About this file
This is a Request for Proposals (RFP) issued by the City of Sacramento Department of Public Works for Construction Management Services for two bridge scour projects: the Tangerine Avenue Bridge at Elder Creek and the Watt Avenue Bridge at Arcade Creek. The City seeks qualified consulting firms to serve as the Resident Engineer and provide comprehensive construction management oversight, inspection, materials testing, contract administration, quality control, traffic management, safety monitoring, storm water quality management, public relations, claims mitigation, and document control. The Tangerine Avenue Bridge project involves installing concrete slope paving to mitigate scour and protect bridge foundations, plus repair of approximately 500 feet of channel lining east of the bridge. The Watt Avenue Bridge project includes reconstructing slope paving, extending end diaphragms, installing structure approach slabs, and installing drainage systems. A virtual pre-proposal meeting is scheduled for November 30, 2026 at 9:00 AM, with proposals due by December 11, 2026 at 11:00 AM via PlanetBids. The tentative consultant selection schedule includes interviews on January 12, 2027 (if needed), notification of results on January 19, 2027, and City Council approval anticipated in April 2027. Construction is anticipated to commence in April 2027 following contract award.
Compensation will be provided on a cost-plus-overhead-plus-fixed-fee format with a maximum 10% profit, with the specific cost estimate remaining unopened until the top-ranked firm is selected for negotiations. The Resident Engineer must be a licensed Professional Civil Engineer registered in California with a minimum of 10 years of construction management experience, and civil inspectors must have at least 7 years of related experience. Minimum insurance requirements include $1,000,000 combined single limit for Comprehensive General Liability and Automotive Liability, and $1,000,000 for Professional Errors & Omissions. The projects are locally funded by the City of Sacramento and potentially involve cost-sharing with Sacramento County and the Department of Utilities. Local Business Enterprise (LBE) participation requirements apply, with a 5% preference available if applicable. Personnel performing material testing and inspection services must comply with California Labor Code prevailing wage requirements and register with the California Department of Industrial Relations. The selected consultant must accept the City's standard Professional Services Agreement without modifications, and key personnel may not be substituted without City approval.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS
FOR
CONSTRUCTION MANAGEMENT SERVICES
FOR
TANGERINE AVENUE BRIDGE AND WATT AVENUE BRIDGE SCOUR PROJECT
(Project #: R15222210 AND R15222209) Bid #: P151111009
CITY OF SACRAMENTO
November 2026
Project Manager: Sabrina Martin Engineering Services Division
915 I Street, Room 2000 Sacramento, CA 95814
E-mail: smartin@cityofsacramento.org
Proposals Due By December 11, 2026 at 11:00 AM Department of Public Works
Uploaded to PlanetBids:
HTTPS://WWW.PLANETBIDS.COM/PORTAL/PORTAL.CFM?COMPANYID=15300
A virtual Pre-Proposal Meeting will be held at 9:00 AM on November 30, 2026
Attendance is not mandatory.
https://www.planetbids.com/portal/portal.cfm?CompanyID=15300
CONSTRUCTION MANAGEMENT SERVICES FOR
TANGERINE AVENUE BRIDGE AND WATT AVENUE BRIDGE SCOUR PROJECT
(Project #: R15222210 AND R15222209)
TABLE OF CONTENTS
INTRODUCTION
A. PROPOSAL
B. PRE-PROPOSAL MEETING
C. TENTATIVE CONSULTANT SELECTION SCHEDULE
TANGERINE AVE BRIDGE BACKGROUND
PROJECT SCHEDULE
SCOPE OF SERVICES
ATTACHMENT A – LOCATION MAP
ATTACHMENT B – PROPOSAL SUBMITTAL REQUIREMENTS
A. INTRODUCTION
B. RECOMMENDED DETAIL
ATTACHMENT C - RFP INFORMATION
ATTACHMENT D - EVALUATION CRITERIA & RATING
ATTACHMENT E - SAMPLE CONSULTANT AND PROFESSIONAL SERVICES AGREEMENT
ATTACHMENT F – LBE PARTICIPATION REQUIREMENTS
ATTACHMENT G – SAMPLE INVOICE & 10-H FORMS
ATTACHMENT H – LABOR COMPLIANCE REQUIREMENTS FOR INSPECTION SERVICES,
MATERIAL/SOIL TESTING AND SURVEYING SERVICES
ATTACHMENT I – PRELIMINARY PLANS & SPECS
ATTACHMENT J – BAN-THE-BOX REQUIREMENTS
CONSTRUCTION MANAGEMENT SERVICES FOR
TANGERINE AVENUE BRIDGE AND WATT AVENUE BRIDGE SCOUR PROJECT
(Project #: R15222210 AND R15222209)
INTRODUCTION
The City of Sacramento (City) is accepting proposals from qualified Consultants for Construction Management Services for the Tangerine Avenue Bridge at Elder Creek and Watt Avenue Bridge at Arcade Creek maintenance projects, in accordance with the included plans, specifications, terms and conditions shown in this Request for Proposals (RFP).
The objective of the contract is to have the Consultant serve as the City’s Resident Engineer along with appropriate staff required for Project inspection, materials testing, contract administration services, quality control, traffic management, safety, storm water quality, public relations and outreach, claims mitigation, document control and construction management. The Consultant’s Construction Manager shall be a licensed Professional Civil Engineer registered in the State of California, with strong general civil engineering construction skills, depth of resources, and sensitivity to local and regulatory issues. “Consultant” is the team providing construction engineering services; “Contractor” is the firm who is awarded the construction work.
