Bid Results~46.doc

DOC document 33 KB Posted

Attached to
DRM 2018-46 #7 Conduit Installation @ MCI - Concord
Solicitation number
BD-23-1025-DOCFS-9814-77922
Issued by
Middlesex County, Massachusetts

About this file

This document is a summary of bid results for a public contract opportunity issued by the Division of Resource Management in Massachusetts. The contract is for conduit installation work at the Massachusetts Correctional Institution in Concord. Two bidders submitted proposals, with JM Electrical Company of Lynnfield, MA bidding $535,000.00 and Brite-Lite Electrical of Weymouth, MA bidding $475,183.00. The project plans and specifications were made available by appointment starting on July 28, 2022, and bid intent forms were required to be submitted by August 5, 2022 to Darlene Keane.

The contract opportunity did not provide details on pricing terms, set asides, incumbent contractors, funding sources, or other salient financial information. The document only included the two bid results and the basic procurement timeline and submission requirements.

View the file

Other files

File Type Posted
Where to get plans and specs~21.docx DOCX document
Prevailing Wage Statement of Compliance~46.pdf PDF
Bid_Intent_Form~48.rtf RTF text file
Bid Package~9.doc DOC document
Prevailing Wage Payroll Report Form~46.pdf PDF
SDP Plan Form 3~4.xlsx XLSX spreadsheet
Plan Holders List~20.docx DOCX document
DRM 2018-46 7 Addendum 1.pdf PDF
Prevailing Wages~18.pdf PDF
Bidder Checklist~38.doc DOC document
Site Visit Attendess.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID RESULTS

DRM 2018-46 #7

Conduit Installation @ MCI - Concord

Bidder’s Name
Bid Amount

JM Electrical Company Lynnfield, MA $535,000.00

Brite-Lite Electrical

Weymouth, MA $475,183.00