Bid Notice.pdf

PDF 1 MB Posted

Attached to
Disaster Response Contingency Services
Solicitation number
902743
Issued by
Alameda County, Hayward City, California

About this file

Summary

This Bid Notice is for Request for Proposal (RFP) No. 902743 issued by the County of Alameda, California for Disaster Response Contingency Services. The County seeks to award a five-year contract with an option to renew for two additional years to a pool of up to eight bidders (one or more bidders per category) across four service categories: Category 1 (Debris Removal, Debris Management, and Environmental Compliance Services), Category 2 (Debris Monitoring Services), Category 3 (Shelter, Food Distribution, and Emergency Support Services), and Category 4 (Administrative Services and FEMA Reimbursement Support). Services are limited to non-construction disaster response and recovery operations in Alameda County, including emergency debris collection, loading, hauling, processing, recycling and disposal; independent debris monitoring; emergency shelter, feeding, water distribution, temporary equipment and logistical support; and administrative support for federal and state disaster reimbursement. The Bidders Conference is scheduled for December 3, 2026 at 10:00 AM (Pacific Time), with written questions due by December 4, 2026 at 5:00 PM. The response deadline is January 15, 2027 by 2:00 PM (Pacific Time), followed immediately by a public bid opening. The Notice of Intent to Award is expected March 29, 2027, with Board consideration and award on June 8, 2027, and a contract start date of July 1, 2027.

Compensation under any resulting contract shall be based solely on pre-established fixed prices and unit prices from the County-approved Bid Form; time-and-materials pricing and payment based on actual labor hours or equipment hours are expressly prohibited. Services will be performed only upon issuance of a written Activation Notice or Work Assignment by the GSA Director or authorized designee, and award of a contract does not guarantee any minimum amount of work or compensation. The County anticipates pursuing reimbursement through Federal Emergency Management Agency (FEMA), Federal Highway Administration (FHWA), or the California Disaster Assistance Act (CDAA); however, no particular funding source, declaration, award, or reimbursement percentage is guaranteed. All contractors must demonstrate at least five years of continuous experience providing all-hazard disaster contingency contracts for local governments in their proposed category, possess all required permits and licenses, maintain sufficient financial capacity to fund performance prior to County payment, carry all necessary insurance coverage, and comply with all applicable federal, state, and local laws and regulations. Bidders must meet all minimum qualifications or face disqualification, and no set-aside has been identified in this procurement.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP Template Rev. 7/10/25

COUNTY OF ALAMEDA

REQUEST FOR PROPOSAL No. 902743 for

DISASTER RESPONSE CONTINGENCY SERVICES

For complete information regarding this project, see Request for Proposal (RFP) posted at County of Alameda Procurement Portal [https://procurement.opengov.com/portal/acgov] or contact the County representative listed below.

Thank you for your interest!

Contact Person: Yulia Margolin

Phone Number: (510) 208 9615

Email Address: Yulia.Margolin@acgov.org

General Services Agency (GSA) – Procurement

RESPONSE DUE

by

2:00 p.m. (Pacific Time) on

JANUARY 15, 2027

through

Alameda County, GSA-Procurement

County of Alameda Procurement Portal https://procurement.opengov.com/portal/acgov

Alameda County is committed to reducing environmental impacts across our entire supply chain. Please print only what you need, print double-sided, and use recycled-content paper if printing this document.

https://procurement.opengov.com/portal/acgov https://procurement.opengov.com/portal/acgov mailto:Yulia.Margolin@acgov.org

Specifications, Terms & Conditions for Disaster Response Contingency Services

RFP No. 902743

CALENDAR OF EVENTS

REQUEST FOR PROPOSAL No. 902743

DISASTER RESPONSE CONTINGENCY SERVICES

EVENT DATE/LOCATION

Request Issued November 23, 2026

Networking/Bidders Conference

December 3, 2026 at 10:00 AM (Pacific Time)

TO ATTEND ONLINE:

Join the Bidders Conference via this link: Join the Bidders Conference for RFP 902743

DISASTER RESPONSE CONTINGENCY SERVICES

Meeting ID: 262 533 832 837 502 Passcode: r7JQ6wY6 Dial in by phone phone number+1 415-915-3950, pin 674524255# United States, San Francisco phone number (888) 715-8170, pin 674524255# United States (Toll-free) Find a local number Phone conference ID: 674 524 255#

Written Questions Due via the “Question & Answer” tab of this project in the County of Alameda Procurement Portal

December 4, 2026, by 5:00 p.m. (Pacific Time)

List of Attendees December 7, 2026

Questions & Answers Issued December 29, 2026

Addendum Issued [only if necessary to amend

RFP]

December 29, 2026

Response Due and Submitted through County of Alameda Procurement Portal

January 15, 2027, by 2:00 p.m. (Pacific Time) Followed immediately by online Public Bid Opening which can be joined here:

Join the public bid opening for RFP 902743

DISASTER RESPONSE CONTINGENCY SERVICES

Meeting ID: 287 442 733 466 337 6 Passcode: yk7QK9v8 Dial in by phone phone number +1 415-915-3950 , pin 893737235# United States, San Francisco https://teams.microsoft.com/meet/262533832837502?p=4FrxsE7u92dJxbiHVy tel:+14159153950,,674524255 tel:8887158170,,674524255 https://dialin.teams.cloud.microsoft/c44e85b4-06d5-44f1-aa66-048146aad930?id=674524255 https://procurement.opengov.com/portal/acgov https://procurement.opengov.com/portal/acgov https://teams.microsoft.com/meet/2874427334663376?p=OmJzOpL5eDrAUirMjs tel:+14159153950,,893737235

(888) 715-8170, 893737235# United States (Toll-free) Find a local number Phone conference ID: 893 737 235#

Evaluation Period January 15, 2027 – March 26, 2027

Optional Vendor Interviews Week of March 1, 2027

Notice of Intent to Award Issued March 29, 2027

Board Consideration Award Date June 8, 2027

Contract Start Date July 1, 2027

NOTE: All dates are tentative and subject to change.

Alameda County Vendor Outreach

Wednesday, December 2, 2026 10:30 a.m. – 11:30 a.m.

TO ATTEND ONLINE:

Vendor Outreach Call-in: +1 415-915-3950

Conference ID: 504 517 635#

COME MEET ALAMEDA COUNTY’S

PROCUREMENT TEAM!

This public event is not specific to any RFP, where vendors can speak with GSA professionals, get to know them, and learn more about contracting opportunities with the

County.

These are usually conducted on Wednesdays.

Dates and locations can be confirmed by checking at Upcoming Events

[https://gsa.acgov.org/do-business-with-us/upcoming-contracting-events/] tel:8887158170,,893737235 https://dialin.teams.cloud.microsoft/c44e85b4-06d5-44f1-aa66-048146aad930?id=893737235 https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZTcwODZiMDctYzdmNi00ZTgxLWJhOTUtMjAyZTRkMWQxMTg4%40thread.v2/0?context=%7b%22Tid%22%3a%2232fdff2c-f86e-4ba3-a47d-6a44a7f45a64%22%2c%22Oid%22%3a%22338906a1-74a0-4066-b6d5-051f1847307a%22%7d https://gsa.acgov.org/do-business-with-us/upcoming-contracting-events/ https://gsa.acgov.org/do-business-with-us/upcoming-contracting-events/

COUNTY OF ALAMEDA

REQUEST FOR PROPOSAL No. 902743

SPECIFICATIONS, TERMS & CONDITIONS

for

DISASTER RESPONSE CONTINGENCY SERVICES

TABLE OF CONTENTS

Page

CALENDAR OF EVENTS

II. STATEMENT OF WORK

A. INTENT

B. SCOPE

C. BACKGROUND

D. BIDDER QUALIFICATIONS

E. SPECIFIC REQUIREMENTS

F. DELIVERABLES / REPORTS

G. BIDDERS CONFERENCE(S)/VENDOR OUTREACH

III. COUNTY PROCEDURES, TERMS, AND CONDITIONS

H. EVALUATION CRITERIA / SELECTION COMMITTEE

I. CONTRACT EVALUATION AND ASSESSMENT

J. NOTICE OF INTENT TO AWARD

K. BID PROTEST / APPEALS PROCESS

L. TERM / TERMINATION / RENEWAL

M. BRAND NAMES AND APPROVED EQUIVALENTS

N. QUANTITIES

O. PRICING

P. AWARD

Q. METHOD OF ORDERING

R. INVOICING

S. ACCOUNT MANAGER / SUPPORT STAFF

IV. INSTRUCTIONS TO BIDDERS

T. COUNTY CONTACTS

U. SUBMITTAL OF PROPOSALS

ATTACHMENTS

EXHIBIT A

BID RESPONSE PACKET

EXHIBIT B Additional Contract Provisions – Federal Provision EXHIBIT B-1 Certification For Contracts, Grants, Loans, And Cooperative Agreements Certification Regarding Lobbying (Appendix A, 44 C.F.R. Part 18)

II. STATEMENT OF WORK

A. INTENT

It is the intent of these specifications, terms, and conditions to describe disaster response contingency services being requested by the County.

The County intends to award a five (5)-year contract (with the option to renew for two [2] years) to a pool of up to eight (8) Bidders (one or more Bidders within each category) selected as the most responsive and responsible Bidders whose responses conform to the RFP and meet the County’s requirements.

These specifications, terms, and conditions are to procure the most environmentally preferable products with equivalent or higher performance and at an equal or lower cost than traditional products.

B. SCOPE

The County of Alameda, located in the San Francisco Bay Area, is at high risk for both natural and man-made disasters. In addition to the ongoing threat of storms, wildfires, and earthquakes, the County is home to major highways, air, sea, and transportation routes; a highly diverse population; suburban and rural agricultural areas; and significant commercial industries that utilize hazardous materials.

The purpose of the County’s Disaster Response and Recovery Contingency Contract is to ensure timely and coordinated operations as defined by the County Operational Area Emergency Operations Center (EOC). The County will provide the Contractors with the names and contact information for designated County points of contact at the beginning of the contract. The County is establishing pre-positioned contracts for non-construction disaster response contingency services. Services may include emergency debris collection, loading, hauling, processing, recycling and disposal; independent debris monitoring; emergency shelter, feeding, water distribution, temporary equipment and logistical support; and administrative support for federal and state disaster reimbursement. Services shall be performed only pursuant to a County-issued written Activation Notice or Work Assignment. Award of a contract does not authorize the Contractor to perform services, incur costs, or deploy resources, and does not guarantee any minimum amount of work or compensation.

