Bid Notice-N-40_ Miller - Amherst - Bridge Replacement.pdf
PDF 26 MB Posted
- Attached to
- N-40, Miller - Amherst - Bridge Replacement
- Solicitation number
- STP-40-4(104)
- Issued by
- Buffalo County, Nebraska
About this file
Summary
This is a Bid Notice and Proposal Form from the Nebraska Department of Transportation (NDOT) for a bridge replacement and roadway resurfacing project on State Highway N-40 in Dawson and Buffalo Counties. The project, identified as Project No. STP-40-4(104) with Control No. 42924, involves milling and resurfacing approximately 10.94 miles of roadway with asphalt, replacing one bridge over Cherry Valley Creek (Structure S040 06642) with a new bridge, replacing one bridge over an unnamed stream (Structure S040 07244) with a concrete box culvert, repairing bridges over the Wood River (Structure S040 07115), extending a box culvert in a Wood River tributary (Structure S040 06686), replacing and updating guardrail, and performing culvert replacements and repairs. The contract is divided into 10 groups of work including grading, culverts, seeding, bridges, guardrail, electrical, bituminous, and general items. The tentative start date is June 28, 2027, with a contract duration of 391 calendar days. Bids are due August 27, 2026, at 1:30 p.m., and will be opened electronically through the BidX website. Bidders must be prequalified in Classes 9 and 10 (Bituminous and General) and are required to submit a combined bid for three call orders: 410, 415, and 405, though separate contracts will be awarded for each call order.
The project is funded through federal-aid highway construction funds and is governed by the 2017 Edition of NDOT Standard Specifications and federal requirements including FHWA Form 1273, Davis-Bacon wage determinations, and Executive Order 11246. No DBE goal has been established for this project. The contractor must comply with extensive environmental commitments including US Army Corps of Engineers Nationwide Permit NWP3 (Non-Notifying), wetland and sensitive area protections, Whooping Crane migration protocols, Bald and Golden Eagle protection measures, Section 4(f) property restrictions, and wellhead protection area requirements. The project requires a Construction Stormwater Permit and Stormwater Pollution Prevention Plan (SWPPP) covering 22 acres of soil disturbance. Contractors must manage utility conflicts with Charter Communications, Dawson Public Power District, and Frontier Communications; coordinate with the concurrent Elm Creek-Miller project (CN 42898); maintain uninterrupted two-lane traffic except during specific bridge work windows from December 1, 2027 to March 1, 2028; and implement traffic control management during certain phases. All right-of-way has been acquired except for one tract from the State Board of Education Lands and Funds, anticipated to be completed in late 2026. The project has specific restrictions on material transfer vehicle loading during asphalt placement, requirements for open-cut culvert construction using half-width operations, and prohibitions on traffic on milled surfaces exceeding 2 inches in depth for more than 14 days.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPOSAL FORM
NEBRASKA DEPARTMENT OF TRANSPORTATION
LETTING DATE: August 27, 2026
LETTING TIME: 1:30 PM
CALL ORDER: 410
CONTROL NO. SEQ. NO.: 42924 000
TENTATIVE START DATE: 06/28/2027
LOCATION: N-40, MILLER - AMHERST
IN COUNTIES: DAWSON, BUFFALO
CONTRACT ID: 42924
PROJECT NO.: STP-40-4(104)
CONTRACT TIME: 391 Calendar Days
DBE GOAL: N/A
PREQUALIFICATION CLASS: 9,10 -
BITUMINOUS, GENERAL (ALL CLASSES)
COMBINED BID REQUIREMENTS: 42899, 42924,
42925
GROUP 1
GROUP 4
GROUP 4A
GROUP 5
GROUP 6
GROUP 6A
GROUP 7
GROUP 8B
GROUP 9
GROUP 10
GRADING
CULVERTS
CULVERT AT STATION 1123+69
SEEDING
BRIDGE AT STATION 806+73.25
BRIDGE AT STATION 1055+50.00
GUARDRAIL
ELECTRICAL
BITUMINOUS
GENERAL ITEMS
-1-
P R
O F
E S
IO
NAL CIVIL
E
N G I N
E E
R
S T
A T
E
OF NEBRA
S
K A
S
E-16878
WURTELE
JARED M.
Jul 22, 2026
Miller - Amherst Project No. 40-4(104)
Contract ID 42924
- 2 -
NOTICE TO ALL BIDDERS
To report bid rigging activities, call: 1-800-424-9071
The U.S. Department of Transportation (DOT) operates the above toll-free “hotline” Monday through Friday, 8:00 a.m. to 5:00 p.m. eastern time. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should use the “hotline” to report such activities.
The “hotline” is part of the DOT’s continuing effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector General. All information will be treated confidentially, and caller anonymity will be respected.
LETTING QUESTIONS
Prior to the letting, any questions pertaining to the Special Provisions or the Plans for this project should be submitted to NDOT in a written format through the Bid Express (BidX) website at https://www.bidx.com/ne/lettings. Likewise, NDOT will post answers exclusively to the BidX website. All official answers will be identified as “Authorized by NDOT.” Questions will not be answered verbally.
The NDOT answers posted in BidX are not a part of the contract documents, are provided for information only, and are subject to change. Only the contract documents, including any addenda thereto, should be relied upon by a potential bidder when submitting a bid.
