County Center Generator Replacement - Bid Notice Summary
This is a Bid Notice issued by the County of Westchester, New York, Department of Public Works and Transportation, Division of Engineering for Contract No. 24-521, the County Center Generator Replacement project located at 198 Central Avenue, White Plains, New York. The project involves furnishing and installing all labor, materials, and equipment necessary to complete the emergency generator system and main switchgear installation, including removal of existing electrical equipment, installation of a concrete pad for the generator and enclosure, grounding rings, a standby emergency generator manufactured by Cummins with switchgear and transfer switches, electrical equipment, wiring devices, electrical manholes, underground duct banks, wire, raceways, and boxes. A mandatory pre-bid site inspection is scheduled for June 23, 2026 at 10:00 a.m. at County Center in White Plains, with bidders required to contact Michael DeFonce at the Department of Public Works to indicate interest. Sealed bids are due by 11:00 a.m. on Wednesday, July 1, 2026, with public opening and reading immediately thereafter in Room 527 of the Michaelian Office Building at 148 Martine Avenue, White Plains. The bid opening will also be livestreamed via WebEx. Bid documents must be obtained from the Empire State Purchasing Group website at bidnetdirect.com/new-york at no cost, available after 1:00 p.m. on the advertising date of June 12, 2026. The completion deadline is 1,095 consecutive calendar days from the date the contractor receives notice to commence work, which must begin within ten days of such notice.
Bids over $100,000 must be accompanied by a Bid Bond equal to twenty-five percent of the bid amount and a Performance and Payment Bond equal to one hundred percent of the total contract price upon award. The contract bond and insurance amount must not exceed three percent of the total contract price. The contractor must directly employ at least ten percent of personnel working on the contract, measured in man-days, and cannot subcontract more than ninety percent of the work. All contractors and subcontractors must be registered with the New York State Department of Labor prior to bidding and commencing work. Prevailing wage requirements apply, with the Contractor required to pay prevailing wage rates and supplements as set forth in New York Labor Law Articles 8 and 9. For contracts exceeding $250,000, all employees must complete OSHA 10-hour training; for contracts exceeding $1,000,000, OSHA 30-hour training is required. A Project Labor Agreement with the Building and Construction Trades Council of Westchester and Putnam Counties is mandatory. The County requires proof of various insurance coverages including workers' compensation, commercial general liability with $1,000,000 combined single limit per occurrence, commercial umbrella/excess insurance of $2,000,000, and automobile liability of $1,000,000. Contractors must comply with the County's Minority Participation Policy and submit a separate sealed list of proposed subcontractors with agreed-upon prices before contract award. No bidder may withdraw its bid within forty-five days after the bid opening date.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Kenneth W. Jenkins, Westchester County Executive
General Requirements and Proposals Information for Bidders General and Special Clauses Technical Specifications
COUNTY CENTER GENERATOR REPLACEMENT
198 CENTRAL AVENUE
WHITE PLAINS, NEW YORK
Contract No. 24-521 Bid Opening: July 1, 2026
DEPARTMENT OF PUBLIC WORKS AND TRANSPORTATION
Division of Engineering
By Bidder (Please Print) For Official Use Only Firm/Business Name:
Address:
CONTRACT NO. 24-521
July 2025
SPECIAL NOTICE
County of Westchester New York
ADDENDA TO THE BID DOCUMENTS
Addenda to the Bid Documents will be published on the Empire State Purchasing Group website at (http://www.bidnetdirect.com/new-york) It is the responsibility of each potential bidder to check the website on a regular basis for further information relative to the bid documents including information relating to any and all addenda prior to submitting its bid. All Bidders are deemed to have reviewed and considered all addendums in their Bid.
SUBMISSION OF BIDS
Bidders should not submit the entire bid document with its bid submission. Instead, each bidder is required to submit the full set of designated Proposal Pages. The Proposal Pages are denoted by a border and are titled on the bottom as “Proposal Page _6__”. The Proposal Pages must be accompanied by the “Bid Bond and Consent of Surety” (as set forth in the Proposal Pages) attached to the outside of the sealed bid. A Bid Bond is NOT required for contracts of $100,000 or less. Failure to submit in this manner may cause the bid to be rejected.
The successful bidder will be required to furnish a Performance and Payment Bond.
March 2026
SPECIAL NOTICE
County of Westchester New York
PRE-BID SITE INSPECTION
A. Superseding the first paragraph of Article “Pre-Bid Site Inspection” of the Information for Bidders, bidders will be permitted to examine the work site only under escort by the County’s representative at 10:00 a.m. on Tuesday, June 23, 2026 at a meeting at the (County Center, White Plains, New York). Monday, June 22, 2026 per Addendum No. 1
B. Bidders shall indicate their interest in the site examination by contacting (Michael DeFonce), Department of Public Works, Division of Engineering at (914-995-7740).
C. All other portions of Article “Pre-Bid Site Inspection” of the Information for Bidders shall remain in full force and effect.
Elaine Sheehan Krauss Line
SPECIAL NOTICE
County of Westchester New York
MINORITY PARTICIPATION POLICY
Contractors must comply with the County’s Minority Participation Policy, including, but not limited to, the requirement that contractors make a demonstrated good faith effort to utilize Minority Owned Businesses (“MOB”) and Women Owned Businesses (“WOB”) (see IFB Article 36). To assist contractors in this effort the County has made available a list of MOB and WOB at http://mwbe.westchestergov.com/ Contractors are also encouraged to utilize other sources to identify potential MOB and WOB as subcontractors and suppliers.
All bidders must submit as part of their bid package the Minority/Women Owned Business Enterprise Questionnaire located in the Proposal Page section of the bid documents.
http://mwbe.westchestergov.com/
SPECIAL NOTICE
County of Westchester New York
CHANGES IN THE WICKS LAW
Effective July 1, 2008, construction contracts of one million five hundred thousand dollars or less will not require the preparation of separate contracts for plumbing and gas fitting; steam heating, hot water heating, ventilation and air conditioning apparatus; and electric wiring and standard illuminating fixtures and general construction.
Each bidder on a public work contract, where the preparation of separate contracts is not required shall, to the full extent applicable, submit with its bid a separate sealed list that names each Subcontractor that the bidder will use to perform work on the contract and the agreed upon price to be paid to each for (a) plumbing and gas fitting, (b) steam heating, hot water heating, ventilating and air conditioning apparatus and (c) electric wiring and standard illuminating fixtures and (d) general construction. The submission (Proposal Page 6) that contains the agreed upon price shall be acknowledged by both Contractor and Subcontractor. For purposes of this paragraph, the acknowledgment from the Subcontractor may contain the facsimile signature of an officer of the Subcontractor.
After the low bid is announced, the sealed list of subcontractors submitted with the bid shall be opened and the names of such subcontractors shall be announced. Thereafter, any changes of subcontractors or agreed-upon amount to be paid to each shall require the approval of the County upon a showing of legitimate construction need for such change.
The Successful low bidder, before award of the contract, must procure and provide to the County, from each of the above denoted Subcontractors, a Contract Disclosure Statement and the Required Disclosure of Relationships to County forms.
The sealed lists of Subcontractors submitted by unsuccessful bidders shall be destroyed after the contract award.
THIS PROJECT IS NOT SUBJECT TO THE REQUIREMENTS OF THE
“WICKS LAW”. ACCORDINGLY, EACH BIDDER IS REQUIRED TO
SUBMIT SPECIFIC INFORMATION PERTAINING TO ITS PROPOSED
SUBCONTRACTORS. PLEASE SEE THE “NOTICE TO CONTRACTORS”
THAT FORMS A PART OF THESE BID DOCUMENTS.
SPECIAL NOTICE
County of Westchester New York
COMPLETION OF GRANT FUNDING FORMS
The bidders are hereby notified that if this project, or any portion thereof, is funded by a grant then the contractor will be responsible to complete all appropriate forms as required by the grant agency in order to complete the application.
PROMPT EXECUTION AND RETURN OF CONTRACT
A. The successful bidder is required to return the completed contract to the County within ten (10) days of receipt of the execution copy of the contract. The contract must be signed, notarized and returned to the County with all insurance certificates, bonds and supporting documentation, including all required Subcontractor information.
B. The County reserves all of its rights, including, but not limited to, proceeding against the bid bond, if the successful bidder fails to submit the complete executed package within the above time frame.
SPECIAL NOTICE
County of Westchester New York
PROOF OF PAYMENT BY CONTRACTOR TO SUBCONTRACTORS AND
MATERIALMEN.
In addition to and without limiting any of the provisions set forth in Section 23 of the Information for Bidders, after the Contractor completes 50% of the work under the contract, the Contractor may be required to supplement each requisition submitted to the County with documentation that establishes that the Contractor has timely and properly paid its subcontractors and materialmen as required by Section 23 of the Information For Bidders. Such documentation required may include copies of both sides of cancelled check(s) paid to the order of the subcontractors and materialmen and such other documentation as may be reasonably requested by the Commissioner. If the Contractor fails to submit such documentation, the Commissioner may, in his sole discretion, withhold payment of the requisition until such time as the documentation is properly submitted. Nothing herein is intended or shall be construed to confer upon or give any subcontractor or materialman, or its successors and assigns, any third party beneficiary rights, remedies or basis for reliance upon, under or by reason of the contract or this Special Notice provision.
SPECIAL NOTICE
County of Westchester New York
PREVAILING WAGE
All public works contracts are subject to the payment of the prevailing wage and supplements as set forth by the laws of the State of New York, including, but not limited to, Articles 8 and 9 of the New York Labor Law (the “Prevailing Wage Laws”). Westchester County has an active Prevailing Wage Enforcement Officer who enforces the Prevailing Wage Laws within the County for public works contracts, including reviewing certified payroll records, visiting job sites, interviewing the employer and employees (See IFB Article 12) and, if necessary, requesting copies of cancelled checks.
