Medford Irrigation District ODOT Utility Relocation RFP Summary
This is a Request for Proposals issued by the Medford Irrigation District (MID) in Central Point, Oregon, for engineering, design, construction management, and/or construction services related to utility relocation work on the Griffin Creek Bridge project (K23548-OR238) to comply with Oregon Department of Transportation (ODOT) funding and reimbursement requirements. The project involves relocating MID irrigation facilities, including canals, laterals, pipelines, and related infrastructure that conflict with an ODOT highway improvement project. Services may be delivered through design-only, design-build, construction-only, or force-account support arrangements, to be confirmed in the final agreement. The RFP was issued on October 9, 2026, with a proposal submission deadline of November 9, 2026, at 4:30 p.m. The deadline for questions is October 23, 2026, with responses posted by October 30, 2026. A Notice of Intent to Award is anticipated on November 20, 2026, with contract execution targeted for December 4, 2026. All relocation work must be completed by February 15, 2027. The contract term and renewal options are not specified in the RFP.
Compensation will be structured to satisfy ODOT reimbursement requirements, with fees proposed as lump sum or time-and-materials for preliminary engineering/design, hourly rates or percentages for construction management/inspection, and detailed estimates or unit prices for construction work. The District and selected consultant/contractor will be reimbursed by ODOT for eligible costs only, provided all work complies strictly with 23 CFR Part 645, the Oregon Utility Relocation Manual, ODOT Utility Relocation Guide, and ORS 366.321. Critical compliance requirements include obtaining written Notice to Proceed from the ODOT State Utility Liaison before any reimbursable work begins, ODOT approval of consultant agreements exceeding $10,000, Buy America compliance for permanently incorporated iron and steel, actual-cost accounting methodologies, and clear segregation of reimbursable versus non-reimbursable betterment costs. The selected firm must maintain Commercial General Liability insurance of $2,000,000 per occurrence/$4,000,000 aggregate, Automobile Liability of $1,000,000 combined single limit, and Professional Liability of $2,000,000 per claim. Evaluation criteria include relevant ODOT/Federal-Aid utility relocation experience (25 points), technical approach and understanding of reimbursement requirements (25 points), qualifications of proposed team (20 points), project schedule and deadline capability (15 points), and cost reasonableness (15 points).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Notice-Engineer of Record Services.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MEDFORD IRRIGATION DISTRICT | Request for Proposals Utility Relocation Services
Page 1 of 7 | Confidential For Solicitation Purposes Only
MEDFORD IRRIGATION DISTRICT
Central Point, Oregon
REQUEST FOR PROPOSALS (RFP)
Engineering, Design, and/or Construction Services for
REIMBURSABLE UTILITY RELOCATION WORK
Meeting Oregon Department of Transportation (ODOT)
Funding & Reimbursement Requirements
RFP Number: RFP-2026-02
Issue Date: October 9, 2026
Proposal Due Date: November 9, 2026, 4:30 pm
Project / Highway: K23548-OR238 Griffin Creek Bridge-MID Relocation
Contact Person: Jack Friend, Manager, Jack@medordid.org, 541-621-0810
Submit proposals electronically to: [Jack@medfordid.org] (or as otherwise directed)
Subject Line: RFP Response Reimbursable Utility Relocation K23548-OR238
1. INTRODUCTION AND PURPOSE
Medford Irrigation District ("District" or "MID") invites qualified firms to submit proposals for professional engineering, design, construction management, and/or construction services related to the relocation of District irrigation facilities that are in conflict with an Oregon Department of Transportation (ODOT) highway improvement project.
Program and applicable Federal regulations (23 CFR Part 645). The selected Consultant/Contractor must perform all work in a manner that preserves the Distr eligible costs from ODOT/FHWA.
The purpose of this RFP is to select a highly qualified firm experienced in irrigation system design and construction, utility coordination with ODOT, and compliance with Federal-aid reimbursement requirements.
1.1 Background
Medford Irrigation District operates and maintains irrigation canals, laterals, pipelines, and related facilities in Jackson County, Oregon. Certain District facilities possess compensable property interests (easements, prior rights under Federal land acts, or other real property interests) that qualify the relocation costs for reimbursement when those facilities conflict with State highway projects.
ODOT has identified conflicts between District facilities and the following project:
Page 2 of 7 | Confidential For Solicitation Purposes Only
K23548-OR238 Griffin Creek Bridge-MID Relocation
The District intends to relocate affected facilities in accordance with the Oregon Utility Relocation Manual, ODOT Utility Relocation Guide, 23 CFR 645, ORS 366.321, and related State and Federal requirements so that eligible costs are fully reimbursable.
1.2 Objectives
capability.
Comply with all ODOT and FHWA requirements for reimbursable utility relocations, including documentation, Buy America, and actual-cost accounting.
Coordinate closely with ODOT Region Utility staff, the State Utility Liaison (SUL), and the District to obtain timely Notices to Proceed.
Minimize impacts to irrigation service to District patrons during the irrigation season.
