Bid Notice-Hal Bartholomew Sports Park Synthetic Turf Replacement Project.pdf
PDF 2 MB Posted
- Solicitation number
- PM-27-026
- Issued by
- El Dorado County, California
About this file
This bid notice pertains to the Hal Bartholomew Sports Park Synthetic Turf Replacement Project in California. The project scope includes removal and disposal of the existing synthetic turf, base leveling and testing, installation of new synthetic turf with shock pad, installation of soccer and flag football markings, installation of soccer goal footings and anchors, GMAX testing to ensure player safety standards, and provision of an eight-year turf warranty covering the installed synthetic surface.
The bid notice establishes the framework for soliciting qualified contractors to execute this synthetic turf replacement initiative. Prospective bidders should reference the notice for specific submission deadlines, any mandatory site visits or pre-bid meetings, contract award timelines, and the full scope of work requirements. The eight-year warranty requirement ensures long-term performance and durability of the installed turf system, protecting the municipality's investment in this athletic facility upgrade.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COSUMNES COMMUNITY SERVICES DISTRICT
ELK GROVE, CALIFORNIA
CONTRACT DOCUMENTS AND SPECIFICATIONS FOR
HAL BARTHOLOMEW SPORTS PARK SYNTHETIC TURF
REPLACEMENT PROJECT
CONTRACT # PM-27-026
Hal Bartholomew Sports Park Synthetic Turf Replacement Project
Contract #PM-27-026
- 1 -
NOTICE INVITING BIDS
NOTICE IS HEREBY GIVEN that the Cosumnes Community Services District (“District”) invites and will receive sealed Bids up to but not later than 10:30 a.m. December 1, 2026, at the office of the District’s Administration Building, located at 8820 Elk Grove Boulevard, Elk Grove, CA 95624, for the Hal Bartholomew Sports Park Synthetic Turf Replacement Project. At said time, Bids will be publicly opened and read aloud at the District Office. Bids received after said time shall be returned unopened. Bids shall be valid for a period of 90 calendar days after the Bid opening date.
The work generally includes removal and disposal of existing synthetic turf, base leveling and testing, installation of new synthetic turf with shock pad, soccer and flag football markings, soccer goal footings and anchors, GMAX testing, and an eight-year turf warranty.
The project is located at Hal Bartholomew Sports Park’s Field #2, 10150 Franklin High Rd. in Elk Grove, CA. See Exhibit “A” for Scope of Services and Specifications, Exhibit “B” for Location Map Photo, and Exhibit “C” for Details.
The District will endeavor to administer the bidding process in accordance with the terms and dates outlined below; however, the District reserves the right to modify the terms, activities, timeline, or other aspects of the process at any time as it deems necessary.
EVENT DATE/TIME
NIB Posting November 10, 2026
Non-Mandatory Pre-Bid Meeting November 18, 2026 10:30 AM PST
Deadline for Questions November 19, 2026 4:00 PM PST
District Provides Responses to Questions November 23, 2026
Bid Closing Date December 1, 2026, 10:30 AM PST
Bid Award Notification December 3, 2026
Board Meeting Date (Approval of Contract) December 16, 2026
Notice to Proceed January 4, 2027
Bids must be submitted on the District’s Bid Forms. Bidders may obtain a copy of the Contract from www.CosumnesCSD.gov/bids. To the extent required by section 20103.7 of the Public Contract Code, upon request from a contractor plan room service, the District shall provide an electronic copy of the Contract at no charge to the contractor plan room.
It is the responsibility of each prospective bidder to download and print all Bid Documents for review and to verify the completeness of Bid Documents before submitting a bid. Any Addenda will be posted on www.CosumnesCSD.gov/bids. It is the responsibility of each prospective bidder to check www.CosumnesCSD.gov/bids on a daily basis through the close of bids for any applicable addenda or updates. The District does not assume any liability or responsibility based on any defective or incomplete copying, excerpting, scanning, faxing, downloading or printing of the Bid Documents. Information on www.CosumnesCSD.gov/bids may change without notice to http://www.cosumnescsd.gov/bid https://www.cosumnescsd.gov/bids https://www.cosumnescsd.gov/bids
- 2 -prospective bidders. The Contract shall supersede any information posted or transmitted by www.CosumnesCSD.gov/bids.
Each Bid shall be accompanied by cash, a certified or cashier’s check, or Bid Bond secured from a surety company satisfactory to the District, the amount of which shall not be less than ten percent (10%) of the submitted Total Bid Price, made payable to Cosumnes Community Services District as bid security. The bid security shall be provided as a guarantee that within five (5) working days after the District provides the successful bidder the Notice of Award, the successful Bidder will enter into a Contract and provide the necessary bonds and certificates of insurance.
The bid security will be declared forfeited if the successful Bidder fails to comply within said time.
No interest will be paid on funds deposited with District.
A non-mandatory Pre-Bid Conference is scheduled for November 18, 2026, at 10:30 a.m. to review the Project's existing conditions at 10150 Franklin High Rd. Elk Grove, CA 95757 (Hal Bartholomew Sports Park, Field 2). Representatives of the District and consulting engineers, if any, will be present. Questions asked by Bidders at the Pre-Bid Conference not specifically addressed within the Contract shall be answered in writing, and shall be sent to all Bidders present at the Pre-Bid Conference and posted on www.CosumnesCSD.gov/bids.