Any Contractor who fails to comply with the Prevailing Wage Laws, including, but not limited to, failing to pay the prevailing wage rates and supplements, failing to submit certified payroll records to the County or failing to post the prevailing wage rates and supplements at the work site, will be subject to enforcement as provided for in the Contract and laws of the State of New York through the Westchester County District Attorney’s office, the Commissioner of the New York State Department of Labor, the County and/or the employee who suffered the underpayment. This enforcement could include, but is not limited to, criminal penalties, civil penalties, debarment from future bid awards, the withholding of payment under the Contract to satisfy the unpaid wages and supplements, including interest and civil penalty. In addition, such a failure shall constitute grounds for cancellation of the Contract (IFB 8(C)). Moreover, a prime contractor is responsible for its subcontractor’s failure to comply with, or evasion of, the provisions of the Prevailing Wage Laws.
SPECIAL NOTICE
County of Westchester New York
MANDATORY OSHA CERTIFICATION
When a public works contract is in excess of $250,000.00, all employees are required to have successfully completed the OSHA 10 hours training class. All contractors and subcontractors must attach copies of proof of completion of the OSHA 10 hour course by all employees to the first certified payroll submitted to the County and on each succeeding payroll where any new or additional employee is first listed. Employees may be requested by the County’s representative to verify compliance with the OSHA 10 hour course by showing their OSHA card.
When a public works contract is in excess of $1,000,000.00, all employees are required to have successfully completed the OSHA 30 hours training class. All contractors and subcontractors must attach copies of proof of completion of the OSHA 30 hour course by all employees to the first certified payroll submitted to the County and on each succeeding payroll where any new or additional employee is first listed. Employees may be requested by the County’s representative to verify compliance with the OSHA 30 hour course by showing their OSHA card.
In addition, on any contract that includes excavation of underground facilities, the excavator is required to be certified and have completed the training and education program provided by the one-call notification system (Dig Safely New York, Inc. Certified Excavator Program in Safe Digging Best Practices) or any other provider authorized by the public service commission to administer such training and education program.
SPECIAL NOTICE
County of Westchester New York
NEW CONTRACTOR REGISTRY LAW
Beginning December 30, 2024, subsection 220-i in Article 8 of the New York State Labor Law (the “Contractor Registry Law”) mandates that all contractors and subcontractors bidding on or performing contracted work on a covered project must register with the New York State Department of Labor
(NYSDOL).
A covered project is defined as any project subject to Article 8 of the New York State Labor Law, including but not limited to, public work projects and those subject to the provisions of Section 224-a and 224-d of the New York State Labor Law.
Who Must Register with the NYSDOL?
• Contractors: Defined as any entity entering into a contract to perform construction, demolition, reconstruction, excavation, rehabilitation, repair, installation, renovation, alteration, or custom fabrication.
• Subcontractors: Defined as any entity subcontracting with a contractor to perform construction, demolition, reconstruction, excavation, rehabilitation, repair, installation, renovation, alteration, or custom fabrication, as outlined in Article 8 of the Labor Law.
For more information on how to register with the NYSDOL, please visit: https://dol.ny.gov/how-register-contractor-and-subcontractor-registry
BIDDERS ARE HEREBY NOTIFIED:
• No contractor shall bid on a contract for public work unless such contractor is registered with the NYSDOL.
• Each contractor must submit its certificate of registration at the time the bid is made.
Applications for registration shall not be accepted as a substitute for a certificate of registration.
• Subcontractors must be registered prior to commencing any work on the covered project.
• Contractors are responsible for verifying that their subcontractors are registered prior to commencing subcontracted work on the contract and shall submit information regarding their subcontractor’s registration as may be requested by the County.
• For a contractor or subcontractor who has been determined unfit by the Commissioner of the NYSDOL while performing contracted work, the contracted work shall only continue if a monitor is appointed to oversee the work completed. Such monitor must be approved by the Commissioner of the NYSDOL. Contractor shall be responsible for securing the appointment of the monitor. The contractor shall take all steps necessary to ensure there is no interruption in the project schedule as a result of such determination. The cost of the monitor shall be at the sole expense of such contractor or subcontractor who has been determined to be unfit. Failure of the contractor to either secure the appointment of a monitor or obtain a replacement contractor or subcontractor to complete the contracted work to the satisfaction of the Commissioner of Public Works and Transportation shall be deemed an act of default under the contract.
https://dol.ny.gov/contractor-and-subcontractor-landing https://dol.ny.gov/how-register-contractor-and-subcontractor-registry https://dol.ny.gov/how-register-contractor-and-subcontractor-registry
SPECIAL NOTICE
County of Westchester
New York
JOINT VENTURES OR CONTRACTORS COMPRISED OF MORE THAN ONE LEGAL
ENTITY
(a) If the Contractor is a joint venture or otherwise comprised of more than one legal entity or any group of partners, participants or joint ventures associated for the purpose of undertaking this agreement, each such entity, partner and/or participant acknowledges and hereby affirmatively represents and agrees that each has the power to bind the Contractor and each of the others hereunder;
and as such, each acts both as principal and agent of the Contractor and of each of the others hereunder. Each further acknowledges and agrees that all such entities, participants and/or partners of the joint venture associated for the purposes of undertaking this agreement expressly agree to be jointly and severably liable for any and all obligations and/or liabilities of the Contractor arising in any way out of and in connection with this agreement.
(b) If the Contractor is a joint venture, or otherwise comprised of more than one legal entity or any group of partners, participants or joint ventures associated for the purposes of undertaking this agreement, the Contractor represents and warrants to the County that it is duly organized under the laws of the State of New York, and that each and every entity, partner, participant or joint venture of Contractor agrees to separately execute the agreement, by its own authorized representative, with the appropriate acknowledgment and verification.
(c) If the Contractor is a joint venture or otherwise comprised of more than one legal entity or any group of partners, participants or joint ventures associated for the purpose of undertaking this agreement, either at least one such entity, partner and/or participant comprising the Contractor and on behalf of the Contractor or the Contractor itself, shall comply with all requirements of the bid specifications herein and prerequisites to submit a bid, including but not limited to attendance of any mandatory pre-bid meetings, if any, and obtaining the bid documents and any addenda from the Empire State Purchasing Group website, or any successor website for posting of bid documents.
(d) If the Contractor is a joint venture or otherwise comprised of more than one legal entity or any group of partners, participants or joint ventures associated for the purposes of undertaking this agreement, each such entity, partner and/or participant acknowledges and hereby affirmatively represents and agrees that the respective rights, duties and liabilities of each hereunder shall be governed by the laws of the State of New York, including but not limited to the New York Partnership Law.
SPECIAL NOTICE
County of Westchester New York
PROJECT LABOR AGREEMENT (PLA)
A. The County of Westchester has determined that a Project Labor Agreement will be used on this Project. The successful bidder will be required as a condition of this Contract to execute the PLA with the Building and Construction Trades Council of Westchester and Putnam Counties, New York, AFL-CIO ("Council"). The PLA will be substantially in the same form as the PLA included in this contract specification book. Bidders are urged to familiarize themselves with the terms and conditions of the PLA.
Contract No. 24-521
SPECIAL NOTICE
County of Westchester New York
INSURANCE REQUIREMENTS
1. The Contractor, upon award of the contract and throughout the term of the contract, shall furnish, deliver and maintain at its own cost and expense the required insurance as indicated below from insurance companies licensed in the State of New York, carrying a Best's financial rating of A or better. The Contractor shall provide evidence of such insurance to the County by providing a copy of the policies, endorsements, and/or certificates as may be required and approved by the Director of Risk Management of the County (“Director”). The policies, endorsements, or certificates thereof shall provide that ten (10) days prior to cancellation or material change in the policy, notices of same shall be given to the Board of Acquisition and Contract of the County of Westchester by registered mail, return receipt requested, for all of the following stated insurance policies, with a copy also sent to the Director. All notices shall name the Contractor and identify the contract number.
If at any time any of the policies required herein shall be or become unsatisfactory to the Director, as to form or substance, or if a company issuing any such policy shall be or become unsatisfactory to the Director, the Contractor shall upon notice to that effect from the County, promptly obtain a new policy, and submit the policy, endorsement, or the certificate as requested by the Director for approval by the Director. Upon failure of the Contractor to furnish, deliver and maintain such insurance, the contract, at the election of the County, may be declared suspended, discontinued or terminated.
Failure of the Contractor to take out, maintain, or the taking out or maintenance of any required insurance, shall not relieve the Contractor from any liability under the contract, nor shall the insurance requirements be construed to conflict with or otherwise limit the contractual obligations of the Contractor concerning indemnification.
All property losses shall be made payable to the “County of Westchester” and adjusted with the appropriate County personnel.
Upon policy renewal or expiration, evidence of renewal or replacement of coverage that complies with the insurance requirements delineated below shall be delivered to the County. If any insurance requirements are not complied with at their expiration or renewal dates, the Contractor shall immediately cease work. The Contractor shall not resume work until authorized to do so by the County. In addition, payment to the Contractor may be withheld until those requirements have been met, or, at the option of the County, the County may pay the renewal premium and withhold such payments from any monies due the Contractor under the contract or under any other agreement the Contractor may have with the County.
In the event that claims, for which the County may be liable, in excess of the insured amounts provided herein are filed by reason of Contractor’s negligent acts or omissions under the contract or by virtue of the provisions of the labor law or other statute or any other reason, the amount of excess of such claims or any portion thereof, may be withheld from payment due or to become due the Contractor until such time as the Contractor shall furnish such additional security covering such claims in form satisfactory to the Director.
In the event of any loss, if the Contractor maintains broader coverage and/or higher limits than the minimums identified herein, the County shall be entitled to the broader coverage and/or higher limits maintained by the Contractor. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the County.
