Bid Notice-Upper Truckee River Bridge Scour Protection Project.pdf
PDF 2 MB Posted
- Solicitation number
- 26-30160088-01
- Issued by
- El Dorado County, Santa Monica City, California
About this file
Upper Truckee River Bridge Scour Protection Project
This is a formal bid notice and contract document package issued by the City of South Lake Tahoe Department of Public Works for the Upper Truckee River Bridge Scour Protection Project (PWC 26-30160088). The scope of work includes installation of rip rap scour protection, traffic control, installation and maintenance of temporary best management practices (BMPs), utility protection and coordination, compliance with regulatory permits, salvaging and replanting willows, and revegetation of all upland areas disturbed by construction activities in accordance with the 2022 California Department of Transportation Standard Specifications. Sealed bids must be received by 2:00 p.m. on July 20, 2026, at the City's Department of Public Works Office located at 1740 D Street, South Lake Tahoe, California 96150-6251. A non-mandatory pre-bid conference is scheduled for July 10, 2026, at 2:00 p.m. via Microsoft Teams. The contract time requires substantial completion within 14 calendar days from the Notice to Proceed (by October 14, 2026) and final completion within 15 calendar days overall (by October 15, 2026), with excavation and grading activities restricted to the period between May 1 and October 15. The anticipated Notice to Proceed is October 1, 2026. The City will award the contract to the lowest responsive, responsible bidder.
The estimated cost for the base bid ranges from $500,000 to $800,000. Bidder's security of not less than ten percent (10%) of the total aggregate bid price is required. Liquidated damages of $500 per calendar day will be assessed for failure to achieve substantial completion and $1,000 per calendar day for failure to achieve final completion. The successful bidder must possess a California Class A General Engineering Contractor's License at the time of bid opening and comply with prevailing wage requirements per California Labor Code Section 1771.1, with all workers paid at rates established by the Director of the California Department of Industrial Relations for El Dorado County. Bidders must provide proof of Department of Industrial Relations registration for all contractors and subcontractors and submit Certificates of Reported Compliance (CRC) for all in-use off-road diesel-fuel fleet vehicles. Performance and payment bonds, each in the amount of 100% of the contract sum, are required. The contract documents are available for free download from the City's Planet Bids website, with hard copies available for viewing at the Department of Public Works Office during regular business hours.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF SOUTH LAKE TAHOE
DEPARTMENT OF PUBLIC WORKS
BID DOCUMENTS
for
UPPER TRUCKEE RIVER BRIDGE SCOUR PROTECTION PROJECT
THE CITY OF SOUTH LAKE TAHOE
PUBLIC WORKS PROJECT NUMBER: 26-30160088
FORMAL BID No. 26-30160088-01
Bid Opening:
July 20, 2026 Stephen Anderjack 2:00 PM Project Manager 1740 D Street 530-721-1102 South Lake Tahoe, CA 96150
UPPER TRUCKEE RIVER BRIDGE SCOUR PROTECTION PROJECT
PUBLIC WORKS PROJECT NUMBER: 26-30160088
FORMAL BID No. 26-30160088-01
The Bid Documents contained herein have been prepared by or under the direction of the following California registered professional engineer:
Approved By for the City of South Lake Tahoe:
Dr. Mohammad Qureshi, PE C #75297 Director of Public Works/City Engineer
Prepared By:
CIVIL ENGINEER, C #54137
Jennifer Roman Engineer of Record, Eastern Sierra Engineering
00100
DOCUMENT 00100 - NOTICE TO BIDDERS
ARTICLE 1 - GENERAL
1.01 NOTICES
1.02 THE WORK
1.03 ESTIMATED COST
1.04 CONTRACT TIME AND MILESTONES
1.05 LIQUIDATED DAMAGES
1.06 BIDS MUST BE RECEIVED BY THE CITY AT THE FOLLOWING ADDRESS
PRIOR TO THE DATE/TIME DESIGNATED FOR BID OPENING:
1.07 BIDDER’S SECURITY
1.08 BID OPENING
1.09 ERRORS OR DISCREPANCIES IN THE BIDS
1.10 BID AWARD
1.11 STANDARD PLANS AND SPECIFICATIONS
1.12 BID ESCROW
1.13 BID RIGGING
ARTICLE 2 - OTHER NOTICES
2.01 CONTRACTOR’S LICENSING REQUIREMENT
2.02 LABOR; PREVAILING WAGE REQUIREMENT
2.03 BONDS; INSURANCE; TAXES
2.04 NON-DISCRIMINATION
2.05 PERFORMANCE OF THE WORK
2.06 APPLICATION OF SOUTH LAKE TAHOE CITY CODE
2.07 PROGRESS SCHEDULE
2.08 RETENTION FROM PAYMENTS DURING CONTRACT TIME
2.09 AVAILABILITY OF BID DOCUMENTS
2.10 NON-MANDATORY PRE-BID CONFERENCE
2.11 PROJECT MANAGER/AUTHORIZED REPRESENTATIVE
2.12 SUBSTITUTIONS
2.13 RESERVED
2.14 CALIFORNIA AIR QUALITY CONTROL BOARD (CARB) EQUIPMENT
EMISSIONS – CERTIFICATES OF REPORTED COMPLIANCE (CRC)
DOCUMENT 00200 - INSTRUCTIONS TO BIDDERS
ARTICLE 1 - GENERAL
ARTICLE 2 - COMPETENCE OF BIDDERS