The successful Bidder will be required to furnish a Faithful Performance Bond and a Labor and Material Payment Bond each in an amount equal to one hundred percent (100%) of the Contract Price. Each bond shall be in the forms set forth herein, shall be secured from a surety company that meets all State of California bonding requirements, as defined in California Code of Civil Procedure Section 995.120, and that is a California admitted surety insurer.
Pursuant to Section 22300 of the Public Contract Code of the State of California, the successful Bidder may substitute certain securities for funds withheld by District to ensure its performance under the Contract.
Pursuant to Labor Code Section 1773, District has obtained the prevailing rate of per diem wages and the prevailing wage rate for holiday and overtime work applicable in Sacramento County from the Director of the Department of Industrial Relations for each craft, classification, or type of worker needed to execute this Contract. A copy of these prevailing wage rates may be obtained via the internet at: www.dir.ca.gov/dlsr
In addition, a copy of the prevailing rate of per diem wages is available at the District’s Park Operations Division and shall be made available to interested parties upon request. The successful bidder shall post a copy of the prevailing wage rates at each job site. It shall be mandatory upon the Bidder to whom the Contract is awarded, and upon any subcontractors, to comply with all Labor Code provisions, which include but are not limited to the payment of not less than the said specified prevailing wage rates to all workers employed by them in the execution of the Contract, employment of apprentices, hours of labor and debarment of contractors and subcontractors.
Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a Contract to perform public work must be registered with the Department of Industrial Relations. No Bid will be accepted nor any Contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded a Contract, the Bidder and https://www.cosumnescsd.gov/bids http://www.cosumnescsd.gov/bids http://www.dir.ca.gov/dlsr
- 3 -its subcontractors, of any tier, shall maintain active registration with the Department of Industrial Relations for the duration of the Project.
This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. In bidding on this Project, it shall be the Bidder’s sole responsibility to evaluate and include the cost of complying with all labor compliance requirements under this Contract and applicable law in its Bid.
Unless otherwise provided in the Instructions for Bidders, each Bidder shall be a licensed contractor pursuant to sections 7000 et seq. of the Business and Professions Code in the following classification(s) throughout the time it submits its Bid and for the duration of the Contract: General A or General B, C-27, or C-61/D-12.
Substitution requests shall be made within 35 calendar days after the award of the Contract.
Pursuant to Public Contract Code Section 3400(b), the District may make findings designating that certain additional materials, methods or services by specific brand or trade name other than those listed in the Standard Specifications be used for the Project. Such findings, if any, as well as the materials, methods or services and their specific brand or trade names that must be used
District shall award the Contract for the Project to the lowest responsive, responsible Bidder as determined by the District from the TOTAL BASE BID ALONE. District reserves the right to reject any or all bids or to waive any irregularities or informalities in any bids or in the bidding process.
For further information, contact Scott Jones at ScottJones@CosumnesCSD.gov
END OF NOTICE INVITING BIDS
mailto:SteveDalton@CosumnesCSD.gov
- 4 -
INSTRUCTIONS TO BIDDERS
SECURING DOCUMENTS
Bids must be submitted to the District on the Bid Forms which are a part of the Bid Package for the Project. Bid and Contract documents may be obtained from www.CosumnesCSD.gov/bids in the Notice Inviting Bids.
Any Addenda will be posted on www.CosumnesCSD.gov/bids. Failure to acknowledge addenda may make a bid nonresponsive and not eligible for award of the Contract.
EXAMINATION OF SITE AND CONTRACT
At its own expense and prior to submitting its Bid, each Bidder shall visit the site of the proposed work and fully acquaint itself with the conditions relating to the construction and labor required so that the Bidder may fully understand the work, including but not limited to, difficulties and restrictions attending the execution of the work under the Contract. Each Bidder shall carefully examine the Drawings, and shall read the Specifications, Contract, and all other documents referenced herein. Each Bidder shall also determine the local conditions which may in any way affect the performance of the work, including local tax structure, contractors’ licensing requirements, availability of required insurance, the prevailing wages and other relevant cost factors, shall familiarize itself with all federal, state and local laws, ordinances, rules, regulations and codes affecting the performance of the work, including the cost of permits and licenses required for the work, and shall make such surveys and investigations, including investigations of subsurface or latent physical conditions at the site or where work is to be performed as may be required. Bidders are responsible for consulting the standards referenced in the Contract. The failure or omission of any Bidder to receive or examine any Contract documents, forms, instruments, addenda, or other documents, or to visit the site and acquaint itself with conditions there existing shall in no way relieve any Bidder from any obligation with respect to its Bid or to the Contract and no relief for error or omission will be given except as required under State law.
The submission of a Bid shall be taken as conclusive evidence of compliance with this Article.
