This is a bid tabulation document for Oregon's Veneta Maintenance Yard Paving project (Opportunity Number S-73000-00013807). The project involves pavement removal and replacement services at a maintenance yard facility. The scope of work includes mobilization, pollution control planning, cold plane pavement removal to a depth of 3 inches across 3,778 square yards, and installation of Level 3, 1/2-inch dense asphalt concrete pavement mixture (PG64-22) totaling 638 tons. Three contractors submitted bids for the project: North Santiam Paving Co, Knife River Corporation - Northwest, and Wildish Construction Co.
North Santiam Paving Co submitted the lowest bid at $82,747.00, with unit prices of $7,000.00 for mobilization, $25.00 for the pollution control plan, $4.00 per square yard for pavement removal, and $95.00 per ton for asphalt mixture installation. Knife River Corporation - Northwest bid $94,494.40, and Wildish Construction Co bid $98,448.00. The bid spread between the low and high bidders represents approximately a 19% price difference. The tabulation presents itemized pricing for each bidder, allowing for transparent comparison of unit rates and total project costs across all three responding contractors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Fruit Applesauce~2.docx | DOCX document | |
| Paving Limits~2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| S-73000-00013807 Veneta Maintenance Yard Paving | ||||||
| BID TABULATION | North Santiam Paving Co | Knife River Corporation - Northwest | Wildish Construction Co | |||
| Bid Item # | Description | Est | ||||
| QTY | UNIT | UNIT | ||||
| PRICE | TOTAL | |||||
| PRICE | UNIT | |||||
| PRICE | TOTAL | |||||
| PRICE | UNIT | |||||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $ 7,000.00 | $ 7,000.00 | $ 9,200.00 | $ 9,200.00 | $ 5,500.00 | $ 5,500.00 |
| 2 | Pollution Control Plan | 1 | LS | $ 25.00 | $ 25.00 | $ 58.00 | $ 58.00 | $ 100.00 | $ 100.00 |
| 3 | Cold Plane Pavement Removal, 3" Deep | 3,778 | SQ YD | $ 4.00 | $ 15,112.00 | $ 5.75 | $ 21,723.50 | $ 6.00 | $ 22,668.00 |
| 4 | Level 3, 1/2" Dense ACP Mixture (PG64-22) | 638 | TON | $ 95.00 | $ 60,610.00 | $ 99.55 | $ 63,512.90 | $ 110.00 | $ 70,180.00 |
| TOTAL | $ 82,747.00 | $ 94,494.40 | $ 98,448.00 |