38,000.00 12 0810-0123 GUARDRAIL END PIECES, TYPE C EACH 2 362.5 725 $525.00 $1,050.00 $200.00 $400.00 13 0810-0129 GUARDRAIL TERMINALS, NON-FLARED EACH 1 5597.5 5597.5 $6,200.00 $6,200.00 $4,995.00 $4,995.00 14 0810-013300SE EXTRA FOR 8 FOOT POSTS, STEEL EA 18 112.5 2025 $150.00 $2,700.00 $75.00 $1,350.00 15 0810-0134 EXTRA FOR 11 FOOT POSTS EACH 18 175 3150 $225.00 $4,050.00 $125.00 $2,250.00 16 0810-0146102AF MIDWEST GUARDRAIL SYSTEM, TYPE 2A FT 470 52.5 24675 $60.00 $28,200.00 $45.00 $21,150.00 17 0810-0320 EXTRA FOR POST HOLE IN ROCK EA (Each) 6 230 1380 $425.00 $2,550.00 $35.00 $210.00 18 0810-0132 GUARDRAIL TERMINALS, BURIED IN BACKSLOPE EACH 1 6425 6425 $5,600.00 $5,600.00 $7,250.00 $7,250.00 19 0810-0132 GUARDRAIL TERMINALS, DOWNSTREAM ANCHOR TERMINAL EACH 2 2137.5 4275 $2,300.00 $4,600.00 $1,975.00 $3,950.00 20 0905-0101 REMOVE AND REINSTALL EXISTING SIGNS LS 1 615 615 $430.00 $430.00 $800.00 $800.00 21 1030-0109000A PERMANENT SEEDING, MIX NO. 1 LS 1 950 950 $550.00 $550.00 $1,350.00 $1,350.00 22 1070-0100 SINGLE MAILBOX SUPPORTS EA (Each) 1 700 700 $1,000.00 $1,000.00 $400.00 $400.00

$125,500.00 $145,777.00

Mid Valley Excavation, LLC CORAL CONSTRUCTION