ARTICLE 3 - COMPLIANCE WITH CONTRACTOR’S LICENSE LAWS
ARTICLE 4 - PRIOR DISQUALIFICATION
ARTICLE 5 - EXAMINATION OF BID DOCUMENTS AND PROJECT SITE
ARTICLE 6 - DISCREPANCIES, CONFLICTS, OMISSIONS, OR ERRORS
ARTICLE 7 – BIDDER’S SECURITY
ARTICLE 8 - BID FORMS
ARTICLE 9 - CONTRACTING PRINCIPLES
ARTICLE 10 - SUBMISSION OF BID FORMS
ARTICLE 11 - WITHDRAWAL OF BID FORMS
ARTICLE 12 - PUBLIC OPENING OF BIDS
ARTICLE 13 - REJECTION OF IRREGULAR BIDS
ARTICLE 14 - COMPETITIVE BIDDING
ARTICLE 15 - ESTIMATED QUANTITIES
ARTICLE 16 - SUBSTITUTION OF ALTERNATIVE MATERIALS, ARTICLES, OR
EQUIPMENT
ARTICLE 17 - RETURN OF BIDDER’S SECURITY
ARTICLE 18 - RELIEF OF BIDDERS
ARTICLE 19 -AWARD OF CONTRACT
ARTICLE 20 – REQUIRED CONTRACT BONDS
ARTICLE 21 - INSURANCE
ARTICLE 22 - EXECUTION OF CONTRACT AGREEMENT
ARTICLE 23 - FAILURE TO EXECUTE AGREEMENT
ARTICLE 24 - NO ORAL AGREEMENTS
ARTICLE 25 - SHEETING, SHORING, AND BRACING
ARTICLE 26 -BID PROTESTS
ARTICLE 27 - cONSTRUCTION STAGING AREAS
DOCUMENT 00300 – RESERVED
DOCUMENT 00400 – BID PROPOSAL
1.0 ENTER INTO AGREEMENT
2.0 BIDDER ACCEPTANCE OF TERMS AND CONDITIONS
3.0 BIDDER REPRESENTATIONS
4.0 BID
4.1 BASE BID SCHEDULE
4.2 DAILY RATE OF COMPENSATION FOR COMPENSABLE DELAY
4.3 TOTAL BASE BID
5.0 BID ALTERNATE ITEMS
6.0 COMPLETION
7.0 ATTACHED DOCUMENTS
8.0 SUPPLEMENTAL INFORMATION SUBMITTED AFTER BID OPENING
9.0 CALIFORNIA CONTRACTOR'S LICENSE AND ENTITY INFORMATION
10.0 BID SECURITY
DOCUMENT 00405 – BID SCHEDULE
DOCUMENT 00410 – BIDDER’S BOND
DOCUMENT 00420 – DESIGNATION OF SUBCONTRACTORS
DOCUMENT 00421 – GOOD FAITH EFFORTS FOR LOCAL HIRING ON PUBLIC WORKS
CONTRACTS
DOCUMENT 00423 – VERIFICATION OF CONTRACTOR AND SUBCONTRACTOR DIR
Registration
DOCUMENT 00424 – CARB CERTIFICATES OF REPORTED COMPLIANCE
DOCUMENT 00425 – SELF-PERFORMANCE DECLARATION
DOCUMENT 00430 – DEBARMENT AND SUSPENSION CERTIFICATION
DOCUMENT 00432 – NON-COLLUSION DECLARATION
DOCUMENT 00435 – CONTRACTOR’S WORKERS COMPENSATION CERTIFICATION
DOCUMENT 00440 – BUSINESS AND PROFESSIONAL CODES 7028.15 AND 7031
STATEMENT
DOCUMENT 00450 – BIDDERS STATEMENT OF FINANCIAL RESPONSIBILITY,
TECHNICAL ABILITY, AND EXPERIENCE
DOCUMENT 00460 – EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION
DOCUMENT 00465 – NON-LOBBYING CERTIFICATION
DOCUMENT 00500 - AGREEMENT
ARTICLE 1 — THE WORK
ARTICLE 2 — COMMENCEMENT AND COMPLETION
ARTICLE 3 — CONTRACT PRICE
ARTICLE 4 — PREVAILING WAGES
ARTICLE 5 — CONTRACT DOCUMENTS
ARTICLE 6 — WORKERS’ COMPENSATION
ARTICLE 7 — INDEMNITY AND INSURANCE
ARTICLE 8 — NOTICES
ARTICLE 9 — MISCELLANEOUS
DOCUMENT 00610 - PAYMENT BOND FORM
DOCUMENT 00620 - PERFORMANCE BOND FORM
DOCUMENT 00630 - SAMPLE ESCROW AGREEMENT FOR SECURITY DEPOSITS IN
LIEU OF RETENTION
DOCUMENT 00635 - WARRANTY/GUARANTEE FORM
DOCUMENT 00640 – ACKNOWLEDGMENT OF CITY CODE
DOCUMENT 00650 – BID DOCUMENTATION CERTIFICATION
DOCUMENT 00700- SPECIAL PROVISIONS
SECTION 1: GENERAL
1.1 GENERAL
1.2 STANDARD SPECIFICATIONS
1.3 BID DOCUMENTS
1.4 SPECIFICATIONS AND PLANS
SECTION 2: BIDDING
2.1 GENERAL
2.2 DISCLOSURES AND COMPLIANCE CERTIFICATIONS
2.3 ESCROW OF BID DOCUMENTS
SECTION 3: CONTRACT AWARD AND EXECUTION
3.1 GENERAL
3.2 CONTRACT BONDS
3.3 BUSINESS AND PROFESSIONS TAX
SECTION 4: SCOPE OF WORK
4.1 GENERAL
4.2 CHANGES AND EXTRA WORK
SECTION 5: CONTROL OF WORK
5.1 GENERAL
5.2 SUBCONTRACTING
5.2.1 SUBLETTING AND SUBCONTRACTING
5.2.2 SUBCONTRACT RELATIONS
5.2.3 CONTROL OF SUBCONTRACTORS
5.2.4 APPLICATION OF CITY CODE TO SUBCONTRACTORS
5.3 SELF-PERFORMANCE REQUIREMENTS
5.4 AUDITS AND ACCESS TO RECORDS
5.5 PROJECT APPEARANCE
5.6 STORAGE OF EQUIPMENT
5.7 DUST CONTROL
5.8 WASTE MATERIAL
5.9 REMOVAL OF ASBESTOS AND HAZARDOUS SUBSTANCES
5.10 JOBSITE SANITARY FACILITIES
5.11 SUBMITTALS
5.12 CONTRACTOR RESPONSIBILITIES
5.12.1 GENERAL
5.12.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY THE
CONTRACTOR
5.12.3 ACCESS TO WORK
5.12.4 USE OF PROJECT SITE
5.12.5 WORKPLACE ENVIRONMENT
5.12.6 DISRUPTION OF CITY’S NORMAL OPERATIONS
5.12.7 ORDER OF WORK
5.12.8 CLEANUP
5.12.9 RESERVED
5.12.10 WORKER’S SANITARY PROVISIONS & USE OF CITY’S FACILITIES
5.12.11 CUTTING AND PATCHING
5.12.12 PATENTS
5.12.13 NON-WAIVER
5.12.14 UNFAIR BUSINESS PRACTICES CLAIMS
5.12.15 STANDARDS FOR WORK & MATERIALS
5.12.16 CONFORMITY WITH CONTRACT DOCUMENTS & ALLOWABLE DEVIATIONS
SECTION 6: CONTROL OF MATERIALS
6.1 GENERAL
6.2 WARRANTY/GUARANTY PERIOD
6.3 PERMEABLE MATERIAL
6.4 CURING COMPOUND
Not Used.6.5 RELATIVE COMPACTION
6.6 PAINTING COLOR OF EXPOSED EQUIPMENT
6.7 INSPECTION AND TESTS
SECTION 7: LEGAL RELATIONS AND RESPONSIBILITY
7.1 GENERAL
7.2 SOUND CONTROL REQUIREMENTS
7.3 RIGHTS IN LAND AND IMPROVEMENTS
7.4 CONTRACTS FOR DIGGING TRENCHES; REQUIREMENTS
7.5 PREVAILING WAGE
7.6 PREVAILING WAGE DETERMINATIONS
7.7 TRAVEL AND SUBSISTENCE PAYMENTS
