Bid Notice-Water_ Plants Improvements Design.pdf

PDF 2 MB Posted

Attached to
Water+ Plants Improvements Design
Solicitation number
P26141311021
Issued by
Sacramento County, San Francisco City, California

About this file

Water+ Plants Improvements Project Design

This Request for Proposals (RFP) is issued by the City of Sacramento, Department of Utilities, for professional design and construction support services for the Water+ Plants Improvements Project. The project encompasses comprehensive design and construction support for improvements to the Sacramento River Water Treatment Plant (SRWTP) and E.A. Fairbairn Water Treatment Plant (FWTP), including resiliency improvements, groundwater well equipping, and expansion improvements. The scope is divided into four phases: Phase 1 consists of 90% design completion for all project elements; Phase 2 includes 100% design and construction support for FWTP resiliency improvements, groundwater well equipping, and SRWTP short list elements; Phase 3 includes 100% design and construction support for SRWTP resiliency improvements and North B Street transmission main replacement; and Phase 4 includes 100% design and construction support for SRWTP expansion improvements to increase capacity from 160 MGD to 310 MGD. A mandatory pre-proposal meeting is scheduled for Wednesday, December 9, 2026, at 9:00 a.m. in Sacramento. Questions are due by Thursday, January 14, 2027, at noon, and proposals are due by Thursday, January 28, 2027, at 3:00 p.m., submitted electronically via PlanetBids. The City anticipates contract award and execution by April 27, 2027. Construction is scheduled to commence in July 2030, requiring 90% design completion by December 2029. The contract will be awarded to a single firm for the entire scope of services, with each phase individually released via written notice to proceed.

The Department of Utilities estimates Phase 1 design effort at approximately $30 million. Proposal costs must be broken down by the four phases and include subcategory costs for design elements, support services (finance, real estate, public outreach, documentation, and construction support), staff hourly rates with a maximum annual increase of 3% across all phases, equipment rental markups, and technical specialist costs. The 5% Local Business Enterprise (LBE) Participation Requirement is applicable to this professional services contract exceeding $250,000, requiring proposers to either qualify as an LBE or subcontract with verified LBE firms. A 5% LBE Preference is also available for qualified LBE prime proposers. The selected firm must comply with the City's Equal Benefits Ordinance, Ban-the-Box Ordinance, and maintain Commercial General Liability, Automobile Liability, Workers' Compensation, Employer's Liability, and Professional Liability (Errors and Omissions) insurance. Firms must arrange criminal background checks for all employees and subcontractor personnel accessing treatment plant sites, with checks required annually and conducted before initial access. The City will maintain full ownership of all documents, files, and supporting data created during the project.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSALS

WATER+ PLANTS IMPROVEMENTS PROJECT DESIGN

Bid Transaction #P26141311021

Issued: 11/12/2026

Mandatory Pre-Proposal Meeting (in-person):

Wednesday, December 9th, 2026, 9:00am Location: Sacramento River Room, 1395 35th Ave., Sacramento

Entrance and Parking are available off 35th Ave. (do not use South Land Park entrance)

NOTE: Proposals from proposers who do not attend a MANDATORY pre-proposal meeting shall be deemed non-responsive and their proposal will not be considered for the award of a contract.

Questions Due by: Thursday, January 14th, 2027 at NOON

RFP SUBMITTAL DEADLINE

Proposal Due by: THURSDAY, January 28th, 2027, 3:00pm Submit Statements of Qualification Electronically Via:

http://www.planetbids.com/portal/portal.cfm?CompanyID=15300

Contact for Additional Information:

Questions regarding this Request for Proposals should be directed via PlanetBids only per the instructions and deadlines outlined in the RFP timeline below.

TABLE OF CONTENTS

A. INTRODUCTION

1. Purpose

2. Background & Current Conditions

3. Scope of Services

4. Ideal Project Team

5. Proposal Cost & Performance Schedule

6. Deadline

7. Applicable Ordinances & Programs

B. RFP SUBMITTAL REQUIREMENTS

1. Submittal Process

2. Contents of Submittal

C. SELECTION PROCESS

1. General

2. Planned Schedule

D. ADMINISTRATIVE INFORMATION

1. Professional Services Agreement

2. Tax Forms

3. Addenda and Supplements

4. Business Operations Tax Certificate (B.O.T.C.)

5. Miscellaneous

E. ATTACHMENTS

Attachment 1 – Proposal Signature Form

Attachment 2 – Rating Form

Attachment 3 – Equal Benefits Ordinance Declaration of Compliance Attachment

4 – Requirements for the Local Business Enterprise Program Attachment 5 -

Local Business Enterprise 5% Preference Form Attachment 6 – Local Business

Enterprise Participation Requirement Form Attachment 7 – City Professional

Services Agreement

Attachment 8 – City Non-Disclosure Agreement

Attachment 9 – CEQA Analyses (Links Only)

Attachment 10 – Basis of Design Report - FWTP (October 2026) Separate File

Attachment 11 – Basis of Design Report – SRWTP (October 2026) Separate File

REQUEST FOR PROPOSALS (RFP)

PROFESSIONAL SERVICES

for the

DEPARTMENT OF UTILITIES

WATER+ PLANTS IMPROVEMENTS PROJECT DESIGN

A. INTRODUCTION

1. Purpose

The City of Sacramento, Department of Utilities (DOU) is requesting the submittal of Proposals for professional services to perform design and construction support for the Water+ Plants Improvements Project. Services will also include supporting services such as public outreach, real estate, grants and financing, environmental documentation, and operator training.

Interested firms are invited to submit their Proposals in accordance with the requirements of this RFP. In response to the Request for Proposals, the City anticipates receiving competitive pricing as well as an assurance of quality services.

This RFP provides information about the project tasks, qualification statement preparation, and the selection process.

2. Background & Current Conditions

About the City of Sacramento

Founded in 1849, the City of Sacramento is the oldest incorporated city in California and is the capital city of California. It has a population of over 500,000. Sacramento is a progressive City with great pride in its ethnic and cultural diversity, concern for environmental and social issues, and emphasis on quality in the provision of governmental services. Sacramento is a Charter City, which operates under a City Council Manager form of government. It has an annual budget of $1.6 billion and approximately 5,000 full-time equivalent positions.

Current Project Conditions

The City owns and operates surface water treatment plants, groundwater wells, storage reservoirs and pump stations, and distribution facilities to provide drinking water to customers in the City’s 100-square-mile service area. These facilities include two surface water treatment plants: the Sacramento River Water Treatment Plant (SRWTP) and E. A. Fairbairn Water Treatment Plant (FWTP). The City’s proposed Water+ Treatment Plants Resiliency and Improvements Project aims to address the reliability of these facilities, provide treatment resiliency, and meet projected potable water demand (via expansion of SRWTP), in keeping with the City’s 2040 General Plan.

Specific objectives of the project include:

• Improve the safety, reliability, and resiliency of the City’s two surface water treatment plants.

• Increase reliable water supplies and treatment capacities to meet anticipated water demands.

• Increase treatment flexibility to address changing water quality in the American and Sacramento Rivers while continuing to meet changing drinking water regulations.

• Provide for consistent treatment and distribution of potable water to the City’s service area.

The project is designed to achieve these objectives through resiliency improvements and expansion improvements. The resiliency improvements will focus on improving treatment reliability at SRWTP and FWTP by replacing facility assets that have reached the end of their useful lives, improving the resiliency of existing assets, and upgrading treatment facilities to handle anticipated water quality challenges. The expansion improvements will only include improvements for SRWTP to increase the overall treatment capacity from 160 million gallons per day (MGD) to 310-MGD (increases completed over phases).

In April 2026, the Environmental Impact Report (EIR) for the project was certified by Council, and an addendum to incorporate an additional parcel into the SRWTP project area was certified in July 2026. In October 2026, the basis of design documents for each treatment plant was finalized, providing the opportunity to proceed into the design phase for the project improvements. The basis of design reports shall be the primary documents for elements needed within the design. However, there will be additional improvements not listed in the basis of design reports that the design will need to incorporate (and are noted below).

The design phase is intended to carry the project to 90% design for all elements of resiliency and expansion. This provides the opportunity to proceed into construction once funding has been confirmed. The intent is to prepare the drawings and specifications for the resiliency improvements under a separate construction set from the expansion improvements, as the resiliency improvements will be completed first.

Due to the nature of the project, it is critical for the design to incorporate phased construction elements to ensure the treatment plants can maintain production throughout the construction of the improvements. As such, DOU is requesting a project design based on a year-to-year construction schedule, providing temporary and permanent improvements in proper sequencing to account for limited potential plant outages (up to 4 consecutive months each winter season, typically November through February, or January through April for a single treatment plant).

To maintain resiliency of water production, the phased construction will focus on completing the resiliency improvements at FWTP before transitioning a contractor to the SRWTP resiliency improvements. The intent of this is to reduce risk and impacts to water production. There are several elements planned to occur at SRWTP at the same time as FWTP resiliency improvements known as the SRWTP “short list” improvements:

• New maintenance building,

• Storm drainage improvements on the southwest corner,

• Transition to sodium hypochlorite, and

• Security improvements.

In addition, due to the minimum space available at FWTP, the resiliency design at FWTP will need to incorporate the equipping of two potable groundwater wells on-site (currently only one constructed, but there will be a second installed mid-2027). There will be connected elements between the resiliency improvements and the wells that will need to be integrated in the design, considering when new elements will be available and when plant shutdown periods are. Some examples of connected elements include power sources, chlorine & fluoride supplies, sewer connections, and integration into the existing reservoir and transmission mains. A basis of design has not been created for the wells at this time and an addendum to the existing well replacement program EIR is anticipated to be needed to address the minor environmental impacts associated with equipping the wells.

Together, the first construction phase will include the SRWTP “short list” items, equipping of the FWTP groundwater wells, and FWTP resiliency improvements. The second construction phase would incorporate all remaining SRWTP resiliency elements and the North B Street transmission main replacement, while the third construction phase would incorporate expansion elements at SRWTP. The design of these elements will require looking at the build-out design conditions for proper and efficient phasing of construction, staging and work area limitations, and avoiding conflicts at each stage of design.

There are site boundary constraints that will need to be part of the design considerations:

• For SRWTP, additional properties are still being procured around the site boundary.

Acquisition will be occurring during the design phase, so access for design purposes will be limited to properties the City actively owns.

• For FWTP, there are no additional properties being secured for the site, though part of the project plans include shifting the existing main gate south to provide needed space for several improvements.

The City owns and operates a pilot plant at FWTP. Pilot plant studies are at their infancy stages and there will be minimal available data upon the start of the design. It is anticipated the City personnel will be supporting pilot plant studies for this project, though testing plans of what needs to be checked for the project design will require support from the design team. There are no plans to relocate the pilot plant to SRWTP for testing. All testing for both treatment plant operations will need to be coordinated at the FWTP facility.

3. Scope of Services

The scope of services will have four (4) phases:

Phase 1) Design of all of the project elements noted in the scope of services through 90% design

Phase 2) Design completion (100% design) and construction support for the FWTP resiliency improvements, FWTP groundwater well equipping, and SRWTP “short list” elements.

Phase 3) Design completion (100% design) and construction support for the SRWTP resiliency improvements and the North B Street transmission main replacement

Phase 4) Design completion (100% design) and construction support for the SRWTP expansion improvements for 235-MGD expansion and 310-MGD build-out.

The overall scope of services for the project includes the following:

Environmental documentation for the FWTP groundwater wells (assume addendum only to existing EIR and possibly NEPA documents if federal grant is obtained)

Environmental documents for the replacement (and upgrade) of the existing 36” transmission main within North B St from Sequoia Pacific to 18th Street (assume mitigated negative declaration only) with a potential realignment due to existing number of utilities within North B Street

NEPA documentation for the project (for levee access for SRWTP and likely federal funding for construction)

Section 214 application support (creation and implementation)

Reports and studies recommended in the basis of design reports for both FWTP and SRWTP within the “Next Step” sections plus the following:

o Solar panel determination study for both FWTP and SRWTP (cost-benefit analysis), incorporating site restrictions for operations and maintenance access of all existing and new infrastructure.

o Flow modeling of the FWTP finish reservoir accommodating for whether or not the FWTP groundwater wells are feeding into the reservoir or not, based on various FWTP operational conditions.

o Structural load rating of existing structures (at SRWTP and FWTP) that provide for vehicular access (including forklifts and other O&M mobile equipment) on their roofs.

o Drainage study of FWTP that incorporates future FWTP conditions (including the FWTP groundwater wells flush-to-waste operation)

Pilot testing support (partnering with City staff) and providing test recommendations based on project design elements. Primary focus shall be associated with sodium hypochlorite switchover, ozone implementation, and bacteriologically activated filters.

Additional tests after the primary tests may be required based on initial results.

Plan and specification creation based on a construction schedule of 4 years at FWTP (including FWTP resiliency improvements, the “short list” items for SRWTP, and equipping the groundwater wells) and 6 years at SRWTP (including SRWTP resiliency improvements and replacement of the North B Street 36” transmission main).

o Expansion elements shall be assumed to be broken into two phases: initial 235-MGD (+75-MGD) and build-out 310-MGD (+150MGD).

o Project design shall commence with the “breakdown” of the 10% design at both FWTP, and SRWTP, highlighting overlapping elements that will require a constructability breakdown. After which, plans and specs will follow for a 30%, 60% and 90% design level for each construction year at each project site (FWTP and SRWTP).

100% plans and specifications (to be completed during the first six months of each construction contract)

Control strategies for all intelligent operational systems (separate documents from the specifications) at the 30%, 60%, 90%, and 100% stages of design, including control strategies during construction with supplier supplied systems (such as ozone) that need to integrate with other project elements

Standard operating procedures (separate documents from the specifications) for the FWTP, FWTP wells and SRWTP processes that include potential operational conditions and limitations at the 60%, 90%, and 100% stages of design including standard operating procedures during construction with supplier supplied systems (such as ozone) that need to account for various operational conditions.

Value engineering analyses and summary report of the design elements.

Coordination and permitting with utilities and regulatory agencies necessary to complete and activate project improvements (including but not limited to SacSewer, Bureau of Reclamation, Central Valley Flood Protection Board, Division of Drinking Water, Sacramento County Environmental Management District, Sacramento Metropolitan Air Quality Management District, SMUD, City DOU storm drainage, and City Community Development).

The project is scheduled to start construction on the FWTP resiliency, SRWTP “short list”, and FWTP groundwater well equipping by July 2030. This requires the 90% plans and specifications for this portion to be completed no later than December 2029. The 100% plans and specifications would be partnered with the contractor (after award of construction contract) for final verifications of the design. Design for SRWTP resiliency elements and the North B Street transmission main replacement should be completed during this same period. Similar to the FWTP elements, the 100% plans and specifications would be partnered with the contractor for final verifications of the design. The SRWTP expansion (and intake) plans and specifications shall be completed by July 2031, but a minimum of 30% design needs to be completed before December 2029 to ensure the resiliency design accounts for the spacing needs for the expansion improvements.