INTERPRETATION OF DRAWINGS AND DOCUMENTS
Prospective Bidders unclear as to the true meaning of any part of the Drawings, Specifications or other proposed Contract documents may submit to the Engineer of the District a written request for interpretation. The prospective Bidder submitting the request is responsible for prompt delivery. Interpretation of the Drawings, Specifications or other proposed Contract documents will be made only by a written addendum duly issued and a copy of such addenda will be mailed or delivered to each prospective Bidder who has purchased a set of Drawings and Specifications.
The District will not be responsible for any other explanation or interpretations of the proposed documents. If a Prospective Bidders becomes aware of any errors or omissions in any part of the Contract, it is the obligation of the Prospective Bidder to promptly bring it to the attention of the District.
PRE-BID CONFERENCE
A non-mandatory Pre-Bid Conference is scheduled for November 18, 2026, at 10:30 a.m. to review the Project's existing conditions at 10150 Franklin High Rd. Elk Grove, CA 95757 (Hal Bartholomew Sports Park, Field 2). Representatives of the District and consulting engineers, if
- 5 -any, will be present. Questions asked by Bidders at the Pre-Bid Conference not specifically addressed within the Contract shall be answered in writing,and shall be sent to all Bidders present at the Pre-Bid Conference and posted to the District website www.CosumnesCSD.gov/bids.
ADDENDA
The District reserves the right to revise the Contract prior to the Bid opening date. Revisions, if any, shall be made by written Addenda. All Addenda issued by the District shall be included in the Bid and made part of the Contract. Pursuant to Public Contract Code Section 4104.5, if the
District issues an Addendum which includes material changes to the Project less than 72 hours prior to the deadline for submission of Bids, the District will extend the deadline for submission of
Bids. The District may determine, in its sole discretion, whether an Addendum warrants postponement of the Bid submission date. Each prospective Bidder shall provide District a name, address, email address, fax, and telephone number by which the District can contact the Bidder for notification of any Addenda. Any Addenda will be posted on the District website http://www.CosumnesCSD.gov/bids
Please Note: Bidders are responsible for ensuring they have received any and all Addenda. To this end, each Bidder should contact the Project Manager to verify that it has received all Addenda issued, if any, prior to the Bid opening. Any Addenda will be posted on www.CosumnesCSD.gov/bids. It is the responsibility of each prospective bidder to check the website on a daily basis through the close of bids for any applicable addenda or updates. The
Bidder shall indicate the Addenda received prior to bidding in the space provided in the Bid Form.
Failure to indicate all Addenda may be sufficient cause for rejecting the Bid.
ALTERNATE BIDS
If alternate bid items are called for in the Contract, the time required for completion of the alternate bid items has already been factored into the Contract duration and no additional Contract time will be awarded for any of the alternate bid items. The District may elect to include one or more of the alternate bid items, or to otherwise remove certain work from the Project scope of work.
Accordingly, each bidder must ensure that each bid item contains a proportionate share of profit, overhead, and other costs or expenses which will be incurred by the bidder.
COMPLETION OF BID FORMS
Bids shall only be prepared using copies of the Bid Forms which are included in the Contract.
The use of substitute Bid Forms other than clear and correct photocopies of those provided by the District will not be permitted. Bids shall be executed by an authorized signatory as described in these Instructions to Bidders. In addition, Bidders shall fill in all blank spaces (including inserting “N/A” where applicable), and initial all interlineations, alterations, or erasures to the Bid Forms. Bidders shall neither delete, modify, nor supplement the printed matter on the Bid Forms nor make substitutions thereon. USE OF BLACK OR BLUE INK, INDELIBLE PENCIL, OR A TYPEWRITER IS REQUIRED. Deviations in the Bid Forms may result in the Bid being deemed non-responsive.
http://www.cosumnescsd.gov/bids
- 6 -
MODIFICATIONS OF BIDS
Each Bidder shall submit its Bid in strict conformity with the requirements of the Contract.
Unauthorized additions, modifications, revisions, conditions, limitations, exclusions or provisions attached to a Bid may render it non-responsive and may cause its rejection. Bidders shall not delete, modify, or supplement the printed matter on the Bid Forms, or make substitutions thereon.
Oral, telephonic and electronic modifications will not be considered.
SUBCONTRACTORS
Bidder shall set forth the name, address of the place of business, and contractor license number of each subcontractor who will perform work, labor, furnish materials or render services to the bidder on said Contract and each subcontractor licensed by the State of California who, under subcontract to bidder, specially fabricates and installs a portion of the Work described in the Drawings and Specifications in an amount in excess of one half of one percent (0.5%) of the total bid price, and shall indicate the portion of the work to be done by such subcontractor in accordance with Public Contract Code Section 4104.
LICENSING REQUIREMENTS
Pursuant to Business and Professions Code Section 7028.15 and Public Contract Code Section 3300, all bidders must possess proper licenses for performance of this Contract. Subcontractors must possess the appropriate licenses for each specialty subcontracted. Pursuant to Business and Professions Code Section 7028.5, the District shall consider any bid submitted by a contractor not currently licensed in accordance with state law and pursuant to the requirements found in the Contract to be nonresponsive, and the District shall reject the Bid. The District shall have the right to request, and Bidders shall provide within ten (10) calendar days, evidence satisfactory to the District of all valid license(s) currently held by that Bidder and each of the Bidder’s subcontractors, before awarding the Contract.
