Bid Notice-Miscellaneous Concrete Installation _ Repair As-Needed - Caswell County.pdf
PDF 1 MB Posted
- Solicitation number
- MG00533
- Issued by
- Catawba County, North Carolina
About this file
This is a bid notice and proposal document from the North Carolina Department of Transportation, Highway Division 7, for Miscellaneous Concrete Installation & Repair As-Needed services in Caswell County under Contract ID MG00533. The contractor shall provide all materials, machinery, tools, labor, and equipment necessary to perform concrete installation and repair work at various locations within the county, including curb and gutter installation, concrete driveways, sidewalks, paved ditches, and islands. The contract is structured as a Small Business Enterprise multi-year maintenance contract with an availability date of October 28, 2026, and a completion date of October 27, 2027. Sealed bids must be delivered to the NCDOT Division 7 office in Greensboro, North Carolina by 2:00 PM on October 1, 2026. The contract term is one year with an option for three additional one-year renewal periods at the Department's discretion, with a maximum limit of $1,000,000 per year. Work shall be assigned through Work Order Assignments by the Engineer, and the contractor must respond within three working days of notification.
This is a state-funded project with no federal aid. The contract does not require a general contractor's license, and bid bonds, payment bonds, and performance bonds are not required unless individual work orders exceed specified thresholds ($450,000 or greater for engineer's estimates, or $500,000 per North Carolina General Statute 44A-26). Liquidated damages are assessed based on work order value, ranging from $100 per calendar day for orders valued $0-$100,000 to $850 per calendar day for orders valued $1M-$2M. Consumer Price Index adjustments may be applied to renewal periods if the adjustment exceeds ten percent, the Department reserves the right to cancel the contract. The contractor must comply with all applicable North Carolina Standard Specifications for Roads and Structures (2024 edition), traffic control requirements, equipment idling guidelines, and nondiscrimination provisions under Title VI. All work must be performed in the United States, and the contractor must obtain appropriate plant and pest quarantine certifications if applicable to Caswell County.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MG00533 N/A Caswell County
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
HIGHWAY DIVISION 7
SMALL BUSINESS ENTERPRISE ID/IQ PROPOSAL
DATE AND TIME OF BID OPENING: OCTOBER 1, 2026, AT 2:00 PM
CONTRACT ID: MG00533
WBS ELEMENT NO.: GMR07.CAS.1P AND GMR07.CAS.2P
FEDERAL AID NO.: STATE FUNDED
COUNTY: CASWELL COUNTY
TIP NO.: N/A
MILES: 0
ROUTE NO.: N/A
LOCATION: VARIOUS LOCATIONS
TYPE OF WORK: MISCELLANEOUS CONCRETE INSTALLATION & REPAIR
AS NEEDED
NOTICE:
UNDER THE PROVISIONS OF THIS PROGRAM, A N.C. GENERAL CONTRACTOR’S LICENSE IS
NOT REQUIRED AND CONTRACT PAYMENT AND CONTRACT PERFORMANCE BONDS ARE NOT
REQUIRED. BIDDERS SHALL ALSO COMPLY WITH ALL OTHER APPLICABLE LAWS,
INCLUDING BUT NOT LIMITED TO, THOSE REGULATING THE PRACTICES OF ELECTRICAL,
PLUMBING, HEATING AND AIR CONDITIONING AND REFRIGERATION CONTRACTING AS
CONTAINED IN CHAPTER 87 OF THE GENERAL STATUTES OF NORTH CAROLINA.
THIS IS A ROADWAY PROJECT. BID BOND IS NOT REQUIRED.
NAME OF BIDDER
ADDRESS OF BIDDER
PROPOSAL FOR THE CONSTRUCTION OF
CONTRACT No. MG00533 IN CASWELL COUNTY, NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION,
RALEIGH, NORTH CAROLINA
The Bidder has carefully examined the location of the proposed work to be known as Contract
No. MG00533; has carefully examined the plans and specifications, which are acknowledged to be part of the proposal, the special provisions, the proposal, the form of contract; and thoroughly understands the stipulations, requirements and provisions. The undersigned bidder agrees to be bound upon his execution of the bid and subsequent award to him by the Department of
Transportation in accordance with this proposal. Payment and performance bonds are not required on this project. The undersigned Bidder further agrees to provide all necessary machinery, tools, labor, and other means of construction; and to do all the work and to furnish all materials, except as otherwise noted, necessary to perform and complete the said contract in accordance with the 2024 Standard Specifications for Roads and Structures by the dates(s) specified in the Project Special Provisions and in accordance with the requirements of the
Engineer, and at the unit or lump sum prices, as the case may be, for the various items given on the sheets contained herein.
The Bidder shall provide and furnish all the materials, machinery, implements, appliances and tools, and perform the work and required labor to construct and complete Contract No.
MG00533 in Caswell County, for the unit or lump sum prices, as the case may be, bid by the
Bidder in his bid and according to the proposal, plans, and specifications prepared by said
Department, which proposal, plans, and specifications show the details covering this project, and hereby become a part of this contract.
The published volume entitled North Carolina Department of Transportation, Raleigh, Standard
Specifications for Roads and Structures, January 2024 with all amendments and supplements thereto, is by reference incorporated into and made a part of this contract; that, except as herein modified, all the construction and work included in this contract is to be done in accordance with the specifications contained in said volume, and amendments and supplements thereto, under the direction of the Engineer.
If the proposal is accepted and the award is made, the contract is valid only when signed either by the Contract Officer or such other person as may be designated by the Secretary to sign for the Department of Transportation. The conditions and provisions herein cannot be changed except over the signature of the said Contract Officer or Division Engineer.
The quantities shown in the itemized proposal for the project are considered to be approximate only and are given as the basis for comparison of bids. The Department of Transportation may increase or decrease the quantity of any item or portion of the work as may be deemed necessary or expedient.
An increase or decrease in the quantity of an item will not be regarded as sufficient ground for an increase or decrease in the unit prices, nor in the time allowed for the completion of the work, except as provided for the contract.
TABLE OF CONTENTS
COVER SHEET
PROPOSAL SHEET
PROJECT SPECIAL PROVISIONS
INTERESTED PARTIES LIST NOT REQUIRED: ................................................................ G - 1
HAUL ROADS: ........................................................................................................................ G - 1
CONTRACT TIME FOR ID/IQ: .............................................................................................. G - 1
WORK ORDER ASSIGNMENT (SINGLE AWARDS) FOR ID/IQ: .................................... G - 1
BONDING REQUIREMENTS FOR ID/IQ: ............................................................................ G - 2
MOBILIZATION AND LIQUIDATED DAMAGES FOR ID/IQ: ......................................... G - 3
RENEWAL OF CONTRACT (CPI PRICE ADJUSTMENT) FOR ID/IQ: ............................ G - 3
DISPUTE RESOLUTION PROCESS FOR ID/IQ: ................................................................. G - 4
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES: ..... G - 4
INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES: ..... G - 6
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES: ..... G - 7
NO MAJOR CONTRACT ITEMS:.......................................................................................... G - 7
NO SPECIALTY ITEMS: ........................................................................................................ G - 7
FUEL PRICE ADJUSTMENT PAPER BID: .......................................................................... G - 7
SCHEDULE OF ESTIMATED COMPLETION PROGRESS: ............................................... G - 8
SMALL BUSINESS ENTERPRISE (MULTI-YEAR MAINTENANCE CONTRACTS): ... G - 9
RESTRICTIONS ON ITS EQUIPMENT AND SERVICES: .................................................. G - 9
USE OF UNMANNED AIRCRAFT SYSTEM (UAS): .......................................................... G - 9
EQUIPMENT IDLING GUIDELINES: ................................................................................... G-10
OUTSOURCING OUTSIDE THE USA: ................................................................................. G-10
ROADWAY ...............................................................................................................................R - 1
STANDARD SPECIAL PROVISIONS
AVAILABILITY OF FUNDS – TERMINATION OF CONTRACTS ................................SSP - 1
ERRATA................................................................................................................................SSP - 1
PLANT AND PEST QUARANTINES .................................................................................SSP - 4
MINIMUM WAGES .............................................................................................................SSP - 5
TITLE VI AND NONDISCRIMINATION: .........................................................................SSP - 5
ON-THE-JOB TRAINING ....................................................................................................SSP-13
UNIT PROJECT SPECIAL PROVISIONS
TRAFFIC CONTROL ............................................................................................................ TC - 1
SIGNATURE SHEETS AND FORMS .................................................................................. S - 1
BID/PAY ITEM SHEETS ....................................................................................................... T - 1
DOT EXECUTION SHEET .................................................................................................. U - 1
INSTRUCTIONS TO BIDDERS
PLEASE READ ALL INSTRUCTIONS CAREFULLY
BEFORE PREPARING AND SUBMITTING YOUR BID.
All bids shall be prepared and submitted in accordance with the following requirements. Failure to comply with any requirement may cause the bid to be considered irregular and may be grounds for rejection of the bid.
TRADITIONAL PAPER BIDS:
1. Small Business Enterprise bidders shall submit a SBE Application for Certification Form within the NC
Online Certification System on the Department’s website and have been approved by the Office of
Economic Opportunity & Compliance prior to bidding. The SBE shall submit this form for approval at a minimum of one week prior to bidding.
2. Download the entire proposal from the Connect NCDOT website and return the entire proposal with your bid.
3. Enter required information on the cover page. The “Name of Bidder” and the “Address of Bidder” should be as it appears in the Directory of Firms found on the Department’s website.
4. In accordance with Article 102-3 of the Standard Specifications, registration on the Interested Parties List is required unless SP1 G02 Interested Parties List Not Required provision is included in the proposal.
5. All entries on the itemized proposal sheet (bid form) shall be written in ink or typed.
6. The Bidder shall submit a unit price for every item on the itemized proposal sheet. The unit prices for the various contract items shall be written in figures. Unit prices shall be rounded off by the Bidder to contain no more than TWO decimal places.
7. An amount bid shall be entered on the itemized proposal sheet for every item. The amount bid for each item shall be determined by multiplying each unit cost bid by the quantity for that item, and shall be written in figures in the "Amount" column of the form.
8. The total amount bid shall be written in figures in the proper place on the bid form. The total amount bid shall be determined by adding the amounts bid for each item.
9. Changes to any entry shall be made by marking through the entry in ink and making the correct entry adjacent thereto in ink. A representative of the Bidder shall initial the change in ink. Do not use correction fluid, correction tape or similar products to make corrections.
10. The bid shall be properly executed on the included Execution of Bid – Non-collusion, Debarment and
Gift Ban Certification form. All bids shall provide the following information:
a. Complete one of the following forms: Corporation, Partnership, Limited Liability Company, Joint
Venture, Individual Doing Business in His Own Name or Individual Doing Business Under a Firm
Name, based on the business entity submitting the bid.
b. Corporations that have a corporate seal shall include it on the bid, otherwise write your corporations name in the seal location.
c. Provide the name of individual or representative submitting bid along with their position or title held on behalf of the bidder.
d. Name, signature, and position or title of witness.
11. The bid shall not contain any unauthorized additions, deletions, or conditional bids.
12. The Bidder shall not add any provision reserving the right to accept or reject an award, nor enter into a contract pursuant to an award.
13. THE ENTIRE PROPOSAL WITH THE ITEMIZED PROPOSAL SHEET AND ALL OTHER
APPLICABLE FORMS SHALL BE COMPLETED AND PLACED IN A SEALED ENVELOPE
AND SHALL BE DELIVERED TO AND RECEIVED IN THE NCDOT DIVISION OFFICE,
LOCATED AT 1584 YANCEYVILLE ST. GREENSBORO, NC 27405-6932, BY 2:00 PM ON,
OCTOBER 1, 2026.
14. The sealed bid must display the following statement on the front of the sealed envelope:
QUOTATION FOR – CONTRACT ID MG00533 – MISCELLANEOUS CONCRETE
INSTALLATION & REPAIR AS NEEDED AT VARIOUS LOCATIONS TO BE OPENED AT
2:00 PM ON, OCTOBER 1, 2026.
As well as the following information:
a. Name of the Corporation, Partnership, Limited Liability Company, Joint Venture, Individual Doing
Business in His Own Name or Individual Doing Business Under a Firm Name, submitting bid.
b. Name of the individual or representative submitting bid along with their position or title held on behalf of the bidder.
c. Address of the Corporation, Partnership, Limited Liability Company, Joint Venture, Individual Doing
Business in His Own Name or Individual Doing Business Under a Firm Name, submitting bid.
d. SAP Vendor Number of the Corporation, Partnership, Limited Liability Company, Joint Venture, Individual Doing Business in His Own Name or Individual Doing Business Under a Firm Name, submitting bid. This information can be found on the Directory of Firms found on the Department’s website.
e. Contractor License Number, if available, of the Corporation, Partnership, Limited Liability Company, Joint Venture, Individual Doing Business in His Own Name or Individual Doing Business Under a
Firm Name, submitting bid.
15. If delivered by mail, the sealed envelope shall be placed in another sealed envelope and the outer envelope shall be addressed as follows:
N. C. DEPARTMENT OF TRANSPORTATION
DIVISION OF HIGHWAYS, DIVISION 7
ATTN: Jennifer Sour
1584 Yanceyville St.
Greensboro, NC 27405-6932
16. Questions should be emailed 7 calendar days prior to the bid opening to Jennifer Sour at jsour@ncdot.gov. Contact with any other NCDOT personnel concerning this project is strictly prohibited, unless otherwise noted, and may result in bids being considered non-responsive.
MG00533 N/A G-1
Caswell County
PROJECT SPECIAL PROVISIONS - GENERAL
INTERESTED PARTIES LIST NOT REQUIRED:
(6-21-22)(Rev. 2-20-24) 102 SP1 G02
Revise the Standard Specifications as follows:
The Interested Parties List sign up process is not applicable to this contract.
Page 1-13, Article 102-3 PROPOSALS AND INTERESTED PARTIES LIST, lines 12-15, delete the first paragraph.
Page 1-14, Article 102-8 PREPARATION AND SUBMISSION OF BIDS, lines 43-44, delete the first sentence of the first paragraph.
HAUL ROADS:
(7-16-24) 105 SP1 G04
Page 1-45, Article 105-15 RESTRICTION OF LOAD LIMITS, line 31, add the following after second sentence of the second paragraph:
At least 30 days prior to use, the Contractor shall notify the Engineer of any public road proposed for use as a haul road for the project.
CONTRACT TIME FOR ID/IQ:
(2-15-22)(Rev. 4-15-25) 108 SP1 G11
The date of availability for this contract is October 28, 2026.
The completion date for this contract is October 27, 2027.
Except where otherwise provided by the contract, observation periods required by the contract will not be a part of the work to be completed by the completion date and/or intermediate contract times stated in the contract. The acceptable completion of the observation periods that extend beyond the final completion date shall be a part of the work covered by the performance and payment bonds.
Work shall be accomplished in a continuous manner once the contractor begins.
The liquidated damages for this contract will be assessed per the Mobilization and Liquidated
Damages for ID/IQ provision located elsewhere in this contract.
WORK ORDER ASSIGNMENT (SINGLE AWARDS) FOR ID/IQ:
(2-15-22)(Rev. 4-19-22) SPD 01-800A
Work orders will be assigned by the Engineer. The Contractor shall respond to the work order assignments with the anticipated start date, within three working days of notification unless
MG00533 N/A G-2
noted otherwise. Failure to complete work in accordance with contract provisions and completion date may result in liquidated damages.
For federal ID/IQ contracts, all work orders will be assigned via the Work Order Assignment
Form (Form IDIQ-1SA), and the Contractor is required to formally respond in writing for federal work orders within three working days, unless noted otherwise. The Work Order Assignment
Form will also be used for any state ID/IQ contract in which the estimated work order cost meets the threshold for Performance and Payment Bonds in accordance with the Bonding Requirements for ID/IQ provision found elsewhere in this contract. For state ID/IQ contracts in which the work order assignment doesn’t meet the threshold for bonds, the Department has the option to use the Work Order Assignment Form or other methods for work order assignments as agreed upon by the Engineer and Contractor.
The Contractor shall be required to prosecute the work in a continuous and uninterrupted manner from the time they begin the work until completion and final acceptance of the work order.
Multiple failures of the Contractor to mobilize and begin work on the work order within the agreed upon time frame or failure to complete the work within the given time frame may result in the Contractor being excluded from future work on this contract in accordance with the
Standard Specifications.
BONDING REQUIREMENTS FOR ID/IQ:
(2-15-22) SPD 01-810
For purposes of this ID/IQ contract, the following definitions apply:
Project Agreement: A transportation improvement with a defined scope of work; a written agreement between NCDOT and the Federal Government defining the extent of construction work to be undertaken in accordance with the submitted plans, specifications and estimates.
Execution of the agreement prompts the authorization to proceed (construction funding).
Project: An undertaking issued to a contractor through a Work Order Assignment. The construction under a Project Agreement may be accomplished by one or more work order assignments, from one or more ID/IQ contracts. Note that for ID/IQ contracts this definition supersedes the definition in the Standard Specifications.
Award: The issuance of a signed Work Order Assignment by NCDOT shall constitute the notice of award of a project.
In accordance with North Carolina General Statute 44A-26, bonds are required on contracts awarded for any one project that exceeds $500,000. Beyond statutory requirements, NCDOT policy requires payment and performance bonds on all projects where the engineer’s estimate is
$450,000 or greater, all Asphalt Surface Treatment projects, and projects containing the 12-month guarantee provision. The limit for waiving bonds for all bridge replacement and major bridge rehabilitation projects (latex overlays, etc.) is $300,000 based on the engineer’s estimate.
The decision of bonding of a work order assignment below the dollar amounts listed shall be at the discretion of the Division’s evaluation of the risks associated with the project.
The need for contract payment and performance bonds will be determined at the Work Order
Assignment level. The Work Order Assignment will notify the Contractor of an award of a
MG00533 N/A G-3 Caswell County project and if required, to provide contract payment and performance bonds per Article 103-7 of the Standard Specifications. The Work Order Assignment replaces the Notification of Award
Letter mentioned in Article 103-4(A) of the Standard Specifications.
MOBILIZATION AND LIQUIDATED DAMAGES FOR ID/IQ:
(2-15-22) SPD 01-820
The Contractor shall mobilize to each location he is required to perform work. There will be no direct pay for Mobilization as it will be incidental to the other bid items. The only exception is if there is an Emergency Mobilization provision within the contract.
The Contractor will be provided a Work Order Assignment for each project with location(s), estimated quantities, and liquidated damages unless waived by the Engineer. Notification will be verbal followed by a faxed or emailed signed Work Order Assignment. There will be no minimum quantities for any line item associated with a particular mobilization. The Contractor shall complete the work identified on each Work Order Assignment.
The Contractor shall mobilize and complete the work within the time specified on the Work
Order Assignment. Failure to complete the work by the completion date may result in the application of liquidated damages. Liquidated damage amounts will be based on the work order estimate and the liquidated damage table below.
Work Order Value Liquidated Damages (per calendar day)
$0 - $100K $100.00
$100K - $200K $250.00
$200K - $300K $500.00
$300K - $500K $600.00
$500K - $1M $700.00
$1M - $2M $850.00
RENEWAL OF CONTRACT (CPI PRICE ADJUSTMENT) FOR ID/IQ:
(2-15-22)(Rev. 9-19-23) SPD 01-840
The Contractor shall submit a bid for one year. At the option of the Department, this contract may be extended for Three (3) additional periods of one year each (maximum (3) three years total). Each year shall have a limit of One Million Dollars ($1,000,000.00).
The compensation payable to the contractor shall be fixed for the first twelve months of this contract. However, upon an application of renewal of the contract, or thirty days prior to the end of each contract period, the renewal contract may be adjusted to reflect the adjustment in the
Consumer Price Index over the latest twelve month period as published by the US Bureau of
Labor and Statistics at http://www.bls.gov/cpi to be applied to new work order assignments. The
Consumer Price Index for All Urban Consumers (CPI-U), US City Average, All Items, 1982-
84=100, not seasonally adjusted will be used. If the amount of the requested adjustment is more than ten percent, the Department of Transportation reserves the right to cancel this contract.
CPI adjustment values can be determined using the calculator on the NCDOT Construction website.
MG00533 N/A G-4
This price escalation method will not be applied to items of work that are separately covered under commodity price escalation clauses. No other changes in the terms, conditions, etc. of this contract will be made when an extension to the contract is implemented. The Engineer will notify the Contractor in writing 90 DAYS BEFORE THE END OF THE CONTRACT
PERIOD if the contract may be extended. The Contractor must notify the Engineer in writing
WITHIN 60 CALENDAR DAYS of his acceptance or rejection of this offer. Failure on the part of the Contractor to reply will be received as a rejection of contract extension.
DISPUTE RESOLUTION PROCESS FOR ID/IQ:
(2-15-22)(Rev. 1-16-24) SPD 01-850
If a question should arise on the contract or assignment of a work order, the contractor should notify the Engineer noted on the assignment documentation or the Division Engineer within 48 hours after the scheduled time of bid opening or work order assignment. The following should be included in the notification if applicable:
(A) the contract for which bids were solicited;
(B) the particular law, regulation, or contract specification violated;
(C) a detailed description of the alleged violation; and
(D) any other information deemed to be relevant.
Once the initial evaluation has been completed, the contractor may be asked to attend a meeting for further discussion and clarification.
Once a determination has been made, the contractor will be notified of the decision by the
Division Engineer. If the decision does not meet the satisfaction of the contractor, they have 24 hours from the Division Engineer’s notification to elevate the dispute to the Chief Engineer. The
Chief Engineer will make the final decision and will not be subject to further review by NCDOT.
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES:
(2-20-07) 108 SP1 G14 A
The Contractor shall complete the required work of installing, maintaining, and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The
Contractor shall not close or narrow a lane of traffic on INTERSTATE, NC OR US during the following time restrictions:
DAY AND TIME RESTRICTIONS
MONDAY THRU FRIDAY
SUNRISE TO SUNSET
In addition, the Contractor shall not close or narrow a lane of traffic on INTERSTATE, NC OR
US, detain and/or alter the traffic flow on or during holidays, holiday weekends, special events, or any other time when traffic is unusually heavy, including the following schedules:
MG00533 N/A G-5
HOLIDAY AND HOLIDAY WEEKEND LANE CLOSURE RESTRICTIONS
1. For unexpected occurrence that creates unusually high traffic volumes, as directed by the Engineer.
2. For New Year's Day, between the hours of SUNRISE December 31st and SUNSET
January 2nd. If New Year's Day is on a Friday, Saturday, Sunday or Monday, then until
SUNSET the following Tuesday.
3. For Easter, between the hours of SUNRISE Thursday and SUNSET Monday.
4. For Memorial Day, between the hours of SUNRISE Friday and SUNSET Tuesday.
5. For Independence Day, between the hours of SUNRISE the day before Independence
Day and SUNSET the day after Independence Day.
If Independence Day is on a Friday, Saturday, Sunday or Monday, then between the hours of SUNRISE the Thursday before Independence Day and SUNSET the Tuesday after Independence Day.
6. For Labor Day, between the hours of SUNRISE Friday and SUNSET Tuesday.
7. For Thanksgiving Day, between the hours of SUNRISE Tuesday and SUNSET
Monday.
8. For Christmas, between the hours of SUNRISE the Friday before the week of Christmas
Day and SUNSET the following Tuesday after the week of Christmas Day.
Holidays and holiday weekends shall include New Year's, Easter, Memorial Day, Independence
Day, Labor Day, Thanksgiving, and Christmas. The Contractor shall schedule his work so that lane closures will not be required during these periods, unless otherwise directed by the
Engineer.
The time of availability for this intermediate contract work shall be the time the Contractor begins to install all traffic control devices for lane closures according to the time restrictions listed herein.
The completion time for this intermediate contract work shall be the time the Contractor is required to complete the removal of all traffic control devices for lane closures according to the time restrictions stated above and place traffic in the existing traffic pattern.
The liquidated damages are Five Hundred Dollars ($ 500.00) per hour.
MG00533 N/A G-6
INTERMEDIATE CONTRACT TIME NUMBER 2 AND LIQUIDATED DAMAGES:
(2-20-07) 108 SP1 G14 A
The Contractor shall complete the required work of installing, maintaining, and removing the traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The
Contractor shall not close or narrow a lane of traffic on SECONDARY ROAD during the following time restrictions:
DAY AND TIME RESTRICTIONS
MONDAY THRU FRIDAY
SUNRISE TO SUNSET
In addition, the Contractor shall not close or narrow a lane of traffic on SECONDARY ROAD, detain and/or alter the traffic flow on or during holidays, holiday weekends, special events, or any other time when traffic is unusually heavy, including the following schedules:
HOLIDAY AND HOLIDAY WEEKEND LANE CLOSURE RESTRICTIONS
1. For unexpected occurrence that creates unusually high traffic volumes, as directed by the Engineer.
2. For New Year's Day, between the hours of SUNRISE December 31st and SUNSET
January 2nd. If New Year's Day is on a Friday, Saturday, Sunday or Monday, then until
SUNSET the following Tuesday.
3. For Easter, between the hours of SUNRISE Thursday and SUNSET Monday.
4. For Memorial Day, between the hours of SUNRISE Friday and SUNSET Tuesday.
5. For Independence Day, between the hours of SUNRISE the day before Independence
Day and SUNSET the day after Independence Day.
If Independence Day is on a Friday, Saturday, Sunday or Monday, then between the hours of SUNRISE the Thursday before Independence Day and SUNSET the Tuesday after Independence Day.
6. For Labor Day, between the hours of SUNRISE Friday and SUNSET Tuesday.
7. For Thanksgiving Day, between the hours of SUNRISE Tuesday and SUNSET
Monday.
8. For Christmas, between the hours of SUNRISE the Friday before the week of Christmas
Day and SUNSET the following Tuesday after the week of Christmas Day.
Holidays and holiday weekends shall include New Year's, Easter, Memorial Day, Independence
Day, Labor Day, Thanksgiving, and Christmas. The Contractor shall schedule his work so that lane closures will not be required during these periods, unless otherwise directed by the
MG00533 N/A G-7
The time of availability for this intermediate contract work shall be the time the Contractor begins to install all traffic control devices for lane closures according to the time restrictions listed herein.
The completion time for this intermediate contract work shall be the time the Contractor is required to complete the removal of all traffic control devices for lane closures according to the time restrictions stated above and place traffic in the existing traffic pattern.
The liquidated damages are Two Hundred Fifty Dollars ($ 250.00) per hour.
INTERMEDIATE CONTRACT TIME NUMBER 3 AND LIQUIDATED DAMAGES:
(9-21-21) 108 SP1 G14 M
For each curb ramp location on a continuous pedestrian facility, the Contractor shall complete all work required of that curb ramp location as shown in the plans.
The date of availability for each individual intermediate contract time is the date when the
Contractor elects to sever the existing continuous pedestrian facility.
The completion date for each individual intermediate contract time is the date which is seven (7) consecutive calendar days after and including the date of availability.
For each curb ramp location on a continuous pedestrian facility, the liquidated damages are Two
Hundred and Fifty Dollars ($ 250.00) per calendar day.
NO MAJOR CONTRACT ITEMS:
(2-19-02) (Rev. 8-21-07) 104 SP1 G31
None of the items included in this contract will be major items.
NO SPECIALTY ITEMS:
(7-1-95)(Rev. 1-16-24) 108-6 SP1 G34
None of the items included in this contract will be specialty items (see Article 108-6 of the
Standard Specifications).
FUEL PRICE ADJUSTMENT PAPER BID:
(11-15-05)(Rev. 1-16-24) 109-8 SP1 G44
Page 1-82, Article 109-8, FUEL PRICE ADJUSTMENTS, add the following:
The base index price for DIESEL #2 FUEL is $ 4.3487 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment.
MG00533 N/A G-8
The pay items and the fuel factor used in calculating adjustments to be made will be as follows:
Description Units Fuel Usage
Factor Diesel
Unclassified Excavation Gal/CY 0.29
Borrow Excavation Gal/CY 0.29
Class IV Subgrade Stabilization Gal/Ton 0.55
Aggregate Base Course Gal/Ton 0.55
Sub-Ballast Gal/Ton 0.55
Erosion Control Stone Gal/Ton 0.55
Rip Rap, Class _____ Gal/Ton 0.55
Asphalt Concrete Base Course, Type ____ Gal/Ton 0.90 or 2.90
Asphalt Concrete Intermediate Course, Type ____ Gal/Ton 0.90 or 2.90
Asphalt Concrete Surface Course, Type ____ Gal/Ton 0.90 or 2.90
Open-Graded Asphalt Friction Course Gal/Ton 0.90 or 2.90
Permeable Asphalt Drainage Course, Type ____ Gal/Ton 0.90 or 2.90
Sand Asphalt Surface Course, Type ____ Gal/Ton 0.90 or 2.90
Ultra-thin Bonded Wearing Course Gal/Ton 0.90 or 2.90
Aggregate for Cement Treated Base Course Gal/Ton 0.55
Portland Cement for Cement Treated Base Course Gal/Ton 0.55
> 11" Portland Cement Concrete Pavement Gal/SY 0.327
Concrete Shoulders Adjacent to > 11” Pavement Gal/SY 0.327
9” to 11" Portland Cement Concrete Pavement Gal/SY 0.272
Concrete Shoulders Adjacent to 9” to 11” Pavement Gal/SY 0.272
< 9” Portland Cement Concrete Pavement Gal/SY 0.245
Concrete Shoulders Adjacent to < 9” Pavement Gal/SY 0.245
For the asphalt items noted in the chart as eligible for fuel adjustments, the bidder may include the Fuel Usage Factor Adjustment Form for Paper Bid with their bid submission if they elect to use the fuel usage factor. The Fuel Usage Factor Adjustment Form for Paper Bid is included toward the end of this paper bid document when asphalt items noted in the chart as eligible for fuel adjustments are part of the project.
Select either 2.90 Gal/Ton fuel factor or 0.90 Gal/Ton fuel factor for each asphalt line item on the Fuel Usage Factor Adjustment Form for Paper Bid. The selected fuel factor for each asphalt item will remain in effect for the duration of the contract.
Failure to complete the Fuel Usage Factor Adjustment Form for Paper Bid will result in using
2.90 gallons per ton as the Fuel Usage Factor for Diesel for the asphalt items noted above. The contractor will not be permitted to change the Fuel Usage Factor after the bids are submitted.
SCHEDULE OF ESTIMATED COMPLETION PROGRESS:
(7-15-08)(Rev. 6-16-26) 108-2 SP1 G58
The Contractor's attention is directed to the Standard Special Provision entitled Availability of
Funds Termination of Contracts included elsewhere in this proposal. The Department of
Transportation's schedule of estimated completion progress for this project as required by that
Standard Special Provision is as follows:
MG00533 N/A G-9
The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the
SMALL BUSINESS ENTERPRISE (MULTI-YEAR MAINTENANCE CONTRACTS):
(4-20-21)(Rev. 2-15-22) SP1 G74
This contract is a multi-year maintenance contract let pursuant to the Small Business Enterprise provisions of N.C. General Statute §136-28.10. No minimum quantity of services is guaranteed to be awarded bidders under this contract. In accordance with N.C. General Statute §136-28.10, an award in a contract may be for an amount less but shall not exceed $1,000,000 per year. No payments in excess of this amount will be disbursed, in accordance with the Statute.
RESTRICTIONS ON ITS EQUIPMENT AND SERVICES:
(11-17-20) SP01 G090
All telecommunications, video or other ITS equipment or services installed or utilized on this project must be in conformance with UNIFORM ADMINISTRATIVE REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS 2 CFR, §
200.216 Prohibition on certain telecommunications and video surveillance services or equipment.
USE OF UNMANNED AIRCRAFT SYSTEM (UAS):
(8-20-19)(Rev. 3-17-26) SP1 G092
The Contractor shall adhere to all Federal, State and Local regulations and guidelines for the use of Unmanned Aircraft Systems (UAS). This includes but is not limited to US 14 CFR Part 107, NC GS 15A-300, American Security Drone Act of 2023 (ASDA), Office of Management and
Budget (OMB) Memorandum M-26-02, all FAA rules, regulations and policies and all NCDOT
UAS Policies. The required operator certifications include possessing a current Federal Aviation
Administration (FAA) Remote Pilot Certificate, as well as operating a UAS registered with the
FAA.
All UAS operations shall be approved by the Engineer prior to beginning the operations.
All contractors or subcontractors operating UAS shall have UAS specific general liability insurance to cover all operations under this contract.
The use of UAS is at the Contractor’s discretion. No measurement or payment will be made for the use of UAS. In the event that the Department directs the Contractor to utilize UAS, payment will be in accordance with Article 104-7 Extra Work.
Fiscal Year Progress (% of Dollar Value)
2027 (7/01/26 - 6/30/27) 22% of Total Amount Bid
2028 (7/01/27 - 6/30/28) 34% of Total Amount Bid
2029 (7/01/28 - 6/30/29) 33% of Total Amount Bid
2030 (7/01/29 - 6/30/30) 11% of Total Amount Bid
MG00533 N/A G-10
EQUIPMENT IDLING GUIDELINES:
(1-19-21) 107 SP1 G096
Exercise reduced fuel consumption and reduced equipment emissions during the construction of all work associated with this contract. Employees engaged in the construction of this project should turn off vehicles when stopped for more than thirty (30) minutes and off-highway equipment should idle no longer than fifteen (15) consecutive minutes.
These guidelines for turning off vehicles and equipment when idling do not apply to:
1. Idling when queuing.
2. Idling to verify the vehicle is in safe operating condition.
3. Idling for testing, servicing, repairing or diagnostic purposes.
4. Idling necessary to accomplish work for which the vehicle was designed (such as operating a crane, mixing concrete, etc.).
5. Idling required to bring the machine system to operating temperature.
6. Emergency vehicles, utility company, construction, and maintenance vehicles where the engines must run to perform needed work.
7. Idling to ensure safe operation of the vehicle.
8. Idling when the propulsion engine is providing auxiliary power for other than heating or air conditioning. (such as hydraulic systems for pavers)
9. When specific traffic, safety, or emergency situations arise.
10. If the ambient temperature is less than 32 degrees Fahrenheit. Limited idling to provide for the safety of vehicle occupants (e.g. to run the heater).
11. If the ambient temperature is greater than 90 degrees Fahrenheit. Limited idling to provide for the safety of vehicle occupants of off-highway equipment (e.g. to run the air conditioning) no more than 30 minutes.
12. Diesel powered vehicles may idle for up to 30 minutes to minimize restart problems.
Any vehicle, truck, or equipment in which the primary source of fuel is natural gas or electricity is exempt from the idling limitations set forth in this special provision.
OUTSOURCING OUTSIDE THE USA:
(9-21-04) (Rev. 5-16-06) SP1 G150
All work on consultant contracts, services contracts, and construction contracts shall be performed in the United States of America. No work shall be outsourced outside of the United
States of America.
Outsourcing for the purpose of this provision is defined as the practice of subcontracting labor, work, services, staffing, or personnel to entities located outside of the United States.
The North Carolina Secretary of Transportation shall approve exceptions to this provision in writing.
MG00533 N/A R-1
PROJECT SPECIAL PROVISIONS – ROADWAY
BURNING RESTRICTIONS:
(7-1-95) 200, 210, 215 SP2 R05
Open burning is not permitted on any portion of the right-of-way limits established for this project. Do not burn the clearing, grubbing or demolition debris designated for disposal and generated from the project at locations within the project limits, off the project limits or at any waste or borrow sites in this county. Dispose of the clearing, grubbing and demolition debris by means other than burning, according to state or local rules and regulations.
GENERAL
(6-10-2012) (REV12-10-24) Div. 7, Dist. 2
The Contractor shall perform the work in accordance with Sections 825, 840, 846, 848, 850 and
852 of the 2024 North Carolina Department of Transportation Standard Specifications for
Roads and Structures. All workmanship and the appearance of all work shall be to the satisfaction of the Engineer.
The Contractor shall provide all materials, equipment, tools, miscellaneous items, and traffic control needed to perform the work.
There will be no less than 20 linear feet of curb and gutter or 4 square yards for concrete driveways or 4 square yards of concrete paved ditches or 4 square yards of islands required for each notification. Quantities may be met through work at more than one location.
The Contractor shall be responsible for all excavation required to install curb and gutter, concrete driveways, concrete paved ditches, and islands. All forming materials, traffic control, labor, tools, and other necessary materials to complete the work shall be provided by the Contractor.
The Contractor shall perform all backfilling work for all items. Backfill shall be placed adjacent to the new concrete no sooner than three (3) curing days after placement and no later than four
(4) days after the three (3) curing days have elapsed. The backfill shall be compacted to a degree comparable to the adjacent undisturbed material.
No additional payment will be made for “Backfilling” as it is considered a part of the work to be completed under the various pay items.
For the bid items specified as “Remove and Replace”, no additional compensation will be made for saw-cutting, removing, and properly disposing of construction debris or excess soil. Proof of disposal at an approved facility shall be required. Illegal dumping will result in the Contractor being declared in default and may result in removal from the bidder’s list.
The Contractor shall seed and mulch all disturbed areas and remove any spoil material, construction debris or excess dirt resulting from the work.
MG00533 N/A R-2
There will be no payment for seeding and mulching disturbed areas or for the removal of any spoil material, debris or excess dirt resulting from this work as it will be considered incidental to the pay items in the contract.
All excavation, forming, tools, removal of waste debris, etc. shall be considered incidental to the contract and no further compensation will be made.
MATERIAL REQUIREMENTS
(6-10-2012) (4-14-22) Div. 7, Dist. 2
Materials shall meet the requirements listed in the 2024 North Carolina Department of
Transportation Standard Specifications for Roads and Structures and will be subject to inspection and testing.
The Contractor shall provide Class B concrete from a State approved plant. Mix designs for a particular plant must be approved by the N. C. Division of Highways’ Laboratory in Raleigh.
Admixtures such as “retarder” from an approved source may be used as needed.
INCIDENTAL CONCRETE CONSTRUCTION
12-10-24 (REV 9/3/26) DIV 7
Construct incidental concrete items in accordance with Section 825 of the North Carolina
Department of Transportation 2024 Standard Specifications for Roads and Structures and the following exceptions and or additions.
Page 8-15, Subarticle 825-1 DESCRIPTION, add the following paragraph:
Construct incidental concrete items as shown on the plans or as directed by the Engineer. This work includes but is not limited to construction of parking aprons, slabs, minor foundation footings, bollards, coping, and other concrete castings.
Page 8-18, Subarticle 825-11 MEASUREMENT AND PAYMENT, replace the first and second paragraph with the following paragraphs:
Incidental Concrete Construction will be measured from the dimensions shown on the plans or from revised dimensions authorized by the Engineer and paid as the actual number of cubic yards of cast in place concrete that has been incorporated into the accepted work. Such price includes, but is not limited to excavating and backfilling; sawing the existing concrete joints;
furnishing and installing form work; furnishing and placing concrete; and constructing and sealing joints.
Payment will be made under:
Pay Item Pay Unit
Incidental Concrete Construction Cubic Yard
MG00533 N/A R-3
REMOVE AND REPLACE 2' - 6" CONCRETE CURB & GUTTER:
(6-27-07)(Rev. 11-19-24) 846 SPI 8-54
Description
Remove existing concrete curb & gutter and replace with 2’ - 6" concrete curb & gutter in accordance with Section 846 of the Standard Specifications, the plans, this special provision and as directed by the Engineer.
Construction Methods
All work for this item shall be in accordance with Section 846 of the Standard Specifications with the following exception:
Disposal of existing 2’ – 6” concrete curb & gutter in accordance with federal, state and local regulations will be incidental to the work.
Measurement and Payment
Remove and Replace 2’ – 6” Concrete Curb & Gutter will be measured and paid for in units of linear feet for the actual number of liner feet that have been completed and accepted. Such price and payment includes, but is not limited to, providing all materials, removal and disposal of existing curb & gutter, excavating and backfilling, forming, placing all concrete, finishing, constructing and sealing joints, and all incidentals necessary to complete the work.
Remove and Replace 2’ - 6” Concrete Curb & Gutter Linear Foot
REMOVE AND REPLACE _6” CONCRETE DRIVEWAY:
(11-19-24) 848 SPI 8-56
Remove and replace existing 6" concrete driveway in accordance with Section 848 of the
Standard Specifications, the plans, this special provision and as directed by the Engineer.
All work for this item shall be in accordance with Section 848 of the Standard Specifications
Disposal of existing 6" concrete driveway in accordance with federal, state and local regulations will be incidental the work.
Remove and Replace 6" Concrete Driveway will be measured and paid for in units of square
MG00533 N/A R-4
yards. Such price and payment will be full compensation for removal and disposal of existing driveway, excavating, backfilling, forming, placing all concrete, finishing, constructing and sealing joints, and all incidentals necessary to complete the work.
Remove and Replace 6" Concrete Driveway Square Yard
REMOVE AND REPLACE _4" CONCRETE SIDEWALK:
(11-19-24) 848 SPI 8-56
Remove and replace existing 4" concrete sidewalk in accordance with Section 848 of the
Standard Specifications, the plans, this special provision and as directed by the Engineer.
All work for this item shall be in accordance with Section 848 of the Standard Specifications
Disposal of existing 4" concrete sidewalk in accordance with federal, state and local regulations will be incidental the work.
Remove and Replace 4" Concrete Sidewalk will be measured and paid for in units of square yards. Such price and payment will be full compensation for removal and disposal of existing sidewalk, excavating, backfilling, forming, placing all concrete, finishing, constructing and
Remove and Replace 4" Concrete Sidewalk Square Yard
REMOVE AND REPLACE _5" MONOLITHIC CONCRETE ISLANDS (KEYED-IN
AND SURFACE MOUNTED):
(11-19-24) 852 SPI 8-60
Remove existing island and replace with 5" monolithic concrete islands (keyed in or surfaced mounted) in accordance with Section 852 of the Standard Specifications, the plans, this special provision and as directed by the Engineer.
MG00533 N/A R-5
All work for this item shall be in accordance with Section 852 of the Standard Specifications.
New islands shall be 5" Monolithic Concrete Islands (keyed in or surface) as shown in Roadway
Standard Drawings, No. 852.01.
Disposal of existing islands in accordance with federal, state and local regulations will be incidental to the work.
Remove and Replace 5" Monolithic Concrete Islands (Surface Mounted) will be measured and paid in square yards. Such price and payment will be full compensation for removal and disposal of existing island, excavating, backfilling, forming, placing all concrete, finishing, constructing and sealing joints, and all incidentals necessary to complete the work.
Remove and Replace 5" Monolithic Concrete Islands (Keyed-In) will be measured and paid in square yards. Such price and payment will be full compensation for removal and disposal of existing island, excavating, backfilling, forming, placing all concrete, finishing, constructing and
Remove and Replace 5" Monolithic Concrete Islands (Surface
Mounted)
Square Yard
Remove and Replace 5" Monolithic Concrete Islands (Keyed-In) Square Yard
REMOVE AND REPLACE _4" CONCRETE PAVED DITCH:
(10-20-26) SPI 8-62
Remove, dispose and replace damaged existing concrete paved ditches within the limits shown in the plans or as directed by the Engineer. All work for this item shall be in accordance with
Section 850 of the Standard Specifications and as shown on Roadway Standard Drawings No.
850.01 except that the concrete paved ditch width shall match existing.
Materials
Use concrete paved ditch materials meeting the requirements of Article 850-2 of the Standard
Specifications.
Remove and replace concrete paved ditch at locations indicated in the plans or as directed by the
Engineer. After removing, grade to drain in accordance with the plans and as directed by the
MG00533 N/A R-6
Dispose of materials and debris in an approved disposal site in accordance with Section 802 of the Standard Specifications, federal, state and local regulations. Disposal of existing ditch materials shall be incidental to the work.
Construct concrete paved ditch in accordance with Article 850-1 and 850-3 of the Standard
Remove and Replace 4" Concrete Paved Ditch will be measured and paid for in square yards that is completed and accepted. Longitudinal measurements will be made along the surface of the pavement at the centerline of the ditch and transverse measurements will be made along the surface of the pavement at right angles to the centerline. No measurement will be made of curtain walls at the beginning or ends of the paved ditches. Such price and payment will be full compensation for removal and disposal of existing materials, excavating, backfilling, grading, furnishing, forming, placing all concrete, finishing, constructing curtain walls, constructing and
Remove and Replace 4" Concrete Paved Ditch Square Yard
DETECTABLE WARNING SURFACE AT CURB RAMPS:
(8-19-25) 848 SP8 R52A
Install detectable warning surface at curb ramps as shown in the plans or as directed by the
Engineer, in accordance with Section 848 of the Standard Specifications and this special provision.
Materials
Detectable warning surface materials shall consist of raised truncated domes found on the
NCDOT APL, meet the requirements of Article 848-2 of the Standard Specifications and be capable of being affixed to or anchored in the concrete sidewalk, including green concrete defined as concrete that has set but not appreciably hardened, cured concrete, or asphalt pavement. Surface applied such as glued or stick down applications are prohibited for permanent installations unless approved by the Engineer.
The detectable warning surface shall be uniform in color and texture, be free of cracks or other defects. The color shall be an approximate visual match to the color specified in the contract or as approved by the Engineer.
Install all detectable warning surface in accordance with the manufacturer’s recommendations, Article 848-3 of the Standard Specifications and as approved by the Engineer. Ensure the
MG00533 N/A R-7
surface is free of debris and irregularities prior to placing the detectable warning on the surface.
Place in fresh concrete, before the concrete has reached initial set, or on a hardened cement concrete surface or asphalt pavement surface. Secure permanent installations with mechanical fasteners. No cutting of the coated colored truncated domes is allowed. Embossing or stamping the wet concrete to achieve the truncated dome pattern or using a mold into which a catalyst-hardened material is applied is not allowed. Detectable warning surfaces shall be 24 inches in the direction of travel and extend the full width of the flush surface. The detectable warning surface shall show no appreciable fading, lifting or shrinkage and fit contours, breaks and faults of concrete and asphalt surfaces and show no significant tearing, rollback, lifting or other signs of poor adhesion.
Remove and replace any damaged or misaligned detectable warning surfaces and repair any damage to adjacent facilities prior to final acceptance at no cost to the Department. The finished installation shall meet all applicable ADA and Public Right-of-Way Accessibility Guidelines
(PROWAG)…
This is the start of the file's text. The full file is on GovTribe.