About this file
This is an Invitation for Bids (IFB) document issued by West County Wastewater District (WCW), a political subdivision of the State of California located in Contra Costa County. WCW is soliciting sealed bids for construction services to upgrade Secondary Sedimentation Basins (SSB) 1 and 2 at the Water Quality & Resource Recovery Plant (WQRRP), including demolition, concrete repairs, mechanical improvements, electrical upgrades, and site restoration. The project involves 13 line items covering mobilization/demobilization, demolition, chain and flight mechanism installation, water piping replacement, concrete repairs, and start-up/commissioning activities for both basins. The Engineer's estimate for the work is $5,625,000. The solicitation was released on October 27, 2026, with a mandatory pre-bid conference scheduled for November 10, 2026, at 10:00 am at 2377 Garden Tract Road, Richmond, California. An alternate mandatory site visit is available on November 12, 2026. The deadline for submitting written questions is November 26, 2026, at 3:00 pm, with responses due by December 8, 2026. Sealed bids must be submitted electronically via WCW's e-Procurement Portal (https://procurement.opengov.com/portal/wcwd) by December 16, 2026, at 3:00 pm. Contract award is anticipated for December 21, 2026, with a Notice to Proceed scheduled for January 13, 2027. Work must be completed with SSB No. 1 operational by May 15, 2027 (dry season requirement), and SSB No. 2 operational by September 30, 2027 (wet season requirement), ensuring the facility maintains at least two to three basins in operation depending on the season.
Bids will be evaluated on the basis of the lowest responsive, responsible bid. WCW will directly procure and furnish replacement collector chains and flights; however, the Contractor is fully responsible for receiving, unloading, handling, storing, protecting, coordinating, and installing this owner-furnished equipment at no cost increase to the contract. Proposal security of 10 percent of the proposal total must accompany each bid in the form of a certified check, cashier's check, or bidder's bond. The successful bidder must provide Performance and Payment Bonds for 100 percent of the proposal total. All bids must remain firm for 60 calendar days from the stated closing time. Contractors must be licensed under California Business and Professions Code Chapter 9, Division 3, and must list all subcontractors exceeding 0.5 percent of the proposal total or $5,000, whichever is greater. The contract includes a one-year warranty period on all equipment, materials, products, and workmanship after final acceptance. Contractors must comply with California prevailing wage requirements, nondiscrimination provisions, and indemnification requirements. No set-asides are identified in this solicitation.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
undefined
26-IFB-040
SECONDARY SEDIMENTATION BASINS UPGRADES PROJECT -
SHORT-TERM IMPROVEMENTS FOR BASINS (1) & (2)
West County Wastewater
2910 Hilltop Drive
Richmond, CA 94806
RELEASE DATE: October 27, 2026
DEADLINE FOR QUESTIONS: November 26, 2026
RESPONSE DEADLINE: December 16, 2026, 3:00 pm
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://procurement.opengov.com/portal/wcwd undefined
Secondary Sedimentation Basins Upgrades Project - Short-term
Improvements for Basins (1) & (2)
1. Notice to Bidders
2. Introduction
3. Instruction to Bidders
4. Schedule of Bid
5. Scope of Work
6. Contract Award
7. Terms and Conditions
8. Vendor Questionnaire
Attachments:
A - Secondary Sedimentation Basins Upgrade - Shor-term Improvements For Basin
(1) & (2) Bid Documents
B - Exhibit A - Secondary Sedimentation Basins Upgrade Project - Short-term
Improvements For Basins (1) & (2) undefined #26-IFB-040 Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
1. Notice to Bidders
1.1. Notice
INVITING SEALED BIDS
WEST COUNTY WASTEWATER
Secondary Sedimentation Basins Upgrade Project - Short-term Improvements For Basin (1) & (2)
PROJECT NO. 24PP505
NOTICE IS HEREBY GIVEN THAT the Board of West County Wastewater, Richmond, California, invites and will receive sealed bids for furnishing all labor, equipment, materials and services specified for the construction of WCW Project No. 26-IFB-040, Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2), in conformance with the approved Contract Documents.
A. The work covered by this contract will be performed at 2377 Garden Tract Road, Richmond, CA
94801.
B. The work includes, but is not necessarily limited to, the following:\
1. Sedimentation Basin No. 1 (SSB No. 1):
a. Procurement of the equipment for SSB No.1 will be covered by the Owner under a separate Procurement Contract. Contractor shall install Owner procured equipment for SSB
No.1.
b. Removal and replacement of the No. 3 water system, including piping, valves, supports, hose reel system, and appurtenances.
c. Removal and replacement of 18 precast concrete walkway panels along SSB Nos. 1 and 2
(as shown on the Drawings), replaced in kind.
d. Removal and replacement of two sluice gates along SSBs Nos. 1 and 2 (as shown on the
Drawings).
e. Miscellaneous concrete surface restoration and crack repair.
f. Upgrades to electrical components, including modifications to existing electrical systems to support new collector equipment and integration with the existing control system.
2.
2. Sedimentation Basin No. 2 (SSB No. 2):
a. Procurement of the equipment for SSB No.2 will be covered by the Owner under a separate Procurement Contract. Contractor shall install Owner procured equipment for
SSB No.2.
b. Removal and replacement of existing chain-and-flight mechanisms and accessories, including drives, motors, wall bearing supports, sprockets, flights, shafts, and chains.
c. Removal and replacement of the No. 3 water system, including piping, valves, supports, hose reel system, and appurtenances.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
d. Removal and replacement of 18 precast concrete walkway panels along SSB Nos. 1 and
2 (as shown on the Drawings), replaced in kind.
e. Removal and replacement of two sluice gates along SSBs Nos. 1 and 2 (as shown on the
Drawings).
f. Miscellaneous concrete surface restoration and crack repair.
g. Upgrades to electrical components, including modifications to existing electrical systems to support new collector equipment and integration with the existing control system.
3. Contractor shall perform all cleaning of SSBs No. 1 and 2 necessary to achieve sanitary working conditions and to prepare surfaces for required tasks.
Contractor shall include sufficient time in the schedule to perform the cleaning, and no delay shall be claimed.
4. The existing facility must be always kept in operation.
C. The Engineer’s estimate for the work is $5,625,000.
A pre-bid conference to discuss the project will be held at10:00 am, local time onTuesday, November
10, 2026 at2377 Garden Tract Road, Richmond, CA 94801. A mandatory site visit shall be conducted by all prime contractors interested in bidding the project. This site visit can be done immediately after the pre-bid conference. The alternate time for the mandatory site visit is at10:00 AM local time on09/12/2026 at the2377 Garden Tract Road, Richmond, CA 94801.
Bid opening date: WCW will receive sealed bids via WCW’s e-Procurement Portal, OpenGov, (https://www.opengov.com) until 3:00 pm, local time, Wednesday, December 16, 2026. At that time, accepted bids will be publicly opened.
Contract Documents are available on WCW's e-Procurement Portal, without charge.
Inquiries regarding further information about the project shall be submitted in writing through the
OpenGov Question/Answer Tab via WCW's e-Procurement portal, on or before, Question & Answer
Submission Date by Question & Answer Submission Time. Please include the section title for each question, if applicable, in order to ensure that questions asked are responded to correctly. All questions submitted and answers provided shall be electronically distributed to bidders following this solicitation on WCW's e-Procurement Portal.
Bidders are directed to submit their bids in accordance with requirements of the Invitation for Bids
(IFB) No. 24PP505, Secondary Sedimentation Basin Upgrade Projects – Short-term Improvements for
Basins (1) and (2), which is included as an attachment on OpenGov. IFB No. 24PP505 supersedes and controls over the OpenGov version of the IFB.
In order to submit a bid, OpenGov requires Bidders to complete a Schedule of Bids. This Schedule of Bids is identical to the one included in IFB No. 24PP505. Bidders should submit their pricing information using
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
OpenGov’s Schedule of Bids, rather than the hard-copy Schedule of Bids included in IFB No. 24PP505.
Bidders must submit all other forms included in IFB No. 24PP505.
The WCW Board of Directors reserves the right to reject any or all bids for the work and waive any irregularity in bids received.
Dated at Richmond, California, this 26th day of October 2026
Mohammed Masoud, Project Manager
County of Contra Costa, State of California
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
2. Introduction
2.1. Summary
West County Wastewater District (WCW) is soliciting bids from qualified contractors to provide construction services for the Secondary Sedimentation Basins 1 and 2 Short-Term Improvements Project at the Water Quality & Resource Recovery Plant (WQRRP). WCW identified the need to rehabilitate and upgrade all four secondary sedimentation basins at the WQRRP to maintain reliable operation and treatment performance and retained Black & Veatch to provide engineering design services for the improvements.
The work under this contract is limited to Secondary Sedimentation Basins (SSB) 1 and 2 and generally includes demolition, concrete repairs, coatings, mechanical improvements, site restoration, and all other work necessary to complete the improvements in accordance with the Contract Documents. West
County Wastewater District will directly procure and furnish the replacement collector chains and flights for SSB-01 and SSB-02; however, the Contractor shall be fully responsible for receiving, handling, storing, protecting, coordinating, and installing the owner-furnished equipment as part of the Work.
Contractors shall provide all labor, materials, equipment, supervision, and incidentals necessary to complete the project and place the rehabilitated facilities into successful operation in accordance with the Plans and Specifications.
2.2. Background
West County Wastewater (WCW) provides wastewater collection and treatment services to approximately 93,000 residents. WCW was created December 19, 1921, pursuant to authority of the
State of California. Today, WCW operates as a political subdivision of the State of California as an independent special district. WCW's current political boundaries are comprised of the City of San Pablo, a portion of the City of Richmond, a portion of the City of Pinole and some unincorporated areas within western Contra Costa County.
WCW's system includes 249 miles of gravity sewer pipelines, 17 lift stations, 6 miles of pressurized force mains, and a water quality resource recovery plant with an NDPES permitted capacity of 12.5 million gallons per day (MGD).
2.3. Contact Information
Mohammed Masoud
Project Manager
2910 Hilltop Dr
Richmond, CA 94806
Email: mmasoud@wcwd.org
Phone: (510) 407-9563
Department:
Infrastructure and Planning
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
2.4. Timeline
Release Project Date October 27, 2026
Pre-Bid Meeting No. 01 (Mandatory) November 10, 2026, 10:00am
2377 Garden Tract Road, Richmond, CA 94801
Pre-Bid Meeting No. 02 (Mandatory) November 12, 2026, 10:00am
2377 Garden Tract Road, Richmond, CA 94801
Question Submission Deadline November 26, 2026, 3:00pm
Question Response Deadline December 8, 2026, 3:00pm
Proposal Submission Deadline December 16, 2026, 3:00pm
Contractor Selection Date (Tentative) December 21, 2026
Notice to Proceed (Tentative) January 13, 2027
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
3. Instruction to Bidders
3.1. PREPARATION AND SUBMISSION OF PROPOSALS
Proposals shall be submitted via WCW’s e-Procurement Portal, ProcureNow as required by this solicitation. All proposal forms shall be properly executed and all information shall be provided as required. Failure to comply may be cause for rejection of the proposal.
The quantities included in the bid proposal are estimates of the work to be completed. WCW may add work of the same nature to this Contract if the addition is in the best interests of WCW.
Partial or incomplete proposals will not be accepted. Proposals shall be in strict conformity with the approved Contract Documents for Project No.26-IFB-040, Secondary Sedimentation Basins Upgrades
Project - Short-term Improvements for Basins (1) & (2), and any Addenda thereto.
The bidder shall submit its proposal prior to the stated closing time. Any proposal received after the stated closing time for receipt of proposals will not be accepted through the e-Procurement Portal.
The preparation of a proposal shall be by and at the expense of the bidder.
Changes in or additions to the bid form, recapitulation of the work bid upon, alternative bids or any other modifications of the bid form which are not specifically called for in the Contract Documents may result in rejection of the bid by WCW, as not being responsive to the Notice to Contractors. No oral or telephonic modification of any bid submitted will be considered.
Proposals shall be firm for sixty (60) calendar days from and after the stated closing time, or until a
Contract is fully executed by WCW and a bidder, whichever is earlier.
3.2. EXAMINATION OF DOCUMENTS AND EXPLANATION TO BIDDERS
Any bidder planning to submit a proposal is responsible for examining with appropriate care the complete Contract Documents, including all Addenda, and is also responsible for being informed with respect to all conditions which might in any way affect the cost or the performance of any work.
Failure to do so will be at the sole risk of the bidder, and no relief can be given for errors or omissions by the bidder.
All questions relative to the Contract Documents shall be in writing and shall be submitted in writing through the ProcureNow Question/Answer Tab via the WCW's e-Procurement portal, on or before, Thursday, November 26, 2026 by 3:00 pm. Please include the section title for each question, if applicable, in order to ensure that questions asked are responded to correctly. All questions submitted and answers provided shall be electronically distributed to bidders following this solicitation on WCWs e-Procurement Portal.
Should the bidder find discrepancies in or omissions from the Contract Documents, or should the intent or meaning of the documents appear unclear or contain patent ambiguities, the bidder shall at once
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2) notify WCW of such findings. Questions received less than ten (l0) calendar days prior to the date for opening of the bids may not be answered. The bidder making such request shall be solely responsible for its timely receipt by WCW. Replies to such findings may be made in the form of addenda which shall be posted on WCW's e-Procurement Portal. Addenda notifications will be emailed to all persons on record as following this ITB. Failure of any bidder to receive any such addenda or interpretation shall not relieve such bidder from any obligation under their bid as submitted. All addenda so issued shall become part of the contract documents. Only questions answered by formal written addenda will be binding.
Copies of the Contract Documents are available for examination without charge via the e-Procurement portal.
Copies of the Contract Documents may be obtained for a non-refundable fee of $110.00 per set if requested by mail. Payment must be made prior to the time any documents are mailed. Make check and/or money order payable to West County Wastewater (WCW).
West County Wastewater
2910 Hilltop Drive
Richmond, CA 94806
3.3. SITE INSPECTION AND CONDITIONS
It is the intent of WCW to provide a safe working environment under normal conditions. BECAUSE OF
POTENTIALLY HAZARDOUS CONDITIONS SUCH AS CONFINED SPACES, POTENTIALLY EXPLOSIVE
ATMOSPHERES, AND POSSIBLE EXPOSURE TO PATHOGENS, SPECIALIZED EQUIPMENT MAY BE
NECESSARY AND STRICT CONFORMANCE WITH SAFETY REGULATIONS WILL BE REQUIRED. Attention is further directed to Section titled "Article GC-20, Laws and Regulations".
In addition to examination of the Contract Documents, each prospective bidder shall become fully informed regarding all existing and expected conditions and matters which could affect any work or performance of any work in any way, and especially the cost of performing any work. The project may be visited and conditions discussed at the pre-bid conference set forth in, “Notice to Contractors”.
Any failure to fully investigate the sites or the foregoing conditions shall not relieve the bidder from responsibility for estimating properly the difficulty or cost of successfully performing any work. Neither
WCW nor any of its representatives or agents assumes any responsibility for any understanding or representation made by WCW or any of its representatives or agents prior to the execution of a
Contract pursuant to the Contract Documents.
3.4. WCW'S MODIFICATION OF THE DOCUMENTS
WCW may modify any provision or part of the document at any time prior to three (3) calendar days before closing time, provided that the closing time set forth in “Notice to Bidders”, may be extended by
WCW at any time prior to said closing time. Such revisions, if any, will be in the form of addenda which will be posted on WCW's e-Procurement Portal. Addenda notifications will be emailed to all persons on
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2) record as following this ITB.
Addenda issued during the time of bidding shall become a part of the documents furnished bidders for the preparation of bids, shall be covered in the bids and shall be made a part of the Contract. Failure to so acknowledge may result in the bid being rejected as non- responsive. Failure of any bidder to receive such addenda shall not be grounds for non-compliance with the terms of the instructions.
3.5. REGISTRATION OF CONTRACTORS
All bidders shall be licensed under the provisions of Chapter 9, Division 3, or the Business and
Professions Code of the State of California to do the type of work contemplated in the project and shall be skilled and regularly engaged in the general class or type of work called for under the Contract.
Each bidder shall set forth in its proposal the number, classification, and date of expiration of such license.
3.6. SCHEDULE OF BID
Bids shall be prepared and submitted in ProcureNow under “Schedule of Bid”. The Total Base Bid shall constitute full compensation for furnishing all materials and doing all work indicated on the drawings or herein specified.
Bidders are advised that a potential exists for the performance of extra work and furnishing of materials by the Contractor which is required for the proper completion of the work or construction of the whole of the project as originally contemplated.
3.7. COMPARISON OF PROPOSALS
Proposals will be compared on the basis of the Total Base Bid stated in “Schedule of Bid ”.
WCW agrees to examine and consider each bid submitted in consideration of the bidder's agreements, as set forth and as set forth in the proposal forms.
Any proposal which, in the opinion of WCW, is so unbalanced between the various Contract items as to be detrimental to the best interests of WCW, will be rejected.
3.8. BIDDER'S STATEMENT OF EQUIPMENT/MATERIAL MANUFACTURERS AND
SUPPLIERS AND STATEMENT OF SUBCONTRACTORS
In the form entitled Bidder's Statement of Equipment/Material Manufacturers and Suppliers, each bidder must submit the name of each person, company, or firm who will, off the job site, specially fabricate and/or provide materials or equipment proposed to be furnished under the bid.
In the form entitled Bidder's Statement of Subcontractors, the bidder shall submit the name and location of the place of business of each subcontractor who will perform work or labor or render service to the prime contractor in or about the construction of the work or improvement, or a subcontractor licensed by the State of California who under subcontract to the prime contractor specially fabricates
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2) and installs a portion of the work or improvement according to detailed drawings contained in the Plans
Specifications, in an amount in excess of one-half of one percent (l/2%) of the proposal total or five thousand ($5,000) dollars, whichever is greater, as set forth in the Schedule of Bid. The prime contractor shall indicate the portion which will be done by each such contractor for each such portion as its defined by the subcontractor in its bid.
Failure to list subcontractors in the “Bidder's Statement of Subcontractors” is an express statement by the bidder that it will perform that portion of the work with its own forces. Any request for substitution of a listed subcontractor must be made as provided in the Public Contract Code Section 4107. The prime contractor may not substitute any person or subcontractor for a listed subcontractor without first obtaining written permission of WCW's Board of Directors.
3.9. QUALIFICATION OF BIDDERS
Each bidder shall examine the site and submit with its proposal a financial responsibility, technical ability, and experience statement, substantially in the form included as, “Bidder's Statement of Financial
Responsibility, Technical Ability, and Experience”.
If bidder is a corporation, it shall submit its state of incorporation in addition to its business address; if a partnership or joint venture, full names of all partners or joint venturers shall be given in the form included in the Proposal.
WCW expressly reserves the right to reject any proposal if it determines that the bidder's business and technical organization, financial resources, plant and equipment to be used in performing work, or lack of successful experience in performing work, or lack of successful experience in performing work of similar type and magnitude, is such that it is not in WCW’s best interest to accept the bidder's proposal.
Contractors or subcontractors who have been determined to have violated any public work laws as set forth in Labor Code Section 1777.7 shall be denied the privilege to bid the work as provided therein.
3.10. CERTIFICATION OF COMPLETION REQUIREMENTS
Each bidder shall submit, as part of its proposal, a completed and executed certificate pertaining to the acceptability of the construction time frame as set forth in “Certificate Regarding Completion Time”.
The Contract time for this work shall be deemed to start five (5) calendar days from the date of the
Notice to Proceed. Contractor must submit a reasonable construction schedule in accordance with
Attachments – “Special Conditions, SC-4, CONSTRUCTION SCHEDULE, PROCEDURES AND, METHODS”.
3.11. PROPOSAL SECURITY
No proposal will be considered unless it is accompanied by proposal security in the form of a certified check or a cashier's check, payable to the order of West County Wastewater, for a sum not less than ten percent (10%) of the proposal total as set forth in the Schedule of Bid, or a bidder's bond in the same amount executed as surety by a corporation acceptable to WCWand authorized to issue such surety bond in the State of California. Such bond shall be in substantial conformity with the form included as
“Bidder’s Bond”. Payment of the proposal security in cash is not acceptable.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
Within fifteen (15) calendar days after execution of the Contract pursuant to the Contract Documents, and in any event not later than seventy (70) calendar days after the proposal opening, WCW will return to each bidder the proposal security which accompanied its proposal, except such security which may have been forfeited in accordance with the provisions of the Contract Documents.
3.12. BIDDER'S MODIFICATION AND WITHDRAWAL OF PROPOSALS
A bidder may, without prejudice to itself, modify or withdraw its proposal by written request, provided that the request is received by WCW prior to the closing time, at the place where the proposals are to be opened. Following withdrawal of its proposal, the bidder may submit a new proposal, provided that such new proposal is received prior to the stated bid opening date as provided in "Notice to Bidders ".
3.13. SUBSTITUTIONS
Proposals for substitution of materials, methods, and alternatives thereto not specified in the
Specifications shall be submitted in writing to WCW. Failure to submit requests for substitutions will be considered as evidence that the work will be accomplished with materials and by methods specified and in a manner approved by WCW.
3.14. PROPOSAL OPENING AND AWARD OF CONTRACT
Proposals will be kept unopened until the time stated for opening of proposals. At such time, the contents of the proposal will be made public. No responsibility shall attach to WCW or any of its officers, employees, or representatives for the premature opening of a proposal. All bidders or their authorized representatives are invited to be present at the proposal opening.
If award is made, it will be based on the lowest responsive, responsible bid whose base bid is the lowest.
The right is reserved, as the interest of WCW may require, to reject any or all proposals and to waive any informality in proposals received.
Within sixty (60) days after the time of opening of the bids, WCW will act either to accept a bid, to reject all bids or with the consent of the bidders and their sureties to extend the time in which WCW may act.
The acceptance of a bid will be evidenced by a Notice of Award of Contract in writing, delivered in person or by certified mail to the bidder whose bid is accepted. No other act of WCW will constitute acceptance of a bid. The Award of Contract shall obligate the bidder whose bid is accepted to furnish performance and payment bonds and evidences of insurance, and to execute the Agreement in the form set forth in the Contract Documents. The Contract will require the completion of the Work according to the Contract Documents.
The Agreement shall be executed by the successful bidder and returned, together with the Contract bonds and evidences of insurance, within the specified time period after receiving written Notice of
Award of the Contract. Time is of the essence in this regard. After execution by the owner, one copy of the Agreement shall be returned to Contractor.
The failure of any bidder to whom WCW may award the Contract, as aforesaid to sign and return to
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
WCW, the Contract together with the required Performance Bond, Payment Bond, and insurance certificates and endorsements the specified time period, shall entitle WCW to declare a breach of
Contract by such bidder, to award the Contract to another bidder in accordance with the provisions of the Contract Documents, and to declare a forfeiture of the bidder's proposal security accompanying its proposal.
In the event of such failure, WCW will suffer damage, the amount of which is difficult, if not impossible, to ascertain, and WCW shall therefore be entitled to retain the amount of such cashier or certified check, submitted by the bidder as proposal security, or to enforce the provisions of the Bidder's Bond in the amount thereof, as liquidated damages for such breach of Contract, as provided by applicable law.
3.15. RELIEF OF BIDDERS
Should a bidder claim a mistake was made in its bid, the bidder shall give the WCW written notice within five (5) calendar days after proposal opening of the alleged mistake, and detail in said notice the circumstances under which the mistake occurred all in accordance with Public Contract Code, Section
5103. Final determination of relief of bidders shall be made by WCW Board. Should the WCW Board accept the bidder's claim for relief, the bidder will be released from all obligations and further requirements and its proposal security will be returned as applicable.
3.16. BONDS AND INSURANCE POLICIES
The bidder to whom the contract award is made shall, at the time of execution of the Contract, furnish to WCW a Performance Bond and a Payment Bond, executed as surety by a corporation acceptable to
WCW and authorized to issue such surety bonds in the State of California. Such bonds shall be substantially in the form included with this solicitation. Such Performance Bond and Payment Bond shall be for one hundred (100) percent of the proposal total as set forth in the Schedule of Bid. The entire cost of these bonds shall be borne by the successful bidder.
If the surety on any bond furnished by the Contractor is declared bankrupt, or becomes insolvent, or its right to do business is terminated, or it ceases to meet the requirements of the above paragraph, the
Contractor shall, within five (5) calendar days thereafter, notify WCW and substitute another bond and surety, both of which must be acceptable to WCW.
3.17. NONDISCRIMINATION IN EMPLOYMENT
Contracts for work under this Proposal will obligate the Contractor and subcontractors not to discriminate in employment practices.
3.18. AGREEMENT TO ASSIGN (BIDDERS)
The bidder's attention is directed to the provisions of Government Code, Section 4552, which requires that in submitting a bid to a public purchasing body, bidders offer to assign all rights arising from violations of antitrust regulations to the public entity if the bid is accepted. In pertinent part, Government Code, Section 4552, reads as follows:
In submitting a bid to a public purchasing body, the bidder offers and agrees that if the bid is accepted, it will assign to the purchasing body all rights, title, and interest in and to causes of action it may have
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2) under Section 4 of the Clayton Act (15 U.S.C. Sec 15) or under the Cartwright Act (Chapter 2
[commencing with Section 16700] of Part 2 of Division 7 of the Business and Professions Code), arising from the purchase of goods, materials, or services by the bidder for sale to the purchasing body pursuant to the bid. Such assignment shall be made and become effective at the time the purchasing body tenders final payment to the bidder.
3.19. PLANS AND SPECIFICATIONS TO SUCCESSFUL BIDDERS
The bidder to whom award is made may obtain four (4) sets of Plans and Specifications for the work at no extra costs. Additional sets may be purchased at $30.00 per set. It is the Contractor's responsibility to provide its own set(s) of conformed Plans and Specifications.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
4. Schedule of Bid
Line Item Description Quantity Unit of
Measure Unit Cost Total
1 Mobilization and demobilization, including but not limited to bonds, insurance, survey staking, storm water BMPs, noise and dust control, temporary facilities such as water, power, fencing and sanitary facilities, as specified in general requirements.
1 LS
2 Sedimentation Basin No.1 Demolition 1 LS
3 Sedimentation Basin No.1 Chain and
Flight Mechanism and Accessories
Installation
1 LS
4 Sedimentation Basin No.1 No.3 Water
Piping
1 LS
5 Sedimentation Basin No.1 Concrete
Crack Repair
1 LS
6 Sedimentation Basin No.1 Concrete
Surface Repair
1 LS
7 Sedimentation Basin No.1 Start-up, Commissioning, Inspection, and
Training
1 LS
8 Sedimentation Basin No.2 Demolition 1 LS
9 Sedimentation Basin No.2 Chain and
Flight Mechanism and Accessories
Installation
1 LS
10 Sedimentation Basin No.2 No.3 Water
Piping
1 LS
11 Sedimentation Basin No.2 Concrete
Crack Repair
1 LS
12 Sedimentation Basin No.2 Concrete
Surface Repair
1 LS
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
Line Item Description Quantity Unit of
Measure Unit Cost Total
13 Sedimentation Basin No.2 Start-up, Commissioning, Inspection, and
Training
1 LS
TOTAL
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
5. Scope of Work
5.1. Work Covered By Contract Documents
The Work to be performed under these Contract Documents is generally described as follows:
1. Sedimentation Basin No. 1 (SSB No. 1):
A. Procurement of the equipment for SSB No.1 will be covered by the Owner under a separate Procurement Contract. Contractor shall install Owner procured equipment for SSB No.1.
B. Removal and replacement of the No. 3 water system, including piping, valves, supports, hose reel system, and appurtenances.
C. installation, inspection and testing of chains-and-flight mechanism and accessories including drivers, motors, wall bearing supports, sprockets, flights, shafts, and chains.
D. Removal and replacement of 18 precast concrete walkway panels along SSB Nos. 1 and
2 (as shown on the Drawings), replaced in kind.
E. Removal and replacement of two sluice gates along SSBs Nos. 1 and 2 (as shown on the
Drawings).
F. Miscellaneous concrete surface restoration and crack repair.
G. Upgrades to electrical components, including modifications to existing electrical systems to support new collector equipment and integration with the existing control system.
2. Sedimentation Basin No. 2 (SSB No. 2):
A. Procurement of the equipment for SSB No.2 will be covered by the Owner under a separate Procurement Contract. Contractor shall install Owner procured equipment for SSB No.2.
B. Removal and replacement of existing chain-and-flight mechanisms and accessories, including drives, motors, wall bearing supports, sprockets, flights, shafts, and chains.
C. installation, inspection and testing of chains-and-flight mechanism and accessories including drivers, motors, wall bearing supports, sprockets, flights, shafts, and chains.
D. Removal and replacement of the No. 3 water system, including piping, valves, supports, hose reel system, and appurtenances.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
E. Removal and replacement of 18 precast concrete walkway panels along SSB Nos. 1 and
2 (as shown on the Drawings), replaced in kind.
F. Removal and replacement of two sluice gates along SSBs Nos. 1 and 2 (as shown on the
Drawings).
G. Miscellaneous concrete surface restoration and crack repair.
H. Upgrades to electrical components, including modifications to existing electrical systems to support new collector equipment and integration with the existing control system.
Please refer to the attachments section (Attachment A) for the entire Bid Documents and
Design Drawings.
5.2. Work Seasons
Work on the secondary sedimentation basins shall conform to the operational requirements of the Water Quality and Resource Recovery Plant (WQRRP)’s Dry and Wet Seasons. These seasons are defined as:
1. Dry Season – From May 15th to September 30th, the Owner must have at least two sedimentation basins in full operation to operate the facility and meet treatment requirements.
2. Wet Season – From October 1st to May 14th, the Owner must have at least three sedimentation basins in full operation to operate the facility and meet treatment requirements.
5.3. Intermediate Milestones
Milestone 1: SSB No.1 Work Approved for District use. This sedimentation basin must be complete and all installation, inspection, startup, functional testing, and commissioning activities must be complete in order for the Owner to take occupancy/utilization of the sedimentation basin. The first sedimentation basin must be accepted for occupancy/utilization by the Owner and treating wastewater by May 15th, 2027. Delay of specific ancillary or remaining items to be completed regarding this sedimentation basin approval may be approved by the Owner in writing.
Milestone 2: SSB No.2 Work Approved for District use. This sedimentation basin must be complete and all installation, inspection, startup, functional testing, and commissioning activities must be complete in order for the Owner to take occupancy/utilization of the sedimentation basin. This sedimentation basin must be accepted for occupancy/utilization by the Owner and treating wastewater by September 30th, 2027. Delay of specific ancillary or remaining items to be completed regarding this sedimentation basin approval may be approved by the Owner in writing.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
Milestone 3: Final Completion: All remaining punch list work, site restoration, project closeout, and all activities not related to previously completed milestones must be completed prior to the expiration of the number of days listed in the Contract. Following completion of Milestone 3, Contractor may request Engineer’s final inspection and Contract acceptance.
5.4. Work By Owner
Owner shall perform certain activities in connection with the Project with its own personnel as follows:
A. Drain and transfer contents of SSBs prior to the work. Process liquid and sludge will be removed and the SSB hosed down.
B. WCW will directly procure and furnish the replacement collector chains and flights for
SSB-01 and SSB-02 and will coordinate the anticipated delivery schedule with the
Contractor.
5.5. Items Furnished By Owner
A. Shop and installation drawings pertaining to the equipment and materials will be furnished to Contractor upon completion of review by Engineer
B. Equipment:
1. Complete chain and flight system associated with SSB’s No. 1 and 2.
C. After delivery, Contractor shall be responsible for the unloading, handling, storage, and installation of the equipment and materials, all in accordance with the Contract Documents.
D. Owner and Engineer shall be responsible for coordination and scheduling of the services provided by the Procurement Vendor.
5.6. Items Furnished By Contractor
Contractor shall be fully responsible for all materials and equipment which it has furnished. This includes but not limited to all labor, equipment, materials, supervision, and coordination necessary to:
A. Receive and unload the WCW-furnished collector chains and flights upon delivery.
B. Inspect the equipment upon receipt and promptly notify WCW of any visible damage, shortages, or discrepancies.
C. Properly handle, store, secure, and protect the equipment from the time of receipt through installation.
D. Coordinate the installation of the owner-furnished equipment with all other Work.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
E. Install, adjust, test, and place the collector chains and flights into service in accordance with the Contract Documents and manufacturer requirements.
F. Perform all associated demolition, concrete repairs, coatings, mechanical improvements, site restoration, and other work necessary to provide complete and operational improvements to SSB-01 and SSB-02.
the Contractor shall not include the purchase cost of the replacement collector chains and flights in its Bid. All costs associated with receiving, unloading, handling, storage, protection, coordination, and installation of the owner-furnished equipment shall be included in the
Contractor's Bid.
5.7. Delivery and Handling of Items Furnished by Owner
A. Equipment and materials shall be protected from exposure to the elements. All equipment shall be stored in accordance with the requirements of the Contract
Documents.
B. All equipment shall be arranged and installed as indicated on the Drawings, and in conformity with installation drawings and instructions furnished to Owner by the manufacturer of the equipment.
C. The chain and flight mechanism components previously ordered to be furnished by
Owner shall be installed under the supervision of an experienced erection supervisor whose services are included as a part of the equipment procurement contract and will be provided by Owner at no expense to Contractor. The extent to which the services of the erection supervisor will be furnished will be determined by Owner. Contractor shall be required to coordinate and schedule this supervision and inspection by the Supplier in order to align with their schedule. Any delay as a result of lack of coordination or communication will be the responsibility of the Contractor.
D. Before being placed in operation, all equipment furnished by Owner and installed by
Contractor will be inspected, checked, and adjusted by an experienced and competent technical representative of the equipment manufacturer. The technical representative will also place the equipment in initial operation under both trial and full load conditions and determine whether its operation is satisfactory and proper. This service is included as part of the equipment procurement contract and will be provided by Owner at no cost to Contractor, as set forth in the Quality Control section.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
6. Contract Award
6.1. Award and Execution of Contract
The successful bidder will be notified in writing by WCW of Award of Contract within Sixty (60) calendar days after opening of proposals. Accompanying WCW’s Notice of Award will be the Contract, in duplicate, which the successful bidder will be required to sign and return together with the Performance
Bond, Payment Bond, and the required number of copies of insurance certificates and endorsements to
WCW within ten (10) calendar days following receipt of such Notice of Award. WCW will promptly determine whether such Contract, bonds, and insurance certificates and endorsements are as required by the Contract Documents, and upon such determination will forward a fully signed copy of the
Contract to the successful bidder. WCW may issue a Notice to Proceed at any time prior to forwarding the Contract. No work shall be performed at the site prior to the date set forth in the Notice to Proceed.
The failure of any bidder to whom WCW may award the Contract, as aforesaid to sign and return to
WCW, the Contract together with the required Performance Bond, Payment Bond, and insurance certificates and endorsements within the specified time period, shall entitle WCW to declare a breach of
Contract by such bidder, to award the Contract to another bidder in accordance with the provisions of the Contract Documents, and to declare a forfeiture of the bidder's proposal security accompanying its proposal.
6.2. Bonds and Insurance Policies
The Bidder to whom the contract award is made shall, at the time of execution of the Contract, furnish to WCW a Performance Bond and a Payment Bond, executed as surety by a corporation acceptable to
WCW and authorized to issue such Surety Bonds in the state of California. Such bonds shall be substantially in the form included in Subsections 3 and 4 respectively, of Section 01004 of the Contract
Documents. Such Performance Bond and Payment Bond shall be for one hundred (100) percent of the
Proposal total as set forth in the Schedule of Bid, Section 01003, Subsection 2. The entire cost of these bonds shall be borne by the successful Bidder.
If the Surety on any bond furnished by the Contractor is declared bankrupt, or becomes insolvent, or its right to do business is terminated, or it ceases to meet the requirements of the above paragraph, the
Contractor shall, within five (5) calendar days thereafter, notify WCW and substitute another bond and surety, both of which must be acceptable to WCW.
The successful Bidder shall at the time of execution of the Contract deliver to WCW one (1) copy of policies of insurance obtained in accordance with the requirements of the Contract Documents.
6.3. Workers' Compensation Statement
The Bidder to whom the Contract Award is made shall, at the time of execution of the Contract, furnish to WCW a statement certifying compliance with the workers' compensation provision of the California
Labor Code. Such certification shall be substantially in the form included in Section 01004, Subsection 6 of the Contract Documents.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
7. Terms and Conditions
7.1. Award and Execution of Contract
The successful bidder will be notified in writing by WCW of Award of Contract within Sixty (60) calendar days after opening of proposals. Accompanying the WCW’s Notice of Award will be the Contract, in duplicate, which the successful bidder will be required to sign and return together with the Performance
Bond, Payment Bond, and the required number of copies of insurance certificates and endorsements to
WCW within ten (10) calendar days following receipt of such Notice of Award. WCW will promptly determine whether such Contract, bonds, and insurance certificates and endorsements are as required by the Contract Documents, and upon such determination will forward a fully signed copy of the
Contract to the successful bidder. WCW may issue a Notice to Proceed at any time prior to forwarding the Contract. No work shall be performed at the site prior to the date set forth in the Notice to Proceed.
The failure of any bidder to whom WCW may award the Contract, as aforesaid to sign and return to
WCW, the Contract together with the required Performance Bond, Payment Bond, and insurance certificates and endorsements within the specified time period, shall entitle WCW to declare a breach of
Contract by such bidder, to award the Contract to another bidder in accordance with the provisions of the Contract Documents, and to declare a forfeiture of the bidder's proposal security accompanying its proposal.
7.2. Bonds and Insurance Policies
The Bidder to whom the contract award is made shall, at the time of execution of the Contract, furnish to WCW a Performance Bond and a Payment Bond, executed as surety by a corporation acceptable to
WCW and authorized to issue such Surety Bonds in the state of California. Such bonds shall be substantially in the form included in Subsections 3 and 4 respectively, of Section 01004 of the Contract
Documents. Such Performance Bond and Payment Bond shall be for one hundred (100) percent of the
Proposal total as set forth in the Schedule of Bid, Section 01003, Subsection 2. The entire cost of these bonds shall be borne by the successful Bidder.
If the Surety on any bond furnished by the Contractor is declared bankrupt, or becomes insolvent, or its right to do business is terminated, or it ceases to meet the requirements of the above paragraph, the
Contractor shall, within five (5) calendar days thereafter, notify WCW and substitute another bond and surety, both of which must be acceptable to WCW.
The successful Bidder shall at the time of execution of the Contract deliver to WCW one (1) copy of policies of insurance obtained in accordance with the requirements of the Contract Documents.
7.3. Workers' Compensation Statement
The Bidder to whom the Contract Award is made shall, at the time of execution of the Contract, furnish to WCW a statement certifying compliance with the workers' compensation provision of the California
Labor Code. Such certification shall be substantially in the form included in Section 01004, Subsection 6 of the Contract Documents.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
7.4. Authority of the Engineer
A. "WCW" is the West County Wastewater. The "Design Engineer" is listed in Notice to Bidders. The
"Engineer" is WCW Engineer of West County Wastewater or the Engineer's duly authorized representative during the life of the Contract. The engineer will observe the work in progress on behalf of WCW. All questions and requests of the Contractor as to compensation (including additional compensation), interpretation of the Contract, instructions, or extensions of time, otherwise shall be submitted in writing to the Engineer for determination.
B. The Engineer is authorized to determine the amount, quality, acceptability, and fitness of all work, materials, and equipment required by the Contract.
C. The Engineer will decide all questions which may arise as to the quality or acceptability of materials furnished and work performed and as to the manner of performance and rate of progress of the work, and the Engineer's decision will be final.
D. The Engineer will decide all questions which may arise as to the coordination and interpretation of the plans and specifications, and the Engineer's decision will be final.
E. The Engineer will decide all questions as to the acceptable fulfillment of the Contract on the part of the Contractor, and the Engineer's decision will be final.
F. The Engineer will decide all questions as to measurement and payment, and the Engineer's decision will be final.
G. The Engineer will have the authority to reject defective work and materials whenever such rejection may be necessary to assure execution of the Contract in accordance with the intent of the Contract Documents.
H. The Engineer will determine all amounts owing to the Contractor.
I. The Engineer will prepare/issue contract change orders for all authorized changes or approved extra work in the Contract.
J. The Engineer will have the authority to monitor project schedules and to enforce project schedule requirements, and to take such measures as may be necessary to maintain overall project schedules.
K. The Engineer will have the authority to enforce and to make effective such decisions and orders which the Contractor fails to carry out promptly.
L. All determinations and instructions of the Engineer whether in response to a question or otherwise will be final unless the Contractor shall file a written protest with the Engineer as set forth in this Article GC-1.
Title: Secondary Sedimentation Basins Upgrades Project - Short-term Improvements for Basins (1) & (2)
7.5. Contractor's Responsibilities and Appeal Procedure
A. The Contractor shall be solely responsible for requesting instructions or interpretations as required by the Contract, and any costs and expenses, including attorneys' fees, arising from its failure to do so shall be borne by the Contractor.
B. The Contractor shall proceed without delay to perform the work as directed, instructed, determined, or decided by the Engineer and shall comply promptly with such directions, instructions, determinations, or decisions. If the Contractor has any objection thereto, the
Contractor may, within ten (10) calendar days of having received any such directions, instructions, determinations, or decisions, require that any such direction, instruction, determination, or decision be put in writing. Within ten (10) calendar days after receipt of any such written determination, the Contractor may file a written protest with the Engineer stating clearly and in detail the Contractor's objections, the reasons therefor, and the nature and amount of additional compensation or extension of time, if any, to which the Contractor contends it will be entitled thereby. The Contractor shall proceed to perform the work that the
Contractor may contend as being outside the scope of the Contract while the Contractor's protest is being considered. The Contractor is cautioned, however, that unless the Contractor has been ordered by WCW pursuant to Article GC- 12.E., Request for Additional Compensation, to perform changes or extra work additional compensation will not be considered. The
Contractor shall prepare daily cost records and obtain an acknowledgment by the Engineer in accordance with GC-12C, Cost Plus Change Orders.
C. The Engineer will issue a decision upon each protest. If the Engineer determines that the facts support the protest, the Contract will be modified accordingly, in writing. If the Engineer determines that the facts do not support the protest, such request will be denied. The
Engineer's finding of fact of either determination will be given to the Contractor and such findings shall be final and conclusive. At all times, the Contractor shall proceed with the work in accordance with the direction, instruction, determination, or decision of the Engineer.