The Consultant shall identify the Project team, including the Resident Engineer, to be used for this Contract. Additional staff and sub-consultants are to be brought in on an as-needed basis. The City maintains the right to request additional staff if, in its opinion, there is inadequate coverage during any phase of the Project. In addition, the City may request a substitution, at any time, for a member of the Project team including the Resident Engineer, if in the opinion of the City, the team members are not fulfilling their responsibilities. Consultant shall immediately provide a qualified substitute.
The Tangerine Avenue Bridge at Elder Creek Project is in the City of Sacramento north of the intersection of Mack Road and Tangerine Avenue. The Watt Avenue Bridge crosses Arcade Creek, between Longview Drive and Business 80. The Watt Avenue Bridge is jointly owned by the City of Sacramento and Sacramento County, as Watt Avenue serves as the boundary between the border along Watt Avenue.
The City of Sacramento is proposing to repair the Tangerine Avenue Bridge over Elder Creek (Bridge No.24C0293) by installing concrete slope paving to mitigate future scour and protect the bridge foundations as well as repair of roughly five hundred feet of channel lining east of the bridge. The City of Sacramento is proposing to repair the Watt Avenue Bridge over Arcade Creek (Bridge No.24C0177) by reconstructing the slope paving, extending the end diaphragms, installing structure approach slabs and drainage systems.
Note: The construction improvement plans for the project are being finalized for advertisement. Preliminary plans are provided with this solicitation as a reference to project scope.
A. PROPOSAL
Qualified consulting firms are invited to submit proposals to provide professional services for the project. Firms responding to this RFP shall submit:
• One (1) electronic PDF copy of the Technical Proposal.
• One (1) electronic PDF copy of the Cost Proposal containing the work plan with proposed hours and a proposed cost estimate titled “Construction Management Services for Tangerine Ave Bridge Scour Project at Elder Creek and Watt Avenue Bridge at Arcade Creek– Fee Proposal”. The cost estimate shall be submitted in a cost plus overhead plus fixed fee format with a maximum 10% profit using the City’s standard cost proposal format; see Attachment E.
Please note: The cost estimate will not be used as part of the evaluation process.
The cost estimate will be unopened until the top ranked firm is selected for negotiations. Then, the cost estimate will be downloaded and provided to the project manager.
The deadline to submit the Technical Proposal and the Cost Proposal is December 11, 2026 @ 11 AM. Both Documents must be posted to PlanetBids before this deadline. See link below.
In the event that it becomes necessary to revise any part of this RFP or provide additional information, a written electronic addendum will be issued. Any amendment to this RFP is valid only if in writing and issued by the City of Sacramento, Department of Public Works. Verbal conversations or agreements with any officer, agent, or employee of the City that modify any terms or obligations of this RFP are invalid.
All addenda for this RFP will be distributed via the PlanetBids website:
http://www.planetbids.com/portal/portal.cfm?CompanyID=15300#
It is solely the proposer’s responsibility to monitor this website for possible addenda to this RFP. Failure of proposer to retrieve addenda from the site shall not relieve him/her of the requirements contained therein. Additionally, failure of proposer to http://www.planetbids.com/portal/portal.cfm?CompanyID=15300 return a signed addendum, when required, may be cause for rejection of his/her proposal.
Refer to “Attachment B - Proposal Submittal Requirements” for additional information regarding proposal requirements. Refer to “Attachment C - RFP Information” for specific details about the consultant selection process and other City of Sacramento submission process requirements.
Additional Requirements for Material Testing, and Inspection Services
Material testing, and inspection services provided for construction projects during the preliminary engineering, design, pre-construction, construction, or post-construction phases of the project constitute “public works” under California Labor Code section 1720 et seq. and are subject to the requirements of Chapter 1 of Part 7 of Division 2 of the Labor Code and its implementing regulations set forth in Title 8 of the California Code of Regulations. If this Agreement includes any of these services (hereafter collectively referred to as “Public Work”), the Contractor and any subcontractor or subconsultant performing any Public Work shall comply with all applicable requirements of the California Labor Code and the Sacramento City Code. Please see Exhibit F of the sample Professional Services agreement included as Attachment E of this RFP.
California Labor Code section 1725.5 requires the Contractor and any subcontractor or subconsultant performing any Public Work under this Agreement to be currently registered with the California Department of Industrial Relations (DIR), as specified in Labor Code section 1725.5. Labor Code section 1771.1 provides that a contractor or subcontractor/subconsultant shall not be qualified to engage in the performance of any contract for public work, unless currently registered and qualified to perform public work pursuant to Labor Code section 1725.5.
B. PRE-PROPOSAL MEETING
A virtual pre-proposal meeting will be held on Microsoft Teams on November 30, 2026 at 9:00 AM using the following link. Attendance is highly recommended but is not mandatory.
Microsoft Teams meeting Join: https://teams.microsoft.com/meet/2920336230520082?p=TR7IYet1ly9x0Oq8tb Meeting ID: 292 033 623 052 008 2 Passcode: MD2tx9EX
Need help? | System reference https://teams.microsoft.com/meet/2920336230520082?p=TR7IYet1ly9x0Oq8tb https://aka.ms/JoinTeamsMeeting?omkt=en-US https://teams.microsoft.com/l/meetup-join/19%3ameeting_YTYwN2YxN2QtNzdlNy00NWZlLTkwNTgtZmQ4YjA0YTNmZWU3%40thread.v2/0?context=%7b%22Tid%22%3a%22e37e01f2-541b-4ffd-b8d4-76aee8b8c08d%22%2c%22Oid%22%3a%22721c5288-a595-44b7-a3a7-25a80d9d7e90%22%7d
Dial in by phone +1 213-373-7064,,957269844# United States, Los Angeles Find a local number Phone conference ID: 957 269 844# For organizers: Meeting options | Reset dial-in PIN
C. TENTATIVE CONSULTANT SELECTION SCHEDULE
Pre-Proposal Meeting November 30, 2026 @ 9 AM Last Day to Submit Questions December 3, 2026 @ 4 PM Proposal Due Date December 11, 2026 @ 11 AM Interviews January 12, 2027 (tentative, if needed) Notification of Results January 19, 2027 City Council Approval of Contract April 2027 tel:+12133737064,,957269844 https://dialin.teams.cloud.microsoft/bbfe1a1a-4f99-4753-8610-31aa724cbf08?id=957269844 https://teams.microsoft.com/meetingOptions/?organizerId=721c5288-a595-44b7-a3a7-25a80d9d7e90&tenantId=e37e01f2-541b-4ffd-b8d4-76aee8b8c08d&threadId=19_meeting_YTYwN2YxN2QtNzdlNy00NWZlLTkwNTgtZmQ4YjA0YTNmZWU3@thread.v2&messageId=0&language=en-US https://dialin.teams.cloud.microsoft/usp/pstnconferencing
TANGERINE AVE BRIDGE BACKGROUND
PROJECT OBJECTIVES
The purpose of this project is to restore the structural integrity and long-term stability of the existing Tangerine Avenue Bridge over Elder Creek. The project will address structural deficiencies associated with scour-related undermining at northern abutment while maintaining the hydraulic function of Elder Creek.
Existing Conditions
The existing Tangerine Avenue bridge at Elder Creek was constructed in 1966 as a 3-span continuous reinforced concrete (RC) slab bridge with integral bent caps supported at each pier on six 15-inch diameter RC columns on a continuous spread footing. The end diaphragm abutments are also supported on spread footings. The bridge measures 71 feet from begin bridge (BB) to end bridge (EB) and the bents are labeled from north to south on the project plans.
The bridge was first identified as requiring scour repair in the 2002 Caltrans Bridge Inspection Report (BIR). The 2005 Scour Plan of Action attributed the condition to localized scour caused by turbulent flow around an existing 30-inch diameter storm drainpipe located beneath Abutment 1. The end slopes originally consisted of unprotected natural surface at approximately 1.5H:1V before rock slope protection (RSP) was installed at both abutments around 2005.
Despite these improvements, scour-related undermining has continued to be identified at the northern abutment. Caltrans BIRs have documented exposed and partially undermined footings, displaced RSP, and loss of backfill, contributing to pavement distress and settlement near the abutment. Additionally, the existing concrete lined channel east of the bridge has deteriorated along a 470ft segment, with sections exhibiting crumbling and failure.
Proposed Improvements
Proposed improvements include pressure grouting beneath the north abutment footing to re-establish bearing along its full length and width, removal of existing RSP at the end slope of both abutments, and reconstruction of the slope at both abutments to their original grade. Concrete slope protection will be installed along the end slopes of the north and south abutments to provide long-term scour protection and slope stabilization within the existing bridge footprint. Additionally, the Project will replace concrete slope paving around the pump outlet west of the bridge, on the north bank of Elder Creek. In addition to the abutment repairs, the Project includes in-kind replacement of a 470 linear foot segment of deteriorated concrete channel lining located east of the bridge, where portions of the existing lining are crumbling and failing. The replacement will occur within the existing footprint and dimensions of the current concrete-lined channel and will not alter the channel's width, alignment, or flowline elevation. The Project is not expected to require permanent right-of-way acquisitions; however, temporary construction easements may be needed to facilitate access and staging. Utility coordination will be required due to the presence of multiple utility lines within the Project area including an existing 30-inch storm drain outlet structure in the end slope of the north abutment.
WATT AVE BRIDGE BACKGROUND
PROJECT OBJECTIVES
The purpose of Watt Avenue Bridge Project at Arcade Creek is to address existing scour damage and undermining at the bridge abutments, restore roadway transitions, and improve long-term stability. The work will improve the structural capacity of the bridge ends, restore proper roadway transitions, reconstruction of approach slabs and backfill to prevent future undermining. Updated approach slabs, drainage, and slope paving will enhance long-term performance and maintain safe access across the structure.
Existing Conditions
Watt Avenue Bridge was originally constructed in 1945 and was widened three times (in 1954, 1966, and 1971). The original portion of Watt Avenue Bridge has experienced scour damage at the abutment cutoff walls. At both original abutments, portions of the walls have been undermined, and the slope paving and bridge approach pavement has experienced settlement and distress.