Services may be delivered through a combination of the County’s workforce, workforces from jurisdictions within the County, and the Contractor’s workforce. The Contractor must have the capacity to manage large-scale projects, including maintaining a sufficient workforce and the financial ability to cover expenses associated with a major recovery operation prior to and between payments. Additionally, the Contractor must carry all necessary insurance coverage. The Contractor must also have an established management team and a reliable network of resources—both within and outside the impacted areas of the County—to ensure timely delivery of required supplies, equipment, and personnel. Furthermore, the Contractor must comply with all applicable federal, state, and local laws, codes, and ordinances.

Given the uncertainty surrounding the type of potential disaster, the scope of services is broad, and the contract is therefore structured as a usage-based contract that will be invoked only in the event of a declared local emergency. No compensation will be due to the Contractor unless and until the contract is formally invoked by the GSA Director, or a designee, either in anticipation of, or in response to, a natural or man-made disaster. It is unlikely that all services described in this contract will be required for every response effort. Contractor shall be compensated solely in accordance with the pre-established unit prices and fixed prices included in the County-approved Bid Form and incorporated into the Contract. Under this Contract, the County will compensate the Contractor solely through the fixed prices and unit prices established in the County-approved Bid Form.

Time-and-materials pricing and payment based on actual labor hours, equipment hours, or material costs are not authorized under this Contract. Payment shall be based on the applicable unit of measure and the quantity of services, goods, or deliverables accepted by the County under each Work Assignment.

As this is a usage-based contract, the quantity of work required is not known at this time, but all work must comply with all potential requirements for reimbursement, including but not limited to the Federal Emergency Management Agency (FEMA), the Federal Highway Administration (FHWA), or the California Disaster Assistance Act (CDAA), to maximize state and federal reimbursement amounts. Payment will be made at the negotiated contract rates specified in the bid form. The services will be verified by the County and/or the participating jurisdictions in the daily operational report. Contractor must be knowledgeable about and comply with all applicable regulations, requirements, and updates related to federal or state reimbursement for the duration of any contract resulting from this RFP, including any specific terms that may be included in any Work Assignment. Contractor must be able to maximize reimbursement for disaster response activities.

There are 4 categories in the RFP:

CATEGORY 1 – DEBRIS REMOVAL SERVICES, DEBRIS MANAGEMENT SERVICES AND

ENVIRONMENTAL COMPLIANCE SERVICES

CATEGORY 2 – DEBRIS MONITORING SERVICES

CATEGORY 3 – SHELTER, FOOD DISTRIBUTION, AND EMERGENCY SUPPORT SERVICES

CATEGORY 4 – ADMINISTRATIVE SERVICES AND FEMA REIMBURSEMENT SUPPORT

When multiple Contractors are awarded within a category, the County generally intends to offer an assignment to the highest-ranked available Contractor within that category that can meet the applicable requirements. The County may move to the next-ranked available Contractor when necessary because of availability, capacity, response time, past performance, actual or apparent conflicts of interest, funding or program requirements, geographic or logistical considerations, or other factors identified in the RFP or applicable Work Assignment request.

EXCLUSION OF CONSTRUCTION AND PUBLIC WORKS

Services under this Contract are limited to non-construction disaster response and recovery services expressly identified in this RFP and authorized through a written Work Assignment. Before issuing a Work Assignment, the County will review the proposed scope to determine whether it involves construction, public works, or other services requiring a separate procurement or legal determination.

This RFP does not authorize construction, alteration, structural demolition, installation, repair, reconstruction, excavation, grading, paving, dredging, permanent utility connections, permanent electrical or plumbing work, facility improvements, or other public works. The Contractor must not perform or subcontract such work under any contract resulting from this RFP.

Collection and disposal of construction and demolition debris must be limited to debris already generated by the disaster or by work separately authorized by the County and must not authorize demolition of any structure. Debris services must be limited to removal of loose, disaster-generated debris and must not include excavation, alteration, repair, or restoration of any drainage structure or facility.

Temporary trailers, shelters, generators, lighting, monitoring towers, and other equipment must be freestanding, portable, or self-contained and must not require foundations, anchoring, trenching, hardwiring, permanent plumbing, structural alteration, or permanent utility connections. Any requirement that the County determines constitutes construction or public works shall be separately scoped, procured, authorized, and administered outside this Contract.

C. BACKGROUND

The Operational Area EOC is comprised of numerous County Departments and Agencies.

The County, in its capacity as the Operational Area, is seeking Contractors to provide disaster response and recovery services to Alameda County. https://gsa.acgov.org/our-work/emergency-services/. Services within incorporated cities may be provided only when authorized through an applicable mutual aid agreement, emergency agreement, interagency agreement, or other legally sufficient arrangement, as determined by the County. The County does not guarantee that services performed within incorporated cities will be eligible for federal or state reimbursement. Before issuing a Work Assignment involving services within an incorporated city, the County will confirm the applicable authorization, jurisdictional responsibilities, reimbursement arrangements, https://gsa.acgov.org/our-work/emergency-services/ and necessary access or property-use permissions. When appropriate, the Work Assignment will identify the participating jurisdiction and include applicable indemnification and insurance requirements. The County of Alameda faces considerable natural and man-made risks and hazards that may overwhelm locally available disaster response resources. Furthermore, the socio-economic characteristics of the County must be considered in determining the extent and scope of resources that may be necessary to serve the public following a disaster. Please refer to the County’s adopted emergency operations plan:

https://www.acgov.org/ready/documents/EmergencyOperationsPlan.pdf.

Alameda County is the seventh largest county in the state of California, with an estimated 2024 population of 1.6 million. Alameda County encompasses most of the East Bay of the San Francisco Bay Area region. The County’s total area of 822 square miles includes 738 square miles of land and 84 square miles of water, and is bordered by the San Francisco Bay on the west. The County includes a coastal plain, populated hillsides from the Berkeley Hills south to the Diablo Range, and to the east includes the Castro and Livermore valleys.

The Hayward and Calaveras faults run through the most populated portions of Alameda County, with the Hayward fault bisecting the cities of Berkeley, Oakland, San Leandro, Hayward, and Fremont. The Calaveras Fault runs through the southern portion of the County, and lesser faults run along the eastern slopes of the hillsides. The hillsides present hazard potential for mudslides, as well as wildland fires. In 1991, the Oakland Hills Firestorm killed 25 people, injured 150 others, and destroyed over 1,520 acres, including 3,354 single-family dwellings and 437 apartment and condominium units. The densely populated County presents significant disaster risk potential.

The Association for Bay Area Governments (ABAG) studied various risks associated with natural disasters within the San Francisco Bay Area (link https://abag.ca.gov/our-work/resilience/data-research).

Alameda County is one of the most racially and ethnically diverse regions in the nation.

Census data does not factor in geographic differences in the cost of living and therefore under-represents poverty within Alameda County. Portions of East and West Oakland and parts of Berkeley experience greater than 40% of children under 18 living in poverty.

These pockets of poverty will present significant challenges for disaster response, as often the building stock in these neighborhoods has not been seismically upgraded or reinforced, and the residents lack the resources to be self-sufficient following a disaster.

Therefore, the engagement of the community in recovery efforts is essential.

The County of Alameda has long-standing policies that promote and sustain economic development and develop capacity in the local business community. While it is anticipated that many local businesses will be disrupted immediately following a disaster, it is widely understood that engaging the local business community in recovery is a best https://www.acgov.org/ready/documents/EmergencyOperationsPlan.pdf https://abag.ca.gov/our-work/resilience/data-research practice. Many of the services contemplated under the scope of service might be performed using local subcontractors and local labor. Including local labor as a partner in disaster response efforts will greatly assist the County in long-term economic recovery.

The hazard risk factors, demographics, and economic profile of Alameda County are all critical factors in estimating the potential scope of work for the all-hazards disaster response contingency contract. Given the potential scale of destruction resulting from a significant earthquake or fire, it is essential that the vendor meet specific qualifications relating to expertise, financial stability, and project management.

A Bidder may be a single vendor that provides services, or a group of vendors working collaboratively to provide services. Collaborating vendors must name a single, lead prime Bidder that will submit on behalf of the collaborating vendors. The prime Contractor must coordinate all fiscal and administrative duties as needed to provide services under any contract resulting from this RFP. If awarded, it is the prime Bidder that will enter into a contract with the County.

D. BIDDER QUALIFICATIONS

This part applies to the bidder and is a qualify/disqualify series of minimum qualifications.

Bidder must meet all minimum qualifications described below, or they will be disqualified, and their proposals will not be evaluated. Bidder must independently meet the minimum qualifications through its own organizational experience and resources. Bidder must not rely on the qualifications or experience of subcontractors, teaming partners, and independent consultants. The following minimum qualifications are required at the time of proposal submission.

1. BIDDER Minimum Qualifications

a. Bidder must be regularly and continuously engaged in the business of providing all-hazard disaster contingency contracts for local governments in each category for which the Bidder is proposing for at least five (5) years, which must be clearly stated or demonstrated in the bid response.

b. Bidder must possess all permits, licenses, and professional credentials necessary to supply products and perform services specified under this RFP. Unless noted otherwise in the RFP, for example the item(s) stated above, including any Addendum, Bidder is not required to submit copies or verification of the permits, licenses and credentials; however, Bidder must provide such proof if requested by County.

E. SPECIFIC REQUIREMENTS

1. GENERAL SPECIFIC REQUIREMENTS (APPLICABLE TO ALL CATEGORIES)

The following requirements apply to all Contractors awarded under any category of this RFP.

a. The Contractor must provide timely, safe, coordinated, non-construction disaster-response services that maintain continuity of essential operations, accurately account for all labor, equipment, supplies, and debris, achieve County-established incident objectives, and produce complete, auditable documentation supporting all allowable federal and state reimbursement.

b. The GSA Director or authorized designee is the sole County official authorized to activate disaster response services under any contract resulting from this RFP. Following activation, service may be performed only under a written Work Assignment issued by a County representative, including the Operational Area Emergency Operations Center or other County representative identified. Each Work Assignment must identify the authorized scope, service locations, performance standards, schedule, deliverables, applicable Contract pricing, estimated quantities, and not-to-exceed compensation. Contractor must not perform additional services, exceed authorized quantities, or incur cost beyond the Work Assignment ceiling without prior written authorization from an authorized County representative. Services performed without the required authorization are at Contractor’s sole expense and are not payable by the County.

c. A Work Assignment is a written authorization issued by the County to an awarded Contractor for a defined scope of services using the pre-established fixed prices and unit prices contained in the Contract. A Work Assignment will typically identify the authorized quantities or fixed-price deliverables, required performance standards, schedule, deliverables, acceptance criteria, and total authorized compensation. A Work Assignment must not establish compensation on a time-and-materials basis.

d. The County may activate services in anticipation of, during, or following an emergency or disaster when the County determines that the services are necessary. Activation does not require prior approval of a state or federal disaster declaration or funding award. However, eligibility for FEMA, FHWA, CDAA, or other reimbursement can depend on the applicable declaration, program authorization, eligibility criteria, and documentation requirements.

e. The County retains final authority over the submission of costs for reimbursement.

f. Assignment Of Work Within the Contractor Pool:

(1) Award of a contract establishes a Contractor’s eligibility to receive assignments within the awarded category but does not guarantee any minimum assignment, quantity, or compensation. When an assignment arises, the County may issue an availability or Work Assignment request to Contractor(s) awarded within the applicable category. The County may consider Contractor(s)’:

(a) Ability to acknowledge and mobilize within the required timeframe;

(b) Available personnel, equipment, supplies, facilities, and subcontractors;

(c) Ability to perform the specific scope and meet required outcomes;

(d) Contract pricing and task-specific price reasonableness;

(e) Past performance under County activations;

(f) Safety, regulatory, and documentation performance;

(g) Actual or apparent conflicts of interest;

(h) Geographic and logistical considerations; and

(i) Equitable distribution of assignments when the other factors are substantially equal.

(2) When incident conditions permit, the County may conduct a secondary competition by requesting written Work Assignment proposals from eligible Contractors within the applicable category.

The request may require confirmation of availability, approach, schedule, resources, and pricing. Selection must be based on the factors stated in the request.

(3) When an emergency or public exigency does not permit secondary competition, the County may issue an assignment directly to an available Contractor. The County will document the circumstances and basis for the selection.

(4) The County may assign work to more than one Contractor, divide or reassign work, or obtain services through another procurement or governmental source when necessary to meet incident objectives.

(5) The County will maintain an assignment record documenting the Contractors considered, selection factors, price reasonableness, conflicts reviewed, and basis for the assignment.

g. Activation Notices and Work Assignment.

(1) No Contractor must begin services, deploy resources, purchase materials, engage subcontractors, or incur costs chargeable to the County without a written Activation Notice or Work Assignment issued by an authorized County representative.

(a) For Work Assignments involving services within incorporated cities or facilities not owned or operated by the County, the County must confirm that appropriate interagency authorizations, access permissions, and reimbursement arrangements are in place before directing the Contractor to perform services. The Work Assignment must identify the applicable jurisdiction, authorized service locations, responsible agency, and any additional insurance, indemnification, or operational requirements.

(2) Each Activation Notice or Work Assignment must identify, as applicable:

(a) The incident and applicable service category;

(b) The authorized scope, locations, and service area;

(c) The incident objectives and required performance outcomes;

(d) The authorized start date, period of performance, operational periods, milestones, and completion date;

(e) Required personnel, equipment, materials, facilities, and quantities;

(f) Deliverables, reporting deadlines, and acceptance criteria;

(g) Applicable fixed prices and unit prices and authorized quantities, as established in the Contract;

(h) The Work Assignment not-to-exceed amount;

(i) Known funding source and funding-specific requirements, if applicable;

(j) Authorized County representatives;

(k) Invoice and supporting-document requirements; and

(l) Any incident-specific or scope-specific safety, environmental, security, accessibility, or regulatory requirements.

(3) The Contractor must acknowledge receipt of an Activation Notice or Work Assignment within one (1) hour. If assigned work, the Contractor must, within the period stated by the County, either accept the assignment in writing or notify the County that the Contractor cannot meet the required scope, schedule, capacity, or other conditions.

(4) The Contractor must not exceed the authorized scope, quantities, period of performance, or not-to-exceed amount without a written Work Assignment amendment signed by an authorized County representative. Services and costs exceeding the Work Assignment are at the Contractor’s sole risk and expense.

(5) When immediate action is necessary to protect life, public health, or safety, an authorized County representative may provide oral operational direction within an existing activation. The Contractor must document the direction, including the name of the authorizing official, date, time, location, resources, and estimated cost. The County shall confirm the direction in writing as soon as practicable. Oral direction must not authorize construction, public works, or an increase in the Work Assignment not-to-exceed amount.

(6) If the Contractor cannot complete an accepted assignment, the County may cancel or reduce the assignment, transfer work to another Contractor, obtain replacement services, or exercise any other contractual remedy.

h. Compensation and Funding Limitations.

(1) Contractor must have sufficient financial capacity to fund its performance, including labor, equipment, materials, supplies, subcontractors, and other costs necessary to perform an authorized Work Assignment, prior to receiving payment from the County. The County will not provide advance payments. Contractor will be compensated after authorized services, goods, or deliverables have been performed or provided, accepted by the

County, and properly invoiced with all required supporting documentation, in accordance with the applicable fixed prices and unit prices established in the Contract. County payment to the Contractor will not be contingent upon the County first receiving reimbursement from FEMA, Cal OES, FHWA, or any other federal or state funding source.

(2) The County does not guarantee any Contractor a minimum number of activations, Work Assignments, hours, quantities, purchases, or compensation. Compensation must be limited to authorized and accepted services performed under a written Work Assignment and must not exceed the applicable Work Assignment ceiling.

(3) Compensation will be based solely on the applicable fixed price or unit price established in the Contract and the quantities or deliverables accepted by the County under the Work Assignment.

The County will not be responsible for Contractor costs incurred in excess of the authorized quantities or prices, including labor, equipment, materials, subcontractor costs, overhead, or other actual costs, unless expressly included as a separately priced line item in the Work Assignment.

(4) All payments are subject to the availability and appropriation of County funds. The County’s anticipated pursuit of federal or state reimbursement does not guarantee that reimbursement will be awarded and does not increase the County’s payment obligations beyond the executed Contract and applicable Work Assignment.

i. Fixed-Price and Unit-Price Cost Control.

(1) Work Assignments will be priced and paid using the pre-established fixed prices and unit prices included in the County-approved Bid Form. Time-and-materials pricing is not permitted.

(2) Each Work Assignment must identify the applicable line items, unit of measure, authorized quantities or fixed price, applicable contract rates, performance requirements, and total authorized amount.

(3) Contractor must not invoice labor, equipment, equipment operating hours, idle time, standby time, materials, supplies, administrative costs, subcontractor costs, overhead, or other costs separately unless expressly established as a separate priced line item in the County-approved Bid Form.

(4) Contractor must not exceed the authorized quantities, fixed price, or total Work Assignment amount without prior written authorization from the County. An authorized County representative may provide oral operational direction within the existing scope and authorized amount of a Work Assignment. Any direction that increases the authorized quantities, changes the fixed price or unit prices, or increases the total Work Assignment amount must be approved in writing by an authorized County representative before the additional work is performed.

(5) Cost-plus-a-percentage-of-cost, percentage-of-recovery, percentage-of-construction-cost, and other pricing methods that increase based on performance cost are prohibited.

(6) FEMA equipment cost codes and schedules may be used as supporting reference information for cost reasonableness and reimbursement documentation but shall not establish additional compensation payable under this Contract.

(7) Contractor must not receive a fee, commission, contingency payment, or other compensation calculated as a percentage of federal or state reimbursement obtained by the County.

j. Federal and State Funding Requirements.

(1) Funds used for payment under any contract or Work Assignment resulting from this RFP may include County funds or may be subject to reimbursement through FEMA, Cal OES, FHWA, or another state or federal program. No particular funding source, declaration, award, reimbursement percentage, or eligibility determination is guaranteed.

(2) The Contractor must comply with all funding requirements incorporated into the Contract and those expressly identified in an applicable Work Assignment. Federal award requirements will include, as applicable, 2 C.F.R. Part 200, the requirements of the applicable federal awarding agency, and any current applicable County-approved Additional Contract Provisions – Federal Provision, a sample of which is attached to this RFP for information.

(3) A Work Assignment may identify the known funding source and applicable program-specific requirements. Additional material terms may be added through written amendment.

(4) Contractor must flow down all applicable funding provisions to each subcontract and purchase order and must remain responsible for subcontractor compliance.

(5) Each Work Assignment must identify the anticipated funding source, if known, and any applicable federal, state, or local funding requirements. The County may incorporate additional funding-specific provisions into a Work Assignment, including requirements associated with FEMA, FHWA, Caltrans, Cal OES, or other applicable funding programs, provided such provisions are consistent with the Contract and applicable law. The Contractor must comply with all funding requirements expressly incorporated into the applicable Work Assignment.

k. Contractor must comply with all applicable federal, state, and local laws, regulations, codes, ordinances, and worker health and safety requirements applicable to the awarded category.

l. Contractor’s identified subcontractors must possess the licenses, certifications, permits, and professional credentials necessary to perform the services assigned to them. Bidders must provide a list of subcontractors, and clearly identify which of their subcontractors are local (i.e. located within Alameda County) and which are from outside Alameda County in their bid responses.

m. Contractor must maintain resources sufficient to meet each County-authorized to meet 100% of accepted Work Assignment staffing, equipment, and operational requirements without unapproved interruption. Within twenty-four (24) hours after County request, Contractor must provide a resource roster showing available personnel by role, equipment by type, subcontractors, facilities, and financial capacity.

n. Contractor must maintain a live 24/7 emergency contact and acknowledge an activation within one (1) hour.

o. Any transition must preserve 100% of active County-authorized services and records without missed operational periods or loss of data.

p. Reimbursement Documentation.

(1) Contractor must maintain contemporaneous, complete, accurate, searchable, and audit-ready records that provide one hundred percent (100%) traceability among the applicable Work Assignment, daily activities, personnel and equipment usage, quantities, monitoring records, invoices, source documents, payments, and reimbursement submissions.

(2) Contractor must separately track:

(a) Work believed to meet applicable funding eligibility requirements;

(b) Questioned or potentially ineligible work;

(c) County-authorized work intended to be funded solely by the County; and

(d) Work associated with another responsible agency or funding program.

(3) Questioned or potentially ineligible work must not be represented as eligible or included in a reimbursement package until the County authorizes its inclusion.

(4) Contractor must promptly notify the County of any condition that may affect reimbursement, including inadequate authorization, missing documentation, unreasonable cost, duplication of benefits, noncompliant procurement, environmental or historic preservation concerns, insurance proceeds, work under another agency’s authority, or deviation from the approved scope.

(5) Contractor must support the County in maximizing supportable and allowable reimbursement. Contractor must not guarantee reimbursement or make a final eligibility determination on behalf of FEMA, Cal OES, FHWA, the County, or another governmental entity.

(6) The County’s obligation to pay the Contractor must be based on the executed Contract, Work Assignment, satisfactory performance, and acceptable invoice documentation and must not be increased by the denial or reduction of federal or state reimbursement.

q. Contractor must maintain all insurance required by the County throughout the contract term.

r. Contractor must have the capacity to manage large-scale projects, including maintaining a sufficient workforce and the financial ability to cover expenses associated with a major recovery operation prior to and between payments.

s. Contractor must coordinate and implement a smooth and timely transition from the current contractors without disruption of County Operations and to future contractors, if any, within 30 calendar days after the Contract effective date, unless otherwise directed by the County, without interrupting active County-authorized services or losing operational records.

t. Contractor must certify that the products proposed for supply are not manufactured with, and do not contain, use, or generate, persistent bioaccumulative toxins (PBTs).

u. Under Measure D (Alameda County's Waste Reduction and Recycling Act), it is the objective of the County to purchase products with the lowest overall environmental impact from manufacturing through end of life and to procure services that achieve this same objective. Contractor must comply with all applicable federal, state, and local environmental laws and regulations relevant to the services performed under this Contract. For Category 1 debris removal and debris management services, Contractor must implement waste reduction, recycling, and diversion practices consistent with applicable legal requirements and the County-approved debris management plan, where feasible and authorized by the County.

Contractor must maintain documentation identifying the quantities and types of disaster-generated debris collected, recycled, reused, processed, and disposed of, as applicable. The County will evaluate compliance through required reports, supporting disposal and recycling records, and performance standards established in this RFP and the applicable Work Assignment. The County has a goal of diverting at least seventy-five percent (75%) of material from landfill through recycling and source reduction and to encourage markets for environmentally preferable goods through its procurement process.

v. Contractor must be responsible for determining what permits are necessary to perform under any contract resulting from this RFP for all services. Contractor must hold all required licenses, registrations, and certifications to perform the work in compliance with applicable state, local, and federal laws and regulations and is responsible for obtaining any necessary, timely permits at no cost to the County to complete the assigned tasks.

w. Within twenty-four (24) hours after each Work Assignment, Contractor must submit a baseline schedule identifying mobilization, staffing, equipment, work locations, daily operating periods, milestones, dependencies, and completion dates. Contractor must achieve at least 95% on-time completion of County-approved milestones. Contractor must notify the County within two (2) hours after identifying a material variance and submit a recovery schedule within four (4) hours. Only a written County direction may revise a milestone or relieve schedule performance.

Bidder must provide a sample mobilization/implementation schedule in a bid response.

x. Contractor must ensure that appropriate approvals are obtained from the Operational Area EOC. All services described under any contract resulting from this RFP will be authorized by the Operational Area EOC based upon a prescribed timeline.

y. Contractor must acknowledge that, in the event of a federally declared catastrophic disaster, jurisdictional approvals from multiple federal agencies may be required, and that all activities must comply with the Stafford Act, including Section 312 (Duplication of Benefits). Contractor must complete all applicable federal forms as necessary in connection with the services provided under this RFP.

z. Contractor must provide and manage its own workforce, including approved subcontractors, as necessary to perform the services required under this Contract. Contractor must coordinate with the Operational Area EOC, County personnel, and representatives of participating jurisdictions and agencies, as applicable, to ensure effective disaster response and recovery operations.

aa. Contractor must achieve incident objectives established by the Operational Area EOC and maintain continuous coordination with designated County personnel throughout the operation period and complete County-approved incident objectives within the milestones established in each Work Assignment.

bb. Contractor must ensure that 100% of public communications related to services under this Contract are reviewed and approved by the Operational Area EOC Public Information Officer prior to release.

Contractor must thoroughly brief External Public Communications directed to Local officials, other stakeholders as specified by the Operational Area EOC, and residents, on the disaster response, accessing support services, environmental standards, health and safety issues, risks, etc. In coordination with the County Operational Area EOC, the Contractor must notify the public of the status of services and updates and provide contact information using mass media notice mechanisms as specified by the EOC Public Information Officer.

cc. Contractor’s personnel are not permitted to accept any additional payments, gratuities, or tips from site personnel or visitors.

dd. Contractor must maintain contemporaneous, complete, accurate, searchable, and audit-ready records in a County-approved electronic format, with 100% reconciliation between work performed, invoices submitted, and supporting documentation.

ee. Supporting records such as labor time records, equipment logs, load tickets, delivery records, and daily operational reports may be required to document performance, compliance, and reimbursement eligibility;

however, such records will not establish the compensation payable by the County unless the applicable Contract line item expressly uses the documented unit as the pricing basis.

ff. Contractor must promptly correct any performance deficiency identified by the County. Unless another timeframe is established by the County based on the nature or urgency of the deficiency, Contractor must submit a corrective action plan within twenty-four (24) hours after notification identifying the cause of the deficiency, corrective action taken or proposed, responsible personnel, and measures to prevent recurrence.

gg. Record Retention and Access.

(1) Contractor must retain all contract, Work Assignment, operational, financial, procurement, subcontract, personnel, equipment, monitoring, delivery, environmental, and reimbursement records until the later of:

(a) Ten years after final payment and administrative closeout of the applicable activation or Work Assignment;

(b) The retention period required by the applicable funding agency;

(c) Final resolution of all audits, appeals, investigations, claims, litigation, or questioned costs; or

(d) A later date identified by written County notice.

(2) Upon request, the Contractor must provide the County and authorized state or federal representatives prompt access to records in searchable, nonproprietary electronic format. Before final payment, termination, or expiration, the Contractor must deliver a complete electronic copy of all records to the County.

Contractor system unavailability or termination of a software license must not limit the County’s access to its records.

hh. Transition Period and Requirements

Upon commencement of the Contract, Contractor(s) must coordinate with the County to ensure an orderly transition from the incumbent Contractor(s), as applicable, without interruption to County operations or emergency response readiness.

The transition period will be thirty (30) calendar days from the Contract effective date, unless otherwise specified by the County. During this period, Contractor must:

(1) Designate a primary transition coordinator responsible for communicating with the County and coordinating transition activities.

(2) Participate in transition meetings with County representatives and incumbent Contractor(s), as directed by the County.

(3) Review available existing operational procedures, emergency response plans, service requirements, reporting procedures, and applicable documentation provided by the County.

(4) Establish emergency contact information, staffing and resource availability, subcontractor coordination procedures, and communication protocols necessary to perform the awarded services.

(5) Submit a written Transition and Implementation Plan, identifying transition activities, responsible personnel, milestones, resource readiness, potential risks, and measures to prevent service disruptions.

(6) Complete all required transition activities and demonstrate readiness to perform the awarded services no later than thirty

(30) calendar days after the Contract effective date, unless otherwise directed by the County.

The County may shorten the transition period or require earlier activation when necessary to address an emergency or disaster. Contractor must comply with applicable emergency activation and mobilization requirements established in this RFP and the authorized Work Assignment.

The County retains responsibility for directing and coordinating the transition.

ii. Invoice And Payment Documentation.

(1) Contractor must submit invoices no more frequently than monthly, unless the applicable Work Assignment establishes another schedule. Each invoice must identify:

(a) Contractor name and remittance address;

(b) Contract and purchase order numbers;

(c) Incident name and number, if assigned;

(d) Work Assignment number and service category;

(e) Invoice number and billing period;

(f) Authorized period of performance;

(g) Work Assignment not-to-exceed amount;

(h) Amount previously invoiced, current amount, and remaining balance; and

(i) Name and contact information of the Contractor representative responsible for the invoice.

(2) Labor charges must not be invoiced on an hourly or time-and-materials basis. Where labor is included in a priced unit, the Contractor must provide sufficient supporting records to substantiate performance of the applicable unit, quantity, staffing requirement, or deliverable identified in the Work Assignment.

Time records may be required for audit, safety, labor compliance, or reimbursement documentation but will not establish the amount payable by the County.

(3) Equipment charges must not be invoiced based on actual operating hours, idle hours, standby hours, fuel consumption, or other time-based costs unless the applicable equipment service is expressly established as a separate unit-priced line item in the County Bid

Form. Where equipment is included in a priced unit, payment must be based on the applicable unit of measure and accepted quantity.

(4) Debris charges must identify debris type, quantity, unit of measure, collection location or Global Positioning System (GPS) coordinates, load-ticket number, hauling vehicle, certified capacity, percentage full or scale weight, Debris Management Site, final disposal or recycling facility, applicable rate, and extended amount.

(5) Goods, supplies, meals, water, temporary facilities, and other delivered items must identify the item, specification, quantity ordered, quantity accepted, quantity rejected, unit rate, delivery date and location, lot or serial number when applicable, and extended amount.

(6) Each invoice must include, as applicable:

(a) Approved daily reports and time records;

(b) Load tickets and scale tickets;

(c) Capacity certifications;

(d) Disposal, recycling, and tipping receipts;

(e) Hazardous-material manifests and chain-of-custody records;

(f) Delivery and acceptance records;

(g) Equipment-use logs;

(h) Inventory reconciliation;

(i) Monitoring reconciliation;

(j) Photographs or GPS records;

(k) Written approvals for substitutions, additional quantities, or changed work; and

(l) Other documentation required by the Work Assignment or applicable funding program.

(7) Every invoice must contain the following certification signed by an authorized Contractor representative:

“I certify that the amounts invoiced are accurate, complete, authorized under the identified Work Assignment, supported by the attached records, not previously billed, and reconciled to the services, goods, labor, equipment, and quantities provided.”

The County may return, withhold, offset, or disallow charges that are unsupported, duplicate, inaccurate, unauthorized, outside the period of performance, inconsistent with monitoring records, or in excess of the Work Assignment ceiling. Payment of an invoice does not waive the County’s right to recover an overpayment or disallowed cost identified through later review or audit.

2. CATEGORY 1 – DEBRIS REMOVAL SERVICES (Public Right-of-Way), DEBRIS

MANAGEMENT AND ENVIRONMENTAL COMPLIANCE SERVICES

Services are limited to the collection, loading, hauling, segregation, processing, recycling, and disposal of disaster-generated debris. Services do not include structural demolition, breaking or removal of attached improvements, excavation, grading, paving, dredging, utility work, facility repair, drainage-system repair, or permanent restoration. Collection of construction and demolition debris means collection of debris already generated by the disaster or by work separately authorized by the County and does not authorize demolition. All services under this Category are subject to the Labor Compliance/Public Works limitations in Section III.O.9.

Contractor must have the capacity to perform the following tasks, if included in a Work Authorization. Contractor must remove debris from public rights-of-way, roadways, and public property; process it at Debris Management Sites; and lawfully dispose of or recycle it, in a manner that eliminates immediate threats to life and public safety, restores public access, and maximizes documentation supporting federal and state reimbursement.

a. Contractor must review applicable existing County debris plans and develop or update incident-specific Debris Removal, Debris Management, Tactical Debris Management, and Demobilization Plans within the timeframe specified by the County. Plans must identify incident scope, objectives, roles and responsibilities, communication protocols, resource requirements, safety measures, environmental requirements, operational procedures, DMS operations, final disposal, and demobilization.

Contractor must revise plans within twenty-four (24) hours following receipt of County comments unless…

This is the start of the file's text. The full file is on GovTribe.