Deliver complete, accurate Plans, Specifications & Estimates (PS&E) and supporting documentation required for ODOT approval and reimbursement.
2. SCOPE OF WORK
The selected firm ("Consultant" or "Contractor") shall provide the services necessary to plan, design, permit, and/or construct the relocation of District irrigation facilities in conflict with the ODOT project.
The specific delivery method (design-only, design-build, construction-only, or force-account support) will be confirmed in the final agreement.
2.1 Preliminary Engineering / Design Phase
1. Review ODOT project plans, conflict letters, right-of-way maps, and existing District as-builts/easements.
2. Perform field surveys, potholing/SUE as needed, and confirm existing facility locations, sizes, materials, and elevations.
3. Prepare detailed relocation plans on ODOT plan sheets or District drawings meeting ODOT Utility Relocation Manual requirements, including:
Scale, north arrow, project name, county, highway number, and stationing
Existing and proposed right-of-way lines and centerline
Location, type, size, material, and depth/clearance of existing and proposed facilities
Joint-use information, temporary facilities, and service continuity provisions
4. Prepare a detailed construction cost estimate in the format required by ODOT (item, unit, quantity, unit cost, totals).
5. Identify any betterments or upgrades and clearly segregate reimbursable vs. non-reimbursable costs.
6. Prepare or assist with the Reimbursement Information Form (RIF ODOT Form 734-5321) and supporting eligibility documentation.
7. Coordinate with ODOT Utility Coordinator / Region Utility Specialist for plan review and acceptance.
8. Obtain or assist with all necessary permits (ODOT occupancy/X-permit, environmental, local, etc.).
2.2 Construction Phase (if applicable)
1. Perform or manage construction of the relocated facilities in accordance with approved plans and specifications.
2. Comply with Buy America requirements (23 CFR 635.410) for all permanently incorporated iron and steel products.
Page 3 of 7 | Confidential For Solicitation Purposes Only
3. Maintain detailed daily records of labor, equipment, materials, and other costs suitable for ODOT audit.
4. Provide construction staking, inspection, and quality control as required.
5. .
Relocation work to be completed by February 15th, 2027.
6. Prepare as-built drawings and final documentation for District and ODOT records.
2.3 Reimbursement Support & Documentation
The Consultant/Contractor shall support the District in meeting all ODOT reimbursement requirements, including but not limited to:
Preparation of detailed estimates and actual-cost invoices consistent with 23 CFR 645.117
Supporting documentation for labor (employee, classification, rate, hours, location), equipment, materials, and overhead
Retention of all records for a minimum of five (5) years after final payment for State and Federal audit
Assistance with responses to ODOT or FHWA audit requests
Clear segregation of betterment costs (non-reimbursable) from replacement-in-kind costs (reimbursable)
2.4 Exclusions / Owner Responsibilities
The District will retain responsibility for: establishing and documenting compensable property interest/prior rights; executing the Utility Construction Agreement or equivalent with ODOT; receiving and processing reimbursements from ODOT; and final acceptance of the relocated facilities.
3. ODOT / FEDERAL COMPLIANCE REQUIREMENTS
All work under this contract that is intended to be reimbursable must strictly comply with the following:
3.1 Governing Documents
Oregon Utility Relocation Manual (current edition)
ODOT Utility Relocation Guide
23 CFR Part 645 Utilities
23 CFR 635.410 Buy America
ORS 366.321 and related Oregon statutes
ODOT Right of Way Manual (applicable sections)
Any project-specific Utility Construction Agreement between the District and ODOT
3.2 Critical Process Requirements
1. No reimbursable Preliminary Engineering or Construction work may begin until the District has received written Notice to Proceed (NTP) from the ODOT State Utility Liaison (or authorized designee).
2. Consultant agreements for PE work must be reviewed and recommended for approval by ODOT before PE work begins (for contracts > $10,000, detailed scope and estimate required).
3. For competitive construction contracts, PS&E must be approved by ODOT prior to advertisement, and bid results approved prior to award/NTP for construction.
4. All permanently incorporated iron and steel must comply with Buy America unless a waiver is obtained.
5. Invoices must be based on actual costs supported by detailed records; percentage-of-construction-cost methods are not acceptable for reimbursement.
Page 4 of 7 | Confidential For Solicitation Purposes Only
6. Betterments (capacity increases, material upgrades beyond like-kind replacement, etc.) are generally non-reimbursable and must be identified and funded separately.
3.3 Documentation Standards
meeting ODOT audit standards, including timekeeping, equipment usage logs, material invoices, and clear cost allocation.
4. PROPOSAL REQUIREMENTS
Proposals shall be organized as follows and limited to [25] pages (excluding covers, tabs, résumés, and required forms):
4.1 Cover Letter
One-page letter signed by an authorized representative identifying the proposing firm, primary contact, and a statement of understanding of the ODOT reimbursable utility relocation process.
