This is a bid tabulation spreadsheet for project S-73000-00014486, the I5 Kuebler NB Offramp Inlay Paving project. The document presents competitive bidding results from five contractors: Riverbend Construction Inc, Roy Houck Construction LLC, Knife River Corporation - Northwest, North Santiam Paving Co., and Brix Paving Northwest Inc. The project scope encompasses seven line items including mobilization, temporary work zone traffic control, pollution control planning, cold plane pavement removal, asphaltic concrete placement, hi-build paint application, and pavement legend installation. Quantities range from single lump sum items to 72 linear feet of painting work and 32 square yards of pavement removal. The bid tabulation does not specify response deadlines, site visits, or contract award dates within its contents.

The total bid prices received range from $22,948.00 (Riverbend Construction Inc, the apparent low bid) to $46,100.00 (Brix Paving Northwest Inc). Individual line item pricing varies significantly across bidders, particularly for pavement removal where bids range from $78.00 to $230.00 per square yard, and for dense asphalt concrete mixture where unit prices span from $475.00 to $2,500.00 per ton. No information regarding set-asides, incumbent contractors, funding sources, or project budget is contained within the bid tabulation document itself.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-73000-00014486 I5 Kuebler NB Offramp Inlay Paving
BID TABULATIONRiverbend Construction IncRoy Houck Construction LLCKnife River Corporation - NorthwestNorth Santiam Paving Co.Brix Paving Northwest Inc
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Mobilization1LS$ 9,900.00$ 9,900.00$ 7,875.00$ 7,875.00$ 12,000.00$ 12,000.00$ 12,250.00$ 12,250.00$ 15,000.00$ 15,000.00
2Temporary Work Zone Traffic Control, Complete1LS$ 2,900.00$ 2,900.00$ 6,100.00$ 6,100.00$ 15,500.00$ 15,500.00$ 10,000.00$ 10,000.00$ 9,500.00$ 9,500.00
3Pollution Control Plan1LS$ 500.00$ 500.00$ 100.00$ 100.00$ 500.00$ 500.00$ 50.00$ 50.00$ 250.00$ 250.00
4Cold Plane Pavement Removal, 2" Deep32SQ YD$ 92.00$ 2,944.00$ 78.00$ 2,496.00$ 80.00$ 2,560.00$ 230.00$ 7,360.00$ 230.00$ 7,360.00
5Level 3, 1/2" Dense ACP Mixture (PG64-22)5TON$ 720.00$ 3,600.00$ 1,085.00$ 5,425.00$ 475.00$ 2,375.00$ 860.00$ 4,300.00$ 2,500.00$ 12,500.00
6Hi-Build Paint, Extruded or Sprayed, Surface72FOOT$ 32.00$ 2,304.00$ 15.00$ 1,080.00$ 24.00$ 1,728.00$ 25.00$ 1,800.00$ 20.00$ 1,440.00
7Pavement Legend, Type AB: Arrows (Narrow)1EACH$ 800.00$ 800.00$ 1,000.00$ 1,000.00$ 750.00$ 750.00$ 605.00$ 605.00$ 50.00$ 50.00
TOTAL$ 22,948.00$ 24,076.00$ 35,413.00$ 36,365.00$ 46,100.00