This document is a Bid Tabulation for the River Rd: Shangri-La Ave to Wheatland Rd (Keizer) project, which is a state and local contract opportunity in Oregon's Marion County. The project requires the provision of Mobilization, Temporary Work Zone Traffic Control, Erosion Control, Removal of Underground Enclosure, Fiber Optic Interconnect System, Install Hand Hole, Install Splice Vault, Existing Conduit Repair, and other related services. The engineer's estimate for the project is between $1,100,000 and $1,600,000. The bid closing date was 12/13/2022, and the low bidder was Brown Contracting, Inc. with a total bid of $1,198,000.
The bid tabulation provides unit prices and total amounts for each of the required items. It also lists the 2nd and 3rd low bidders, which were Aaken Electrical Corp and Global Electric, respectively. The engineer's estimate for the project is provided, and the bid amounts from the three lowest bidders are included. No information is provided regarding pricing terms, set asides, incumbents, funding requirements or sources, or any other salient details beyond the bid tabulation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Preliminary Bid Register.pdf | ||
| Addendum 1~3.pdf | ||
| Project Manual~6.pdf | ||
| 223085 Bid Opening Zoom Link.pdf | ||
| Preliminary Results~27.xlsx | XLSX spreadsheet | |
| Intent to Award letter.pdf | ||
| Original Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABULATION OF BIDS FOR:
Average of 3
(*) figures changed to reflect accurate extension or addition 2 nd
Low Bidder 3 rd
Low Bidder Lowest Bidders
NO. QUANTITY
UNIT OF
MEASURE UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE UNIT PRICE UNIT PRICE
1 Mobilization All Req'd Lump Sum 100,000.00 100,000.00 146,000.00 146,000.00 175,000.00 110,000.00 143,666.67
Temporary Work Zone Traffic Control, Complete All Req'd Lump Sum 150,000.00 150,000.00 126,000.00 126,000.00 110,000.00 150,000.00 128,666.67
3 Erosion Control All Req'd Lump Sum 50,000.00 50,000.00 26,000.00 26,000.00 17,000.00 25,000.00 22,666.67
4 Removal of Underground Enclosure 44 Each 2,000.00 88,000.00 2,000.00 88,000.00 4,500.00 2,000.00 2,833.33
Fiber Optic Interconnect System, Complete All Req'd Lump Sum 850,000.00 850,000.00 553,000.00 553,000.00 450,000.00 782,500.00 595,166.67
6 Install Hand Hole, Complete 19 Each 2,000.00 38,000.00 8,500.00 161,500.00 5,810.00 4,000.00 6,103.33
7 Install Splice Vault, Complete 7 Each 2,500.00 17,500.00 9,000.00 63,000.00 9,200.00 5,000.00 7,733.33
Existing Conduit Repair, 25 Feet or Less, Complete 6 Each 3,000.00 18,000.00 3,000.00 18,000.00 6,000.00 6,000.00 5,000.00
Existing Conduit Repair, Greater than 25
Feet, Complete 300 Lin. Ft. 80.00 24,000.00 55.00 16,500.00 233.00 75.00 121.00
Total 1,335,500.00 1,198,000.00
2nd Low Bidder 1,230,690.00
3rd Low Bidder 1,325,000.00
1,388,883.00
Aaken Electrical Corp
Global Electric
Aaken Electrical
Corp Global Electric12/13/2022
Engineer's
Estimate
Brown Contracting, Inc.
River Rd: Shangri-La Ave to Wheatland Rd (Keizer)
NorthStar Electrical Conractors
11055 SW Clay St
Low Bidder
Sherwood OR 97140
Project Number:
Bid/Contract Number:
Closing Date:
718506
223085 Will Kuenzi, PE, PLS
Senior Project Manager
Remaining Bidders
\\pubwks\pwfiles\Group\Engineering\Projects\CIP\718506 River Rd N TS Interconnect\11 Ad-Bid-Award\Contract Book\aba-master1.xlsm\Bid TabulationPage 1 of 1 Tabulation of Bids