- 3 -
TABLE OF CONTENTS
DIVISION 100 – GENERAL REQUIREMENTS
SPECIAL PROSECUTION AND PROGRESS
STATUS OF UTILITIES
STATUS OF RIGHT-OF-WAY
ENVIRONMENTAL COMMITMENTS
DIVISION 100 – GENERAL REQUIREMENTS AND COVENANTS
DIVISION 200 – EARTHWORK
DIVISION 400 – LIGHTING, SIGNS, AND TRAFFIC CONTROL
DIVISION 500 – BITUMINOUS PAVEMENT
DIVISION 600 – PORTLAND CEMENT CONCRETE PAVEMENTS
DIVISION 700 – BRIDGES, CULVERTS, AND RELATED CONSTRUCTION
DIVISION 800 – ROADSIDE DEVELOPMENT AND EROSION CONTROL
DIVISION 900 – INCIDENTAL CONSTRUCTION
DIVISION 1000 – MATERIAL DETAILS
FHWA-1273 REQUIRED CONTRACT PROVISIONS FEDERAL-AID
CONSTRUCTION CONTRACTS
EXECUTIVE ORDER 11246
DAVIS-BACON WAGE DETERMINATION
TRAINING SPECIAL PROVISIONS
- 4 -
SPECIAL PROVISIONS
FOR
FEDERAL AID
PROJECT NO. 40-4(104)
GENERAL CONDITIONS
(1-1-0826)
Bids for the work contemplated in this proposal form will be received at the office of the Nebraska Department of Transportation in Room 109 of the Central Office Building at 1500 Nebraska Parkway at Lincoln, Nebraska, until the date and time shown on page 1 of the Proposal.
a. Bids submitted by mail should be addressed to the Nebraska Department of Transportation, c/o Contract Lettings Section, P.O. Box 94759, Lincoln, NE 68509-4759.
b. Bids submitted electronically over the internet, shall be submitted using www.bidx.com.
Contractors contemplating submitting a bid for this contract must submit a request to bid via the Department’s ‘Request for Bidding Document’ website at: https://dot.nebraska.gov/business-center/bid-request-planholder-registration/. An Authorization to Bid will only be issued to, and bids accepted from, Contractors who are prequalified for the Prequalification Class indicated on page 1 of the Proposal Form.
Bids will be opened, and the bid totals will be read via the Department’s designated online meeting platform immediately following the letting date and time indicated on page 1 of the Proposal. Access information for the online bid opening will be available on the BidX Letting webpage a minimum of 2 days prior to the opening, and can be found by selecting the applicable letting from: https://www.bidx.com/ne/lettings.
The 2017 Edition of the Standard Specifications for Highway Construction, including all amendments and additions thereto effective at the date of the contract, are made a part of these Special Provisions, through reference.
The Required Contract Provisions, Form FHWA 1273, (Rev. 10-23), and the Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity and Standard Federal Equal Employment Opportunity Construction Contract Specifications dated November 3, 1980, are attached to and are a part of this proposal form.
The General Wage Decision issued under the Davis-Bacon and Related Acts is attached to and is a part of this proposal form.
- 5 -
NOTICE TO BIDDERS
To be eligible for the award of this contract, bidders shall submit a completed bid for Call Order No. 410 Project No. STP-40-4(104)}, Call Order No. 415 {Project No. STP-40-4(105)}, and Call Order No. 405 {Project No. STP-183-2(112)}.
Award of Contract, if awarded, will be made on the combined bid for these Call Order Numbers.
Separate contracts will be awarded for each Call Order Number.
SPECIAL PROSECUTION AND PROGRESS
(Weight Restrictions/Milling/Asphaltic Concrete Placement)
A Class I Material Transfer Vehicle (MTV) will have load restrictions during placement of the bottom lift. The Class I MTV shall be equipped with a “warning light” system having a daytime visibility that is satisfactory to the Engineer and which activates at a pre-determined limiting value of not more than 16 tons, and remains activated until the quantity of material in the hopper becomes less than that pre-determined limiting value. [Example: Maximum hopper capacity is 25 tons and a “warning light” activates (e.g. comes on, changes color, starts blinking, etc.) when the hopper is 60% full. The “pre-determined limiting value” is 15 tons (0.6 x 25 ton)]
A Class I MTV shall not be used to place asphaltic concrete in areas of load restrictions if the MTV’s hopper is loaded with 16 tons or more of material.
When the warning light indicates that the MTV is loaded to the pre-determined limiting value, the Contractor shall immediately take steps to reduce the rate of inflow of asphaltic concrete into the MTV hopper. The MTV shall not be used to place asphaltic concrete after it has placed a nominal 50 tons (e.g. 2-truckloads) of asphaltic concrete while the warning light is activated.
Any asphaltic concrete in front of the MTV shall be relocated until the MTV reaches an approximate 10-ton loading level or less. Any damage caused while the MTV was overloaded shall be repaired to the satisfaction of Engineer at no cost to the Department of Transportation.
Before the MTV and warning light system is used, the Contractor shall provide to the field inspection team members:
1. A demonstration of the functionality of each light’s activation states (off, on, blinking variations, etc.) for all lights on the system.
2. The pre-determined limiting value (target maximum of material in the MTV’s hopper).
3. A demonstration of how the warning light system shall indicate when the pre-determined limiting value is reached.
If in the opinion of the Engineer the Contractor is unable to consistently maintain a maximum hopper capacity of not more than 16 tons, the allowance to use a Class I MTV in-place of a Class II MTV will be revoked for the entire project.
- 6 -
(Milling/Asphaltic Concrete Placement)
Traffic shall not be allowed on any surface that has been milled to a depth greater than 2 inches.
Traffic shall be limited to 14 days on any surface milled less than or equal to 2 inches. On the 15th day of traffic the Contractor shall become responsible for any and all costs of Asphaltic Concrete Patching and the cost of Temporary Traffic Control to perform patching.
(General Requirements)
1. The Plans and these Special Provisions depict phasing and construction sequences that are to be used in the construction of this project. Any deviation from these phasing and construction sequences shall require the approval of the Engineer.
2. The Contractor shall be required to install new guardrail prior to shifting traffic to the next phase(s), completing the last phase, or as directed by the Engineer.
3. Group 6 and Group 6A bridges can be constructed concurrently.
4. This time allowance was computed with the assumption that Group 6 bridges, concrete box culverts, and grading would be constructed in 2027. Asphalt milling and placement and remaining roadway construction would be constructed in 2028.
