Bid_Schedule.doc
DOC document 38 KB Posted
- Attached to
- Herbicide Application - BLM IDAHO Federal contract opportunity
- Solicitation number
- 140L2625Q0076
About this file
This document is a Bid Schedule for a Bureau of Land Management (BLM) herbicide application contract in Idaho for Fiscal Year 2025. The solicitation (No. 140L2625Q0076) covers herbicide treatment for three specific fire areas: MM97 Fire (4,071 acres), South Coy Fire (293 acres), and Blackstone Fire (3,083 acres), totaling 7,447 acres. The contract requires the contractor to complete all herbicide applications within seven calendar days, with an approximate pre-work meeting scheduled for September 19, 2025, and an anticipated application start date of October 15, 2025.
Key performance requirements include starting work within three days of notification from the Contracting Officer Representative and purchasing imazapic herbicide prior to the application start date. The contract is issued by the Department of the Interior's Bureau of Land Management Idaho Region, with the herbicide application timing dependent on fall weather conditions and the phenological stage of target species. The bid schedule indicates an "ALL or NONE" pricing structure for the total estimated acreage, with specific line items for each fire area but without disclosed unit or total pricing in the provided document.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Wage_Determination.pdf | ||
| Maps.pdf | ||
| Sol_140L2625Q0076.pdf | ||
| Specifications.doc | DOC document | |
| Work_Statement.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID SCHEDULE
SCHEDULE OF SUPPLIES AND SERVICES
BDO BLM FY25 HERBICIDE 1
Line Item
Number
| Description |
| Est. |
Quantity Unit of
Issue
| Unit Price |
| Total Cost |
| 0001 |
| MM97 Fire |
| 4,071 |
| Acres |
| 0002 |
| South Coy Fire |
| 293 |
| Acres |
| 0003 |
| Blackstone Fire |
| 3,083 |
| Acres |
BDO BLM FY25 HERBICIDE 1
TOTAL – ALL or NONE
Total Estimated Acres: 7,447 Approximate Pre-Work Meeting: September 19, 2025 Approximate Application Start Date: October 15, 2025 Performance Time: Seven (7) days. Contractor will be required to complete all line items in seven (7) calendar days from date of actual herbicide application initiation. Herbicide application start dates will be determined by fall weather and phenological stage of target species. For more information, see Detailed Specifications.
The contractor will be required to start work within three days after notification from the Contracting Officer Representative.
Contractor will be required to purchase imazapic prior to application start date.
File details come from the government source that posted it. Updated .