Proposed Improvements
The proposed improvements to address scour and related issues are summarized below:
• Extend end diaphragms and return walls at each original abutment down approximately 5 feet to a total depth of 8 feet
• Reconstruct backfill behind original abutments from above after installation of end diaphragm and return wall extensions
• Install an approach slab drainage system
• Install structure approach slabs, modified for length (10 feet at the bridge widenings and approximately 18’-9” at the original bridge)
• Reconstruct concrete channel lining to a 1.5:1, or as steep as 1:1, slope
• Eliminate benches at top of slope protection
• Replace pull boxes and electrical conduit for streetlight near southeast corner of bridge
Environmental Review
Environmental clearance for the project has been addressed. The proposed improvements are covered under the City’s existing Routine Maintenance Agreement (RMA) with the California Department of Fish & Wildlife (CDFW). The project also qualifies for authorization under section 404 U.S Army Corps of Engineers (USACE) non-notifying Nationwide Permit 3(a) for maintenance activities. An individual Clean Water Act Section 401 Water Quality Certification is being pursued through Regional Water Quality Control Board (RWQCB). Environmental compliance and permit coordination will be required throughout construction.
Project Funding
Both projects are locally funded.
PROJECT SCHEDULE
The following is the preliminary project schedule which may be subject to change.
Advertisement of Construction Contract January 2027 Construction Contract Award April 2027 Notice to Proceed (Construction) April 2027
It is anticipated that preconstruction services will begin immediately upon execution of the agreement, but that full-time services will begin at the commencement of construction and continue until acceptance of the project.
SCOPE OF SERVICES
Listed below are tasks the consultant is expected to incorporate in the proposed Scope of Services. It is not intended that these tasks comprise a comprehensive list or are the only tasks required for this project. Each consultant team should, based on their expertise, develop a comprehensive and detailed Scope of Services necessary to provide comprehensive oversight and management of the construction contract.
The consultant will provide complete construction management services including preconstruction services, construction management, coordination, scheduling, administration, inspection, materials testing, contract administration services, quality control, traffic management, safety, biological monitoring, storm water quality, claims mitigation, and document control. Construction management, scheduling, and administration services to be provided include all construction activities undertaken by outside entities in connection with the project, as well as the monitoring and implementation of all permits, and agreement provisions associated with the project.
TYPICAL DUTIES
Typical duties to be performed by Consultant personnel will include but not be limited to the following:
• Provide technical and administrative management services for the project, coordination oversight of all activities related to the construction of the project, maintain close liaison with the Agency Project Manager, and copy Agency Project Manager(s) on all correspondence.
• Perform the duties of a Resident Engineer including construction inspection, quantity calculations, materials sampling and testing, construction surveying verification, and approve all submittals and ensure compliance with project plans, specifications, permits and agreements. Also, coordinate with the appropriate outreach communication.
• Review and monitor the contractor’s schedule (including notifying all stakeholders of any deviations) through weekly meetings, prepare daily inspection records and weekly status reports, and correspondence related to project activities.
• Identify actual and potential problems associated with the construction project and consult with the design engineer and Agency Project Manager(s) to implement engineering solutions.
• Propose solutions to problems identified
• Check construction-engineering calculations conduct submittals reviews and coordinate with design engineer.
• Maintain an awareness of safety and health requirements and enforce applicable regulations and contract provisions for the protection of the public and project personnel.
• Prepare and approve progress payments, negotiate and prepare contract change orders, and accept project completion in accordance with the State Standard Specifications and City procedures.
• Perform material testing. Testing to be performed by Caltrans certified technicians and labs and in accordance with the City’s Quality Assurance Plan (QAP).
• Prepare final record drawings at the completion of construction, as outlined in Task 4, “Post Construction Services”.
• Maintain job records in accordance with Caltrans standards.
• Evaluate cost reduction incentive proposals and provide recommendation to
Agency Project Manager(s) for acceptance or denial.
• Coordinate with the CDFW, Water Board and all other agencies involved with this project.
• Prepare a construction outreach plan, and through close communication and under the direction of the Project Manager, address public inquiries and construction related impacts as they affect the project’s stakeholders, traveling public and surrounding residential and business community.
• Review all permits and CEQA/NEPA mitigation requirements for elements related to construction and post-construction activities, as needed. Review all construction specification and site development plans to verify that all permit requirements are included and that areas to be preserved or protected during construction are clearly shown on the plans.
• Conduct any biological or cultural resource surveys required for CEQA/NEPA mitigation.
• Develop and maintain tracking system that incorporates all permit and mitigation requirements, including agency notification requirements, as needed.
• Track project compliance and required agency notification throughout construction for all permits and CEQA/NEPA construction-related mitigation measures and provide regulatory agency liaison as requested by the City Project Manager, as needed.
• Be available to provide quick response time for incidents that may arise in the field (spill incidents, BMP failure, discovery of species of concern, etc.).
• Provide storm water support to the Construction Manager throughout construction including but not limited to: review of contractors SWPPP; monthly SWPPP inspections and identification of correction actions, inspections to support preparation of the Notice of Termination (NOT) package.
• Evaluate cost reduction incentive proposals and provide recommendations to Agency Project Manager(s) for acceptance or denial.
• Coordinate closely with adjacent property owners during encroachment removals and clearing operations.
• Review and assure compliance with traffic control plans.
• Track force account work for clearing operations.
• Prepare as-builts plans.
All construction administration and inspection shall be performed in accordance with the Caltrans Local Programs and Construction Manuals.
Personnel and Performance Requirements
All personnel shall be knowledgeable of and comply with all applicable local, State, and Federal regulations; cooperate and consult with City staff during the course of the contract; and perform other duties as may be required to assure that the construction is being performed in accordance with the project plans and specifications.
The Consultant’s team shall be staffed with personnel to meet the needs and ensure delivery of a high quality project on time and within budget. Personnel shall have the following minimum qualifications and experience:
• Resident Engineer – shall be registered in the State of California as a Professional Civil Engineer with a minimum of 10 years of experience in construction management of projects similar in size and scope.
• Civil Inspector – Minimum of 7 years of experience in inspecting projects with similar improvements and elements.
• Claim/ Schedule Analyst- Consultant to provide on as needed basis, a person that is highly experienced and qualified in schedule analysis and evaluation of potential claim issues.
• Team members who have experience can use the City Construction Management Information System (CMIS).
• The construction contract requires close coordination with agencies including City of Sacramento Public Works, Department of Utilities, County of Sacramento, Caltrans, CDFW, and Water Board.
• Sub-consulting is permitted, but sub-consultants’ personnel will be considered as direct employees of the Consultant.
Materials and Services to be provided by Consultant
• Consultant shall provide all necessary safety equipment required for their personnel to perform their work efficiently and safely.
• Consultant shall provide outreach materials (if needed).
• Consultants shall provide personnel with cellular-phone and vehicles suitable for the location and nature of work involved.
• Testing to be performed by Caltrans certified technicians and labs and in accordance with the City’s Quality Assurance Plan (QAP).
A preliminary scope of services, with work items, is provided below:
Task 1 – Pre-construction Services
• Perform constructability review contract plans, specifications, easements and environmental documents. Identify issues and problems, provide owner with tabulation of issues and solutions.
• Review Resident Engineer files. Resident Engineer’s files consist of design engineer memos to Resident Engineer, and technical reports and studies.
• Prepare project instructions and establish proposed contract administration and record keeping procedures to be used during construction for review and approval by City Project Manager.
• Attend meeting with City and design consultant to discuss design features. The intent of this meeting is to answer questions from the Resident Engineer, meet key staff, and review contract administration procedures.
• Prepare for and conduct a preconstruction conference with the Contractor awarded the construction contract and City staff. The intent of this meeting is to outline major project milestones and meet key personnel.
Task 2 – Construction Management Services During Construction
This task includes project management, construction administration, scheduling, resident project observation/inspection, reviewing and approving all contractor submittals and materials testing during construction. Contract administration shall be in accordance with the Caltrans Local Program and Construction Manuals. Services include the following:
Project Coordination and Correspondence
• Serve as focal point for coordination among the contractors, surveyors, material testers, the design engineer, the City, other agencies, utility companies, and other parties.
• Maintain close contact with the City Project Manager and copy the City Project Manager on all correspondence.
• Receive all Contractor correspondence and prepare and transmit responses.
Coordinate with applicable parties as required to develop responses.
• This project requires close coordination with property owners during encroachment removals and clearing operations.
• Conduct weekly, or as necessary, construction contract coordination meetings with the Contractor. Take minutes and distribute to parties designated in the project instructions.
• Maintain contract files in a systematic and orderly manner consistent with the Caltrans Construction Manual.
Schedule Management, Progress Meetings, and Reports
• Review Contractor's planned schedule for conformance with the specifications and for reasonableness of the sequence and duration of the activities.
• Review works progress as compared to the planned schedule and notifies Contractor of schedule slippage. Analyze schedule to determine impact of weather and change orders. Obtain from Contractor updates of construction schedule incorporating actual progress, weather delays, and change order impacts.
Negotiate time extensions due to change orders, weather, and other delays.
• Prepare and submit a monthly progress report to Agency Project Manager(s) describing key issues, cost status, and schedule status.
Payment Recommendations
• Review Contractor's initial schedule of values for reasonableness and ease of monitoring.
• Prepare monthly progress payment requests, negotiate differences over amount, and process payments through the City Project Manager.
• Assist City staff segregating items for reimbursement through various agreements with Sacramento County and Department of Utilities.
Submittals Management
• Receive, stamp, and log submittals, and review and approve/distribute for review as necessary.
• Monitor the review and return of submittals to Contractor.
• Develop a submittal distribution list to identify parties responsible for review and acceptance.
Requests For Information (RFI) and Shop Drawings
• Receive, process, and monitor requests for information and shop drawings from Contractor.
• Prepare responses to RFI and shop drawings related to construction issues.
• Transmit design-related RFI's to design engineer and copy City Project Manager.
• Transmit design-related shop drawings to design engineer and copy City Project
Manager.
• Conduct meetings with Contractor and other parties as needed to discuss and resolve RFI's and shop drawing issues.
Change Orders and Claims
• Prepare change orders related to construction issues based on drawings, specifications, and other design information from design engineer and City Project Manager. Change orders shall be prepared on a monthly basis to stay ahead of the required change order authority.
• Prepare recommendations to accompany change order documents and forward to City Project Manager for review and approval.
• Perform change order administration, including obtaining City approval of change order requests, issuing proposed change orders to Contractor, maintaining logs of proposed change orders, receiving change order quotations from Contractor, negotiating change order costs and time extension, processing final negotiated change orders, and incorporating approved change orders into progress payment breakdown.
• Perform quantity and cost analysis as required for negotiation of change orders.
• Analyze additional compensation claims that are submitted during the construction period and prepare responses.
• Perform claims administration, including coordinating and monitoring claims response preparation, logging claims, and tracking claims status.
Construction Observation/Inspection Services
• Provide inspectors for day-to-day on-the-job observation/inspection of all works and improvements as shown on the plans.
• Observe, coordinate and monitor utility relocations being performed by private/public utilities.
• The inspectors shall make reasonable efforts to guard the City against defects and deficiencies in the work of the Contractor and to ensure provisions of the contract documents are being fulfilled; prepare daily inspection reports documenting observed construction activities; take progress photographs and bind and label them; mark up a field blueline set of drawings to incorporate Contractor record drawing markups; prepare punch lists; coordinate and conduct final inspection;
and assist with equipment testing and startup and other matters relating to construction of the project.
• The inspectors shall assist with monthly progress payment recommendations by making measurements of bid items on the project cost breakdown, checking the percent complete in the field, and assisting with Contractor meetings to resolve any differences in percent complete.
Quality Assurance Testing
• Schedule and perform quality assurance materials testing to verify compliance of the work with the contract documents. Maintain testing records.
• Review test reports other than field samplings, as submitted by others to substantiate contract compliance.
Task 3 – Public Relations and Outreach (Watt Ave Bridge Only)
The public relations and outreach tasks include:
• Coordinate with Contractor to obtain accurate and up to date construction information in preparation of Public Outreach publications and reports.
• Coordinate with local business owners and residents immediately adjacent to the Project for any items of work that may impact access to or use of their property.
• Prepare Public Outreach information for updates in preparation of temporary construction impacts to the traveling public.
• All notifications to be provided to the public shall be reviewed and approved by the City prior to distribution.
• Prepare Public Outreach information for updates in preparation of road closure impacts to the traveling public and distribute to both City and County as appropriate.
• Prepare regular updates to the city webpage
Task 4 - Post Construction Services
The post construction services task includes project closeout after issuance of notice of completion for the construction Contractor. This task will consolidate punch lists of remaining work, compile record drawing information, and provide one copy of a revised As–Built plans of the project drawings to the City. Final payment will be recommended and all project files (organized in an orderly manner) will be transmitted to the City for archiving.
ATTACHMENT A – LOCATION MAP
ATTACHMENT B – PROPOSAL SUBMITTAL REQUIREMENTS
A. INTRODUCTION
The purpose of these guidelines is to ensure consistency in format and content of proposals that are prepared by consultants and submitted to the City.
The proposal should contain the following information:
1) Introductory Letter
2) Office Location at which Work will be Performed
3) Qualifications and Experience of Project Manager and Team
4) Project Understanding and Approach
5) Supportive Information
6) Scope of Services
7) Project Schedule
8) References
9) Conflict of Interest Statement
10) Insurance Coverage
11) Work Hours and Cost Estimate
12) Litigation
B. RECOMMENDED DETAIL
Note: All references to the maximum number of pages are to a single side, not including tabs or section dividers. A ten (10) page maximum proposal may be submitted for required Items 1 through 5 (see above). The minimum font size for the body text shall be 11 point.
The required page limit does not apply to Items 6 through 12. An appendix may be included for supplemental information but not considered in the ranking of proposals.
1. Introductory Letter This letter should be addressed to:
City of Sacramento Department of Public Works
Engineering Services Division 915 I Street, Room 2000 Sacramento, CA 95814
Attn: Sabrina Martin, Project Manager
Indicate the name of the firm submitting the proposal, its mailing address, telephone number, and the name of an individual to contact if further information is desired. This letter should reflect the consultant’s project understanding and summarize critical issues, challenges, milestone tasks, and appropriate resourcing. This should be based on information available in this RFP, from a site visit, available documents, and from applicable regulations or requirements. This letter should also contain an expression of the consultant's interest in the work, a brief summary statement regarding the qualifications of the consultant to do the work, and a brief summary of any information about the project team or the consultant that may be useful or informative to the City.
NOTE: Along with the introductory letter, the consultant should indicate his/her acceptability of the terms and conditions of the standard consultant services agreement contained in Attachment E “Sample Consultant and Professional Services Agreement.”
To ensure uniformity and consistency with the numerous professional services the City contracts for, no modifications to the agreement will be permitted.
Cost Proposal
The Consultant shall upload a cost proposal to Planet Bids. Labor costs, other direct costs, indirect costs and profit shall be segregated in the fee proposal and submitted in the format as shown in Attachment E. This information will not be available to the Consultant Selection Panel until the top firm is selected.
2. Office Location at which Work will be performed Identify the office location or locations where the consultant and any sub-consultants will complete the work.
3. Qualifications and Experience of Project Manager and Team
An organization chart for the proposed team must be included.
Describe how the consultant team will be organized. Discuss the qualifications and experience of the consultant firm, project manager, and project team on similar projects.
Specific experience with City, state and federal projects and procedures should also be included.
NOTE: After the contract is awarded, the City Project Manager must approve any changes in key personnel before they are made. Loss of key personnel or subject matter experts by the firm without a replacement that has been approved by the City via supplement to the original contract, may result in the City terminating its contract or the selected firm.
4. Project Understanding and Approach The proposal shall include a discussion which presents the consultant’s understanding of the project and their approach to delivering the work. Identify key personnel that will be made available to the project and define their level of involvement. This description should be concise yet include sufficient detail to describe the planned approach.
This project has a mixture of funding sources, including multiple city departments and County of Sacramento. Include any special services your firm offers to meet the City’s need for timely completion and overall success in project delivery.
5. Supportive Information Supportive information may include graphs, charts, photos, etc. Information shared is to the consultant's discretion.
6. Scope of Services This proposal shall include a Scope of Services which details the work phases to be completed, the tasks to be accomplished, and the deliverables to be provided. The scope of services will ultimately become part of the contract by reference to the proposal. The consultant’s internal control for ensuring communication with City staff is adequate and timely and that submittals are complete and on time should also be discussed. This section should be concise yet include enough detail to completely describe the planned approach. Description of how the objectives will be achieved shall be presented in a logical and feasible plan.
7. Project Schedule The consultant shall prepare a schedule that is both adequate and reasonable to ensure timely completion of the tasks listed in the Scope of Services.
8. References This section should describe work which is similar in scope and complexity to the project and which the consultant team has undertaken in the last five years. A discussion of project challenges and solutions developed by the team is highly recommended. The section shall also include a summary table with the following information:
• Name of project, project cost, and date consultant services were provided
• Names of consultant’s project manager and key team personnel
• Scope of the consultant team’s assignment on the project
• Name, address, and phone number of the client project manager
A minimum of three (3) references is required for each of the following: prime consultant, any sub-consultants, Project Manager, and Key Staff on the project team. Each may be contacted by City staff. References with incorrect contact information will not count toward the required minimum.
9. Conflict of Interest Statement The prospective consultant shall disclose any financial, business, or other relationship with the City that may have an impact upon the outcome of this contract or the City construction project. The prospective consultant shall also list current clients who may have a financial interest in the outcome of this contract or the City construction project that will follow. In particular, the prospective consultant shall disclose any financial interest or relationship with any construction company that might submit a bid on the City construction project.
a. Generally, under the California Political Reform Act, Government Code §§ 81000 et seq., designated employees of the City are required to comply with the City’s Conflict of Interest Code. The term “designated employees” includes individuals working for contractors providing services or performing work for the City, if such individuals are considered to be “consultants” under the Political Reform Act. The term “consultant” generally includes individuals who make, or participate in making, governmental decisions or who serve in a staff capacity. Individuals who perform work that is solely clerical, ministerial, manual or secretarial are not “consultants.”
The City’s Conflict of Interest Code requires individuals who qualify as “consultants” to file the following statements of economic interests with the City:
(1.) An “assuming office” statement of economic interests to be filed within 30 days after execution of the agreement between the City and the contractor
(2.) Annual statements of economic interest while the agreement remains in effect, to be filed not later than April 30th of each year
(3.) A “leaving office” statement of economic interests to be filed within 30 days of completion of the contract.
The above statements of economic interests are public records subject to public disclosure under the California Public Records Act.
The City’s Conflict of Interest Code also requires individuals who qualify as “consultants” under the Political Reform Act to comply with the conflict-of-interest provisions of the Political Reform Act, which generally prohibit individuals from making or participating in the making of decisions that will have a material financial effect on their economic interests.
b. Conflict of Interest Statements. The standard agreement attached to this RFP indicates whether or not the individual(s) who will provide services or perform work pursuant to the agreement will be considered “consultants” within the meaning of the Political Reform Act and the City’s Conflict of Interest Code. The submission of a proposal in response to this RFP constitutes the proposer’s acknowledgement and agreement that, if the proposer is awarded the agreement by the City, the individuals who will provide services or perform work pursuant to the agreement will not have a conflict of interest under the City’s Conflict of Interest Code.
c. In addition, if the proposer is awarded the agreement by the City, such proposer shall cause the following to occur within 30 days after execution of the agreement:
(1.) The proposer shall identify the individuals who will provide services or perform work under the agreement as “consultants” within the meaning of the Political Reform Act and the City’s Conflict of Interest Code (2.) The proposer shall cause these individuals to file with the City Representative identified in the agreement the “assuming office” statements of economic interests required by the City’s Conflict of Interest Code (3.) Thereafter, throughout the term of the agreement, the proposer shall cause these individuals to file with the City Representative annual statements of economic interests, and “leaving office” statements of economic interests, as required by the City’s Conflict of Interest Code. The City may withhold all or a portion of any payment due under the agreement until all required statements are filed.
10. Insurance Coverage The prospective consultant shall provide a summary of the firm's insurance coverage for Comprehensive General Liability Insurance, Automotive Liability Insurance, Professional Liability Insurance, and Worker's Compensation Insurance.
For additional information regarding insurance requirements, see Attachment C, “RPF Information,” of this RFP.
11. Work Hours and Cost Estimate
The consultant shall submit their proposed fee for the project as a separate file from the proposal. The consultant shall submit their proposed work hours and project cost estimate. The estimate shall be submitted in a cost plus overhead plus fee format (City format) and should include the following detail:
• Work hours for each team member, by task, and total work hours by all members for each task.
• Billable rates of each member of the project team.
• Breakdown of direct costs, profit, indirect rate, and estimated reimbursable expenses. Mark ups on sub-consultants are not allowed.
• Project cost estimates and fee from each sub-consultant on the project team for his/her portion of the work at the same level of detail noted above.
• The 10-H form is exceedingly important for future payments. In order for future payments to efficiently be processed, the names, titles, and rates of staff should match the 10-H form. Any substitutions of key staff will need to be approved by a contract supplement agreement prior to performing work. Upon completion of negotiations with the selected firm, updated 10-H forms must be submitted to the City with the executed contract prior to award.
• The prime consultant and sub-consultants should only propose an audited indirect rate.
12. Litigation
List any lawsuit or litigation and its outcome resulting from any public agency project undertaken by your firm within the last five (5) years or any project where a claim or settlement was paid by your firm or its insurers within the last five (5) years
ATTACHMENT C - RFP INFORMATION
1. Selection Process
The selection process is described below.
A. After the period has closed for receipt of the RFP, each will be examined to determine compliance with the format requirements specified in the RFP.
Any proposal that does not meet the format requirements will be eliminated from competition and returned to the consultant. The City may reject any proposal if it is conditional, incomplete, or contains irregularities.
B. A Selection Panel (SP) will review each proposal that meets the format requirements. SP members will individually evaluate and score each in accordance with the scoring system shown in Attachment D.
C. Following independent evaluation of the proposal, the top candidates may be requested to participate in an interview which will be scored in accordance with Part 2 of the evaluation criteria contained in Attachment D.
However, the City reserves the right to determine the qualifications of the firm on the basis of the written proposal only.
D. All competitors will be notified of the results via email.
2. Late Submittal
A proposal is late if received at any time after the required submittal date and time.
A proposal received after the specified time will not be considered and will be returned to the proposer.
3. Modification or Withdrawal of Submittal
Any proposal received prior to the date and time specified above for receipt of proposal may be withdrawn or modified by written request of the consultant. To be considered, however, the modified proposal must be received by the required time and date specified.
4. Written Questions
Written questions should be submitted through the PlanetBids website where the RFP has been posted under the “Q&A” tab. Questions will be answered as they are received.
The deadline to submit questions is 4:00 PM on December 3, 2026. Questions submitted after that time will not be addressed. Responses will not be provided to questions via phone or email.
5. Signature
The proposal shall be transmitted with a cover letter that must be signed by an official authorized to bind the prospective consultant contractually.
The signed cover letter constitutes certification by the prospective firm, under penalty of perjury, of the debarment and suspension certificate required under Part 29, Title 49, CFR, and also constitutes certification under penalty of perjury, that the prospective consultant complies with non-discrimination requirements of the State and the Federal Government.
An unsigned proposal or one signed by an individual not authorized to bind the prospective firm will be rejected.
6. Insurance
The firm shall provide a summary of the firm's present and proposed insurance coverage (comprehensive general liability, professional errors and omissions (if required), automotive liability, and workers' compensation) for this project.
Minimum limits of coverage are as follows:
Comprehensive General Liability $1,000,000 combined single limit
Professional Errors & Omissions (if required) $1,000,000
Automotive Liability $1,000,000 combined single limit
Workers' Compensation (in accordance with State laws)
Prior to commencement of the work described in Scope of Services, a certificate of insurance shall be furnished stating the following:
1. That the insurer will not cancel the insured's coverage without 30 days prior written notice to the City.
2. That the City will not be responsible for any premiums or assessments on the policy.
The firm agrees that the bodily injury liability insurance herein provided for shall be in effect at all times during the term of this contract. In the event said insurance coverage expires at any time or times during the term of this contract, the firm agrees to provide, at least thirty (30) calendar days prior to said expiration date, a new certificate of insurance evidencing insurance coverage as provided for herein for not less than the remainder of the term of the contract, or for a period of not less than one (1) year. New certificates of insurance are subject to approval by the City. In the event the firm fails to keep in effect at all times insurance coverage as herein provided, the City may in addition to any other remedies it may have, terminate this contract upon occurrence of such event.
7. Property Rights
A proposal received within the prescribed deadline becomes the property of the City and all rights to the contents therein become those of the City.
8. Confidentiality
Prior to award of the contract, all proposals will be designated confidential to the extent permitted by the California Public Records Act. After award of the contract, or if not awarded, after rejection of all proposals, all responses will be regarded as public records and will be subject to review by the public. Any language purporting to render all or portions of the proposal confidential will be regarded as non-effective and will be disregarded.
9. Amendments to Request for Qualifications
The City reserves the right to amend the RFP by addendum prior to the final proposal submittal date. The City also reserves the right to extend the due date, or to cancel this RFP at any time.
10. Non-Commitment of City
This RFP does not commit the City to award a contract, to pay any costs incurred in the preparation of a proposal for this request, or to procure or contract for services. The City reserves the right to accept or reject any or all proposals received as a result of this request, to negotiate with any qualified firm or to modify or cancel in part or in its entirety the RFP if it is in the best interest of the City to do so.
11. Approval of Agreement
It is anticipated that compensation under any contract resulting from this RFP will be on a cost plus fee basis with a not-to-exceed amount. Negotiations to establish the contract amount shall take place after the consultant selection process is completed.
Any contract awarded as a result of this RFP will be awarded without discrimination based on race, color, religion, age, sex, or national origin.
The prospective consultant will be required to adhere to the provisions of a fully executed agreement. Provisions of the agreement shall be based on a standard agreement approved by the City Attorney. Attachment E is a sample of this standard agreement.
Please include a statement in your cover letter that you agree to the terms and conditions set forth in the attached agreement.
12. Execution of Agreement
The prospective firm is advised that should this RFP result in recommendation for approval of an…