Bid sheetPawnee Water Softener Filtration ReplacementProj OK3PAA02CB - Bid Sheet.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Furnish and Install a domestic water softener and filtration system replacement for the Pawnee Indian Health Center, Pawnee, OK
Solicitation number
246-23-Q-0168r1
Issued by

About this file

This document contains a bid sheet template for a federal contract opportunity to replace the domestic water softener and filtration system at the Pawnee Indian Health Center in Pawnee, Oklahoma. The bid sheet requests itemized direct and material costs, sales tax, overhead, profit, bond costs, and a total estimate. It includes 15 line items for general requirements, administration, onsite supervision, removal of existing equipment and piping, installation of new equipment and piping, electrical work, concrete work, and DDC integration. The related federal contract opportunity is solicitation number 246-23-Q-0168r1 from the Department of Health and Human Services Indian Health Service to furnish and install a domestic water softener and filtration system replacement for the Pawnee Indian Health Center. Bids are requested using the provided template to complete the cost breakdown for the project.

View the file

Other files

File Type Posted
SF 24 Bid Gurantee.pdf PDF
SOW Pawnee Domestic Water Softener Filtration System Replacement Proj OK3PAA02CB.pdf PDF
SF25 Performance Bond.pdf PDF
OF306AddendumToDeclarationForFederalEmp updated.pdf PDF
Drawing.pdf PDF
SF18 RFQ and Clauses.pdf PDF
ok51.txt TXT text file
of0306.pdf PDF
SF25A Payment Bond.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID Schedule

Bid Sheet
Pawnee Indian Health Center
Domestic Water Softener & Filtration System ReplacementProject # OK3PAA02CB
Date:

Summary

Direct Labor Cost$
Direct Material Costs$
Sales Tax ( %)$
Subtotal:$
Overhead ( %)$
Subtotal:$
Profit ( %)$
Totla with Overhead and Profit:$
Bond ( %)$

Estimate Total: $

Cost Breakdown

No.DescriptionMaterialSales Tax ( %)LaborSubtotal
1General Requirements and Admin
2GC Admin Supervision
3GC Onsite Supervision
4Domestic Water Softener & Filtration System Replacement
5Water Softner System
6Brine Tank Sytem
7Carbon Filter System
8Booster Pump Unit
9Ultra Violet Disenfectant Unit
10Bag Filter Unit
11Final Filter Unit
12Removal Existing Equipment & Piping
13Installation of New Equipment
14Installation of New Piping & Accessories
15Electrical Old Equipment Disconnect
16Electrical New Equipment Installation
17Demo of Existing Concrete Pad
18New Concrete Pad
19DDC Integration
20
21
SubTotal:$$$$
Input Sum
Total AboveInput Sum
Total AboveInput Sum