SPECIAL NOTICE
County of Westchester New York
2. The Contractor shall provide evidence of the insurance for each coverage indicated by a blackened box (■) or by an X in a to the left below:
Workers' Compensation and Employer’s Liability: Certificate form C-105.2 or State Fund Insurance Company form U-26.3 is required for proof of compliance with the New York State Workers' Compensation Law. State Workers' Compensation Board form DB-120.1 is required for proof of compliance with the New York State Disability Benefits Law. Location of operation shall be "All locations in Westchester County, New York."
Where an applicant claims to not be required to carry either a Workers' Compensation Policy or Disability Benefits Policy, or both, the employer must complete NYS form CE-200, available to download at:
http://www.wcb.ny.gov.
If the employer is self-insured for Workers’ Compensation, he/she should present a certificate from the New York State Worker's Compensation Board evidencing that fact (Either SI-12, Certificate of Workers’ Compensation Self-Insurance, or GSI-105.2, Certificate of Participation in Workers’ Compensation Group Self- Insurance).
Commercial General Liability Insurance with a combined single limit of $1,000,000 (c.s.l.) per occurrence and either no aggregate limit or, if there is an aggregate limit, a minimum $2,000,000 aggregate limit, naming the “County of Westchester” as an additional insured on a primary and non-contributory basis. This insurance shall include the following coverages:
i. Premises - Operations.
ii. Broad Form Contractual.
iii. Independent Contractor and Sub-Contractor.
iv. Products and Completed Operations.
NOTES: (a) Additional insured status shall be provided by standard or other endorsement that extends coverage to the County of Westchester for both on-going and completed operations.
(b) All Contracts involving the use of explosives, demolition and/or underground work shall provide proof that XCU is covered.
Commercial Umbrella/Excess Insurance: $2,000,000 per occurrence and either no aggregate limit, or, if there is an aggregate limit, a minimum $4,000,000 aggregate limit, naming the “County of Westchester” as an additional insured, written on a “follow the form” basis.
NOTES: Notes (a) through (b) above under the Commercial General Liability Insurance shall also apply to Commercial Umbrella/Excess Insurance.
http://www.wcb.ny.gov/
SPECIAL NOTICE
County of Westchester New York
Automobile Liability Insurance with a minimum limit of liability per occurrence of $1,000,000 for bodily injury and a minimum limit of $100,000 per occurrence for property damage or a combined single limit of $1,000,000 unless otherwise indicated in the contract specifications, and naming the “County of Westchester” as an additional insured. This insurance shall include for bodily injury and property damage the following coverages:
(i) Owned automobiles.
(ii) Hired automobiles.
(iii) Non-owned automobiles.
Builder’s Risk Insurance for Bridges, Viaducts or Similar Structures: For the construction, renovation or repair of bridges, viaducts or similar structures, the Contractor at its own cost and expense shall furnish, deliver and maintain a "Bridge Builder's Risk Form, All Risk Insurance Contract," with flat premium endorsement, until the construction contract is accepted by the Board of Acquisition and Contract of the County of Westchester. The coverage shall also include business interruption and contingent interruption and extra expense coverage. The coverage shall be written for 100% of the completed value, covering and naming the Contractor and “County of Westchester” as the insureds. The Contractor shall provide the original and duplicate copy of the policy, as well as any and all endorsements, to the County.
Builder’s Risk Insurance for Buildings and Facilities: For the construction of (a) new buildings and (b) for additions or repairs of existing buildings or facilities, the Contractor at its own cost and expense shall furnish, deliver and maintain a "Builder's Risk Form, All Risk Insurance Contract," with flat premium endorsement, until the construction contract is accepted by the Board of Acquisition and Contract of the County of Westchester.
The coverage shall also include business interruption and contingent business interruption and extra expense coverage. The coverage shall be written for 100% of the completed value, covering and naming the Contractor and “County of Westchester” as the insureds. The Contractor shall provide the original and duplicate copy of the policy, as well as any and all endorsements, to the County.
Owners Protective Liability Policy covering and naming the “County of Westchester” as insured, with a minimum limit of liability per occurrence of $3,000,000. The Contractor shall provide the original and duplicate copy of the policy to the County.
Crane, Rigging, & Crane Operator (Rigger Liability) Insurance with a minimum limit of liability per occurrence of $5,000,000 for bodily injury and a minimum limit of $500,000 per occurrence for property damage or a combined single limit of $5,000,000, naming the “County of Westchester” as an additional insured
Pollution Liability, either by separate policy of insurance or through endorsement to the General Liability
Policy with a minimum limit of $1,000,000.00, naming the “County of Westchester” as an additional insured.
This insurance shall indicate the following coverages:
(i) Transit
(ii) Sudden and Accidental
(iii) Clean-up
SPECIAL NOTICE
County of Westchester New York
Asbestos and Lead Abatement General Liability Occurrence Policy in amounts not less than $1,000,000 and naming the “County of Westchester” as an additional insured.
Other:________________________________________________________________________________
3. All policies of the Contractor shall be endorsed to contain the following clauses:
(a) Insurers shall have no right to recovery or subrogation against the County (including its employees and other agents and agencies), it being the intention of the parties that the insurance policies so effected shall protect both parties and be primary coverage for any and all losses covered by the above-described insurance.
(b) The clause "other insurance provisions" in a policy in which the County is named as an insured, shall not apply to the County.
(c) The insurance companies issuing the policy or policies shall have no recourse against the County (including its agents and agencies as aforesaid) for payment of any premiums or for assessments under any form of policy.
(d) Any and all deductibles in the above described insurance policies shall be assumed by and be for the account of, and at the sole risk of, the Contractor.
4. In the event that any portion of the work described in this contract is to be performed by a subcontractor, the Contractor shall require in a written agreement with the subcontractor that the subcontractor furnish and maintain the above insurance, including naming the “County of Westchester” as an additional insured where indicated, unless, in the sole discretion of the County Director of Risk Management, the subcontractor is released from the requirement to provide such insurance. The Contractor shall provide proof of such insurance to the County Director of Risk Management. The subcontractor shall not commence work under the contract unless and until such proof of insurance has been approved by the Director of Risk Management.
5. The above policies for the Contractor and/or any of its subcontractors shall not contain any endorsements, terms, conditions or definitions that result in any labor law or action over exclusions.
6. The types of insurance required and/or policy limits listed above may be adjusted any time during the contract term by the Director when deemed appropriate, even if not indicated above by a blackened box (■) or by an X.
Certificate Holder on all certificates of insurance shall read: The County of Westchester, 148 Martine Avenue, White Plains, New York 10601.
PLEASE NOTE: Printed copies of all of your full insurance policies, and any and all endorsements, are required.
NOTICE TO CONTRACTORS
County of Westchester New York
Sealed proposals for the following construction work:
CONTRACT NO: 24-521 ADVERTISING: June 12, 2026
PRE-BID INSPECTION: June 23, 2026
County Center Generator Replacement 198 Central Avenue
White Plains, New York
Will be received by the Board of Acquisition and Contract in Room 104, Michaelian Office Building, 148 Martine Ave., White Plains, New York until 11:00 a.m., Wednesday, July 1, 2026, and immediately thereafter, the bids will be publicly opened and read aloud in Room 527 of the said building.
The bid opening also will be made accessible to the public via the livestreaming service WebEx. The livestreaming of the bid opening via WebEx is in addition to and not in place of the publicly bid opening to be held in Room 527 of the Michaelian Office Building. For additional bidding information or questions call (914) 995-2274.
Instructions for livestreaming via WebEx. Attendees may join by computer browser at https://westchestergov.webex.com/meet/bac-bidopening or by phone 1-415-655-0001 US Toll or 1-844-621-3956 US Toll Free. The Access Code is 614 981 028.
The Bid Documents (General Requirements, Information for Bidders, Technical Specifications, etc. with Authorized Proposal Pages and Contract Drawings) MUST BE OBTAINED from the Empire State Purchasing Group website at the following web address:
http://www.bidnetdirect.com/new-york.
There is no cost to the bidder for this service. Bid documents will be available after 1:00 p.m. on the advertising date.
PLEASE TAKE NOTICE: IN ORDER TO SUBMIT A BID, BIDDERS MUST REGISTER AND DOWNLOAD THE BID DOCUMENTS FROM THE EMPIRE STATE PURCHASING GROUP WEBSITE AND MUST REGISTER USING THE NAME OF THE PERSON OR BUSINESS ENTITY THAT WILL BE SUBMITTING THE BID. IN ORDER TO ENSURE THAT COUNTY BID DOCUMENTS HAVE NOT BEEN ALTERED IN ANY WAY, THE COUNTY WILL NOT ACCEPT BIDS FROM PERSONS OR BUSINESS ENTITIES THAT HAVE NOT FOLLOWED THIS REQUIREMENT.
Each bidder is required to submit the full set of authorized Proposal Pages and all bids over $100,000.00 must also be accompanied by the “Bid Bond and Consent of Surety” (as set forth in the Proposal Pages) attached to the outside of the sealed bid. Failure to submit in this manner may cause the bid to be rejected. The successful bidder, no matter the amount of its bid, will be required to furnish a Performance and Payment Bond with its signed contract.
To the full extent applicable, each bidder shall submit with its bid a separate sealed list that names each Subcontractor that the bidder will use to perform work on the contract and the agreed upon price to be paid to each for: (a) plumbing and gas fitting, (b) steam heating, hot water heating, ventilating and air conditioning apparatus and (c) electric wiring and standard illuminating fixtures and (d) general construction. The submission (Proposal Page 41) that contains the agreed upon price shall be acknowledged by both Contractor and Subcontractor. For purposes of this paragraph, the acknowledgment from the Subcontractor may contain the facsimile signature of an officer of the Subcontractor.
The Successful low bidder, before award of the contract, must obtain and provide to the County, from each of the above denoted Subcontractors, fully completed and signed Contract Disclosure Statement (Proposal Pages 24-
32) and Required Disclosure of Relationships to County (Proposal Pages 33) forms.
The sealed lists of Subcontractors submitted by unsuccessful bidders shall be destroyed, unless you request that it be returned by checking the applicable box on Proposal Page 5.
The County of Westchester reserves the right to waive any informalities in the bids, or to reject any or all bids. No bidder may withdraw its bid within forty-five (45) days after the date of the bid opening.
Pursuant to Chapter 308 of the Laws of the County of Westchester, it is the goal of the County to use its best efforts to encourage, promote, and increase the participation of business enterprises owned and controlled by persons of color or women - Minority Business Enterprise (MBE) and Women Business Enterprise (WBE).
REMINDER: All required licenses should be submitted with the Bid.
COUNTY OF WESTCHESTER, NEW YORK
DEPT OF PUBLIC WORKS AND TRANSPORTATION
BY: Hugh J. Greechan, Jr., P.E., Commissioner
June 22, 2026 Addendum No. 1 https://westchestergov.webex.com/meet/bac-bidopening%20or%20by%20phone%201-415-655-0001 https://westchestergov.webex.com/meet/bac-bidopening%20or%20by%20phone%201-415-655-0001 http://www.bidnetdirect.com/new-york Elaine Sheehan Krauss Line
TABLE OF CONTENTS
SECTION 1: GENERAL REQUIREMENTS AND PROPOSALS
TOC 1
(WC DPW E Version 1/18)
General Requirements
1. Description Of The Work .................................................................................................1.1
2. Subcontracting & Direct Employment Of Labor ..............................................................1.2
3. Required Time For Completion Of The Work .................................................................1.2
4. Security Regulations .........................................................................................................1.3
5. Payment for Bonds and Insurance ....................................................................................1.5
Contract Drawings
Contract Drawings ........................................................................................... Contract Drawings 1
Proposal Forms
Bidder's Identification .............................................................................................. Proposal Page 1 Proposal Requirements and Addendum Receipt...................................................... Proposal Page 2 Non-Collusive Bidding Certification ....................................................................... Proposal Page 4 Bid Page(s) ............................................................................................................... Proposal Page 6 Contractor's Acknowledgement ............................................................................... Proposal Page 7 Contractor’s Acknowledgement (Corporation/Sole Officer) ................................... Proposal Page 8 Limited Liability Company Acknowledgement ...................................................... Proposal Page 9 Certificate of Authority .......................................................................................... Proposal Page 10 Certificate of Authority-Limited Liability Company ............................................ Proposal Page 11 Bid Bond and Consent of Surety ........................................................................... Proposal Page 12 Affirmative Action Program Requirement (Contractors) ...................................... Proposal Page 13 Apprenticeship Training Program Requirement .................................................... Proposal Page 14 Certificate of License (Electrical) .......................................................................... Proposal Page 15 Certificate of License (Plumbing) .......................................................................... Proposal Page 17 Certificate of License (Hauler) .............................................................................. Proposal Page 19 Stormwater Pollution Prevention Certification ...................................................... Proposal Page 20 Prevailing Wage Rates and Supplement ............................................................... Proposal Page 21 MBE/WBE Program Questionnaire ...................................................................... Proposal Page 22 Contractor Disclosure Statement .......................................................................... Proposal Page 23 Required Disclosure of Relationships to County .................................................. Proposal Page 32 Service-Disabled Veterans-Owned Business Questionnaire ................................. Proposal Page 34 Schedule “F” Criminal Background Disclosure .................................................... Proposal Page 35 Subcontractors Sealed Bid Submission…………………………………………..Proposal Page 41
SECTION 2: INFORMATION FOR BIDDERS
TOC 2
(WC DPW E Version 11/24/08)
1. Addenda And Interpretation .............................................................................................2.1
2. Voided Clauses .................................................................................................................2.1
3. Pre-Bid Site Inspection .....................................................................................................2.1
4. Bid Security ......................................................................................................................2.1
5. Performance And Payment Bond......................................................................................2.2
6. Indemnification Agreement ..............................................................................................2.3
7. Insurance Requirements....................................................................................................2.3
8. Prevailing Wage Rates And Supplements ........................................................................2.6
9. Labor And Compliance With Labor Law .........................................................................2.9
10. Contractor's Report Of Employment And Weekly Affidavit .........................................2.13
11. Laws/Regulations And Appropriations...........................................................................2.13
12. Refusal To Answer Questions ........................................................................................2.13
13. Bid Requirements............................................................................................................2.14
14. Miscellaneous Additional Work (Item W-800) ..............................................................2.14
15. Correction Of Errors .......................................................................................................2.15
16. Shown Quantities ............................................................................................................2.15
17. Qualification Of Bidders.................................................................................................2.15
18. Required Experience.......................................................................................................2.16
19. Increase Or Decrease Of Quantities: Elimination Of Items............................................2.16
20. Breakdown Cost Of Lump Sum Items And Contracts....................................................2.16
21. Engineering Charges.......................................................................................................2.17
22. Estimates And Payments.................................................................................................2.17
23. Payments To Subcontractors And Materialmen By Contractor .....................................2.21
24. Time Of Starting .............................................................................................................2.22
25. Safety And Health Regulations For Construction And Demolition Work .....................2.22
26. Accident Prevention And First Aid Facilities.................................................................2.23
27. Fire Prevention And Control...........................................................................................2.23
28. State And Local Sales Tax Exemption ...........................................................................2.24
29. Apprentices .....................................................................................................................2.24
30. Affirmative Action Provision .........................................................................................2.24
31. Affirmative Action Program Requirement .....................................................................2.24
32. Authority To Do Business In New York ........................................................................2.25
33. License Requirements (Electrical)..................................................................................2.25