4.2 Firm Qualifications & Experience
Company overview, years in business, and relevant Oregon experience
At least three (3) comparable projects involving irrigation or utility relocation in coordination with ODOT or another state DOT, preferably with Federal-aid reimbursement
Demonstration of knowledge of 23 CFR 645, Buy America, and ODOT Utility Relocation Manual procedures
Any experience working with irrigation districts or similar special districts
4.3 Project Team
Organizational chart and key personnel (Project Manager, Lead Designer, Construction Manager if applicable)
Résumés of key staff (max 2 pages each) highlighting relevant experience
Availability and proposed time commitment of key personnel
4.4 Technical Approach
Understanding of the specific project conflicts and proposed relocation concepts
Approach to coordinating with ODOT Utility staff and obtaining timely NTPs
Methodology for cost estimating, betterment segregation, and actual-cost documentation season
Quality control and risk management procedures
4.5 Cost Proposal
Provide a fee proposal as follows (format may be adjusted based on delivery method):
Preliminary Engineering / Design: lump sum or time-and-materials not-to-exceed, with rate schedule
Construction Management / Inspection (if applicable): hourly rates or percentage
Construction (if design-build or construction contract): detailed estimate or unit prices
Page 5 of 7 | Confidential For Solicitation Purposes Only
Note: Final compensation terms for reimbursable work will be structured to satisfy ODOT requirements (actual cost basis for force-account, competitive bidding for contracts, etc.).
4.6 Required Forms & Certifications
Signed Proposal Form (Attachment A)
Conflict of Interest Disclosure
Certification regarding Debarment, Suspension, and other Responsibility Matters
Buy America awareness acknowledgment
Proof of insurance (or ability to meet requirements in Section 7)
Any additional forms required by the District
5. EVALUATION CRITERIA
Proposals will be evaluated by a District selection committee. The following criteria and weights will be used:
Evaluation Criterion Maximum Points
Relevant Experience with ODOT / Federal-Aid Utility Relocations 25
Technical Approach & Understanding of Reimbursement Requirements 25
Qualifications of Proposed Team & Key Personnel 20
Project Schedule & Ability to Meet Critical Deadlines 15
Cost / Fee Proposal Reasonableness 15
TOTAL 100
The District reserves the right to interview short-listed firms, request clarifications, and negotiate with the highest-ranked proposer. Award will be based on the proposal determined to be most advantageous to the District, not solely on lowest cost.
6. SCHEDULE
Activity Date
RFP Issued October 9, 2026
Deadline for Questions October 23, 2026
Responses to Questions Posted / Issued October 30, 2026
Proposals Due November 9, 2026 @ 4:30PM
Notice of Intent to Award November 20, 2026
Contract Execution Target December 4, 2026
7. INSURANCE AND BONDING
The selected firm shall maintain, at a minimum, the following insurance coverages (or such higher limits as required by ODOT or the final agreement):
Commercial General Liability: $2,000,000 per occurrence / $4,000,000 aggregate
Page 6 of 7 | Confidential For Solicitation Purposes Only
Automobile Liability: $1,000,000 combined single limit
Professional Liability (Errors & Omissions): $2,000,000 per claim
The District and ODOT (as applicable) shall be named as additional insureds on general liability and auto policies. Certificates of insurance shall be provided prior to commencement of work.
If construction services are included, payment and performance bonds in the full amount of the construction contract may be required.
8. GENERAL TERMS AND CONDITIONS
8.1 Reservation of Rights
The District reserves the right to reject any or all proposals, to waive informalities, to cancel this RFP at any time, and to negotiate with the selected proposer. This RFP does not commit the District to award a contract or to pay any costs incurred in the preparation of a proposal.
8.2 Public Records
Proposals are subject to Oregon Public Records Law. Proposers should clearly mark any proprietary or confidential information.
8.3 Protest Procedure
Any proposer who is adversely affected may submit a written protest to the District Contact within seven (7) calendar days of the Notice of Intent to Award. Protests must specify the grounds and supporting facts.
8.4 Governing Law
This RFP and any resulting contract shall be governed by the laws of the State of Oregon. Venue shall lie in Jackson County, Oregon.
8.5 Non-Discrimination
The District is an equal opportunity employer and does not discriminate on the basis of race, color, religion, sex, national origin, age, disability, or any other protected status.
9. ATTACHMENTS (TO BE PROVIDED OR DEVELOPED)
Attachment A Proposal Form / Signature Page
Attachment B Sample Professional Services / Construction Agreement
Attachment C ODOT Project Plans and Conflict Information (as available)
Attachment D District Standard Insurance Requirements
Attachment E Reference to ODOT Utility Relocation Manual and Key Forms (RIF, Checklist, etc.)
Attachment F Buy America Compliance Guidance Summary
10. QUESTIONS AND CLARIFICATIONS
Page 7 of 7 | Confidential For Solicitation Purposes Only
All questions regarding this RFP must be submitted in writing to the Contact Person listed on the cover page no later than the Deadline for Questions. Responses will be issued in writing to all known proposers or posted as an addendum. Oral statements are not binding.
END OF REQUEST FOR PROPOSALS