7.8 PAYROLL RECORDS
7.9 LABOR NONDISCRIMINATION
7.10 ASSIGNMENT OF ANTITRUST ACTIONS
7.11 INDEMNIFICATION
7.12 INSURANCE COVERAGES AND AMOUNTS
SECTION 8: PROSECUTION AND PROGRESS
8.1 GENERAL
8.2 DELAYS
8.3 CONSTRUCTION SCHEDULE, COMPLETION AND LIQUIDATED
DAMAGES 136
8.4 BREACHES, DEFAULTS AND TERMINATION FOR CAUSE
SECTION 9: MEASUREMENT AND PAYMENT
9.1 GENERAL
9.2 PROGRESS AND PARTIAL PAYMENTS
9.3 WITHHOLDING OF PAYMENTS
9.4 RETAINAGE FROM PAYMENTS
9.5 PROMPT PROGRESS PAYMENTS TO SUBCONTRACTORS
9.6 USE BEFORE ACCEPTANCE
9.7 SUBSTANTIAL COMPLETION
9.8 FINAL COMPLETION AND PAYMENT
9.9 COMPENSATION FOR COMPENSABLE DELAY
9.10 CLAIMS AND DISPUTE RESOLUTION
SECTION 10 CONSTRUCTION DETAILS
10-1.01 CONTROL OF WORK
10-1.02 MOBILIZATION
10-1.03 PERMITS
10-1.04 WATER POLLUTION CONTROL
10-1.05 CONTROL OF WATER
10-1.06 RELATIONS WITH TAHOE REGIONAL PLANNING AGENCY
10-1.07 COOPERATION
10-1.08 OBSTRUCTIONS
10-1.09 CONSTRUCTION STAKING
10-1.10 CONSTRUCTION AREA SIGNS
10-1.11 RECORD DRAWINGS
10-1.12 MAINTAINING TRAFFIC
10-1.13 TRAFFIC CONTROL
10-1.14 TRENCH SHORING
10-1.15 TREE AND VEGETATION PROTECTION
10-1.16 CLEARING AND GRUBBING
10-1.17 EARTHWORK
10-1.18 WASTE MATERIAL
10-1.19 CONSTRUCTION WATER
10-1.20 UTILITY RELOCATION AND ADJUSTMENT
10-1.21 ROCK SLOPE PROTECTION
10-1.22 EXISTING FACILITIES
10-1.23 REVEGETATION & RESTORATION
DOCUMENT 01300 - CONSTRUCTION PROGRESS DOCUMENTATION
ARTICLE 1 190
1.01 DEFINITIONS
Article 2 - PRODUCTS
2.01 SCHEDULING SOFTWARE
Article 3 - EXECUTION
3.01 CPM PROGRESS SCHEDULE
3.02 BASELINE SCHEDULE
3.03 OFFICIAL PROGRESS SCHEDULE
3.04 MONTHLY UPDATE OF THE OFFICIAL PROGRESS SCHEDULE
3.05 SHORT INTERVAL SCHEDULE
3.06 RECOVERY SCHEDULE
3.07 TIME EXTENSIONS
APPENDICES
Appendix A – TRPA General Conditions and Attachment Q
NOTICE TO BIDDERS
DOCUMENT 00100 - NOTICE TO BIDDERS
ARTICLE 1 - GENERAL
1.01 NOTICES
A. NOTICE IS HEREBY GIVEN that sealed Bids will be accepted at the Public Works Office, City of South Lake Tahoe, 1740 D Street, South Lake Tahoe, California 96150-6251 until 2:00 p.m., on July 20, 2026 for the UPPER TRUCKEE RIVER BRIDGE SCOUR PROTECTION
PROJECT in accordance with Bid Documents for the Work on file and available for viewing in the Department of Public Works Office at 1740 D Street, City of South Lake Tahoe, and available to view and download free of charge from the City of South Lake Tahoe’s Planet Bids website as described herein Section 2.09, “Availability of Bid Documents” in this Notice to Bidders.
1.02 THE WORK
A. The “Work” will consist of:
1. The Bidder shall furnish all labor, equipment and materials and perform all work necessary for the UPPER TRUCKEE RIVER
BRIDGE SCOUR PROTECTION PROJECT in the City of South Lake Tahoe in strict conformance with the Contract Documents (as defined in the Agreement), including, without limitation, the specifications and construction drawings. Work to be performed includes, but is not limited to: installation of rip rap scour protection, traffic control, installation and maintenance of temporary BMPs, utility protection and coordination, compliance with regulatory permits, salvaging and replanting willows, revegetating all upland areas disturbed by construction activities and all other work as described in the Contract documents, including, without limitation, project construction drawings, bid documents, Special Provisions, City of South Lake Tahoe Public Improvements and Engineering Standards, and the 2022 edition of the California Department of Transportation, Standard Specifications.
1.03 ESTIMATED COST
A. The estimated cost for the Base Bid Schedule of this Work is in the range of: $500,000 - $800,000.
1.04 CONTRACT TIME AND MILESTONES
A. Final Completion (as defined in Section 9.9 of the Special Provisions) must be achieved within 15 calendar days and by October 15, 2026 (“Contract Time”). The Work must be completed in accordance with the Contract Documents subject to the following:
1. Milestone #1: Achieve Substantial Completion of the Work (in accordance with Section 9.7 of the Special Provisions) within 14 calendar days from the date that the commencement of the Work is authorized pursuant to the Notice to Proceed and by October 14, 2026.
2. Milestone #2: Achieve Final Completion of the Work (in accordance with Section 9.8 of the Special Provisions) within 1 calendar days after Substantial Completion of the Work has been achieved, but not more than calendar days from the date that the commencement of the Work is authorized pursuant to the Notice to Proceed.
3. Excavation and grading activities may only be undertaken between May 1 and October 15; except that all Work shall be performed after the issuance of the Notice to Proceed, and Final Completion achieved within the Contract Time as set forth in these Bid Documents.