34. License Requirements (Plumbing)..................................................................................2.26
35. License Requirements (Haulers).....................................................................................2.27
36. Minority Participation Policy..........................................................................................2.30
37. Sexual Harassment Policy...............................................................................................2.32
38. Smoke-Free Workplace Policy .......................................................................................2.33
39. County Energy Efficient Purchasing Policy ...................................................................2.33
40. Restriction On Use Of Tropical Hardwoods...................................................................2.33
41. Disclosure Of Relationships To County .........................................................................2.34
42. Contractor Disclosure Statement ....................................................................................2.34
43. Criminal Background Information..................................................................................2.34
44. Mandatory OSHA Construction Safety And Health Training........................................2.36
SECTION 3: GENERAL CLAUSES
TOC 3
WC DPW E Version 11/24/08
1. Material And Workmanship .............................................................................................3.1
2. Definitions.........................................................................................................................3.1
3. Boundaries Of Work .........................................................................................................3.2
4. Overlapping Work ............................................................................................................3.2
5. Proper Method Of Work And Proper Materials ...............................................................3.4
6. Control Of Area ................................................................................................................3.5
7. Permits, Fees, Etc..............................................................................................................3.5
8. Traffic ...............................................................................................................................3.5
9. Inspection..........................................................................................................................3.5
10. Stopping Work ..................................................................................................................3.5
11. Dimensions .......................................................................................................................3.6
12. Payments To County.........................................................................................................3.6
13. Protection Of Utilities And Structures..............................................................................3.6
14. Protection Of Water Resources & The Environment .......................................................3.6
15. Sanitary Regulations .........................................................................................................3.8
16. Cleaning Up ......................................................................................................................3.8
17. Prevention Of Dust Hazard...............................................................................................3.8
18. Representative Always Present.........................................................................................3.9
19. Work In Bad Weather .......................................................................................................3.9
20. Protection Of Work Until Completion..............................................................................3.9
21. Removal Of Temporary Structures And Cleaning Up......................................................3.9
22. Gross Loads Hauled On Highway ....................................................................................3.9
23. Concrete Batch Proportions - Yield..................................................................................3.9
24. Damage Due To Contractor's Operations .......................................................................3.10
25. Property Damage ............................................................................................................3.10
26. Claims For Damages.......................................................................................................3.10
27. Extensions Of Time ........................................................................................................3.11
28. Request For Approval Of Equal .....................................................................................3.12
29. Substitution .....................................................................................................................3.15
30. Extra Work: Increased Compensation/Decreased Work: Credit To The Owner............3.18
31. Disputed Work - Notice Of Claims For Damages ..........................................................3.20
32. Contractor's Subcontracts And Material Lists ................................................................3.21
33. Assignment Of Contract .................................................................................................3.22
34. Payment For General Provisions ....................................................................................3.22
35. Costs Incurred By County...............................................................................................3.22
36. Guarantee Of Work.........................................................................................................3.23
37. Separate Contracts ..........................................................................................................3.23
38. Cooperation With Owner................................................................................................3.24
39. Job Meetings & Project Superintendant .........................................................................3.24
SECTION 3: GENERAL CLAUSES
TOC 4
(WC DPW E Version 11/24/08)
40. Patent Warranty ..............................................................................................................3.25
41. Materials .........................................................................................................................3.26
42. Standard Of Quality ........................................................................................................3.29
43. Proprietary Item ..............................................................................................................3.29
44. Shop Drawings................................................................................................................3.30
45. Sequence Of Construction Operations............................................................................3.34
46. Protection ........................................................................................................................3.36
47. Cleanup And Removal Of Debris ...................................................................................3.36
48. Temporary Service..........................................................................................................3.36
49. Operating Tests ...............................................................................................................3.37
50. Operating Instructions And Parts Lists ...........................................................................3.37
51. Cutting And Patching......................................................................................................3.37
52. Conflicts Among Contract Documents...........................................................................3.39
53. Record Drawings ............................................................................................................3.39
54. Time ................................................................................................................................3.40
55. Acceleration Of The Work..............................................................................................3.40
56. Ultra Low Sulfur Diesel Fuel..........................................................................................3.40
57. Qualified Transportation Fringe Program.......................................................................3.42
58. Use of Fluorescent Light Bulbs & Energy Efficient Bulbs ............................................3.42
59. County of…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .