Bid_Schedule.doc
DOC document 43 KB Posted
- Attached to
- ELKO FENCE EXCLOSURES Federal contract opportunity
- Solicitation number
- 140L3925Q0049
About this file
The Bid Schedule document details a fence construction and modification project for the Bureau of Land Management in the Nevada Region, with Solicitation Number 140L3925Q0049. The project involves multiple fence-related tasks, including removing and constructing new fencing, installing drainage crossings, and handling various steel pipe panels and barbed wire gates. Specific line items include: removing 3,562 linear feet of old 4-wire fence, constructing 12,167 linear feet of new 4-wire fence, installing 3,527 linear feet of modified steel pipe rail fence, and completing 16 two-post end panels, 22 three-post end/corner panels, and 14 barbed wire gates. The bid schedule provides a detailed breakdown of quantities, unit prices, and total pricing for each component of the fence exclosures project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L3925Q0049.pdf | ||
| A06_Drawings.zip | ZIP file | |
| A06_Maps.pdf | ||
| A04_SOW.doc | DOC document | |
| B03_DBA_Wage_Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM
DESCRIPTION OF COMMODITY
AND/OR SERVICE
| QTY |
| UNIT OF |
MEASURE
UNIT
PRICE
TOTAL
PRICE
| 1 |
| Drainage Crossing |
(simple type “A”)
| 1 |
| Ea. |
| 2 |
| 2- post end panel or stress panel (Steel Pipe) (removed burned wood) |
| 16 |
| Ea. |
| 3 |
| 3- post end panel or corner panel (Steel Pipe) (remove burned wood) |
| 22 |
| Ea. |
| 4 |
| 4- post panel corner (Steel Pipe) |
(remove burned wood)
| 4 |
| Ea. |
| 5 |
| 5- post panel corner (Steel Pipe) |
(remove burned wood)
| 14 |
| Ea. |
| 6 |
| Barbed wire gate – Type A |
| 14 |
| Ea. |
| 7 |
| Remove Old 4 wire fence |
| 3562 |
| L.F. |
| 8 |
| Construct New 4 Wire Fence |
| 12,167 |
| LF. |
| 9 |
| Modified Steel Pipe Rail fence |
| 3527 |
| LF. |
TOTAL=