4. Work shall commence in accordance with the City’s issuance of a “Notice to Proceed” as set forth in the Contract Documents. The Anticipated Notice to Proceed is October 1st, 2026.
1.05 LIQUIDATED DAMAGES
A. Substantial Completion (Milestone #1): Liquidated Damages will be assessed in the amount of $500 for each calendar day beyond that portion of the Contract Time within which the Bidder is required to achieve Milestone #2, Substantial Completion as set forth in Document 00100, Article 1.04.A.2
B. Final Completion (Milestone #2): Liquidated Damages will be assessed in the amount of $1000 for each calendar day beyond that portion of the Contract Time within which the Bidder is required to achieve Milestone #3, Final Completion as set forth in Document 00100, Article 1.04.A.3.
D. In the event that Bidder fails, concurrently, to achieve multiple Milestones within the allocated portions of Contract Time as set forth in the Contract Documents, the Liquidated Damages assessed by the City shall be cumulative. Therefore, the City may, concurrently, assess Liquidated Damages for the Bidder’s failure to achieve two or more Milestones on the same calendar day.
E. The City may withhold Liquidated Damages from payments to the Bidder as such damages accrue, or, at the City's sole discretion, withhold Liquidated Damages from any payments due or that become due pursuant to the Agreement, including retention and final payment (pursuant to California Government Code §53069.85).
1.06 BIDS MUST BE RECEIVED BY THE CITY AT THE FOLLOWING
ADDRESS PRIOR TO THE DATE/TIME DESIGNATED FOR BID OPENING:
Department of Public Works
1740 D Street
South Lake Tahoe, California 96150-6251
Sealed envelopes containing bids must bear the Project name and Project number(s).
1.07 BIDDER’S SECURITY
A. Each Bid must be accompanied by cash, a certified or cashier's check, or a bond in the sum of not less than ten percent (10%) of the total aggregate of the Bid price, including all additive Bid items, as required in the Instructions to Bidders.
1.08 BID OPENING
A. A representative on behalf of the Department of Public Works will open Bids at the City of South Lake Tahoe, Department of Public Works Office located at 1740 D Street, South Lake Tahoe, California 96150-6251, at 2:00 p.m., on July 20, 2026.
1.09 ERRORS OR DISCREPANCIES IN THE BIDS
A. The City, in its sole discretion, reserves the right to reject any and all Bids, and to waive any errors or discrepancies in the Bids.
1.10 BID AWARD
A. If the Agreement is to be awarded, the City will award the Agreement to the lowest responsive, responsible bidder; provided, however, that the City, in its sole discretion, reserves the right to reject any and all bids. Subject to the full and complete satisfaction of the requirements set forth in the Bid Documents by the Bidder(s), said award shall be determined pursuant to an evaluation of the Total Base Bid Price submitted by each Bidder. For the
Work, the Total Base Bid Price shall be determined by adding the amounts set forth in the Base Bid Schedule and the Daily Rate of
Compensation for Compensable Delay For Contractor And All
Subcontractors/Suppliers Multiplied By 60.
The Contract Sum for the Agreement, if awarded, between the City and
Contractor shall be for the price indicated in the Base Bid Schedule.
The City reserves the right, in its sole discretion, to make any changes to the Work in accordance with the Bid Documents (and Contract
Documents) at any time, including, without limitation, the deletion, addition or modification of any aspect(s) or scope(s) of the Work to be performed, whether before or after the Agreement is awarded, if at all.
1.11 STANDARD PLANS AND SPECIFICATIONS
A. The Work shall be done in accordance with the Contract Documents, which shall include, without limitation, the Standard Specifications of the State of California Department of Transportation, dated 2022, and the Standard Plans, dated 2022, of the State of California Department of Transportation, insofar as the same may apply, as amended and augmented by the Bid Documents, the City's Special Provisions, the Project plans and drawings, the South Lake Tahoe City Code, the City of South Lake Tahoe Public Improvement and Engineering Standards, and all other applicable laws, regulations and codes.
1.12 BID ESCROW
A. In accordance with the requirements of the Contract Documents, the three apparent low Bidders shall submit into a bid escrow, within three (3) business days after opening of bids, one (1) copy of all documentary information and data generated in preparation of the Bid Proposal for the Project (in the format as required pursuant to the Contract Documents).
1.13 BID RIGGING
A. The U.S. Department of Transportation (DOT) provides a toll-free hotline to report bid rigging activities. Use the hotline to report bid rigging, bidder collusion, and other fraudulent activities. The hotline number is (800) 424- 9071. The service is available 24 hours 7 days a week and is confidential and anonymous. The hotline is part of the DOT's effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector General.
ARTICLE 2 - OTHER NOTICES
2.01 CONTRACTOR’S LICENSING REQUIREMENT
A. Pursuant to Document 00200, Article 3 “Compliance with Contractor’s License Law,” the Bidder must possess the following Contractor’s License(s) classifications to perform the Work: “Class A – General Engineering”.
B. The Bidder must possess the required classification of Contractor’s License at the time of the bid opening.
2.02 LABOR; PREVAILING WAGE REQUIREMENT
A. Pursuant to Labor Code Section 1771.1, a contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in Labor Code Section 1720, unless currently registered and qualified to perform public work pursuant to Labor Code Section 1725.5. It is not a violation of Labor Code Section 1771.1 for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Labor Code Section 1725.5 at the time the contract is awarded.
Only vendors/contractors that are subject to the public works statutes would be required to register. No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code Section
1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)]. Department of Industrial Relations, Contractor Registration information and web link:
http://www.dir.ca.gov/Public-Works/PublicWorks.html
In compliance with Senate Bill 854 (2014) and the California Labor Code, all bidders shall include with their bid proof of registration from the
Department of Industrial Relations that includes the contractor’s legal name, registration number, license type/number, registration date and expiration date, for every contractor and subcontractor, regardless of tier.
This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. Contractors must submit their certified payroll records directly to the Division of Labor Standards Enforcement Compliance Monitoring Unit through the electronic certified payroll reporting (eCPR) system, as well as to the City.
B. Pursuant to the Contract Documents, all workers employed in the performance of the Work must be paid rates at least equal to the prevailing wage rates last adopted by the Director of the California Department of Industrial Relations for the County of El Dorado, and which are incorporated herein by reference. In accordance with California Labor Code § 1773.2, these wage rates are on file at the offices of the City (Department of Public Works) and shall be made available to any interested party upon request.