5. From December 1, 2027 to March 1, 2028 the Contractor will be allowed to work on
Group 6 Bridge, S040 06642 with lane closures, signals, and concrete protection barriers in place. The Contractor will also be allowed to perform work that does not affect uninterrupted two-lane, two-way traffic. Uninterrupted two-lane, two-way traffic is defined as uninterrupted traffic flow at the pre-construction posted speed limit. No lane closures will be allowed on the roadway during this time with the exception of the Group 6 bridge replacement.
(Traffic Control Management)
Traffic Control Management shall be utilized for the following work, unless otherwise directed by the Engineer:
Group 6, 6A, & 4A work, when a temporary signal is being utilized.
During the time when traffic control management is being paid for, it shall be provided on the entire project.
- 7 -
(Open-Cut Culverts)
1. When constructing the open cut culverts the Contractor shall be required to construct each one 1/2 at a time utilizing flagging operations. Traffic shall be returned to normal two-lane, two-way traffic at the end of each day. Any deviation from this requirement shall require approval of the Engineer.
2. If temporary shoring is necessary to construct the culvert replacements, it shall be considered subsidiary to other items of work for which direct payment is made.
(Coordination With Others)
The Contractor for this project shall be required to coordinate signing and construction activities with the Contractor for Project STP-183-2(111), Elm Creek - Miller, CN 42898. This project was let to contract in the March 12, 2026 letting. This project consists of milling and resurfacing the roadway with asphalt, adding 6’ surfaced shoulders with asphalt, culvert work, guardrail replacement, and bridge repairs and rehabilitation.
(Migratory Bird Responsibility)
1. The Contractor will be responsible for preventing migratory birds from nesting on this project until the tentative start date or an approved, earlier, Contractor-requested start date, whichever occurs first, and throughout the duration of this project, in accordance with the Standard Specifications and other provisions contained in the contract.
2. After receipt of the Notice to Proceed, and prior to the date established in the Notice to
Proceed, and after notifying the Department, the Contractor may perform any environmentally related tasks to satisfy environmental commitments or avoid environmental impacts without the charge of working or calendar days.
STATUS OF UTILITIES
Project No.: STP-40-4(104) Control No.: 42924 Location: Miller - Amherst
The following information is current as of June 26, 2026.
All utility work has been completed, or the necessary arrangements have been made for the required utility work to be undertaken and completed as required for proper coordination with
- 8 -the physical construction schedules. If any utility facilities are encountered and deemed to be in conflict during construction, the relocation work will be concurrent with construction.
The Contractor is directed to review Subsection 105.06 of the NDOT Standard Specifications for Highway Construction, 2017 Edition for additional information regarding cooperation with utilities.
The Contractor should request a utility status update at the project pre-construction conference, and/or prior to start of work. Any utility adjustments or interruption of service for the convenience of the Contractor shall be the sole responsibility of the Contractor.
To arrange for utilities to locate and flag their underground facilities, contact Nebraska One Call at 1-800-331-5666 or dial 811.
After review of the project, the following utility companies have facilities within the project limits:
Black Hills Energy Are conflicts with this facility anticipated? No Description of existing location(s) and facility type:
Black Hills Energy has a 2-inch gas main undercrossing N-40 at approximate Sta.
1226+75.
Contact Information:
Craig, Nelson, 402-461-9440, Craig.nelson@blackhillscorp.com
Charter Communications (Spectrum) Are conflicts with this facility anticipated? Yes Description of existing location(s) and facility type:
Charter Communications has buried fiber throughout the project at the following locations:
• At the beginning of the project their facilities are parallel to N-4 on the north side, continuing to Miller to an undercrossing at approximate Sta. 747+40.
• Continuing southeast on the north side of N-40 to an undercrossing at approximate Sta. 869+75.
• Continuing southeast along the south side of N-40 to the end of the project.
Description of conflict(s):
Charter Communications has conflicts at the following locations:
• Sta. 802+50 to 811+00, at the bridge replacement
• Sta 1019+73 to 1058+00, at the culvert replacement and ditch grading
• Sta. 1122+00 to 1126+00, at the bridge replacement
Relocation Work and Schedule:
Required relocations will be completed prior to the beginning of the project work.
Additional Coordination with Contractor:
Potholing may be required at this location for field verification of the facility, see the “POTHOLING” Special Provision included in this contract.
- 9 -
Additional Comments:
NDOT Utilities Unit will continue to work with Charter Communications to confirm conflicts.
Contact Information:
Wesley Turnipseed, 308-440-8707, Wesley.turnipseed@spectrum.com
Dawson Public Power District Are conflicts with this facility anticipated? Yes Description of existing location(s) and facility type:
Dawson PPD has overhead power facilities in the project area.
Description of conflict(s):
A power pole at approximate Sta. 120+90, 64’ RT will have to be removed, and the overcrossing of N-40 will be converted to an undercrossing.
Relocation Work and Schedule:
Dawson PPD is working with District 4 to confirm conflict and will relocate prior to the beginning of the project.
Gary Haines, 308-627-5248, gahines@dawsonpower.com
Frontier Communications Are conflicts with this facility anticipated? Yes Description of existing location(s) and facility type:
Frontier Communications has buried fiber facilities that run parallel to N-40 along the SW in ROW.
Description of conflict(s):
Frontier Communications is analyzing conflicts at the following locations:
• Sta. 803+50 to 811+00, at the bridge replacement
• Sta. 868+00
• Sta. 890+17, at the culvert replacement
• Sta. 898+40, at the culvert replacement
• Sta. 1020+00 to 1055+00 through the ditch grading
• Sta. 1123+69, at the bridge replacement Relocation Work and Schedule:
If conflicts are confirmed, Frontier Communications will complete relocation work prior to the beginning of the project work.
