This is a bid tabulation spreadsheet for Oregon Department of Transportation (ODOT) project S-10900-00006352, a culvert repair project located on OR36 MP 22.68. The project encompasses comprehensive culvert rehabilitation and related infrastructure work, including mobilization, traffic control, temporary water management, erosion control, culvert rehabilitation, video inspection, riprap bank protection, stream channel work, streambed enhancement, pipe salvage and relaying, directional boring, water service connections, turbidity monitoring, and culvert drainage markers. The bid tabulation reflects proposals from two vendors: Mid Valley Excavation LLC and Suulutaaq Inc, with estimated quantities ranging from single lump-sum items to 122 linear feet of video inspection work.

Mid Valley Excavation LLC submitted a total bid of $238,080.00, while Suulutaaq Inc submitted a total bid of $273,818.00. Mid Valley Excavation LLC's bid is lower across most line items, including the significant culvert rehabilitation work at $1,765.00 per foot compared to Suulutaaq Inc's $913.00 per foot, though Suulutaaq Inc provided more competitive pricing on certain items such as temporary work zone traffic control ($30,000.00 versus $11,400.00) and temporary water management facilities ($32,000.00 versus $9,600.00). The bid tabulation does not specify contract award information, set-asides, incumbent vendor status, or project funding sources within the document presented.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-10900-00006352 OR36 MP 22.68 Culvert Repair Project
BID TABULATIONMid Valley Excavation LLCSuulutaaq Inc
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Mobilization1LS$53,435.00$ 53,435.00$ 53,000.00$ 53,000.00
2Temporary Work Zone Traffic Control, Complete1LS$ 11,400.00$ 11,400.00$ 30,000.00$ 30,000.00
3Portable Changeable Message Signs2EACH$ 1,850.00$ 3,700.00$ 1,800.00$ 3,600.00
4Temporary Water Management Facility1LS$ 9600.00$ 9,600.00$ 32,000.00$ 32,000.00
5Pollution Control Plan1LS$ 500.00$ 500.00$ 500.00$ 500.00
6Erosion Control1LS$ 1,975.00$ 1,975.00$ 4,000.00$ 4,000.00
7Rehabilitate 48 inch culvert61FOOT$ 1765.00$ 107,665.00$ 913.00$ 55,693.00
8Mainline Video Inspection122FOOT$ 10.00$ 1,220.00$ 115.00$ 14,030.00
9Class 200 riprap bank protection14CU YD$ 155.00$ 2,170.00$ 340.00$ 4,760.00
10Stream Channel1LS$ 7,200.00$ 7,200.00$ 5,800.00$ 5,800.00
11Streambed enhancement1LS$ 14,150.00$ 14,150.00$ 25,000.00$ 25,000.00
12Salvaging and Relaying 4" Pipe, 5' Depth65FOOT$ 5.00$ 325.00$ 13.00$ 845.00
13Directional bore, 6" steel casing65FOOT$ 330.00$ 21,450.00$ 586.00$ 38,090.00
14Connect to extg. water service2EACH$ 450.00$ 900.00$ 1,000.00$ 2,000.00
15Turbidity Monitoring1LS$ 1,975.00$ 1,975.00$ 4,000.00$ 4,000.00
16Culvert Drainage Markers, Type 11EACH$ 180.00$ 180.00$ 250.00$ 250.00
17Culvert Drainage Markers, Type 21EACH$ 235.00$ 235.00$ 250.00$ 250.00
TOTAL$ 238,080.00$ 273,818.00