Additional support services will also need to be provided by the Firm as part of this contract. The following list describes anticipated needs to get the project to construction:

Finance (Phases 1 thru 4) o Grant application, reporting, and associated documentation support o WIFIA and SRF application, reporting, and associated documentation support (partnered with City staff) o Multi-year financing strategies

Real Estate (Phase 1) o Property acquisition o Demolition permit support o Parcel mergers o New easement recordation o Temporary access easements

Public Outreach (Phases 1 thru 4) o Telephone support and reporting o Email support and reporting o Stakeholder briefings o Public meetings o New intake specialized outreach

Documentation and cataloging (Phase 1 thru 4) o Scanning original documents o Filing (hard copies and electronic copies) o Documentation of libraries (at FWTP and SRWTP)

Construction Support (Phases 2 thru 4) o Live as-built updates of new improvements through construction o Live site overview updates (both FWTP and SRWTP) through construction o Live asset recordation into DOU’s asset management system through construction o Submittal review o Request for Information review and responses o Operator training on new/modified processes o Plant and equipment activation support

For the design elements, the project team should assume the following at a minimum:

Project elements shall include improvements noted in the FWTP basis of design report and SRWTP basis of design report plus additional improvements at both plants. For proposal budgeting estimates, the additional improvements generally include:

FWTP

o Repair of failed sidewalk, curb & gutter, and paved areas to eliminate tripping hazards and drainage impacts o Upgrade existing electrical systems at the high lift pump station and intake, including the additional of cooled spaces for temperature sensitive equipment o Replace original pumps and pump column at the intake o Replace leaking roofs with Weatherweld roofing material o Improve roof drainage systems that regularly flood o Replace aged HVAC systems (lower equipment currently on roofs to ground level access, where feasible) o Operations building reorganization to provide for needed office and work spaces (including the pilot plant) o Replacement of failed and aged ceiling panels, carpets, flooring, and wall paper o Replace galvanized plumbing in Operations Building o Lab building HVAC and gas line (and storage location) update o Concrete repairs (and possible surface treatment and repairs) to process areas impacted by corrosion o Repair concrete corrosion in ceiling of CT and finish reservoirs and improve air flow venting o Addition of second low flow pump (5-MGD) at high lift pump station o Replacement of failed baffles and corroded access stairways in sedimentation basins o Elevate chain and flights upper rails and provide interior walkways, within existing sedimentation basins to improve maintenance access o Repair or replace grit basin sluice gates o Improve accessibility for parked cars adjacent to chemical building (when chemical deliveries occur) o Remove and update baffles in finish reservoir to accommodate existing water circulation needs as well as new fill point for groundwater wells o Safety improvements for O&M access into confined spaces and elevated maintenance areas o Structural loading improvement on transmission main fronting the high lift pump station o Repair access stairways in all existing sedimentation basins o Replace chemical dosing lines older than 20 years o Repurpose chlorine and scrubber area with an expanded maintenance shop o Assess existing lime building drainage lines and secondary containment o Repair/update crane in high lift pump station o Add generator support for lab equipment o Upgrade existing PLC’s with Modicon 580 o Improve jig booms at dewatering building o Update aged kitchenettes o Replace heat pumps for Operations Building o Add safety railing around loading dock o Remove obsolete electrical equipment in electrical work space and replace in protected area o Upgrade sewer manhole (and associated sewer lines) to eliminate the need for a sewer plug o Repair / replace sewer along east side of plant o Recoat failed coatings on metallic infrastructure (like underside of intake roof) o Update dewatering centrifuges with stainless steel covers o Integration of additional vehicle charging stations o Update exterior staircase accessways to improve security on upper deck of the process area (sed basins, filters, and future ozone) o Update site security video system o Building exterior paint refresh

SRWTP

o Repair of failed concrete pads, sidewalk, curb & gutter, and paved areas to eliminate tripping hazards and drainage impacts o Repair and fill sinkholes o Replace leaking roofs with Weatherweld roofing material o Improve roof drainage systems that regularly flood o Replace aged HVAC systems (lower equipment currently on roofs to ground level access, where feasible) o Operations building reorganization to provide for needed office and work spaces o Replacement of failed and aged ceiling panels, carpets, flooring, and wall paper o Safety improvements for O&M access into confined spaces o Upgrade existing PLC’s with Modicon 580 o Upgrade structure and crane at high lift pump station to support 15-ton lift o Improve accessibility and plumbing for lime room air filters and venting o Improve cooling system for electrical equipment at intake o Recoat failed coatings on metallic infrastructure (like intake gate and filter gallery ceiling) o Update obsolete screen cleaning equipment at intake o Provide a more permanent baffle wall system at intake o Assess intake for potential golden mussel mitigation improvements o Provide drain lines for raw water pipes from intake o Replace corroded baffle supports in sedimentation basins 1 & 2 o Repair access stairways in all existing sedimentation basins o Elevate chain and flights upper rails and provide interior walkways, within existing sedimentation basins to improve maintenance access o Improve sump capacity in filter gallery o Improve monitoring systems of backwash air blowers o Improve air release systems in filter process (backwash sequence) o Improve exterior lighting at filters 9 thru 16 o Repair concrete corrosion in ceiling of Reservoir 3 and improve air flow venting o Improve existing lime building drainage lines and secondary containment o Replace existing stucco on Operations Building and Chemical Building with alternative resilient (low/no maintenance) surface treatment o Provide mitigation for condensation build-up in high lift pump station o Underground all electrical power on-site o Update dewatering centrifuges with stainless steel covers o Provide options for protecting processes from elevated properties along south side of the facility o Add level monitoring equipment to on-site monitoring well o Replace aged flow meters monitoring post-production flows o Relocate flow meter from within Bercut Street to the interior of the plant boundaries o Integration of additional vehicle charging stations.

o Update site security video system o Relocate active electrical systems from the basement of the historic head house o Historic building rehabilitation (such as paint, crack repair, window repair, lead and/or asbestos abatement, sumps, and plumbing)

The equipping of the FWTP groundwater wells will require the creation of a basis of design.

This will be based on water quality and well yield determination after the construction of the second groundwater well (estimated Summer 2027). Generally, the design will need to accommodate for the following:

o All improvements to remain on the west side of the FWTP property (FWTP resiliency improvements get priority of space needs) o Operation and treatment of both wells simultaneously or individually (one on and one off). Existing well has a yield of 3,000-gpm, and there is potential the second well will be close to this yield, even when operating in conjunction with each other.

o Treatment systems for manganese and arsenic (adsorption systems and resins preferred, new chemical systems should be avoided) o Integration of dechlorination system for flush-to-waste (should be able to accommodate other plant maintenance drainage at FWTP) and shared storage with the treatment plant (if same chemical is required for treatment operations) o Shared sewer, utility water, and storm drainage with FWTP (existing limitations may require additional utility improvements which will need to work in conjunction with surface water treatment plant needs) o Shared chlorine and fluoride storage with the treatment plant (i.e. no new storage) with dedicated dosing pumps for the wells o Electrical supply to come from new treatment plant control centers o SCADA controls shall be on a separate node than FWTP o System shall be designed with flush-to-waste o Provide for three finish water options: 1) feed into the finish reservoir, 2) flush to waste into storm drainage, or 3) into the 60” transmission main (systems to be designed are not to impact typical surface water treatment plant operations)

Meetings with City team during the design phase (Phase 1) shall include (at minimum):

o Primary team weekly in-person check-ins with City project manager o Initial team daily site visits for up to 2 weeks at FWTP and up to 3 weeks at SRWTP at the start of design to bring the team up to speed, gather data, and commence site assessments o Virtual reality one-on-one plan reviews with City project manager and up to three other City staff members (design team to provide needed equipment) o Bi-weekly check-ins with outreach team (weekly during active stakeholder interactions for the second SRWTP intake) o In-person briefings at each submittal of design plans (10%, 30%, 60%, and 90%) to review the general details of the plans o In-person briefings at the return of comments of each submittal of design plans (10%, 30%, 60%, and 90%) to review critical comments on the plans

Meetings with City team during the construction phases (Phase 2 thru 4) shall include (at minimum):

o Team project manager weekly in-person check-ins with City project manager and awarded contractor o Primary team bi-weekly in-person check-ins with the City project manager during the 100% design portion of work o Bi-weekly check-ins with outreach team (weekly during active construction outside of the FWTP and SRWTP fencelines affecting publicly accessible areas) o In-person briefings with contractor at beginning of contractor award regarding the 90% design, initial field checks for the 100% design, and at the 100% design to review the details of the plans

Reports and findings (in addition to those listed in the FWTP basis of design and SRWTP basis of design, and above) shall include, at a minimum:

o Quarterly summary updates, including schedule projections, for DOU executive team for Phases 1 thru 4.

o Cost estimate updates with the 30%, 60% and 90% design submittals (include current day value and projected value based on construction schedule).

o Bi-annual (twice a year) update for DOU director to share with City Manager for Phases 1 thru 4.

All drafted documents shall be completed in AutoCAD / Civil 3D only (no other platform permitted).

All specifications shall be completed in Microsoft Word only (no other platform permitted).

Reviews shall be available for virtual reality (plans only), Bluebeam PDFs (plans only), and Word documents (specifications, control strategies, and standard operating procedures). City shall maintain full ownership of all documents, files, and supporting data created/built for this project.

At any time, the consultant shall provide the raw working files upon the City’s request.

At the completion of the 90% design for each phase of construction, the following shall be provided to the City:

Three (3) bound hard copies of the specifications

Three (3) bound hard copies of the plan sheets (11x17)

Three (3) hard copy sets of binders of the standard operating procedures

Printable pdf files of the plans (in 11x17 and 24x36 format) and specifications

Printable pdf files of the standard operating procedures and control narratives

At the completion of the 100% design for each phase of construction, the following shall be provided to the City:

Seven (7) bound hard copies of the specifications

Seven (7) bound hard copies of the plan sheets (11x17)

Five (5) bound hard copies of the plan sheets (24x36)

Three (3) hard copy sets of binders of the standard operating procedures

Three (3) hard copy sets of binders of the control narratives

Printable pdf files of the plans (in 11x17 and 24x36 format) and specifications

Printable pdf files of the standard operating procedures and control narratives

AutoCAD files of the plan sets

During construction Phases 2 thru 4, monthly drafted as-built updates of the construction plans shall be submitted to the City in AutoCAD format and quarterly updates of the site overview updates shall be submitted to the City in AutoCAD format and printable pdf format (11x17 and 24x36). Any and all changes to the project design shall be placed in a dedicated layer(s) to separate original from the as-built conditions.

In addition, throughout construction Phases 2 thru 4, three (3) 24x36 printouts shall be provided quarterly to the City of the site overview updates for each plant, detailing the location of buried utilities and above ground visible features of the site. Points of connection to utilities (from the utility supplier) and key isolation valves (for irrigation, utility water, and potable mains on-site) shall be highlighted for ease of location for operators. At the completion of construction of each phase, two (2) 24x36 laminated versions of the site overview maps shall be provided for each plant and submitted to the plant supervisor for their use.