Notwithstanding anything contained herein, if the Work involves federal funds, the Contractor shall be properly licensed by the time the Contract is awarded, pursuant to the provisions of Public Contract Code section 20103.5.
BID GUARANTEE (BOND)
Each bid shall be accompanied by: (a) cash; (b) a certified or cashier’s check made payable to Cosumnes Community Services District; or (c) a Bid Bond secured from a surety company satisfactory to the District, the amount of which shall not be less than ten percent (10%) of the Total Bid Price, made payable to Cosumnes Community Services District as bid security.
Personal sureties and unregistered surety companies are unacceptable. The surety insurer shall be California admitted surety insurer, as defined in Code of Civil Procedure Section 995.120. The bid security shall be provided as a guarantee that within ten (10) working days after the District provides the successful bidder the Notice of Award, the successful bidder will enter into a Contract and provide the necessary bonds and certificates of insurance. The bid security will be declared forfeited if the successful bidder fails to comply within said time, and District may enter into a Contract with the next lowest responsive responsible bidder, or may call for new bids. No interest shall be paid on funds deposited with the District. District will return the security accompanying the bids of all unsuccessful bidders no later than 60 calendar days after award of the Contract.
- 7 -
IRAN CONTRACTING ACT OF 2010
In accordance with Public Contract Code Section 2200 et seq., the District requires that any person that submits a bid or proposal or otherwise proposes to enter into or renew a contract with the District with respect to goods or services of one million dollars ($1,000,000) or more, certify at the time the bid is submitted or the contract is renewed, that the person is not identified on a list created pursuant to subdivision (b) of Public Contract Code Section 2203 as a person engaging in investment activities in Iran described in subdivision (a) of Public Contract Code Section 2202.5, or as a person described in subdivision (b) of Public Contract Code Section 2202.5, as applicable.
The form of such Iran Contracting Certificate is included with the bid package and must be signed and dated under penalty of perjury.
UKRAINE/RUSSIA-RELATED SANCTIONS COMPLIANCE
Contractor is aware of the requirements of California Executive Order N-6-22 (“Ukraine/Russia- Related Sanctions), which obligates contractors to comply with existing economic sanctions imposed by the U.S. government in response to Russia’s actions in Ukraine, as well as any sanctions imposed under state law. The Services may be subject to compliance monitoring by the District. It shall be the Contractor’s sole responsibility to comply with all applicable economic sanctions.
NONCOLLUSION DECLARATION
Bidders on all public works contracts are required to submit a declaration of noncollusion with their bid. This form is included with the bid package and must be signed and dated under penalty of perjury.
BIDDER INFORMATION AND EXPERIENCE FORM
Each Bidder shall complete the questionnaire provided herein and shall submit the questionnaire along with its Bid. Failure to provide all information requested within the questionnaire along with the Bid may cause the bid to be rejected as non-responsive. The District reserves the right to reject any Bid if an investigation of the information submitted does not satisfy the Engineer that the Bidder is qualified to properly carry out the terms of the Contract.
WORKERS' COMPENSATION CERTIFICATION
In accordance with the provisions of Labor Code Section 3700, Contractor shall secure the payment of compensation to its employees. Contractor shall sign and file with the District the following certificate prior to performing the work under this Contract:
I am aware of the provisions of Section 3700 of the Labor Code, which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.
The form of such Workers' Compensation Certificate is included as part of this document.
- 8 -
SIGNING OF BIDS
All Bids submitted shall be executed by the Bidder or its authorized representative. Bidders may be asked to provide evidence in the form of an authenticated resolution of its Board of Directors or a Power of Attorney evidencing the capacity of the person signing the Bid to bind the Bidder to each Bid and to any Contract arising therefrom.
If a Bidder is a joint venture or partnership, it may be asked to submit an authenticated Power of Attorney executed by each joint venturer or partner appointing and designating one of the joint venturers or partners as a management sponsor to execute the Bid on behalf of Bidder. Only that joint venturer or partner shall execute the Bid. The Power of Attorney shall also: (1) authorize that particular joint venturer or partner to act for and bind Bidder in all matters relating to the Bid;
and (2) provide that each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations of Bidder assumed under the Bid and under any Contract arising therefrom. The Bid shall be executed by the designated joint venturer or partner on behalf of the joint venture or partnership in its legal name.
SUBMISSION OF SEALED BIDS
Once the Bid and supporting documents have been completed and signed as set forth herein, they shall be placed, along with the Bid Guarantee and other required materials, in a sealed envelope, addressed and delivered or mailed, postage prepaid, to the Project Manager of the District before the time and day set for the receipt of bids. The envelope shall bear the title of the work and the name of the bidder. No oral or telephonic bids will be considered. No forms transmitted via the internet, e-mail, facsimile, or any other electronic means will be considered unless specifically authorized by the District as provided herein. Bids received after the time and day set for the receipt of bids shall be returned to the bidder unopened. The envelope shall also contain the following in the lower left-hand corner thereof:
Bid of (Bidder’s Name) for the Hal Bartholomew Sports Park Synthetic Turf Replacement Project
Only where expressly permitted in the Notice Inviting Bids may bidders submit their bids via electronic transmission pursuant to Public Contract Code sections 1600 and 1601. Any acceptable method(s) of electronic transmission shall be stated in the Notice Inviting Bids. District may reject any bid not strictly complying with District’s designated methods for delivery.
