Bid_Schedule.pdf
PDF 65 KB Posted
- Solicitation number
- ITB-2025-042
- Issued by
- Miami-Dade County, Florida
About this file
This document is a Bid Schedule for the City of North Miami Beach Department of Public Works, specifically for the NE 168 St. & NE 20 Ave. Traffic Circle project (CTA# 21-0025-001-01). The bid schedule details a comprehensive list of roadway, traffic, and infrastructure work including selective clearing, excavation, removal of existing concrete and asphalt, tree removal, base stabilization, pavement milling, concrete curb and gutter installation, sidewalk construction, signing, and pavement markings. The project involves multiple line items across three main categories: General Requirements, Roadway Work, and Signing and Pavement Markings, with quantities specified for each item using standard measurement units like linear feet, square yards, cubic yards, and tons.
The bid schedule includes a landscape allowance of $25,000 and encompasses detailed specifications for various construction activities, such as installing inlet protection systems, relocating trees and palms, creating performance turf with sod, and applying thermoplastic pavement markings. The document is dated 7/7/2025 and uses the ITB-2025-042 reference number, indicating it is part of a competitive bidding process. While specific unit prices are not filled in, the schedule provides a comprehensive framework for potential contractors to price out the complete scope of work for this traffic circle construction project in North Miami Beach, Florida.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITB -2025-042 Updated:
BID SCHEDULE 7/7/2025
I GENERAL
PAY ITEM PAY ITEM DESCRIPTION PLAN
QUANTITY
UNIT UNIT PRICE TOTAL UNIT COST
101-1 GENERAL REQUIREMENTS: TO INCLUDE TEMPORARY FACILITIES, EQUIPMENT,
MOBILIZATION/DEMOBILIZATION
1 LS
102-1 MAINTENANCE OF TRAFFIC 1 LS
II ROADWAY
PAY ITEM PAY ITEM DESCRIPTION PLAN
QUANTITY
UNIT UNIT PRICE TOTAL UNIT COST
104-18 INLET PROTECTION SYSTEM 8 EA
110-2-2 SELECTIVE CLEARING AND GRUBBING, AREAS WITH TREES TO REMAIN 0.28 AC
110-4-10 REMOVAL OF EXISTING CONCRETE 110 SY
110-4-11 REMOVAL OF EXISTING ASPHALT 191 SY
110-4-12 REMOVAL OF TYPE F CURB AND GUTTER 406 LF
110-4-13 REMOVAL OF TYPE D CURB 348 LF
110-4-14 REMOVAL OF VALLEY GUTTER 574 LF
110-23 TREE REMOVAL 4 EA
120-1 REGULAR EXCAVATION 1286 CY
160-4 TYPE B STABILIZATION 638 SY
285-7-01 OPTIONAL BASE, BASE GROUP 01 27 SY
285-7-04 OPTIONAL BASE, BASE GROUP 04 131 SY
285-7-06 OPTIONAL BASE, BASE GROUP 06 119 SY
327-70-1 MILLING EXISTING ASPHALT PAVEMENT, 1" AVG DEPTH 1730 SY
334-1-13 SUPERPAVE ASPHALTIC CONC, TRAFFIC C 116 TN
425-5 MANHOLE, ADJUST, UTILITIES 1 EA
425-6 VALVE BOXES, ADJUST 2 EA
425-11 MODIFY EXISTING DRAINAGE STRUCTURE 2 EA
520-1-10 CONCRETE CURB & GUTTER, TYPE F 420 LF
520-2-4 CONCRETE CURB, TYPE D 420 LF
520-2-8 CONCRETE CURB, TYPE RA 97 LF
520-3 VALLEY GUTTER- CONCRETE 715 LF
522-2 CONCRETE SIDEWALK AND DRIVEWAYS, 6" THICK 231 SY
527-1 DETECTABLE WARNINGS 271 SF
570-1-2 PERFORMANCE TURF, SOD 1521 SY
581-1-4 RELOCATE TREES AND PALMS, PALMS, <14' OF CLEAR TRUNK, SABAL PALM ONLY 2 EA
III SIGNING AND PAVEMENT MARKINGS
PAY ITEM PAY ITEM DESCRIPTION PLAN
QUANTITY
UNIT UNIT PRICE TOTAL UNIT COST
700-1-11 SINGLE POST SIGN, F&I GROUND MOUNT, UP TO 12 SF 13 EA
706-1-1 RAISED PAVEMENT MARKER, TYPE B WITHOUT FINAL SURFACE MARKINGS 326 EA
711-11-125 THERMOPLASTIC, STANDARD, WHITE, SOLID, 24" FOR STOP LINE AND CROSSWALK 360 LF
711-11-224 THERMOPLASTIC, STANDARD, YELLOW, SOLID, 18" FOR DIAGONAL OR CHEVRON 110 LF
711-14-123 THERMOPLASTIC, PERFORATED, WHITE, SOLID 12" FOR CROSSWALK 622 LF
711-16-101 THERMOPLASTIC, STANDARD, WHITE, SOLID, 6" 0.20 GM
711-16-201 THERMOPLASTIC, STANDARD, YELLOW, SOLID, 6" 0.17 GM
LANDSCAPE ALLOWANCE 1 LS $25,000.00 $25,000.00
CITY OF NORTH MIAMI BEACH
DEPARTMENT OF PUBLIC WORKS
Project Name: CTA# 21-0025-001-01 - NE 168 ST. & NE 20 AVE. TRAFFIC CIRCLE
I-GENERAL SUB-TOTAL
TOTAL BID PRICE
II-ROADWAY SUB-TOTAL
III-SIGNING AND PAVEMENT MARKINGS SUB-TOTAL
ABBREVIATION UNIT OF MEASUREMENT
AC ACRE
CY CUBIC YARD
EA EACH
GM GROSS MILE
LF LINEAR FOOT
LS LUMP SUM
SF SQUARED FOOT
SY SQUARED YARD
TN TON