Additional Coordination with Contractor:
Potholing may be required at this location for field verification of the facility, see the “POTHOLING” Special Provision included in this contract.
Contact Information:
Dave Love, (217) 294-0993, dave.love@ervincable.com Kris Mojica , (414) 208-6395, kris.mojica@ervincable.com
Lumen(Centurylink) Are conflicts with this facility anticipated? No Description of existing location(s) and facility type:
Lumen has buried cable that runs parallel along the west side of US-183 that undercrosses N-40 at their intersection.
Andrew Harris, 531-263-1485, andrew.harris@lumen.com
- 10 -
Nebraska Public Power District Are conflicts with this facility anticipated? No Description of existing location(s) and facility type:
NPPD has overcrossings of N-40 at the following locations:
• Sta. 1070+00
• Sta. 1167+25
• Sta. 1188+50 Contact Information:
Traci Custard, 402-563-5893, TJCusta@nppd.com
Village of Amherst Are conflicts with this facility anticipated? No Description of existing location(s) and facility type:
The Village of Amherst has sewer and water facilities that are not within the project limits.
Contact Information:
Janice Taubenheim, 308-826-3441 villageofamherst@gmail.com
Village of Miller Are conflicts with this facility anticipated? No Description of existing location(s) and facility type:
The Village of Miller has sewer and water facilities that are not within the project limits.
Contact Information:
Amy Graham, 308-457-2050, villageofmiller@frontier.com
NDOT Owned Utilities There are NO existing NDOT Owned Utilities within the project limits.
- 11 -
STATUS OF RIGHT OF WAY
July 9, 2026
The right of way for Project Number 40-4(104), Control Number 42924 has been acquired and physical possession is held by the State of Nebraska and ready for the contractor’s use, except tracts listed below.
Unacquired Right-of-Way Tracts as follows:
Tract Number
Contract Name Status of Tract Anticipated Completion
Date
3 The State of Nebraska, Board of Education Lands and Funds (BELF)
Permission to occupy letter is completed, waiting on payment completion
Late 2026
Right-of-Way Tracts with Pay Items:
Tract Number
Pay Items
Station Distance
Left
Distance
Right none
• No encroachments on the old right of way.
• The Contractor will not be able to perform work on any tract listed as “Unacquired Right of Way Tracts” until legal and physical possession has been acquired by the State.
• The balance of the right of way has been acquired in accordance with the Federal Highway Administration directives covering the acquisition of real property.
• No residential occupants were required to be relocated.
• All necessary arrangements have been made for the right of way clearance to be undertaken and completed concurrently with the highway construction.
- 12 -
NOTICE TO BIDDERS
(Environmental Commitments)
1. Below are the Conservation Conditions that will be required for this project. All conditions and regulations of any permit obtained for this project shall be followed by the contractor.
CONSERVATION MEASURE FOR ENVIRONMENTALLY SENSITIVE AREAS
1. This project is permitted under the US Army Corps of Engineers (USACE) Nationwide
Permit NWP3, Non-Notifying.
2. The Contractor shall follow all Nationwide Permit General and Special Conditions and
Nebraska Regional Conditions, as applicable. Based on the project scope (NDOT Control No. 42924), the items indicated with checkmarks in the attached NWP 3 Non- Notifying Form appear to be applicable and relevant to the Contractor and Engineer.
3. Regulated Wetlands and/or Water Resources for this project have been identified and delineated by NDOT. The Contractor shall not drive through, stage, store, waste or stockpile materials and equipment within delineated wetland boundaries (Wetlands – Do Not Disturb) and/or environmentally sensitive areas (Sensitive Area – Do Not Disturb) as shown in the project plan aerial sheets and/or the erosion control plan sheets included in the plan set.
GENERAL THREATENED AND ENDANGERED SPECIES CONSERVATION CONDITIONS
CONSERVATION CONDITIONS
1. The Contractor shall fully implement conservation conditions within the project limits as shown on the plans.
EARLY CONSTRUCTION STARTS
1. Contractor requests for early construction starts shall be coordinated by the Engineer with the NDOT Environmental Section for approval to ensure avoidance of listed species sensitive lifecycle timeframes. Early start requests may require consultation with the USFWS and NGPC. Agency coordination time will vary depending on species and project location.
T&E SPECIES
1. If federal or state listed species are observed during construction, Contractor shall contact the Engineer who will contact the NDOT Environmental Section to determine if additional species conservation conditions would be required prior to continuing project construction activities. Contact NDOT Environmental for a reference of federal and state listed species. Coordination with the USFWS and NGPC may be required depending on the species identified and construction activities.
REFUELING
1. The contractor shall conduct refueling outside of those sensitive areas identified on the plans, in the contract, and/or marked in the field.
- 13 -
RESTRICTED ACTIVITIES
1. The following project activities shall, to the extent possible, be restricted to between the beginning and ending points (stationing, reference posts, mile markers, and/or section-township-range references) of the project, within the right-of-way designated on the project plans: borrow sites, burn sites, construction debris waste disposal areas, concrete and asphalt plants, haul roads, stockpiling areas, staging areas, and material storage sites.
2. For activities outside the project limits, the Contractor shall refer to the Nebraska Game and
Parks Commission website to determine which species ranges occur within the off-site area.
The Contractor shall plan accordingly for any species surveys that may be required to approve the use of a borrow site, or other off-site activities. The Contractor shall review the T&E Matrix agreement (on NDOT’s website), where species survey protocols can be found, to estimate the level of effort and timing requirements for surveys.