OPENING OF BIDS
At the time and place set for the opening and reading of bids, or any time thereafter, each and every bid received prior to the time and day set for the receipt of bids will be publicly opened and read. The District will leave unopened any Bid received after the specified date and time, and any such unopened Bid will be returned to the bidder. It is the bidder’s sole responsibility to ensure that its Bid is received as specified. Bids may be submitted earlier than the date(s) and time(s) indicated.
The public reading of each bid will include the following information:
The name and business location of the bidder.
The nature and amount of the bid security furnished by bidder.
- 9 -
The bid amount.
Bidders or their representatives and other interested persons may be present at the opening of the bids. The District may, in its sole discretion, elect to postpone the opening of the submitted Bids. The District reserves the right to reject any or all Bids and to waive any informality or irregularity in any Bid.
WITHDRAWAL OF BID
Any bid may be withdrawn either personally or by written request, incurring no penalty, at any time prior to the scheduled closing time for receipt of bids. Requests to withdraw bids shall be worded so as not to reveal the amount of the original bid. Withdrawn bids may be resubmitted until the time and day set for the receipt of bids, provided that resubmitted bids are in conformance with the instructions herein.
Bids may be withdrawn after bid opening only by providing written notice to District within five (5) working days of the bid opening and in compliance with Public Contract Code Section 5100 et seq., or as otherwise may be allowed with the consent of the District.
BIDDERS INTERESTED IN MORE THAN ONE BID
No Bidder shall be allowed to make, file or be interested in more than one bid for the same work unless alternate bids are specifically called for. A person, firm or corporation that has submitted a sub-proposal to a Bidder, or that has quoted prices of materials to a Bidder, is not thereby disqualified from submitting a sub-proposal or quoting prices to other bidders. No person, firm, corporation, or other entity may submit a sub-proposal to a Bidder, or quote prices of materials to a Bidder, when also submitting a prime Bid on the same Project.
SUBSTITUTION OF SECURITY
The Contract call for monthly progress payments based upon the percentage of the Work completed. The District will retain a percentage of each progress payment as provided by the Contract. At the request and expense of the successful Bidder, the District will substitute securities for the amount so retained in accordance with Public Contract Code Section 22300.
PREVAILING WAGES
The District has obtained from the Director of the Department of Industrial Relations the general prevailing rate of per diem wages in the locality in which this work is to be performed for each craft or type of worker needed to execute the Contract. These rates may be obtained online at http://www.dir.ca.gov. Bidders are advised that a copy of these rates must be posted by the successful Bidder at the job site(s).
DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS
In accordance with the provisions of the Labor Code, contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Labor Code Sections 1777.1 or 1777.7. Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract. Any public money that is paid to a debarred http://www.dir.ca.gov/
- 10 -subcontractor by the Contractor for the Project shall be returned to the District. The Contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the Project.
INSURANCE REQUIREMENTS
Before beginning any work, the contractor shall furnish or have on file, satisfactory certificates of insurance for the insurance types listed below. The certificates must be held by the Cosumnes Community Services District and must remain in effect for the duration of the contract. See Section 3-9 of the City of Elk Grove Standard Construction Specifications for additional Insurance Requirements. The standard Insurance Accord Form is acceptable.
A. Worker’s Compensation Insurance in accordance with the provisions of Section 3700 of the Labor Code of the State of California.
B. General liability for limits of not less than $4,000,000 per occurrence and $2,000,000 aggregate for bodily injury, personal injury and property damage. If general aggregate limits of liability are used, then the minimum general aggregate shall be twice the “each occurrence” limit.
C. Automobile liability for limits of not less than $1,000,000 for each occurrence.
Public Liability and Property Damage Insurance shall name as an insured, the Cosumnes Community Services District, and shall assume the defense of the District, its officers, employees, and agents from all suits, actions, damages, or claims of every type and description to which they may be subjected, or put by reason of, or resulting from, the contractor’s operations in the performance of the contract.
PERFORMANCE BOND AND PAYMENT BOND REQUIREMENTS
The successful bidder will be required to furnish a Labor and Material Payment Bond and a Faithful Performance Bond each in an amount equal to one hundred percent (100%) of the contract price. Each bond shall be secured from a surety company that meets all State of California bonding requirements, as defined in California Code of Civil Procedure Section 995.120 and is admitted by the State of California. Each bond shall be accompanied, upon the request of District, with all documents required by California Code of Civil Procedure Section 995.660 to the extent required by law. All bonding and insurance requirements shall be completed and submitted to District within ten (10) working days from the date the District provides the successful bidder with the Notice of Award.
SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES AND FEES
Contractor and its subcontractors performing work under this Contract will be required to pay California sales tax and other applicable taxes, and to pay for permits, licenses and fees required by the agencies with authority in the jurisdiction in which the Work will be located, unless otherwise expressly provided by the Contract.