C. The applicable prevailing wage rates are also available on the State of California Department of Industrial Relations website at California Department of Industrial Relations Home Page https://www.dir.ca.gov/OPRL/DPreWageDetermination.htm.
D. Bidder must comply with all applicable requirements of the California Labor Code, including, without limitation, all requirements set forth in Division 2, Part 7, Chapter 1. Attention of Bidder is also directed to the following sections of the California Labor Code: Prevailing Wage Requirements (§§ 1771.5 and 1776); Apprentices (§1777.5); Working Hours (§§ 1810 to 1815); Workers Compensation (§ 1860); and Protection of Workers in Trench Excavations (§§ 6705 and 6707).
Bidder may also reference additional information concerning prevailing wage requirements at the following websites:
http://www.dir.ca.gov/dlsr/DPreWageDetermination.htm
2.03 BONDS; INSURANCE; TAXES
A. Notwithstanding any other documents or data required by the Contract Documents or the City as a condition precedent to the City’s execution of the Agreement, the successful Bidder must timely deliver signed Contract bonds (including, without limitation, payment bond and performance bond) and all required insurance documents to the City for review and acceptance by the City, through the City Council, before the City will execute the Agreement and issue a Notice to Proceed.
B. No Agreement shall exist until all required Contract bonds and insurance documents have been accepted by the City.
C. Bidder, and all listed subcontractors, shall pay all City required business and professional taxes and fees prior to the issuance of the Notice to Proceed.
2.04 NON-DISCRIMINATION
A. This Project is subject to contract nondiscrimination and compliance requirements (pursuant to California Government Code, Section 12990.
The City hereby notifies all Bidders that it will affirmatively ensure that in any Agreement entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full opportunity to submit Bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration of an award.
2.05 PERFORMANCE OF THE WORK
A. No grading, excavation or other land disturbance will be performed pursuant to the Agreement between October 15 and May 1, unless a Grading Season Exception application is approved by regulatory agencies, Regional Water Quality Control Board (Lahontan) and Tahoe Regional Planning Agency (TRPA), allowing ground disturbance activities to occur before May 1st or after October 15th grading prohibition. All Work shall be performed after the issuance of the Notice to Proceed and Final Completion achieved within the Contract Time as set forth in these Bid Documents.
2.06 APPLICATION OF SOUTH LAKE TAHOE CITY CODE
A. In addition to any other applicable federal, state, and local rules, regulations and laws, this Project shall be subject to the South Lake Tahoe City Code.
Bidders shall review and be familiar with the requirements of the South Lake Tahoe City Code prior to the submission of any Bid.
2.07 PROGRESS SCHEDULE
A. Pursuant to the Contract Documents, a computerized CPM Progress Schedule is required pursuant to Part 2.01(A) of Document 01300 (“Construction Progress Documentation”).
2.08 RETENTION FROM PAYMENTS DURING CONTRACT TIME
A. Pursuant to the Contract Documents, Bidder may substitute securities for any money withheld from progress payments in accordance with Document 00630, “Sample Escrow Agreement for Security Deposit In Lieu of Retention.”
2.09 AVAILABILITY OF BID DOCUMENTS
A. Bid Documents (as defined in the Contract Documents), but not including the California Department of Transportation Standard Specifications and Plans, are available for download to each prospective bidder at the City of South Lake Tahoe website, Purchasing Department webpage. Interested bidders must register as a vendor by logging on to the City of South
Lake Tahoe, Planet Bids website:
http://www.planetbids.com/portal/portal.cfm?CompanyID=14997#
These Bid Documents may be viewed and downloaded free of charge by visiting the above website. A hard copy of the Plans and Specifications will be available for viewing at the Department of Engineering at the City of South Lake Tahoe Public Works Office, 1740 D Street, Monday through Friday, between the hours of 9 AM to 5 PM.
2.10 NON-MANDATORY PRE-BID CONFERENCE
A. A Non-Mandatory Pre-Bid Conference will be held on July 10, 2026 at 2:00 PM on Microsoft Teams (available at the link below). Bidders should become thoroughly familiar with the terms and conditions of the Bid Documents and local conditions affecting the performance and costs of the Work before attending this conference.
Microsoft Teams meeting
Join:
https://teams.microsoft.com/meet/234326167354801?p=TRJx5dbRsvR
HhRKO70
Meeting ID: 234 326 167 354 801 Passcode: Ja9rG2Vr
Need help? | System reference
For organizers: Meeting options
B. Bidders must fully inspect the Project site in all particulars before submitting a Bid.
C. Bidders shall submit all questions through the Planet Bids website.
2.11 PROJECT MANAGER/AUTHORIZED REPRESENTATIVE
A. The City’s Project Manager and Authorized Representative for this Project is: Stephen Anderjack, telephone number (530) 721-1102; and e-mail:
sanderjack@cityofslt.gov. Please do not call or email regarding questions on the bid. All questions and clarifications must be made through the Planet Bids website.
2.12 SUBSTITUTIONS
A. Except as may otherwise be provided in the Contract Documents, Bidder may offer any material, process, article, or equipment that is substantially equal or better in every respect to that so indicated or specified in the Contract Documents; provided, however, that if the material, process, article, or equipment offered by Bidder is not, in the opinion of the City’s Authorized Representative, substantially equal or better in respect to that specified, then Bidder must furnish that material, process, article, or equipment specified or one that in the opinion of the City’s Authorized Representative is substantially equal or better in every respect.
B. Proposals for alternative material(s), process, article(s), or equipment requested during the bidding period must be submitted in writing, in accordance with the requirements of the Contract Documents and all applicable federal, state, and local rules, regulations and laws, including the most recent version of the Public Contract Code and the South Lake Tahoe City Code.
2.13 RESERVED
2.14 CALIFORNIA AIR QUALITY CONTROL BOARD (CARB) EQUIPMENT
EMISSIONS – CERTIFICATES OF REPORTED COMPLIANCE (CRC)
A. Bidders shall include Certificates of Reported Compliance (CRC) for all In-Use Off-Road Diesel-Fuel Fleet Vehicles from all contractors and subcontractors with their bid proposal. Failure to include CRC records with the bid proposal is/are causes for the Bid to be rejected as non-responsive.
END OF DOCUMENT 00100
00200
INSTRUCTIONS TO BIDDERS
DOCUMENT 00200 - INSTRUCTIONS TO BIDDERS
ARTICLE 1 - GENERAL
1.01 Bidder must examine these Instructions carefully and respond to all requirements and conditions.
1.02 Bidders must be aware of the requirements of all applicable codes and other legal references, whether or not identified in the Bid Documents (as defined in the Special Provisions), and including, without limitation, the most recent version of the applicable Building Codes, the South Lake Tahoe City Code and the City of South Lake Tahoe Public Improvement and Engineering Standards.
ARTICLE 2 - COMPETENCE OF BIDDERS
2.01 Bidders must meet all qualifications and requirements as contained in the Bid Documents.
2.02 Any Bidder may be required to furnish evidence satisfactory to the City that the Bidder and its proposed subcontractors have sufficient means and experience in the type of Work required to assure satisfactory completion of all the requirements of the Contract Documents.
ARTICLE 3 - COMPLIANCE WITH CONTRACTOR’S LICENSE LAWS
3.01 Bidder’s attention is directed to the provisions of Chapter 9 of Division 3 of the California Business and Professions Code, and section 3300 of the California Public Contract Code.
3.02 If a Bidder does not possess the required Contractor’s License(s) at the time of Contract Award, in accordance with Public Contract Code §20103.5, the Bid will be considered non-responsive and will be rejected by the City. The City may require forfeiture of the Bidder’s Security.
3.03 Joint venture Bidders must possess a joint venture license. Each party to a joint venture must be properly licensed for the Work of this Project.
ARTICLE 4 - PRIOR DISQUALIFICATION
4.01 A Bid may be rejected on the basis of a Bidder, any officer of such Bidder, or any employee of such Bidder who has a proprietary interest in such Bidder, having been disqualified, removed or otherwise prevented from bidding on, or completing a federal, state or local project because of a violation of a law or a safety regulation.
4.02 The City will review the circumstances and information presented in the Bid Documents and related disclosures and certifications. The City, in its sole discretion, will determine if acceptance of any Bid is in the City’s best interest.
ARTICLE 5 - EXAMINATION OF BID DOCUMENTS AND PROJECT SITE
5.01 The Bidder must carefully examine the site of the Work and Bid Documents.
5.02 The submission of a Bid will be conclusive evidence that the Bidder has investigated and is fully aware of the conditions and difficulties that may be encountered including the availability of labor and materials to be provided, of the character, quality and quantities of Work to be performed, and of the requirements of all Bid Documents.
5.03 Where investigation of subsurface conditions has been made by the City with respect to foundation or other design aspects, Bidders may inspect the City’s records of such investigation, including examination of samples and drill cores, if any.
5.04 When logs of test borings indicating a record of the data obtained by the City’s investigation of subsurface conditions are made available, said logs represent only the investigator’s opinion as to the character of material encountered in test borings and are made available only for the convenience of bidders.
5.05 Investigation of subsurface conditions is made for the purpose of design, and the City assumes no responsibility, whatsoever, with respect to the sufficiency of test borings, accuracy of the log of test borings, of other preliminary investigations, or in the interpretation thereof. There is no warranty or guarantee, express or implied, that the conditions indicated are representative of those existing throughout the Work, or any part of it, or that unforeseen conditions may not be encountered.
5.06 No information derived from such inspection of records of preliminary investigations made by the City, or from the maps, drawings, plans, or Contract Documents relieve Bidder from any risk or from properly fulfilling all the terms of the Contract. Records of such preliminary investigations as may have been made by the City may be inspected by contacting the City’s Authorized Representative as identified in the Notice to Bidders.
5.07 Making information available to Bidders is not to be construed in any way as a waiver of the aforesaid provisions, and Bidders must satisfy themselves through their own investigations as to conditions to be encountered. Should Bidder wish to perform any inspection or investigation of the Project site so as to satisfy itself as to the condition(s) that may be encountered, Bidders shall submit a written request to the City, at least two weeks prior to the date specified for the submission of bids, identifying any reasonable inspection or investigation that Bidder wishes to perform. Thereafter, and within the sole discretion of the City, Bidder may be allowed to perform the requested inspections or investigations at the Project site subject to the express satisfaction of any conditions required by the City, including, without limitation, the procurement by Bidder of acceptable insurance coverage(s) and the performance of the requested inspections or investigations at times and locations as specified by the City.
5.08 Failure by Bidder to educate itself with available information will not relieve Bidder from responsibility for estimating properly the difficulty or cost of successfully performing the Work.
5.09 Bidders are required to inform themselves fully of the conditions relating to the construction and labor under which the Work will be or is now performed, and, so far as possible, the successful Bidder must employ such means and methods in carrying out its Work as will not cause any interruption or interference with any other contractor and/or work undertaken directly by City forces.
ARTICLE 6 - DISCREPANCIES, CONFLICTS, OMISSIONS, OR ERRORS
6.01 If any person contemplating submitting a Bid is in doubt as to the intended meaning of any part of the Bid Documents, or finds discrepancies in, or omissions in the Bid Documents, that person must submit a written request for an interpretation or correction thereof at least five (5) calendar days before the deadline for the submission of Bids.
6.02 Inquiries must be addressed to the City’s Authorized Representative identified in the Notice to Bidders, and must be submitted to the City through the City’s Planet Bid website.
6.03 Any request received fewer than five (5) calendar days before the said deadline may not be answered. The person submitting the request will be responsible for its prompt delivery.
6.04 Any interpretation or correction of the Bid Documents will be made only by written Addenda, and will be made available by the City to each person included on the City’s plan holders list for the Project. The date and time of the bid opening shall be extended by no less than 72 hours if the City issues any material changes, additions, or deletions to Bid Documents less than 72 hours prior to the closing of the time within which bids are to be received.
6.05 The City shall not be responsible for any explanation or interpretation of the Bid Documents not communicated to Bidders in written Addenda. If no written Addenda are issued relating to supposed discrepancy, conflict, omissions or errors in figuring the Work, the supposed discrepancies, conflicts, or omissions are governed by appropriate provision(s) applicable to such aspects of the Work as set forth in the Contract Documents.
ARTICLE 7 – BIDDER’S SECURITY
7.01 Each Bid must be accompanied by cash, a certified or cashier’s check, or an original Bidder’s Bond in an amount not less than ten percent (10%) of the total aggregate of the Bid, including all additive Bid items, if any, to be used in determining the low bid for the Project.
7.02 A Bid will be considered non-responsive if not accompanied by proper Bidder’s Security.
7.03 The original Bid Bond must be provided by an admitted surety, authorized to issue surety bonds in the State of California, and the surety must properly execute the Bid Bond.
7.04 Bonds and checks must be made payable to “The City of South Lake Tahoe.”
7.05 All bonds must be provided on the forms included with the Bid Documents or the Bid may be considered non-responsive.
ARTICLE 8 - BID FORMS
8.01 Prospective Bidders are furnished with a Bid Proposal form at Document 00400.
The Bid Proposal form may contain a schedule of items requesting lump sum prices. It may also state estimated quantities of various kinds of Work to be performed, or materials to be provided, with a schedule of items for which unit prices are required.
8.02 The unit prices or lump sum pricing must include full compensation for providing all labor, materials, services, tools, equipment and whatever else is required to perform all Work in accordance with the requirements of the Bid Documents.
8.03 All Bids must be submitted on the forms furnished by the City, and Bidder is solely responsible to diligently follow all directions required by the City with respect to the completion and submission of the Bid Proposal form as set forth in the Bid Documents, including these Instructions and the Bid Proposal form. A Bid Proposal not submitted on the form furnished by the City, or that does not comply with the City’s directions with respect to the completion and submission of the Bid Proposal form, may be considered non-responsive by the City in its sole discretion. The City reserves all rights to reject any or all Bids, and to waive any minor irregularity in the completion of the Bid Proposal form, within its sole discretion.
8.04 Completing the Bid Proposal form:
A. The Bidder’s name must be the same as listed on Bidder’s California State Contractor’s license.
B. Bid Price(s) must be in the manner required by the Bid Proposal form.
C. Bid Proposal form must be signed by the Bidder or duly authorized representative:
1. If the Bidder is an individual, name must be stated.
2. If the Bidder is a partnership, name of the partnership must be stated and one or more partners must sign the Bid Proposal form.
3. If the Bidder is a limited liability company, the name of the company must be stated, and the title of the person with authority to sign and bind the company must be stated.
4. If the Bidder is a corporation, the name of the corporation must be stated, the state of incorporation must be listed, the title of the person with authority to sign and bind the corporation must be stated, and the corporate seal must be affixed.
5. The Bidder’s business and mailing address must be stated.
D. Comply with all instruction as required in the Bid Documents and as set forth on the Bid Proposal form.
8.05 Required Listing of Proposed Subcontractors:
A. Failure of a Bidder to list the names and locations of all Subcontractors performing more than one-half of one percent of the value of the Work as required under the Public Contract Code, or to provide the description of the subcontracted Work performed by any listed Subcontractor, and/or to provide all information required pursuant to Document 00420 (“Designation of Subcontractors”) as part of the Bid is/are causes for the Bid to be rejected as non-responsive.
B. The attention of Bidder is directed to the provisions of the Subletting and Subcontracting Fair Practices Act, beginning with Public Contract Code §4100, related to penalties for use of unauthorized Subcontractors or by making unauthorized substitutions.
8.06 Self-Performance Requirements:
A. Pursuant to Section 5-1.13 (“Subcontracting”) of the Standard Specifications, as amended pursuant to Section 5.3 of the Special Provisions, the Bidder is required to certify that it shall perform with the Bidder’s own organization contract Work in an amount not less than 30% of the original price of the Work.
B. The Bidder must complete Document 00425 (“Self-Performance
Declaration”) and submit the same with the Bid or, alternatively, to the City within 24 hours after the time of bid opening. Failure of a Bidder to provide the Self-Performance Declaration within the time specified may result in a non-responsive bid.
ARTICLE 9 - CONTRACTING PRINCIPLES
9.01 The successful Bidder must, during the Contract Time:
A. Comply with all applicable federal, state, and local rules, regulations, codes, and laws, including, without limitation, the most recent version of the South Lake Tahoe City Code and the City of South Lake Tahoe Public Improvement and Engineering Standards.
B. Maintain financial records adequate to show that the City’s funds paid pursuant to the Contract were used for purposes consistent with the terms of the Agreement.
ARTICLE 10 - SUBMISSION OF BID FORMS
10.01 Bid Proposal forms must be completed in ink, completely filled out, and submitted on the Bid Proposal forms furnished as part of the Bid Documents. Bid Proposal forms delivered by facsimile (unless expressly authorized pursuant to the Bid Documents) or e-mail, or modifications to a Bid Proposal form delivered by facsimile, will not be considered by the City, and will be cause for the City to reject the Bid as non-responsive.
10.02 It is the sole responsibility of the Bidder to ensure that its Bid is received at the proper time and at the proper location. Bids received after the time fixed for receiving them will not be considered.
10.03 Late Bids will be returned by the City to the Bidder unopened.
10.04 Each Bid must be addressed to the Department of Public Works, City of South Lake Tahoe, and must be delivered to and received by the City Public Works Office at 1740 D Street, South Lake Tahoe, CA 96150-6251 no later than the date and time set for the opening of Bids in the published Notice to Bidders.
10.05 Each Bid must be enclosed in a sealed envelope bearing the title of the Project, Project number, the name of the Bidder and the date and time of the opening. Failure to do so may result in a premature opening of, or failure to open, such bid. Bids improperly marked may be disregarded.
ARTICLE 11 - WITHDRAWAL OF BID FORMS
11.01 Any Bid may be withdrawn at any time before the time fixed in the Notice to Bidders for the opening of Bids only by written request of the Bidder or a duly authorized representative.
11.02 Withdrawal of a Bid does not prejudice the right of the Bidder to file a new Bid at any time prior to the time fixed for receiving Bids in the Notice to Bidders.
11.03 Whether or not Bids are opened exactly at the time stated in the Notice to Bidders, a Bid will not be accepted after the time stated.
11.04 After the opening of Bids, Bids may only be withdrawn in accordance with the provisions of Public Contract Code Section 5100 through 5107, and the Bidders’ attention is directed to those provisions.
ARTICLE 12 - PUBLIC OPENING OF BIDS
12.01 Bids will be opened and read publicly at the time and place indicated in the Notice to Bidders. Bidders or their authorized agents are invited to be present.
ARTICLE 13 - REJECTION OF IRREGULAR BIDS
13.01 The City reserves the right to reject any and all Bids, in its sole discretion.
13.02 The City may, in it sole discretion, reject any Bid, including, without limitation, if there appears to be any alteration of the Bid Proposal forms, any addition or condition not called for, or any incompleteness, erasure or irregularity of any kind.
13.03 Bids not completed in ink will be rejected.
13.04 If the Bid amount or other material information is changed or revised, the change must be initialed.
ARTICLE 14 - COMPETITIVE BIDDING
14.01 More than one Bid from an individual, firm, partnership, corporation, or combination thereof, as a principal, under the same or different names will not be considered. Reasonable basis for believing that any individual, firm, partnership, corporation, or combination thereof is a principal in more than one Bid for the Work contemplated may cause the rejection of all Bids in which such individual, firm, partnership, corporation, or combination thereof is a principal.
14.02 If there is a reason for believing that collusion exists among the Bidders, any or all Bids may be rejected.
14.03 A person, firm, or corporation submitting a sub-bid to a Bidder, or who quoted prices on materials to a Bidder, is not thereby disqualified from submitting a sub-bid or quoting prices to other Bidders or from being a principal Bidder for the same Work.
14.04 Bids in which unit prices or line items are obviously unbalanced may be rejected.
14.05 Bidders are put on notice that any collusive agreement fixing the prices to be bid so as to control or affect an award of the Agreement is in violation of the competitive bidding requirements of the Public Contract Code, and may render void any Agreement let under such circumstances.
ARTICLE 15 - ESTIMATED QUANTITIES
15.01 The quantities stated in a schedule of items for which unit prices are asked to be bid are approximate only.
15.02 The quantities are given as a basis for the comparison of Bids.
15.03 The City does not, expressly or by implication, represent that the actual amount of Work will correspond with quantities given and reserves the right to increase or decrease the quantities of Work for any Bid item, or to omit portions of the Work, as the City may deem necessary or advisable.
ARTICLE 16 - SUBSTITUTION OF ALTERNATIVE MATERIALS, ARTICLES, OR
EQUIPMENT
16.01 Bids must be based upon use of items named in the Bid Documents, if applicable.
16.02 In certain cases, specific items have been named (named products) because of operational or maintenance considerations; approval of proposed equals should not be assumed by a Bidder under any circumstances.
16.03 Pursuant to Public Contract Code §3400, alternative material(s), article(s), or equipment that are of equal quality and of required characteristics for the purpose intended may be proposed provided the Bidder complies with the following requirements:
A. The proposal will not be considered unless the submittal is made within 35 calendar days after the award of the Agreement, and is accompanied by complete information and descriptive data necessary to determine equality of offered material(s), article(s) or equipment.
B. Samples must be submitted when requested by the City.
C. Burden of proof as to comparative quality, suitability, and performance of offered material(s), article(s), or equipment is the sole responsibility of the Bidder submitting the proposal.
D. Requests for approval must comply with the requirements of all applicable federal, state, and local rules, regulations and laws, including the most recent version of the South Lake Tahoe City Code and the City of South Lake Tahoe Public Improvement and Engineering Standards.
16.04 The City’s Authorized Representative, as identified in the Contract Documents, is the sole judge as to such matters involving the proposed substitution of any material, article or equipment. In the event the City’s authorized representative rejects the use of such alternative(s) submitted, then the Bidder must furnish one of the particular named products originally specified in the Bid Documents.
ARTICLE 17 - RETURN OF BIDDER’S SECURITY
17.01 Subject to California law and the requirements of the Bid Documents, if the City does not accept the Bid within the period of days after the Bid opening stated in Document 00400 (“Bid Proposal”), the City will return Bidder’s Security.
ARTICLE 18 - RELIEF OF BIDDERS
18.01 Attention is directed to the provisions of California Public Contract Code sections 5100 through 5107 that set forth the criteria and procedures for relief of Bidders, and for authorizing an award of the Agreement to another Bidder.
ARTICLE 19 -AWARD OF CONTRACT
19.01 The Agreement, if awarded, will be to that responsible Bidder submitting the lowest responsive Bid.
19.02 No Bidder may withdraw its Bid for the period of days stated in Document 00400 (“Bid Proposal”) after the date set for the opening thereof, and the Bid will be subject to acceptance by the City throughout such time period.
19.03 The time period within which award of Contract may be made is subject to an extension of such further period as may be agreed upon in writing between the City and the Bidder.
19.04 No contract is formed until all required bonds and insurance documents have been accepted by the City, and the Agreement is signed by the City.
19.05 The City reserves the right, in its sole discretion, to make any changes to the Work in accordance with the Bid Documents (and Contract Documents) at any time, including, without limitation, the deletion, addition or modification of any aspect(s) or scope(s) of the Work to be performed, whether before or after the Agreement is awarded, if at all.
ARTICLE 20 – REQUIRED CONTRACT BONDS
20.01 The successful Bidder must pay all bond premiums, costs thereof, and incidental thereto.
20.02 Each bond must be signed by both Bidder and the applicable surety(ies).
20.03 As a condition to the City signing the Agreement, the successful Bidder must file with the City on the approved forms, the two surety bonds in the amounts and for the purposes noted below, duly executed by a surety company meeting the requirements of California law (including, without limitation, Civil Code Sections 9550, et seq., and Code of Civil Procedure Section 995.311) and the Contract Documents.
20.04 The “payment bond for public works” must be in an amount of one hundred percent (100%) of the Contract Sum as determined from the prices in the Bid Proposal form, including the Base Bid and all additive and/or deductive Bid items accepted by the City and identified in the award, and shall inure to the benefit of persons performing labor or furnishing materials in connection with the Work. This bond must be maintained in full force and effect until all Work is completed and accepted by the City, and until all claims for materials and labor have been paid.
20.05 The “performance bond” must be in an amount of one hundred percent (100%) of the Contract Sum as determined from the prices in the Bid Proposal form, including the Base Bid and all additive and/or deductive Bid items accepted by the City and identified in the Agreement, and must be so conditioned as to ensure the faithful performance by Bidder of all Work. It shall also include the replacing, or making acceptable, of any defective materials or faulty workmanship during the applicable defect, warranty and/or guarantee period(s).
20.06 If any surety or sureties are deemed unsatisfactory at any time by the City, the City will notify Contractor, and Contractor must forthwith substitute a new surety or sureties satisfactory to the City. No further payment will be deemed due or made until the replacement surety or sureties qualify and are accepted by the City.
20.07 All changes to the Contract Price, Contract Time, or Contract Documents may be made without securing the consent of the surety or sureties on the bonds.
20.08 Any surety must be a California admitted surety.
ARTICLE 21 - INSURANCE
21.01 Bidder will be required to furnish to the City concurrently with Bidder’s execution of the Agreement, insurance documents evidencing coverage as required by the Contract Documents.
ARTICLE 22 - EXECUTION OF CONTRACT AGREEMENT
22.01 The form of Agreement which the successful Bidder, as Contractor, must execute, and the form of Contract bonds and insurance coverage that it must provide are included in the Bid Documents and must be carefully examined by each Bidder. All Contract bonds, policies or certificates of insurance, and insurance policy endorsements must be delivered with or before the delivery of the signed Agreement form, and must be acceptable to the City.
22.02 The Bidder to whom the Agreement is awarded by the City must,…
This is the start of the file's text. The full file is on GovTribe.