3. Any project related activities that occur outside of the project limits must be environmentally cleared/permitted with the Nebraska Game and Parks Commission as well as any other appropriate agencies by the contractor and those clearances/permits submitted to the Engineer prior to the start of the above listed project activities. The Contractor shall submit information such as an aerial photo showing the proposed activity site, a soil survey map with the location of the site, a plan-sheet or drawing showing the location and dimensions of the activity site, a minimum of 4 different ground photos showing the existing conditions at the proposed activity site, depth to ground water and depth of pit, and the “Platte River depletion status” of the site. The Contractor shall receive notice of acceptance from NDOT environmental, prior to starting the above listed project activities. These project activities cannot adversely affect state and/or federally listed species or designated critical habitat.
WASTE/DEBRIS
1. The Contractor shall dispose of construction waste/debris in areas or a manner that will not adversely affect state and/or federally listed species and/or designated critical habitat.
POST CONSTRUCTION EROSION CONTROL
1. Erosion control activities carried out by NDOT Maintenance or others after construction is complete, but prior to project close-out, shall adhere to any standard conservation conditions for species designated for the project limits during construction.
PLATTE RIVER DEPLETIONS
1. To the maximum extent practical, efforts will be made to design the project and select borrow sites to prevent depletions to the Platte River. If there is any potential to create a depletion, NDOT (during design) and the Contractor (for borrow sites) shall follow the current Platte River depletion protocols for coordination, minimization, and mitigation. In general, the following are considered de minimis depletions but may still require agency coordination; a project which:
a. Creates an annual depletion less than 0.1 acre feet,
b. Creates a detention basin that detains water for less than 72 hours,
c. Diverted water that will be returned to its natural basin within 30 days,
d. Creates a one-time depletion of less than 10 acre feet.
- 14 -
WHOOPING CRANE
1. Construction activities will not occur during Whooping Crane migration periods. (Spring migration: March 6 – April 29; and fall migration: October 9 – November 15).
OR
2. If construction activities occur during Whooping Crane migration periods (Spring migration: March 6 – April 29; and fall migration: October 9 – November 15), NDOT trained personnel, or a qualified biologist, will conduct surveys according to protocol at the following locations:
a. Project Alignment (prior to the start of daily construction activities)
3. If species are present, the Engineer will notify the Contractor to stop work within ½ mile of the Whooping Crane and follow the protocol to determine when work can resume (also not initiate work if species is found in the morning survey). Options for resuming work may include but are not limited to:
a. Construction activities are limited to the hours from 10:00 am to 4:00 pm
(CST) during the migration period, unless morning survey indicates Whooping Cranes are not present.
b. If a Whooping Crane is observed during the survey within ½ mile of the project but departs the area (further than ½ mile from the project), then work can resume. Document this departure according to protocol.
BALD AND GOLDEN EAGLE PROTECTION ACT
1. Suitable Bald Eagle nesting and/or roosting habitat exists within 0.5 miles of the
Environmental Study Area. If construction will begin between February 1 and April 15, a nest survey shall be completed at least 1 but not more than 14 days prior to construction.
If construction will begin between April 15 and October 1, a nest survey completed in March is sufficient, as nests will likely already be constructed if nesting will occur that year.
However, a nest survey may be completed anytime during this timeframe, as long as it is completed prior to construction. If Bald Eagles are nesting in the area, consultation with NGPC and USFWS shall occur prior to beginning construction activities. Eagle roosting surveys shall be conducted if construction occurs between October 1 and January 31.
SECTION 4(f)
1. The contractor shall not complete work, stage, stockpile, or store materials within the boundaries of the following Section 4(f) property:
a. Amherst Ballfields
2. If it is determined that temporary or permanent right-of-way is required from, or access is restricted to, a Section 4(f) property, coordination shall occur with NDOT Environmental.
- 15 -
WELLHEAD PROTECTION AREA
1. A portion of the project has been identified as being located within the Village of Miller and Village of Amherst Wellhead Protection Areas. NDOT’s Standard Specifications 107.01,
107.09 and 107.18 address the Contractor’s responsibility to keep fully informed of, observe, and comply with all federal, state, and local laws and ordinances that affect the conduct of the work.
TRAFFIC DISRUPTION
1. This project shall be constructed under traffic with lane closures controlled by approved temporary traffic control. The project shall not result in traffic disruptions requiring detours, temporary roads, or ramp closures that are greater than 30 working days.
ACCESS DISRUPTION
1. The Contractor shall maintain access to adjacent properties at all times during construction. Access may be disrupted temporarily at times due to construction activities but shall not be closed.
NIGHTTIME WORK
1. Nighttime work is not authorized for this project. Requests for nighttime work will require a re-evaluation.
HISTORIC PROPERTIES
1. No grading or project activities, including but not limited to, working, staging, borrowing, stockpiling, or storing material and/or equipment, shall occur within the boundary of the Sensitive Areas listed below:
a. STA 983+86 to STA 992+96 Lt (MM 69.80 to MM 69.90)
TOXIC METAL-BASED PAINT/LEAD
1. There is potential for lead or toxic metal-based paint to be found on the structures to be demolished or repaired. Regardless of toxicity, extreme caution shall be taken to minimize the amount of painted material or debris from causing or threatening to cause pollution of the air, land, and waters of the State. The Contractor shall create an implementation plan to dispose of paint waste in accordance with NDOT’s Standard Specification for Highway Construction Section 732 (Lead-Based Paint Removal) and Title 128 Nebraska Hazardous Waste Regulations. The Contractors implementation plan shall be provided to the Engineer.
2. Bridge Structure No. S040 06642 will be replaced or repaired. The Contractor shall create an implementation plan to recycle any lead-bearing plates and/or lead shims at a legitimate recycling facility as found in paragraph 3 (lead plate recycling) in Section 203.01 of the Standard Specification for Highway Construction and in accordance with Title 128, Nebraska Hazardous Waste Regulations. The Contractors implementation plan shall be provided to the Engineer.