At the completion of each construction phase, the following shall be provided to the City:

Three (3) bound hard copies of the conformed specifications

Three (3) bound hard copies of the as-built plan sheets (11x17)

Two (2) finalized hard copy sets of binders of the standard operating procedures

Two (2) finalized hard copy sets of binders of the control narratives

Printable pdf files of the plans (in 11x17 and 24x36 format), specifications, and plant overviews

Printable pdf files of the standard operating procedures and control narratives

AutoCAD files of the project as-builts and the site overviews

4. Ideal Project Team

This project requires a significant amount of specialized experience and expertise of the drinking water industry including medium voltage systems, treatment processes, process control systems, and constructability around live assets. The project also requires teams with the experience designing for large treatment facilities as well as groundwater wells. As such, the desired project team will know how to:

• Minimize risk to existing structures and operations by recognizing critical process and equipment needed to treat drinking water.

• Design temporary elements capable of successfully being constructed during a limited plant shutdown window on existing aged assets.

• Work collaboratively with City engineers, operators, maintenance (machinists, electricians, and instrumentation specialists) and support staff (regulatory, SCADA programmers, security, and communications) to produce quality design, control narratives, and standard operating procedures (new processes) for a successful transition between each year of construction and implementation of the improvements.

• Recognize the core concern of City staff is to minimize risk to operations whenever feasible.

• Design under the tight project timeline without sacrificing quality nor completeness of documents submitted to the City.

• Be responsive to the City project manager when questions or concerns arise (during design and during construction).

• Keep current with changing drinking water regulations and potential issues of concern (including but not limited to golden mussels, cybersecurity, and emergency conditions).

• Support and design to real-time condition changes in surface water supplies.

• Provide quality support functions during the design phase including grants, WIFIA, public outreach, real estate, NEPA, and constructability.

• Evolve the design of both FWTP and SRWTP together while avoiding dissimilarities in look and feel of the drafted documents and specifications.

• Supports “outside of the box” thinking in engineering and design concepts to address unique situations and conditions that exist at both treatment plants.

In addition, the design team will understand specialized elements of drinking water treatment processes and high capacity treatment plants including:

• Treatment processes beyond conventional treatment such as ozone, biologically activated filters, and solids handling;

• Hydraulic gradient limitations under multiple operational conditions;

• Medium and high voltage electrical systems;

• Control systems and how they function with process needs;

• Treatment operations and tools for improved operations such as pilot plants and Zeta meters; and

• Constructability around existing water systems and equipment to remain in service.

5. Proposal Cost & Performance Schedule

The proposal cost shall be broken down between the four (4) phases:

Phase 1) Design of all of the project elements noted in the scope of services through 90% design

Phase 2) Design completion (100% design) and construction support for the FWTP resiliency improvements, FWTP groundwater well equipping, and SRWTP “short list” elements.

Phase 3) Design completion (100% design) and construction support for the SRWTP resiliency improvements and the North B Street transmission main replacement

Phase 4) Design completion (100% design) and construction support for the SRWTP expansion improvements.

With the exception of phase 1 for design through 90% of all project elements (resiliency, wells, and expansion), timing of the remaining three phases will be dependent on funding for construction and timing needs for additional water treatment capacity.

Due to the uncertain start time for phases 2, 3, and 4, percentage increases for annual hourly rates shall not exceed 3% for all phases of the project scope of work (including the primary firm and subcontractors).

Proposal costs shall be broken down into the following categories and subcategories (at a minimum):

Phase 1 - Design (10% “breakdown”, 30%, 60%, and 90% plans and specifications) o FWTP resiliency design o FWTP groundwater well equipping o SRWTP “short list” design - to include sodium hypochlorite, maintenance building, storm drainage adjustment to Sump 163, and boundary security improvements o SRWTP resiliency design including North B Street transmission main replacement o SRWTP expansion design

Phase 2 - Design (100% plans and specifications) o FWTP resiliency design o FWTP groundwater well equipping o SRWTP “short list” design - to include sodium hypochlorite, maintenance building, storm drainage adjustment to Sump 163, and boundary security improvements

Phase 3 - Design (100% plans and specifications) o SRWTP resiliency design including North B Street transmission main replacement

Phase 4 - Design (100% plans and specifications) o SRWTP expansion design

Project Support (design, resiliency construction, and expansion construction) broken down for each phase (Phases 1 thru 4):

o Finance (Phases 1 thru 4) o Real estate (Phase 1) o Public Outreach (Phases 1 thru 4) o Documentation and cataloging (Phases 1 thru 4) o Construction support (Phases 2 thru 4)

Please note that some elements will overlap between categories (such as SMUD undergrounding at SRWTP will be necessary in order to complete the maintenance building). The full design will be proceeding forward, so proposals should ensure that overlapping elements are accounted for in the resiliency design packages when in doubt.

For supporting elements, cost estimates should include efforts during design and then efforts during the FWTP resiliency construction (including SRWTP “short list” and FWTP well equipping).

Updated cost estimates will be requested before following phases of construction, though cost estimates should be included with this proposal.

The Department is estimating the Phase 1 design effort (including project support) to be around $30 million.

The City is intending to award one team for the entirety of the scope of services and duration of the project. However, the City reserves the right to amend the contract in the future to adjust the scope, timing, and other factors as the project proceeds through each phase. Each project phase shall be individually released with a notice to proceed. No work will proceed to the next phase until the firm receives a written notice to proceed from the City project manager. Each new notice to proceed will be released no less than 30 calendar days prior to the phase starting.

The cost proposal shall include staff hourly rates (both regular and overtime) for the primary firm and all subconsultants, percent markup on equipment rental rates, and cost of technical specialists work. If hourly rates are broken down per personnel title (instead of specific personnel), the proposal shall include applicable list of personnel and their titles proposed to be working on any of the project elements. As noted percentage increases for annual hourly rates shall not exceed 3% for all phases of the project design and support services (including the primary firm and subcontractors).

The cost proposal must be submitted via PlanetBids only along with the proposal.

6. Deadline

Proposals must be received by 3:00 pm on Thursday, January 28th, and must include the information requested in Section B of this RFP.

7. Applicable Ordinances & Programs

Local Business Enterprise (LBE) Five Percent (5%) Proposal Evaluation Preference

☒ The LBE 5% Preference is applicable to this Request for Proposals.

-or- ☐ The LBE 5% Preference is not applicable to this Request for Proposals.

-or-

☐ The LBE 5% Preference is not applicable to this Request for Proposals as the project is Federally-funded.

For contracts under $250,000, firms that qualify as a local business enterprise (LBE) will receive a 5% preference on all City procurement opportunities. The prime proposer must qualify under the LBE to receive preference points and subcontractors may not be considered. For professional service contracts only, this preference also applies to procurement opportunities of $250,000 or more.

A prime contractor that qualifies as an LBE shall receive additional points during the scoring process, so the final score awarded to the LBE is increased by 5% of the total possible evaluation points.

Detailed information about this program can be found in the City’s LBE Policy, located at:

https://www.cityofsacramento.gov/finance/procurement/contract-ordinances

Local Business Enterprise (LBE) Participation Program

☒ The LBE Participation Requirement is applicable to this Request for Proposals.

-or- ☐ The LBE Participation Requirement is not applicable or has been waived for this Request for Proposals -or- ☐ The LBE Participation Requirement is not applicable to this Request for Proposals as the project is Federally-funded.

The LBE Participation Program is applicable to non-professional, professional, and public project/construction contracts $250,000 or more unless waived by the City Manager or the City Manager's designee. This program provides enhanced opportunities for the participation of qualifying business in the City's contracting and procurement activities. A minimum of 5% LBE participation is required. To receive credit for the 5% minimum participation requirement, proposers must either (a) be an LBE, or (b) subcontract with a qualified LBE. Proposers wishing to qualify for this requirement using subcontractors must submit the Subcontractor and Local Business Enterprise Participation Verification Form with their proposal.

Detailed information about this program and the Subcontractor and Local Business Enterprise Participation Verification Form can be found at:

https://www.cityofsacramento.gov/finance/procurement/contract-ordinances

SB 1383

☐ Goods/services being requested on this solicitation qualify as Recovered Organic Materials and will be subject to reporting requirements outlined in SB 1383.

-or- ☒ SB 1383 requirements are not applicable to this solicitation.

Beginning January 1, 2022, SB 1383 requires cities and counties to procure annually a quantity of recovered organic waste products to meet their annual procurement target.

These procurement requirements will strengthen California’s green, self-sustaining economy. CalRecycle assigns an annual procurement target to each jurisdiction based on its population. Jurisdictions can fulfil their target by procuring any combination of the following recovered organic waste products:

Compost Mulch Renewable Energy (Transportation Fuel, Heat, Electricity) from Anerobic Digestion and Electricity from Biomass Conversion.

Full regulatory requirements can be found at:

https://govt.westlaw.com/calregs/Browse/Home/California/CaliforniaCodeofRegulations?guid =IBB2CD6505B4D11EC976B000D3A7C4BC3&originationContext=documenttoc&transition Type=Default&contextData=(sc.Default)

Additional City Ordinances

Information on additional ordinances may be found at:

https://www.cityofsacramento.org/Finance/Procurement/Contract-Ordinances

The Local Ordinance & Bid Preference Requirements Table outlines which ordinances apply to procurement contracts by type and dollar amount:

https://www.cityofsacramento.gov/content/dam/portal/finance/Procurement/contract-ordinances/Local-Ordinances-and-Bid-Preference-Requirements-Table.pdf

B. RFP SUBMITTAL REQUIREMENTS

1. Submittal Process

Firms or individuals interested in submitting proposals for this project should respond to this Request for Proposals (RFP) by submitting an electronic proposal, via PlanetBids, providing all the information requested below. The proposal will be considered complete only if all of the items listed in this section are included in the submittal.

Please note that the proposal must include a completed and signed Submittal Signature Page (Attachment 1).

2. Contents of Submittal

Each submittal shall include, at a minimum, the RFP transaction number, project name, company name, and the information as called for below. The SOP will be considered complete only if all of the items listed in this section are included in the submittal.

1) Transmittal Letter:

The proposal should be signed by an officer authorized to bind the proposing firm. The letter shall not exceed 2 pages in length, and shall include (at a minimum):

Contact information for the company, including name and contact phone number, email, business address, and website address (if applicable);

The state in which the firm is headquartered and office from which services will be provided;

The firm’s basic understanding of the services identified;

An expression of the firm’s interest in the work;

Whether the firm will be using any subcontractors; and, A statement regarding the qualifications of the firm to do the work.

A list of the subcontractors (and the offices from which services will be provided) to be working with the firm to complete the scope of services.

Conflicts of Interest - A disclosure identifying any actual, apparent, or potential conflicts of interest that the primary firm (or supporting firms) may have regarding the project. If there are no conflicts of interest, a statement to that effect should be included in the proposal.

The transmittal letter must also acknowledge any addendums provided on the City of Sacramento's Online Bid Portal PlanetBids.

2) Firm Qualifications & Experience:

In 3 pages or less, describe the primary firm’s experience working on similar drinking water projects over the past 10 years (within California preferred). Discussion should focus on the firm’s comprehension, experience, and expertise with operations, processes, process controls, and engineering around (and with) existing drinking water treatment systems that need to remain live. If one or more of the supporting firms have experience on similar drinking water projects over the past 10 years, include them. Please note that the primary firm is anticipated to be able to provide most of the experience needed to support this project.

In addition to the above, answer the following questions:

What is the primary firm’s policy on AI use? What is the primary firm’s intent for AI use on the project?

Are any of the supporting firms’ policies different than the firm’s? If so, what differences do they include? What are the supporting firms’ intent for AI use on the project?

3) Project Team:

The project team will be one of the primary reasons for a successful completion of the project.

It will require a number of specialists with the expertise and experience to fill all elements of the design, supporting studies, and additional support services. For this project, DOU is interested in understanding the team you are proposing for this effort from the primary firm as well as any partnering firm needed to fill in various functions of the project.

At a minimum, information regarding the project team should include the following:

Name of firms (primary and supporting firms) Size and location of primary office for each firm. “Primary office” is the office in which most work on the project will be occurring.

Description of experience and expertise within the primary office for each firm.

Description of non-primary office experience and expertise that is planned to be used for each firm (if applicable) Name specific personnel from each firm that will be supporting primary functions in the project design and those providing primary functions for the additional support services. “Primary function” is any notable title that will play a significant role in the design or support needed to complete the project elements.

o From the list of personnel, identify those who are proposed to serve the following roles: Project Manager, Project Manager Back-up, Electrical Specialist, Treatment Process Specialist, Control Systems Specialist, and Constructability Specialist. For these personnel, note what primary office location they work from.

Provide reduced (simplified) resumes for each person listed that includes:

o Years of experience serving the noted primary function (i.e. structural engineer designing water infrastructure, or civil engineer designing groundwater well treatment systems), o Any applicable certifications and/or licenses, and o Any specific potable water projects (if any) within the past 10 years that they personally served the noted function (project name, brief project description, location, years worked on the project, brief description of their role).

This element of the proposal should encompass all support services requested in the Scope of Services listed above. Please include any plans for back-up personnel for key positions or succession planning for key personnel that may retire / leave during or shortly after the 5 year design period. Key personnel located within 30 miles of the City of Sacramento preferred.

Firms selected to be interviewed will be required to attend in-person (remote interviews will not be an option). Minimum required attendees shall include the individuals listed in the proposal as Project Manager, Electrical Specialist, Treatment Process Specialist, Control Systems Specialist, and Constructability Specialist.

4) Specialized Questions:

The proposal shall include answering the following questions. Answers to the questions should be based on the proposed team’s approach, not necessarily the firm’s standard approach. The team should be comfortable applying responses to the questions below as they would during the project design:

a. Project Design & Schedule: Based on the need to phase construction year to year in order to maintain water service throughout the construction period, how would your team approach the constructability “breakdown” of the 10% design to determine year to year construction? Please include any special nuances to the approach that might be different than a typical design-bid-build project. Note how this approach may help or impact the schedule for design completion dates noted above.

b. Construction Impacts: Based on the limited shutdown period available year to year, how would the team’s approach to the design change (if at all) knowing construction of the FWTP improvements would fall in the middle of a series of wet years (many rain events, shallow groundwater)? How would the team’s approach to the design change (if at all) knowing construction years 2 thru 5 at SRWTP would fall in the middle of a series of wet years (many rain events, shallow groundwater)? Please include any conditions that the team might foresee impacting the construction schedule understanding the shutdown period of a single treatment plant is limited and fixed to a four month window each winter season.

c. Introduction of Groundwater: For the groundwater wells at FWTP, it is planned for the finish water to have the ability to go 1) into the finish reservoir of the surface treatment plant (air gap from the top of the reservoir) 2) to feed directly into the distribution system (anticipated 60-psi), or 3) treated to waste (i.e. sent to storm draining after treatment).

How would the team approach the design to be able to run water through the groundwater well treatment processes and still be able to switch sending finish water into one of three distinctively different discharge points? What design considerations would there be, if any, to the well water discharging to these locations?

d. Project Management & Accountability: Based on the size and scope of this project, how would the team provide accountability that everyone on the team is on the same page for level of effort (per design phase) and ensuring no one is moving ahead of the other groups? For example, there are a number of reports and additional assessments that need to be conducted in order to move to 30% design, but some sections of design may not require information in order to proceed forward. Include any special project management approach the team would use to improve accountability.

e. Process Controls and Processes: Given a conventional treatment filter that has been updated to operate as a biologically activated filter, what is a high-level process control strategy approach that would be recommended for the filter…