Bid_Schedule.docx

DOCX document 16 KB Posted

Attached to
TFD FUELS SOUTH FLATS MOWING IDAHO BLM
Solicitation number
140L2626Q0025
Issued by

About this file

This is a Bid Schedule for mowing services at South Flats under the 2026 TFD Fuels program managed by the Department of the Interior Bureau of Land Management Idaho Region (Solicitation Number: 140L2626Q0025). The contract requires mowing of 2,176 acres of South Flats Pasture, with pricing to be submitted by contractors on a per-acre basis. The performance period runs from October 1, 2026 through November 15, 2026 (46 calendar days including holidays and weekends), and the work is estimated to require two 14-foot mowers operating at a capacity of 60 acres per day.

Key operational requirements include contractor notification of work start within three days from the Contracting Officer Representative, with work contingent upon weather and ground conditions suitable for mowing. Work is prohibited if soil damage or non-target vegetation damage would result from the operations. The schedule notes that during the performance period, roads may become impassable and access may be limited due to muddy or wet conditions typical of fall and early winter weather in the region. The contract is structured as an "all or none" award for the total acreage, and contractors must submit unit prices for evaluation.

View the file

Other files

File Type Posted
wage_determination.pdf PDF
Work_Statement.docx DOCX document
Maps.pdf PDF
Sol_140L2626Q0025.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

SCHEDULE OF SUPPLIES AND SERVICES

2026 TFD FUELS SOUTH FLATS MOWING

Line Item Number
Item Description
Estimated Quantity
Unit of Measure
Unit Price
Total
0001
South Flats Pasture
2,176
AC
$
$
2026 TFD Fuels South Flats Mowing Total (All or None)
$

AC = Acre

Performance Time: 10/01/2026 – 11/15/2026. 46 Days Total (including holidays and weekends).

*Calculated based on two 14-foot mowers accomplishing 60 acres per day.

The mowing will coincide with fall/early winter weather and ground conditions for the period of performance. During the mowing, roads may not be passable, and access may be limited due to muddy or wet conditions. Work will not be permitted if conditions will result in damage to soils and non-target vegetation. The contractor shall be required to start work within three (3) days after being notified by the Contracting Officer Representative (COR).