- 16 -
UNEXPECTED WASTE
1. If contaminated soils/groundwater or unexpected wastes are discovered, the Contractor shall stop all work within the immediate area. The Contractor shall secure the area of the discovery and notify the Engineer. The Contractor shall not reenter the discovery area until notified by the Engineer. At the time of discovery, the Engineer and Contractor shall utilize the NDOT Unexpected Waste Action Plan (UWAP) to coordinate appropriate actions. The Contractor is required by NDOT's Standard Specification Section 107 (legal relations and responsibilities to the public) to handle and dispose of regulated material in accordance with applicable laws.
BORROW SITE
1. Any material needed shall be provided by the Contractor. The Contractor shall try to obtain borrow from an upland site to prevent depletion issues. If the borrow site is within a depletion area of concern, the Contractor shall coordinate with the appropriate agencies and NDOT to offset or minimize impacts. The Contractor shall obtain all environmental clearances and permits required for the borrow site prior to obtaining borrow material for the project.
2. The Contractor shall have a staging area for the project where material and equipment for the project is stored (e.g., re-steel, forms, etc.). The Contractor shall be required to dispose of material removed as part of the project described above and miscellaneous obstructions encountered and removed along the project. The disposal shall be the responsibility of the Contractor. A waste site may be needed. The Contractor shall be responsible to obtain all permits and clearances and all conditions of those permits shall be followed.
CONSTRUCTION STORMWATER
1. This project requires a Construction Stormwater Permit and a Storm Water Pollution Prevention
Plan (SWPPP) be maintained for the project. The Contractor shall understand the terms and conditions of the general National Pollutant Discharge Elimination System (NPDES) permit that authorizes the storm water discharges associated with activity from the construction site. For reference, the general permit is posted on the Department’s website.
- 17 -
STATUS OF ENVIRONMENTAL COMMITMENTS
- 18 -
ENVIRONMENTAL COMMITMENTS
Control No.: 42924 Project No.: STP-40-4(104)
Project Name: Miller-Amherst
Below are the Conservation Conditions that will be required for this project. All conditions and regulations of any permit obtained for this project will be followed by the contractor.
(Responsible Party for the measure is found in parentheses)
404-NWP3 Permit, Non-Notifying
This project is permitted under the US Army Corps of Engineers (USACE) Nationwide Permit NWP3, Non-Notifying.
All Nationwide Permit General and Special Conditions and Nebraska Regional Conditions will be followed, as applicable. Based on the project scope (NDOT Control No. 42924), the items indicated with checkmarks in the attached NWP 3 Non-Notifying Form appear to be applicable and relevant to the contractor and project manager. (Contractor, District Construction)
Regulated Wetlands and/or Water Resources for this project have been identified and delineated by NDOT. The Contractor shall not drive through, stage, store, waste or stockpile materials and equipment within delineated wetland boundaries (Wetlands – Do Not Disturb) and/or environmentally sensitive areas (Sensitive Area – Do Not Disturb) as shown in the project plan aerial sheets and/or the erosion control plan sheets included in the plan set.
(Contractor, District Construction)
Contact Person: Nick Jenkins, Ecologist, (402) 479-3969
General Threatened and Endangered Species Conservation Conditions
A-1 Changes in Project Scope. If there is a change in the project scope, the project limits, or environmental commitments, the Highway Project Manager shall coordinate with the NDOT Environmental Section to evaluate potential impacts prior to implementation.
Environmental commitments are not subject to change without prior written approval from the NDOT Environmental Section. (District Construction)
A-2 Conservation Conditions. Conservation conditions are to be fully implemented within the project limits as shown on the plans. (District Construction, Contractor)
A-3 Early Construction Starts. Contractor requests for early construction starts must be coordinated by the Project Construction Engineer with the NDOT Environmental Section for approval to ensure avoidance of listed species sensitive lifecycle timeframes. Early start requests may require consultation with the USFWS and NGPC. Agency coordination time will vary depending on species and project location. (District Construction, Contractor)
A-4 T&E Species. If federal or state listed species are observed during construction, the
Highway Project Manager will contact NDOT Environmental Section to determine if additional species conservation conditions would be required prior to continuing project
- 19 -construction activities. Contact NDOT Environmental for a reference of federal and state listed species. Coordination with the USFWS and NGPC may be required depending on the species identified and construction activities. (NDOT Environmental, District Construction, Contractor)
A-5 Refueling. Refueling will be conducted outside of those sensitive areas identified on the plans, in the contract, and/or marked in the field. (Contractor)
A-6 Restricted Activities. The following project activities shall, to the extent possible, be restricted to between the beginning and ending points (stationing, reference posts, mile markers, and/or section-township-range references) of the project, within the right-of-way designated on the project plans: borrow sites, burn sites, construction debris waste disposal areas, concrete and asphalt plants, haul roads, stockpiling areas, staging areas, and material storage sites.
For activities outside the project limits, the contractor should refer to the Nebraska Game and Parks Commission website to determine which species ranges occur within the off-site area. The contractor should plan accordingly for any species surveys that may be required to approve the use of a borrow site, or other off-site activities. The contractor should review the T&E Matrix agreement (on NDOT’s website), where species survey protocols can be found, to estimate the level of effort and timing requirements for surveys.
Any project related activities that occur outside of the project limits must be environmentally cleared/permitted with the Nebraska Game and Parks Commission as well as any other appropriate agencies by the contractor and those clearances/permits submitted to the District Construction Project Manager prior to the start of the above listed project activities. The contractor shall submit information such as an aerial photo showing the proposed activity site, a soil survey map with the location of the site, a plan-sheet or drawing showing the location and dimensions of the activity site, a minimum of 4 different ground photos showing the existing conditions at the proposed activity site, depth to ground water and depth of pit, and the “Platte River depletion status” of the site.
The contractor must receive notice of acceptance from NDOT environmental, prior to starting the above-listed project activities. These project activities cannot adversely affect state and/or federally listed species or designated critical habitat. (NDOT Environmental, District Construction, Contractor)
A-7 Waste/Debris. Construction waste/debris will be disposed of in areas or a manner that will not adversely affect state and/or federally listed species and/or designated critical habitat. (Contractor)
A-8 Post Construction Erosion Control. Erosion control activities carried out by NDOT
Maintenance or others after construction is complete, but prior to project close-out, shall adhere to any standard conservation conditions for species designated for the project limits during construction. (NDOT Maintenance, District Construction, Contractor)
S-2 Platte River Depletions. To the maximum extent practical, efforts will be made to design the project and select borrow sites to prevent depletions to the Platte River. If there is any potential to create a depletion, NDOT (during design) and the Contractor (for borrow sites) shall follow the current Platte River depletion protocols for coordination, minimization, and mitigation. In general, the following are considered de minimis depletions, but may still require agency coordination; a project which: a) creates an annual depletion less than 0.1 acre feet, b) creates a detention basin that detains water
- 20 -for less than 72 hours, c) diverted water that will be returned to its natural basin within 30 days, or d) creates a onetime depletion of less than 10 acre feet. (NDOT Roadway Design, Contractor)
S-3 Revegetation. All permanent seeding and plantings (excluding managed landscaped areas) shall use species and composition native to the project vicinity as shown in the Plan for the Roadside Environment. However, within the first 16 feet of the road shoulder or within high erosion prone locations, tall fescue or perennial ryegrass may be used at minimal rates to provide quick groundcover to prevent erosion, unless state or federally listed threatened or endangered plants were identified in the project area during surveys.
If listed plants were identified, any seed mix requirements identified during resource agency consultations shall be used for the project. (NDOT Environmental)
S-4 Sensitive Areas Environmentally Sensitive Areas will be marked on the plans, in the field, or in the contract by NDOT Environmental for avoidance. (NDOT Environmental, NDOT Roadway Design, District Construction)
S-5 Species Surveys If species surveys are required during the construction phase of the project (including pre-construction surveys), results will be sent by NDOT Environmental Section to the USFWS, NGPC, and if applicable the USACE. (NDOT Environmental, District Construction)
S-6 Permanent LED Lighting (NDOT Design Commitment) Only LED roadway luminaries listed on the NDOT “Nebraska Qualified Material Vendors List” will be considered for use on Nebraska highway lighting projects. Proposed changes to the following LED lighting requirements would require resource agency (USFWS and/or NGPC) coordination and approval prior to installation:
• Nominal CCT – 3000 +/- 300 K
• BUG Ratings – Maximum nominal Backlight (N/A), Uplight (0), Glare (N/A)
• Lumen Output – N/A\
Any proposed changes to the listed requirement(s) must be presented to the NDOT Environmental Section for Agency Coordination and approval.
Whooping Crane:
WC-1 Construction activities will not occur during Whooping Crane migration periods. (Spring migration: March 6 – April 29; and fall migration: October 9 – November 15). (NDOT Environmental, Construction, Contractor)
OR
WC-2 If construction activities occur during Whooping Crane migration periods (Spring migration: March 6 – April 29; and fall migration: October 9 – November 15), NDOT trained personnel, or a qualified biologist, will conduct surveys according to protocol at the following locations: Project Alignment (location of suitable habitat). (prior to the start of daily construction activities). If species are present the District will notify the
- 21 -
Contractor to stop work within 1/2 mile of the whooping crane and follow the protocol to determine when work can resume (also not initiate work if species is found in the morning survey). Options for resuming work may include but are not limited to (NDOT Environmental, Construction, Contractor):
• Construction activities are limited to the hours from 10:00 a.m. to 4:00 p.m. (CST) during the migration period, unless morning survey indicates Whooping Cranes are not present.
• If a whooping crane is observed during the survey within ½ mile of the project, but departs the area (further than ½ mile from the project), then work can resume. Document this departure according to protocol.
AND
WC-3 Herbaceous species used for re-seeding within ¼ mile of the following location: US-81 forb species. Native shrub or woody species used in restoration should reach no more
Bald and Golden Eagle Protection Act
• Suitable Bald Eagle nesting and/or roosting habitat exists within 0.5 miles of the Environmental Study Area. If construction will begin between February 1 and April 15, a nest survey must be completed at least 1 but not more than 14 days prior to construction. If construction will begin between April 15 and October 1, a nest survey completed in March is sufficient, as nests will likely already be constructed if nesting will occur that year. However, a nest survey may be completed anytime during this timeframe, as long as it is completed prior to construction. If bald eagles are nesting in the area, consultation with NGPC and USFWS will be required prior to beginning construction activities. Eagle roosting surveys will be conducted if construction occurs between October 1 and January
31. (NDOT Environmental, Contractor)
NDOT Construction Project Managers should contact NDOT Environmental at 402-479-3969 or nicholas.jenkins@nebraska.gov at least 30 days prior to construction start to schedule required surveys.
Contact Person: Nick Jenkins, Ecologist, (402) 479-3969
NEPA Commitments
4(f) Mitigation
The contractor shall not complete work, stage, stockpile or store materials within the boundaries of the following Section 4(f) properties: Amherst Ballfields. If it is determined that temporary or permanent right-of-way is required from, or access is restricted to, a Section 4(f) property, coordination shall occur with NDOT Environmental. (Contractor)
- 22 -
Wellhead Protection
A portion of the project has been identified as being located within the Village of Miller and Village of Amherst Wellhead Protection Areas. NDOT’s Standard Specifications - Section 107 address the Contractor’s responsibility to keep fully informed of, observe, and comply with all federal, state, and local laws and ordinances that affect the conduct of the work. (Contractor)
Utilities
Utility relocation or replacement is not anticipated for the project. If utility relocation or replacement is required in a later phase of the project, a re-evaluation shall be required if: (1) federal funds will be used for the utility work; or (2) the project construction contractor will be responsible for the work. If this utility work is identified during final design, the project sponsor shall initiate the reevaluation prior to project letting. If the work is identified during construction, the project sponsor shall initiate the re-evaluation prior to commencing utility work. (NDOT Environmental, NDOT District)
If either one of the above two conditions does not apply, later relocation or replacement of utilities shall be coordinated through NDOT and the Contractor per NDOTs Standard Specifications for Highway Construction, Subsection 105.06. Any environmental permits required for these utility relocations or replacements shall be the responsibility of the Utility.
(NDOT District, Utility Provider (s))
Traffic Disruption
This project shall be constructed under traffic with lane closures controlled by approved temporary traffic control. The project shall not result in traffic disruptions requiring detours, temporary roads, or ramp closures that are greater than 30 working days. (Contractor)
Access Disruption
Access to adjacent properties shall be maintained at all times during construction. Access may be disrupted temporarily at times due to construction activities but shall not be closed.
(Contractor)
Public Involvement
A minimum of one news release shall go to all local and area media, and be posted on the NDOT website, prior to the start of construction work. (NDOT District, NDOT Communications) Nighttime work is not authorized for this project. Requests for nighttime work will require a reevaluation. (Contractor)
Contact Person: Cydney Calhoun, NEPA Specialist, (402) 479-3548
Section 106 Commitments
Historic Properties:
A Sensitive Area has been identified along the alignment of this project. The Sensitive Area includes the area between STA 983+86 to STA 992+96 Lt (MM 69.80 to MM 69.90). No grading or project activities, including but not limited to, working, staging, borrowing, stockpiling, or
- 23 -storing material and/or equipment, shall occur within the boundary of the Sensitive Area(s).
(Contractor)
Contact Person: Katie Turner, Section 106 Specialist, (402) 479-3514
Hazardous Materials:
Lead
There is potential for lead or toxic metal-based paint to be found on the structures to be demolished or repaired. Extreme caution shall be taken to minimize the amount of painted material or debris from causing or threatening to cause pollution of the air, land, and waters of the State. The Contractor shall create an implementation plan to dispose of paint waste in accordance with NDOT’s Standard Specification for Highway Construction Section 732 (Lead-based Paint Removal) and Title 128 Nebraska Hazardous Waste Regulations. The Contractors implementation plan shall be provided to the HPM and documented in OnBase. (Contractor, NDOT Environmental)
Bridge Structure/s
The bridge structure/s (S040 06642) will be replaced or repaired. The Contractor shall create an implementation plan to recycle any lead-bearing plates and/or lead shims at a legitimate recycling facility as found in paragraph 3 (lead plate recycling) in Section 203.01 of the Standard Specification for Highway Construction and in accordance with Title 128, Nebraska Hazardous Waste Regulations. The Contractors implementation plan shall be provided to the HPM and documented in OnBase. (Contractor, NDOT Environmental)
Unexpected Waste
If contaminated soils/groundwater or unexpected wastes are discovered, the Contractor shall stop all work within the immediate area. The Contractor shall secure the area of the discovery and notify the Highway Project Manager (HPM). The Contractor shall not reenter the discovery area until notified by the HPM. At the time of discovery, the HPM and Contractor shall utilize the NDOT Unexpected Waste Action Plan (UWAP) to coordinate appropriate actions. The actions to be carried out by the HPM are (but not limited to): verification that the Contractor has suspended construction activities in the area of the discovery, contact the Roadside Development & Compliance Unit (RDCU) hazmat representative and make an entry into AASHTOware Project that an unexpected waste discovery was made. The HPM shall then utilize the UWAP Notification Form (NDOT Form 691) to properly document the extent and type of waste. The HPM will ensure that proper disposal of the waste and any required health and safety mitigation is implemented by the Contractor. The Contractor is required by NDOT's Standard Specification Section 107.11 (Hazardous Material Discoveries) to handle and dispose of regulated material in accordance with applicable laws.
Contractor Commitment
If contaminated soils/groundwater or unexpected wastes are discovered, the Contractor shall stop all work within the immediate area. The Contractor shall limit access to authorized personnel within the area of the discovery and notify the Highway Project Manager (HPM). The Contractor shall not reenter the discovery area until notified by the HPM. At the time of
- 24 -discovery, the HPM and Contractor shall utilize the NDOT Unexpected Waste Action Plan (UWAP) to coordinate appropriate actions. The Contractor is required by NDOT's Standard Specification Section 107.11 (Hazardous Material Discoveries) to handle and dispose of regulated material in accordance with applicable laws.
Contact Person: Aaron Bedea, Noise, Air Quality & Hazardous Materials Specialist, (402) 479-4312
Borrow Site
Any material needed shall be provided by the Contractor. The Contractor shall try to obtain borrow from an upland site to prevent depletion issues. If the borrow site is within a depletion area of concern, the Contractor shall coordinate with the appropriate agencies and NDOT to offset or minimize impacts. The Contractor shall obtain all environmental clearances and permits required for the borrow site prior to obtaining borrow material for the project.
(Contractor)
The Contractor shall have a staging area for the project where material and equipment for the project is stored (e.g. re-steel, forms, etc.). The Contractor shall be required to dispose of material removed as part of the project described above and miscellaneous obstructions encountered and removed along the project. The disposal shall be the responsibility of the Contractor. A waste site may be needed. The Contractor shall be responsible to obtain all permits and clearances, and all conditions of those permits shall be followed. (Contractor)
Contact Person: Carson Jones, Roadside Development Team Lead, (402) 479-3642
Construction Stormwater
This project requires a Construction Stormwater Permit and a Storm Water Pollution Prevention Plan (SWPPP) be maintained for the project. The Contractor shall understand the terms and conditions of the general National Pollutant Discharge Elimination System (NPDES) permit that authorizes the storm water discharges associated with activity from the construction site. For reference, the general permit is posted on the Department’s website. (Contractor)
Carson Jones, Roadside Development Team Lead, (402)…