- 11 -
PERMITS, TESTING AND INSPECTION REQUIREMENTS
The Contractor shall be responsible for obtaining and maintaining all permits, licenses, and authorizations customarily required for the Contractor's means, methods, and performance of the Work, as applicable. The Contractor shall comply with all applicable laws, regulations, and requirements of the authorities having jurisdiction.
No City building permit or similar project-specific construction permit is anticipated to be required for this Project. If any such permit is determined to be necessary, the District shall be responsible for obtaining it unless otherwise directed in writing.
The Contractor shall be responsible for providing and coordinating all testing required by the Contract Documents, including testing of materials, products, and completed installations as specified. All costs associated with required testing, including laboratory fees, sampling, scheduling, and coordination, shall be included in the Contractor's Bid Price. Testing shall be performed by qualified independent testing agencies where required by the Contract Documents.
The Contractor shall provide test results and documentation to the District for review and acceptance.
FILING OF BID PROTESTS
Bidders may file a “protest” of a Bid with the District’s General Manager. In order for a Bidder’s protest to be considered valid, the protest must:
Be filed in writing within five (5) calendar days after the bid opening date;
Clearly identify the specific irregularity or accusation;
Clearly identify the specific District staff determination or recommendation being protested;
Specify in detail the grounds for protest and the facts supporting the protest; and
Include all relevant, supporting documentation with the protest at time of filing.
If the protest does not comply with each of these requirements, the District may reject the protest without further review.
If the protest is timely and complies with the above requirements, the District’s General Manager, or other designated District staff member, shall review the protest, any response from the challenged Bidder(s), and all other relevant information. The General Manager will provide a written decision to the protestor.
The procedure and time limits set forth in this Article are mandatory and are the sole and exclusive remedy in the event of a Bid protest. Failure to comply with these procedures shall constitute a failure to exhaust administrative remedies and a waiver of any right to further pursue the Bid protest, including filing a Government Code Claim or legal proceedings.
- 12 -
BASIS OF AWARD; BALANCED BID
The District shall award the Contract to the lowest responsible Bidder submitting a responsive Bid. The lowest Bid will be determined on the basis of the Total Base Bid Price.
The District may reject any Bid which, in its opinion when compared to other Bids received or to the District’s internal estimates, does not accurately reflect the cost to perform the Work. The District may reject as non-responsive any Bid which unevenly weights or allocates costs, including but not limited to overhead and profit to one or more particular bid items.
AWARD PROCESS
Once all Bids are opened and reviewed to determine the lowest responsive and responsible Bidder, the District may award the Contract. The apparent successful Bidder should begin to prepare the following documents: (1) the Performance Bond; (2) the Payment Bond; and (3) the required insurance certificates and endorsements. Once the District notifies the Bidder of the award, the Bidder will have ten (10) working days from the date of this notification to execute the Contract and supply the District with all of the required documents and certifications. Regardless of whether the Bidder supplies the required documents and certifications in a timely manner, the Contract time will begin to run twenty (20) working days from the date of the notification. Once the District receives all of the properly drafted and executed documents and certifications from the Bidder, the District shall issue a Notice to Proceed to that Bidder.
EXECUTION OF CONTRACT
As required herein the Bidder to whom an award is made shall execute the Contract in the amount determined by the Contract. The District may require appropriate evidence that the persons executing the Contract are duly empowered to do so. The Contract and bond forms to be executed by the successful Bidder are included within these Specifications and shall not be detached.
TIME FOR COMPLETION AND LIQUIDATED DAMAGES
Time is of the essence in the completion of the Work. Work shall be commenced within ten (10) Working Days of the date stated in the District’s Notice to Proceed and shall be completed by Contractor in 30 working days as specified in the Contract Documents. The District is under no obligation to consider early completion of the Project; and the Contract completion date shall not be amended by the District’s receipt or acceptance of the Contractor’s proposed earlier completion date. Furthermore, Contractor shall not, under any circumstances, receive additional compensation from the District (including but not limited to indirect, general, administrative or other forms of overhead costs) for the period between the time of earlier completion proposed by the Contractor and the Contract completion date. If the Work is not completed as stated in the Contract Documents, it is understood that the District will suffer damage. In accordance with Government Code section 53069.85, being impractical and infeasible to determine the amount of actual damage, it is agreed that Contractor shall pay to the District $1,500/day as fixed and liquidated damages, and not as a penalty, the sum stipulated in the Contract for each working day of delay until the Work is fully completed. Contractor and its surety shall be liable for any liquidated damages. Any money due or to become due the Contractor may be retained to cover liquidated damages.
Inclement Weather.
- 13 -
1. Contractor’s attention is directed to Section 7-7, “Pursuance of Work During Inclement Weather,” Section 7-10, “Protection of Works, Persons, and Property,” and Section 10-4, “Erosion, Sediment, and Water Pollution Control “of the Standard Construction Specifications.
2. Compensation for ceasing operations (demobilization) and resuming operations (mobilization) after inclement weather shall be considered as included in the prices paid for the various contract items of Work involved as specified in Section 8-3, “Work to be Done without Direct Payment,” of the Standard Construction Specifications and therefore no additional compensation shall be allowed.
3. Contractor shall abide by the Engineer’s determination of what constitutes inclement weather.
Time extensions for inclement weather shall only be granted when the work stopped during inclement weather is on the critical path of the Project schedule.
4. Extension of Time.
• Contractor shall not be charged liquidated damages because of any delays in completion of the Work due to unforeseeable causes beyond their control.
QUESTIONS
Questions regarding this Notice Inviting Bids may be directed to Scott Jones, at ScottJones@CosumnesCSD.gov. All questions are due by 4:00 p.m on November 19, 2026.
No other members of the District’s staff or District Board should be contacted about this procurement during the bidding process. Any and all inquiries and comments regarding this Bid must be communicated in writing, unless otherwise instructed by the District. The District may, in its sole discretion, disqualify any Bidder who engages in any prohibited communications.
mailto:SteveDalton@CosumnesCSD.gov
- 14 -
BID FORMS
1.1 Bid.
Bids will be received at the Cosumnes Community Services District, 8820 Elk Grove Boulevard, Elk Grove, CA 95624, until 10:30 a.m. on December 1, 2026.
NAME OF BIDDER: ______________________________________________
To the Cosumnes Community Services District 8820 Elk Grove Boulevard Elk Grove, CA 95624
The undersigned hereby declare that we have carefully examined the location of the proposed Work, and have read and examined the Contract, including all plans, specifications, and all addenda, if any, for the following Project:
Hal Bartholomew Sports Park Synthetic Turf Replacement Project Contract # PM-27-026
We hereby propose to furnish all labor, materials, equipment, tools, transportation, and services, and to discharge all duties and obligations necessary and required to perform and complete the Project, as described and in strict conformity with the Drawings, and these Specifications for TOTAL BID PRICE indicated herein.
The undersigned acknowledges receipt, understanding, and full consideration of the following addenda to the Contract:
Addenda No. ________________________________________________
1. Attached is the required Bid Guarantee in the amount of not less than 10% of the Total Bid Price.
2. Attached is the completed Designation of Subcontractors form.
3. Attached is the completed Bidder Information and Experience form.
4. Attached is the fully executed Non-Collusion Declaration form.
5. Attached is the completed Iran Contracting Act Certification form.
6. Attached is the completed Public Works Contractor Registration Certification form.
7. Attached is the completed Contractor’s Certificate Regarding Workers’ Compensation form.
- 15 -
BID SCHEDULE
ITEM
NO.
ITEM DESCRIPTION UNIT LUMP SUM BID PRICE
1. Mobilization LS $
2.
Demolition, Removal, & Disposal of Existing Synthetic Turf
LS $
3.
Existing Base Evaluation, Leveling, Compaction & Testing
LS $
4.
ALLOWANCE: Additional Top Rock for Releveling
($30,000.00 fixed allowance established by the District for additional top rock materials, placement, and related Work required to address unforeseen existing base conditions. Bidder shall include the full $30,000.00 allowance in the Total Bid Price.)
LS $ 30,000.00
5. Shock-Absorbing Pad LS $
6. New 2” Synthetic Turf System LS $
7. GMAX Testing LS $
8.
8-Year 3rd Party Prepaid Insured Turf Warranty
LS $
9.
Inlaid 4” U9 Soccer Markings with NFL Flag Football Overlay
LS $
10.
Concrete Footings & Anchor System for Soccer Goals (6 Total)
LS $
11.
Removal & Disposal of Football Field Goals (2 Total)
LS $
TOTAL BID PRICE: Sum of Each Item, including Allowance $
Basis of Total Bid Price and Allowance
The Total Bid Price shall be the sum of the individual bid amounts for Items 1 through 11, including the fixed $30,000.00 allowance identified in Item 4. The Bidder shall include the full
- 16 -amount of the allowance in its Total Bid Price and shall not modify, reduce, or omit the allowance amount.
The costs of all Work shown, specified, or otherwise required by the Contract Documents, but not specifically identified as a separate bid item, shall be included in the related bid items. No additional compensation shall be due for such Work.
For purposes of evaluating Bids, the District will verify the arithmetic addition of the individual bid amounts for Items 1 through 11, including the $30,000.00 allowance, to determine the Total Bid Price. In the event of a discrepancy between the sum of the individual bid item amounts and the Total Bid Price entered by the Bidder, the sum of the individual bid item amounts shall govern. The District will correct the Total Bid Price accordingly for purposes of determining the lowest responsive, responsible Bidder.
TOTAL BID PRICE:
TOTAL BID PRICE BASED ON BID SCHEDULE
for
Hal Bartholomew Sports Park Synthetic Turf Replacement Project
Total Bid Price in Numbers
Total Bid Price in Written Form
The Total Bid Price entered above shall be the same as the sum of Items 1 through 11 in the Bid Schedule, including the $30,000.00 allowance.
In the event of a discrepancy between the numerical and written Total Bid Price, the written Total Bid Price shall govern, provided it is consistent with the sum of the individual bid items.
In the event of a discrepancy between the Total Bid Price stated above and the sum of the individual bid items, the individual bid item amounts shall govern, and the District shall correct the Total Bid Price accordingly for purposes of bid evaluation.
The undersigned agrees that this Bid Form constitutes a firm offer to the District which cannot be withdrawn for the number of calendar days indicated in the Notice Inviting Bids from and after the Bid opening, or until a Contract for the Work is fully executed by the District and a third party, whichever is earlier.
- 17 -
The successful bidder hereby agrees to sign the Contract and furnish the necessary bonds and certificates of insurance within ten (10) working days after the District provides the successful bidder with the Notice of Award.
Upon receipt of the signed Contract and other required documents, the Contract will be executed by the District, after which the District will prepare a letter giving Contractor Notice to Proceed.
The official starting date shall be the date of the Notice to Proceed, unless otherwise specified.
The undersigned agrees to begin the Work within ten (10) working days of the date of the Notice to Proceed, unless otherwise specified.
The undersigned has examined the location of the proposed work and is familiar with the Drawings and Specifications and the local conditions at the place where work is to be done.
If awarded the Contract, the undersigned agrees that there shall be paid by the undersigned and by all subcontractors to all laborers, workers and mechanics employed in the execution of such Contract no less than the prevailing wage rate within Sacramento County for each craft, classification, or type of worker needed to complete the Work contemplated by this Contract as established by the Director of the Department of Industrial Relations. A copy of the prevailing rate of per diem wages are on file at the District’s Administration Office and shall be made available to interested parties upon request.
Enclosed find cash, bidder’s bond, or cashier’s or certified check No. _________ from the __________________ Bank in the amount of ____________________________, which is not less than ten percent (10%) of this bid, payable to Cosumnes Community Services District as bid security and which is given as a guarantee that the undersigned will enter into a Contract and provide the necessary bonds and certificates of insurance if awarded the Work.
The bidder furthermore agrees that in case of bidder’s default in executing said Contract and furnishing required bonds and certificates of insurance, the cash, bidder’s bond, or cashier’s or certified check accompanying this proposal and the money payable thereon shall become and shall remain the property of the Cosumnes Community Services District.
Bidder is an individual ______, or corporation ______, or partnership ______, organized under the laws of the State of _______________________________.
Bidder confirms license(s) required by California State Contractor’s License Law for the performance of the subject project are in full effect and proper order. The following are the Bidder’s applicable license number(s), with their expiration date(s) and class of license(s):
If the Bidder is a joint venture, each member of the joint venture must include the required licensing information.
Sureties that will furnish the Faithful Performance Bond and the Labor and Material Payment Bond, in the form specified herein, in an amount equal to one hundred percent (100%) of the contract price within ten (10) working days from the date the District provides the successful bidder
- 18 -the Notice of Award. Sureties must meet all of the State of California bonding requirements, as defined in California Code of Civil Procedure Section 995.120 and must be authorized by the State of California.
The insurance company or companies to provide the insurance required in the Contract documents must have a Financial Strength Rating of not less than “A-” and a Financial Size Category of not less than “Class VII” according to the latest Best Key Rating Guide. At the sole discretion of the District, the District may waive the Financial Strength Rating and the Financial Size Category classifications for Workers’ Compensation insurance.
(signatures continued on next page)
- 19 -
I hereby certify under penalty of perjury under the laws of the State of California that all of the information submitted in connection with this Bid and all of the representations made herein are true and correct.
Executed at _________________________, on this ____ day of __________, _____.
(Bidders Name – Print or Type)
(Name and Title)
(Corporate Seal)
(Signature)
Names of individual members of firm or names and titles of all officers of corporation and their addresses are listed below:
Name Title
Complete Address
Phone FAX
Name Title
Complete Address
Phone FAX
Name Title
Complete Address
Phone FAX
Name Title
Complete Address
Phone FAX
- 20 -
1.2 Bid Bond
[Note: Not required when other form of Bidder’s Security, e.g. cash, certified check or cashier’s check, accompanies bid.]
The makers of this bond are, _____________________________________________, as Principal, and ______________________________________________________, as Surety and are held and firmly bound unto the Cosumnes Community Services District, hereinafter called the District, in the penal sum of TEN PERCENT (10%) OF THE TOTAL BID PRICE of the Principal submitted to District for the work described below, for the payment of which sum in lawful money of the United States, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that whereas the Principal has submitted the accompanying bid dated ________________, 20 ____, for PM-27-046 Hal Bartholomew Sports Park Synthetic Turf Replacement Project. If the Principal does not withdraw its Bid within the time specified in the Contract; and if the Principal is awarded the Contract and provides all documents to the District as required by the Contract; then this obligation shall be null and void.
Otherwise, this bond will remain in full force and effect.
Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract shall in affect its obligation under this bond, and Surety does hereby waive notice of any such changes.
In the event a lawsuit is brought upon this bond by the District and judgment is recovered, the Surety shall pay all litigation expenses incurred by the District in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and expenses.
IN WITNESS WHEREOF, the above-bound parties have executed this instrument under their several seals this _______ day of ________________, 20____, the name and corporate seal of each corporation.
(Corporate Seal) Contractor/ Principal
By
Title
(Corporate Seal) Surety
By Attorney-in-Fact
(Attach Attorney-in-Fact Certificate) Title
- 21 -
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.
STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory Name(s) of Signer(s) evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .