Natural Gas Valve Replacement Project (770 E Elm Ave) - Bid Notice Summary

This is a Bid Notice issued by the City of Coalinga, California, prepared by Tri City Engineering, for a Natural Gas Valve Replacement Project located at 770 E Elm Ave in Coalinga. The project involves contractor-performed improvements including hot tapping, bypass installation, welding, and installation of 2" carbon steel pipe, PC fittings, test nipples, and a valve to replace existing 2" gas main serving West Hills Community College, along with site improvements including excavation to access utilities. The City of Coalinga Public Works Department will complete valve riser and box installation, backfill, and concrete improvements. All base bid work must be completed within fourteen (14) working days from the Notice to Proceed. A mandatory virtual pre-bid meeting is scheduled for October 20, 2026, at 10:00 A.M. via Zoom. Sealed bids will be received at Tri City Engineering's office located at 4630 W. Jennifer Ave, Suite 101, Fresno, CA 93722, until 2:00 P.M. (DST) on November 10, 2026, with a public bid opening immediately following. The apparent low bidder will be announced at bid opening, and the successful bidder will be determined following the City Council meeting. Construction is scheduled to begin January 11, 2027, with completion targeted for January 29, 2027. Liquidated damages will be assessed at $1,000.00 per calendar day for work extending beyond the contract end date.

Bidders must submit bids as a lump sum, include bid security of no less than ten percent (10%) of the total bid amount, and must have purchased plans and specifications from Tri City Engineering (available for $10.00 on USB flash drive or $50.00 for a printed set) to be considered eligible prime bidders. The successful bidder will be required to provide a Performance Bond and Labor and Materials Bond, each equal to one hundred percent (100%) of the contract amount. Contractors and all subcontractors must comply with prevailing wage requirements as determined by the California Department of Industrial Relations for Fresno County - Area 2. The project is a local public works project requiring all contractors and subcontractors to be registered with the Department of Industrial Relations. Contractors must obtain a valid Class "C-34" Contractor's license prior to contract award and must secure City business licenses and construction permits. The City reserves the right to reject any and all bids, waive minor irregularities, and disqualify bids in accordance with its Ordinance Related to Disqualification of Contractors for Public Works Projects.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Coalinga Fresno County, California

Contract Documents & Specifications for:

Natural Gas Valve Replacement Project (770 E Elm Ave)

PW 26-11

Prepared By:

Tri City Engineering 4630 W. Jennifer Ave, Suite 101

Fresno, CA 93722-6415 www.tricityengineering.com

Bid Opening: November 10, 2026,2:00 P.M. (DST) Addendum No.: ________

Rev: 28-Oct-26

Natural Gas Valve Replacement Project (770 E Elm Ave)

TOC

Table of Contents

TABLE OF CONTENTS

TABLE OF CONTENTS .......................................................................................................... - 1 - DIVISION 0 – DOCUMENTATION .......................................................................................... - 3 -

SECTION 00010 - NOTICE TO CONTRACTORS ....................................................................................................... - 3 -

SECTION 00015 - LIST OF DRAWINGS ................................................................................................................... - 5 -

SECTION 00020 - PLANS AND SPECIFICATIONS .................................................................................................... - 6 -

SECTION 00050 - BID PACKET CHECKLIST ............................................................................................................. - 7 -

SECTION 00060 - DEFINITIONS AND TERMS ......................................................................................................... - 8 -

SECTION 00200 - INSTRUCTIONS TO BIDDERS .................................................................................................... - 10 -

SECTION 00360 - PERMITS INFORMATION ......................................................................................................... - 18 -

SECTION 00410 - BID PROPOSAL ........................................................................................................................ - 20 -

SECTION 00420 - BID ITEM DESCRIPTION ........................................................................................................... - 38 -

SECTION 00481 - NONDISCRIMINATION CLAUSE ............................................................................................... - 40 -

SECTION 00500 - CONSTRUCTION AGREEMENT (SAMPLE) ................................................................................ - 44 -

SECTION 00620 - INSURANCE CERTIFICATES ...................................................................................................... - 49 -

SECTION 00700 - GENERAL CONDITIONS ........................................................................................................... - 50 -

SECTION 00800 - SUPPLEMENTARY CONDITIONS .............................................................................................. - 51 -

DIVISION 1 – GENERAL REQUIREMENTS ......................................................................... - 63 - SECTION 01100 - SUMMARY ............................................................................................................................... - 63 -

SECTION 01200 - PRICE AND PAYMENT PROCEDURES ....................................................................................... - 65 -

SECTION 01270 - UNIT PRICES ............................................................................................................................ - 67 -

SECTION 01300 - ADMINISTRATIVE REQUIREMENTS ......................................................................................... - 68 -

SECTION 01325 - CONSTRUCTION PROGRESS SCHEDULE .................................................................................. - 73 -

SECTION 01400 - QUALITY REQUIREMENTS ....................................................................................................... - 75 -

SECTION 01500 - TEMPORARY FACILITIES AND CONTROLS ............................................................................... - 78 -

SECTION 01510 - TEMPORARY UTILITIES ............................................................................................................ - 80 -

SECTION 01550 - VEHICULAR ACCESS AND PARKING ......................................................................................... - 81 -

SECTION 01565 - SECURITY MEASURES .............................................................................................................. - 84 -

SECTION 01575 - TEMPORARY EROSION AND SEDIMENTATION CONTROL ....................................................... - 85 -

SECTION 01600 - PRODUCT REQUIREMENTS ..................................................................................................... - 87 -

SECTION 01700 - EXECUTION REQUIREMENTS .................................................................................................. - 89 -

SECTION 01732 - WASTE MANAGEMENT ........................................................................................................... - 91 -

SECTION 01780 - CLOSEOUT SUBMITTALS ......................................................................................................... - 93 -

TOC

Table of Contents

DIVISION 2 – SITE CONSTRUCTION .................................................................................. - 94 - SECTION 02200 - SITE PREPARATION ................................................................................................................. - 94 -

SECTION 02230 - SITE CLEARING ........................................................................................................................ - 97 -

SECTION 02315 - EXCAVATION .........................................................................................................................- 100 -

SECTION 231123 - FACILITY NATURAL-GAS PIPING ..........................................................................................- 101 -

SECTION 02316 - FILL AND BACKFILL ................................................................................................................- 107 -

DIVISION 3 – DIVISION 48 (NOT USED) ........................................................................... - 109 - APPENDIX A: PERMITS ..................................................................................................... - 110 -

Caltrans ENCROACHMENT PERMIT ..................................................................................................................- 111 -

APPENDIX B: LOCAL AGENCY CONSTRUCTION FORMS ............................................ - 112 - City of Coalinga Business License Application ..................................................................................................- 113 -

City of Coalinga Construction Meter Application .............................................................................................- 117 -

CITY OF COALINGA QUALITY ASSURANCE PROGRAM ......................................................................................- 122 -

Work Delay Form ..............................................................................................................................................- 131 -

APPLICATION FOR PAYMENT (G702/G703) ......................................................................................................- 132 -

FORM W-9: REQUEST FOR TAXPAYER IDENTIFICATION NUMBER AND CERTIFICATION ..................................- 135 -

Certificate of Construction Completion ............................................................................................................- 137 -

Mid Valley Solid Waste Disposal Schedule Map ...............................................................................................- 139 -

APPENDIX C: PRE-CONSTRUCTION SITE PHOTOS ...................................................... - 141 - END OF SPECIFICATIONS ................................................................................................ - 143 -

00010 - 3 -

Notice to Contractors

DIVISION 0 – DOCUMENTATION

SECTION 00010 - NOTICE TO CONTRACTORS

NOTICE IS HEREBY GIVEN that the City of Coalinga, California will receive sealed bids at the City Engineer’s Office (Tri City Engineering, Inc.) 4630 W. Jennifer Ave, Suite 101, Fresno, CA 93722, (559) 447-9075, Fax (559) 447-9074 on or before 2:00 P.M. (D.S.T.) November 10, 2026, for:

Natural Gas Valve Replacement Project (770 E Elm Ave)

Gas Valve Replacement north-east of 770 E Elm Ave in Coalinga, CA. Contractor improvements include hot tap, bypass, weld, and installation of 2" CS pipe, PC fittings, test nipples and valve of existing 2" gas main and a tee servicing West Hills Community College (WHCC). Site improvements include excavating existing soil to access utilities and bypass. City of Coalinga Public Works Department to complete valve riser and box, backfill, and concrete improvements.

All base bid work shall be completed within fourteen (14) working days from the date of the Notice to Proceed (NTP).

The contract is a local public works project and all contractors and subcontractors on public works projects must meet prevailing wage requirements. The Contractor shall pay not less than the prevailing rates of per diem wages as determined by the California Department of Industrial Relations (DIR) for the locality in which the work is performed.

The applicable wage determinations shall be those in effect at the time of advertisement for bids, based on the project location (Fresno County – Area 2, where applicable).

The Contractor shall be responsible for payment of any increases in wage rates and employer payments that are predetermined and identified within the applicable DIR wage determinations.

There will be a Mandatory virtual Pre-Bid Meeting on October 20, 2026, at 10:00 A.M. via Zoom. No one will be admitted after 10:05 A.M. All interested Bidders are directed to contact info@tricityengineering.com for an invitation request.

Project plans and specifications may be examined at Tri City Engineering, Inc.’s Office, the Fresno Builder’s Exchange and Coalinga City Hall, 155 W. Durian Ave., Coalinga, CA 93210.

Only those who have purchased Plans and Specifications from the office of the Engineer will be considered eligible Prime Bidders.

Copies may be obtained at the Tri City Engineering, Inc. office for a non-refundable fee of Ten Dollars ($10.00) for a USB Flash Drive or Fifty Dollars ($50.00) for a printed set in the form of a check made payable to Tri City Engineering, Inc. Call (559) 447-9075 for an appointment.

Each bid shall be accompanied by Bid Security, cash, a cashier’s or certified check payable to the City of Coalinga, or bid bond issued by a corporate surety, for an amount not less than ten percent (10%) of the aggregate of the bid, as a guarantee that the Bidder will enter into the proposed contract if the same is awarded to him. Such guarantee will be forfeited should the bidder to whom the contract is awarded fail to enter into the contract.

A Performance Bond in the amount equal to one hundred percent (100%) of the contract amount and a Labor and Materials Bond in the amount equal to one hundred percent (100%) of the contract amount will be required by the City from the bidder to whom the contract is awarded. Said bonds shall be issued by a surety company who is an admitted

00010 - 4 -

Notice to Contractors surety insurer authorized by the California Department of Insurance to transact business in this state, and acceptable to the City of Coalinga. Bidders are cautioned that representations made by surety companies will be verified with the California Department of Insurance. Pursuant to Public Contract Code Section 22300, substitution of securities for any monies withheld by the City of Coalinga to ensure performance under the contract shall be permitted.

The successful Bidder must possess or obtain a valid Class “C-34” Contractor’s license prior to the scheduled award date of this contract. Award consideration will take place at the earliest available Council meeting or as the City Manager has been authorized to award and execute the contract. All representations made on the proposal are made under penalty of perjury.

Bidders must review and adhere to the Project Specifications, Plans, Addenda and execute, sign, and seal Bids for a Formal Bid to be evaluated and deem responsive. The Apparent Low Bidder shall be announced during the Bid Opening and Successful Bidder announced following the City Council Meeting.

The City reserves the right, in its sole discretion, to reject any and all bids for any reason whatsoever, to waive minor irregularities in such bids, to determine the lowest responsible bidder, and to accept any bid. The City reserves the right, in its sole discretion, to disqualify bids, proposals, and/or affiliates as referred in the Ordinance Related to Disqualification of Contractors for Public Works Projects.

Pursuant to Section 1770, et. Seq., of the California Labor Code, the successful bidder shall not pay less than the prevailing rate of per diem wages as determined by the Director of the California Department of Industrial Relations.

These wage rates are available from the California Department of Industrial Relations’ Internet website at http://www.dir.ca.gov/DLSR/PWD. A copy of the mentioned wage rates shall be posted by the Contractor at the job site where it will be available to any interested party.

Pursuant to Section 1725.5 of the California Labor Code, no contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations at the time the contract is awarded.

Pursuant to Labor Code section 1771.1, no contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations.

Furthermore, no contractor or subcontractor may be awarded a contract on a public works project (awarded on or after April 1, 2015), unless registered with the Department of Industrial Relations.

Pursuant to Labor Code section 1771.4, all bidders are hereby notified that this project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.

Direct all questions for clarification of this Notice to Bidders to the Engineer in writing via Fax (559) 447-9074 or Email info@tricityengineering.com. All questions must be received on or prior to 12:00 P.M. (D.S.T.), November 5, 2026.

END OF SECTION

00015 - 5 -

List of Drawings

SECTION 00015 - LIST OF DRAWINGS

GENERAL SHEET INDEX:

Project Name: Natural Gas Valve Replacement Project (770 E Elm Ave) Project Plan No.: 3156 Local Project No.: PW 26-11

SHEET NO. TITLE:

BASE BID: NATURAL GAS VALVE REPLACEMENT PROJECT (770 E ELM AVE)

T1 TITLE SHEET

GN1 GENERAL NOTES SHEET

D1 DETAILS SHEET 1

D2 DETAILS SHEET 2

C1 CONSTRUCTION SHEET 1

ESCP EROSTION SEDEMENT CONTROL PLAN SHEET

00020 - 6 -

Plans and Specifications

SECTION 00020 - PLANS AND SPECIFICATIONS

The work embraced herein shall be done in accordance with the Standard Specifications dated 2025 and the City Standards dated December 2006, insofar as the same may apply and these special provisions.

In case of conflict between the Standard Specifications and these special provisions, the special provisions shall take precedence over and be used in lieu of the conflicting portions.

Amendments to the Standard Specifications set forth in these special provisions shall be considered as part of the Standard Specifications for the purposes set forth in Paragraph 5-1.04, "Coordination and Interpretation of Plans, Standard Specifications and Special Provisions," of the Standard Specifications. Whenever either the term "Standard Specifications is amended" or the term "Standard Specifications are amended" is used in the special provisions, the indented text or table following the term shall be considered an amendment to the Standard Specifications. In case of conflict between such amendments and the Standard Specifications, the amendments shall take precedence over and be used in lieu of the conflicting portions.

00050 - 7 -

Bid Packet Checklist

SECTION 00050 - BID PACKET CHECKLIST

BID CHECKLIST – COVER PAGE

Project Name: Natural Gas Valve Replacement Project (770 E Elm Ave) Project No.: PW 26-11 Plan No.: 3156

Owner's Name: City of Coalinga City Engineer's Name: Tri City Engineering, Inc.

REQUIRED CHECKLIST (INCLUSIVE OF ALL ITEMS A-D):

Bidders shall complete and submit one Bid Packet of all documents listed below for bids to be considered responsive. Documents required on the checklist but not included may render your Bid non-responsive and ineligible for award. Bids received by the City Engineer by the scheduled Bid Opening time will be opened and publicly read but are subject to verification during the evaluation process that all the required documents have been submitted.

A. ☐ BID CHECKLIST – COVER PAGE (Section 00050)

B. ☐ BID SECURITY in the form of:

[ ] Certified Check [ ] Bidder’s Bond [ ] Cashier’s Check

C. ☐ BID PROPOSAL (Section 00410)

1. ☐ BID PROPOSAL SUMMARY PAGE

2. ☐ BIDDER’S INFORMATION

3. ☐ ITEMIZED BID PROPOSAL

4. ☐ LIST OF SUBCONTRACTORS & SUBCONSULTANTS

5. ☐ LIST OF REFERENCES

6. ☐ GUARANTEE

7. ☐ INSURANCE CERTIFICATION

8. ☐ NONCOLLUSION AFFIDAVIT

9. ☐ PUBLIC CONTRACT CODE

10. ☐ EQUAL EMPLOYMENT OPPORTUNITY CERTIFICATION

11. ☐ LABOR CERTIFICATION

12. ☐ DEBARMENT AND SUSPENSION CERTIFICATION

13. ☐ DISCLOSURE OF LOBBYING ACTIVITIES

D. ADDENDA - All Addenda issued, Addenda No. to . (Enter numbers)

SUBMITTED BY:

Name of Company

Contact Name

Address

City

State Zip

Phone No. Fax No.

00060 - 8 -

Definitions and Terms

SECTION 00060 - DEFINITIONS AND TERMS

Terms below shall have the same meanings indicated in the Bidders Instructions, General Conditions and Supplementary Conditions, Ordinance Related to Disqualification of Contractors for Public Works Projects; additional terms may be called out. All terms apply throughout the entire Specifications which are applicable to both the singular and plural thereof:

Addenda (Addendum) – Written information adding to, clarifying and/or modifying the Contract Documents after publication.

Apparent Low Bidder – The Bidder with the lowest, responsive bid.

Bid – An offer by the Bidder for the work. Bid Packets are submitted in a sealed package of signed and executed Bid Documents as specified in Sections 00050 and 00200.

Bid Amount – Monetary sum identified by the Bidder.

Bid Documents – Contract Document Forms required to complete for a formal bid; as listed in Section 00050.

Bid Security – The cash, certified check, cashier’s check, or bid bond accompanying the Bid submitted by the Bidder as a guaranty that the Bidder will enter into a contract with the City for the construction of the work, if awarded to that Bidder.

Bidder – The individual or entity who submits a Bid.

Bidder’s Guaranty – See Guarantee Form and Bid Security.

Business Days – Monday through Friday, from 8:00 a.m. to 5:00 p.m., excluding City observed holidays and City closure days and times.

Calendar Days – All days in a month excluding federally observed holidays.

City – City of Coalinga.

Contract Document – Documents and Forms prepared for the work and packaged as Project Specifications; defined in State Standard Specifications and EJCDC C-700 Article 1 including issued Addenda.

Department of Public Works – Department of Public Works of the City of Coalinga.

Design Engineer – Tri City Engineering, Inc., also known as the City Representative.

Issuing Office – The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered.

Project Title – Natural Gas Valve Replacement Project (770 E Elm Ave).

Proposal – See Bid.

Proposal Form – See Bid Documents.

00060 - 9 -

Definitions and Terms

City Standards Plans – City of Coalinga Standards 2006.

State Standards – State of California Department of Transportation Standard Specifications, 2025. Any reference therein to the State of California or a State agency, office or officer shall be interpreted to refer to the City or its corresponding agency, office or officer acting under this contract.

State Standard Plans – The Standard Plans of the State of California, Department of Transportation.

Successful Bidder – Individual or entity whom submitted the lowest responsive Bid and all required Bid Documents to whom the Owner (on the basis of The Owner’s evaluations as hereinafter provided) makes an award.

Superintendent – The executive representative of the Contractor present on the project at all times during progress, authorized to receive and fulfill instructions from the Public Works Department.

Working Days – Monday through Friday from 7am to 6pm local time, and excludes weekends and public holidays.

Utilize Caltrans 5-Day Construction Workday Calendar.

00200 - 10 -

Instructions to Bidders

SECTION 00200 - INSTRUCTIONS TO BIDDERS

INVITATION

BID SUBMISSION

A. Bids signed and under seal, executed, and dated will be received at the Issuing Office of the Design Engineer, Tri City Engineering, Inc. at 4630 W. Jennifer Ave, Suite 101, Fresno, CA 93722 until 2:00 P.M. (D.S.T.) on November 10, 2026.

B. Bids submitted after the above time shall be returned to the Bidder unopened.

C. Bids will be opened publicly immediately after the time of receipt of bids.

D. Amendments to the submitted offer will be permitted if received in writing prior to bid closing and if endorsed by the same party or parties who signed and sealed the offer.

INTENT

The intent of this Bid request is to obtain an offer to perform work to complete the Natural Gas Valve Replacement Project (770 E Elm Ave) Project for a Stipulated Sum Contract, in accordance with the Contract Documents.

WORK IDENTIFIED IN THE CONTRACT DOCUMENTS:

Gas Valve Replacement north-east of 770 E Elm Ave in Coalinga, CA. Contractor improvements include hot tap, bypass, weld, and installation of 2" CS pipe, PC fittings, test nipples and valve of existing 2" gas main and a tee servicing West Hills Community College (WHCC). Site improvements include excavating existing soil to access utilities and bypass. City of Coalinga Public Works Department to complete valve riser and box, backfill, and concrete improvements.

CONTRACT TIME

Perform the base bid work in fourteen (14) working days.

CONSTRUCTION SCHEDULE (D.S.T.)

Mandatory Pre-Bid Meeting: November 5, 2026 10:00 A.M. via Zoom Questions/Clarifications Due: November 12, 2026 12:00 P.M.

Bid Opening: November 17, 2026 2:00 P.M. at Tri City Engineering, Inc.

Bid Award: December 3, 2026 Pre-Construction Meeting: December 15, 2026 1:30 P.M. at City Hall, 155 W Durian, Coalinga, CA

Construction Start: January 11, 2027 Construction End: January 29, 2027

Construction Schedule with no foreseeable changes.

LIQUIDATED DAMAGES

Liquidated Damages will be assessed at $1000.00 per day for every calendar day beyond the end of contract.

BID DOCUMENTS AND CONTRACT DOCUMENTS

DEFINITIONS

A. Terms below shall have the same meanings indicated in Section 00060 – Definitions and Terms; additional terms may be called out in these sections. All terms apply throughout the entire Specifications which are applicable to both the singular and plural thereof:

1. Prime Bidder: The individual or entity who purchases Plans and Specifications from the Office of the Engineer and submits a Formal Bid directly to Issuing Office.

2. Issuing Office: The office from which the Bid Documents are to be issued, submitted to, and where the bidding procedures are to be administered.

00200 - 11 -

3. Bid Documents: See Section 00060, Required Contract Document Forms to execute as instructed and package together with the remaining required Bid items.

4. Addendum (pl. Addenda): Written information adding to, clarifying and/or modifying the Contract Documents after publication. Addenda may replace and/or add Contract and Bid Documents, bidders shall adhere to all instructions.

5. Bidding: Act of submitting an offer/proposal under seal.

6. Bid Amount: Monetary sum identified by the Bidder in the Bid Form.

7. Evaluation: Formal review of all the formal Bids to verify if responsive or non-responsive. Completed after the Bid Opening by and in privacy of the City Engineer.

CONTRACT DOCUMENTS IDENTIFICATION

The Contract Documents are identified for the project Natural Gas Valve Replacement Project (770 E Elm Ave), Project Number PW 26-11, as prepared by Tri City Engineering, Inc., located at 4630 W. JENNIFER AVE. SUITE 101, FRESNO, CA 93722-6415 and identified in the Table of Contents. Specific Contract Documents are required to execute and submit as Bid Documents for all formal Bids and are identified in Section 00050 – Bid Packet.

AVAILABILITY

A. Contract Documents may only be purchased at Tri City Engineering, Inc., 4630 W. Jennifer Ave, Suite 101, Fresno, CA 93722.

B. Interested bidders may purchase a USB Flash Drive of the contract drawings and specifications for Ten Dollars

($10.00) or Fifty Dollars ($50.00) for a printed set. Payment is non-reimbursable and shall be made in the form of cash or a check made payable to Tri City Engineering, Inc. Call (559) 447-9075 for an appointment.

1. Only those who have purchased Plans and Specifications from the office of the Engineer will be considered eligible Prime Bidders and inserted on the Plan Holders List.

C. Bid Documents are made available only for the purpose of obtaining offers for this project. Their use does not grant a license for other purposes.

DOCUMENT EXAMINATION

A. Bid Documents may be viewed at Tri City Engineering, Inc., 4630 W. JENNIFER AVE, SUITE 101, FRESNO, CA 93722.

B. Bid Documents are on display at the office of the Fresno Builders Exchange, 1244 N. Mariposa Street, Fresno, CA 93703.

C. Upon receipt of Bid Documents verify that documents are complete. Notify the City Engineer should the documents be incomplete.

D. Immediately notify the City Engineer at (559) 447-9075 upon finding discrepancies or omissions in the Bid

Documents.

E. Complete sets of Bidding Documents must be used in preparing Bids; neither City nor Tri City Engineering, Inc., assumes any responsibility for errors or misinterpretation resulting from the use of incomplete sets of Bidding Documents.

INQUIRIES/ADDENDA

A. Direct questions to Tri City Engineering, Inc., info@tricityengineering.com or (559) 447-9075.

B. Clarifications requested by Bidders must be in writing and must be received not less than 4 days before date set for receipt of bids. The reply will be in the form of an Addendum, a copy of which will be forwarded to Plan Holders.

C. Addenda may be issued during the bidding period. All Addenda become part of the Contract Documents.

Include resultant costs in the Bid Amount.

D. Verbal answers are not binding on any party.

00200 - 12 -

PRODUCT/ASSEMBLY/SYSTEM SUBSTITUTIONS

A. Where the Bid Documents stipulate a particular product, substitutions will be considered up to 10 days before receipt of bids.

B. When a request to substitute a product is made, the Owner’s Representative may approve the substitution and will issue an Addendum to Plan Holders.

C. The submission shall provide sufficient information to determine acceptability of such products.

D. Provide complete information on required revisions to other work to accommodate each proposed substitution.

E. Provide products as specified unless substitutions are submitted in this manner and accepted.

SITE ASSESSMENT & EXAMINATION

Assess & examine the site before submitting a bid. Pre-bid meeting attendance is required to bid.

PRE-BID MEETING

There will be a Mandatory virtual Pre-Bid Meeting on October 20, 2026, at 10:00 A.M. via Zoom. No one will be admitted after 10:05 A.M. All interested Bidders are directed to contact info@tricityengineering.com for an invitation request.

QUALIFICATIONS

EVIDENCE OF QUALIFICATIONS

To demonstrate qualification for performing the work of this Contract, Bidders may be requested to submit written evidence of financial position, previous experience, and current commitments, license to perform work in the State and City. A bidder may be deemed not responsible because of past unsatisfactory performance, as evidenced by failure to meet the qualification requirements per the Ordinance Related to Disqualification of Contractors for Public Works Projects, or because of state or federal suspension/debarment action. Provide references from at least three

(3) other clients of similar scope that have been installed by your company in the last five (5) years. Include name of project, description of project, year completed, and project contact name, phone, and email address.

SUBCONTRACTORS/SUPPLIERS/OTHERS

City reserves the right to reject a proposed subcontractor for reasonable cause. Refer to EJCDC C-700 Article 6.06 of General Conditions and the Ordinance Related to Disqualification of Contractors for Public Works Projects.

BRAND NAMES

“Trade Names and Alternatives” – Wherever an article, or any class of materials, is specified by the trade name or by the name of any particular patentee, manufacturer or dealer, or by reference to the catalog of any such manufacturer or dealer, it shall be taken as intending to mean and specify the article of material described or any other equal thereto in quality, finish and durability, and equally as serviceable for the purpose for which it is or they are intended. It is not the intent of these plans and specifications to exclude or omit the products of any responsible manufacturer, if such products are equal in every respect to those mentioned herein.

STATE OF CALIFORNIA WAGE REQUIREMENTS

Notice is hereby given that, pursuant to 1773 of the Labor code of the State of California, the Owner has obtained from the Director of the Department of Industrial Relations the general prevailing rate of per diem wages and the general prevailing rate for holidays and overtime work for each craft, classification, or type of worker required to execute the Contract.

The Contractor shall pay not less than the prevailing rates of per diem wages as determined by the California Department of Industrial Relations (DIR) for the locality in which the work is performed. The applicable wage determinations shall be those in effect at the time of advertisement for bids, based on the project location (Fresno County – Area 2, where applicable).

The Contractor shall be responsible for payment of any increases in wage rates and employer payments that are

00200 - 13 -predetermined and identified within the applicable DIR wage determinations.

A copy of said prevailing rate of per diem wages is on file in the principal office of the Owner, to which reference is hereby made for further particulars. These wages are set forth in the General Prevailing Wage Rates for this project, available from the California Department of Industrial Relations’ Internet Web Site at: http://www.dir.ca.gov.

A. Statutory Penalty for Failure to Pay Minimum Wages

1. In accordance with 1775 of the California Labor Code, the Contractor shall as a penalty to the State of political subdivision on whose behalf a Contract is made or awarded, forfeit Eighty Dollars ($80.00) for each worker employed in the execution of the Contract by the Contractor or by any Subcontractor for each calendar day during which said worker is required or permitted to work more than eight hours in any one calendar day and forty hours in any one calendar week in violation of 1820-1815 of the California Labor Code.

B. Worker's Compensation Notice

1. As required by 1860 of the California Labor code and in accordance with the provisions of 3700 of the

Labor Code, every Contractor will be required to secure the payment of worker's compensation to its employees.

C. Worker's Compensation Certification by Contractor

1. In accordance with 1861 of the California Labor Code, the Contractor shall furnish the Owner a notarized statement as follows: "I am aware of the provisions of 3700 of the Labor Code which requires every employer to be insured against liability for worker's compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this Contract."

D. Apprenticeship Requirements

1. Contractor agrees to comply with 1777.5, 1777.6 and 1777.7 of the California Labor Code relating to the employment of apprentices. The responsibility for compliance with these provisions is fixed with the prime Contractor for all apprenticeship occupations. Under these sections of the law, Contractors and Subcontractors must employ apprentices in apprenticeship occupations, where journeymen in the craft are employed on the public work, in a ratio of not less than one apprentice hour for each five journeymen hours (unless an exemption is granted in accordance with 1777.5) and Contractors and Subcontractors shall not discriminate among otherwise qualified employees as indentured apprentices on any public work solely on the ground of race, religious creed, color, national origin, ancestry, sex, or age, except as provided in 3077 of the Labor Code. Only apprentices, as defined in 3077, which provides that an apprentice must be at least 16 years of age, who are in training under apprenticeship standards and who have signed written apprentice agreements will be employed on public works in apprenticeship occupations.

E. Payroll Records

1. Contractor shall keep accurate payroll records on forms provided by the Division of Labor Standards

Enforcement, or alternatively, the Contractor shall keep accurate payroll records containing the same information. Said information shall include, but not be limited to, a record of the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and actual per diem wages paid to each journeyman, apprentice, or worker employed by the Contractor. Such record shall be made available for inspection at all reasonable hours, and a copy shall be made available to employee or his authorized representative, the Division of Labor Standards Enforcement, and the Division of Apprenticeship Standards in compliance with California Labor Code, Section 1776. Upon written notice from the Owner or the Division of Labor Standards Enforcement, the Contractor shall, within ten (10) days, file with the Owner a certified copy of the payroll records. The Contractor shall cause an identical clause to be included in every subcontract for the work.

SUBCONTRACTOR LISTING LAW

REQUIREMENTS

A. In accordance with Section 4104 of the California Public Contract Code, each Bidder, in his or her Bid, shall set forth the name and the location of the place of business of each Subcontractor who will perform work or labor or

00200 - 14 -render service to the prime Contractor in or about the construction of the work or improvement, or a Subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the Plans and Specifications, in an amount in excess of one-half of one percent of the prime Contractor's total bid.

B. In accordance with Section 4107 of the California Public Contract Code, no Contractor whose Bid is accepted shall without consent of the Owner either:

1. Substitute a person as a Subcontractor in place of the Subcontractor listed in the original Bid; or

2. Permit a subcontract to be voluntarily assigned or transferred or allow it to be performed by anyone other than the original Subcontractor listed in the original Bid; or Sublet or subconsult any portion of the Work in excess of one-half of one percent of the prime Contractor's total Bid as to which his or her original Bid did not designate a Subcontractor.

C. Penalties for failure to comply with the foregoing sections of the California Public Contract Code are set forth in Sections 4106, 4110 and 4111 of the Public Contract Code. A prime contractor violating this law violates his or her contract and the awarding authority may exercise the option, in its own discretion, of (1) canceling his or her contract or (2) assessing the prime contractor a penalty in an amount of not more than (10%) percent of the amount of the subcontract involved, and this penalty shall be deposited in the fund out of which the prime contracts awarded. In any proceedings under this section the prime contractor shall be entitled to a public hearing and to five (5) days’ notice of the time and place thereof.

BID/PROPOSAL PACKET

BID PACKET REQUIREMENTS

A. Formal Bid Packets consists of required Bid Documents as described in Section 00050.

B. Bid Packets should be filled out, executed, and submitted in accordance with the instructions per this specification.

C. The Itemized Bid Proposal for this project includes both work listed as Lump Sum and work listed as Unit Price.

Bids shall be submitted as follows:

1. Lump Sum

i) Bidders shall submit a Bid on a Lump Sum basis as set forth in the Itemized Bid Proposal.

ii) The City reserves the right, in its sole discretion, to request scheduled values (itemized values) of lump sums following a bid submission.

2. Unit Price

i) Bidders shall submit a Bid on a unit price basis for each item of Work listed in the Itemized Bid Proposal.

ii) Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between words and figures will be resolved in favor of the words.

BONDING REQUIREMENTS

A. Bid Bond of 10% of bid amount.

B. Performance Bond 100% of contract amount.

C. Labor and Materials Bond 100% of contract amount.

SECURITY DEPOSIT

A. Bids shall be accompanied by a security deposit as follows:

1. Bid Security of a sum no less than (10%) percent of the Bid Amount.

B. Endorse the Bid Security in the name of the Owner as obligee, signed and sealed by the principal (Contractor) and surety.

C. The security deposit will be returned after delivery to the City of the required Performance and Payment Bond(s) by the accepted Bidder.

00200 - 15 -

D. Include the cost of bid security in the Bid Amount.

E. If no contract is awarded, all security deposits will be returned.

BIDDERS SIGNATURE

A. The Bid Documents shall be signed by the Bidder, as follows:

1. Sole Proprietorship: Signature of Sole Proprietor in the presence of a witness who will also sign. Insert the words "Sole Proprietor" under the signature. Affix seal.

2. Partnership: Signature of all partners in the presence of a witness who will also sign. Insert the word "Partner" under each signature. Affix seal to each signature.

3. Corporation: Signature of a duly authorized signing officer(s) in their normal signatures. Insert the officer's capacity in which the signing officer acts, under each signature. Affix the corporate seal. If the bid is signed by officials other than the president and secretary of the company, or the president/secretary/treasurer of the company, a copy of the by-law resolution of their board of directors authorizing them to do so, must also be submitted with the Bid Form in the bid envelope.

4. Joint Venture: Each party of the joint venture shall execute the Bid Form under their respective seals in a manner appropriate to such party as described above, similar to the requirements of a Partnership.

B. In 1999, California enacted the California Uniform Electronic Transactions Act (CUETA) in Civil Code 1633.1 to give electronic signatures the same legal authority as "wet" signatures on contracts.

1. An electronic signature is defined as an electronic sound, symbol or process that is attached to or logically associated with a record and executed or adopted by a person with the intent to sign the record.

2. By Signing electronically, all signatory parties of the contract agree to the use of electronic signatures to execute the contract.

BID SUBMISSION PROCEDURE

A. Bidders shall be solely responsible for the delivery of their bids in the manner and time prescribed.

B. Submit one copy of the executed Bid Packet in a sealed envelope, clearly identified with Bidder's name, Project name and City’s name on the outside.

1. Improperly identified submission, late submission or unsealed envelope may be cause not to open the

Bid envelope and declare the bid invalid, informal or non-responsive.

2. Oral, fax or email modifications to governing bid proposal after Bid Opening time prescribed will not be considered.

C. By submitting Bid Packet, the Bidder certifies that Bidder has visited the project site, is aware of existing conditions which affect the work, and has reviewed the Contract Documents, including the all Addenda.

PUBLIC BID OPENING PROCEDURE

A. The Bid Opening shall take place at the Issuing Office on the date and time prescribed.

B. Bid Packets shall be collected and remained sealed until after the Bid Opening Start time.

C. This project will have a Public Bid Opening, bidders may be present.

D. The City Engineer shall open sealed Bid Packets and read aloud the Bidders Name and Bid Amount.

E. After all bid packets have been opened and read, the apparent low bidder shall be announced and the Bid

Opening shall be closed.

F. After the Bid Opening closes, the evaluation to verify each bid packet in privacy of the City Engineer shall take place and a staff report (summary of the bid opening) shall be prepared and issued to the City Council for final award.

G. An abstract summary of submitted bids will be made available to all Bidders twenty-four (24) hours following bid closing.

BID INELIGIBILITY/NON-RESPONSIVE

A. Bids Packets that are unsigned, improperly signed, conditional, illegible, obscure, contain arithmetical errors, erasures, alterations, or irregularities of any kind, will at the discretion of the City, be declared unacceptable or

00200 - 16 -non-responsive.

B. Bid Documents, Appendices, Addenda and enclosures which are improperly prepared, will at the discretion of the City, be declared unacceptable or non-responsive.

C. Failure to provide bid security or acknowledge addenda, will at the discretion of the City, be declared unacceptable or non-responsive.

D. The Owner reserves the right to modify the Contract Documents and rebid the project, if necessary.

E. The City reserves the right, in its sole discretion, to disqualify bids, proposals, and/or affiliates as referred in the

Ordinance Related to Disqualification of Contractors for Public Works Projects.

PERFORMANCE ASSURANCE

Accepted Bidder: Provide a Performance and Payment bond as described in Document 00800 - Supplementary Conditions.

INSURANCE

Upon award of contract, contractor will be obligated to file certificates of insurance evidencing coverage as specified in the bid documents and in a form acceptable to the City.

SELECTION AND AWARD OF ALTERNATIVES

The lowest responsible bid price shall be determined by the Total Base Bid.

If there are alternatives, the lowest bid price shall be determined by adding the total of all bid items and the price of all alternatives. This does not preclude the City Council of the City of Coalinga from selecting any combination of alternates after the lowest responsible bidder has been determined.

Bids will be compared in the following strict order:

Total Base Bid = Base Bid

BID PROTEST PROCEDURES

The lack of prompt procedure to resolve disputes regarding the bidding process would impair the City’s ability to carry out its purpose of contracting this project in a timely manner. Therefore, to the maximum extent authorized by law and notwithstanding any other procedures specified in these Contract Documents, all disputes and/or protests regarding the bidding process shall be subject to the following procedure. In submitting a Bid to the City for this project, the Bidder agrees to comply with and to be bound by this procedure.

A. Any bid protest must be submitted in writing and in person to the City Engineer before 4:00 p.m. on the fifth (5th) working day following bid opening. Failure to give written notice before date and time prescribed shall waive the right to protest.

B. The bid protest must contain a complete statement of the basis for the protest and all supporting documentation.

A nonrefundable fee of seven hundred fifty dollars ($750) made payable to the City of Coalinga shall accompany the protest documents and will be used by the Owner to recover costs in evaluating the bid protest. A bid protest submitted without the requisite fee will be considered incomplete and will not be considered by the Owner.

C. The party filing the protest must concurrently transmit a copy of the initial protest document and any attached documentation to all other bidders. The bid protest must contain proof of service of the bid protest on the other bidders. If Proof of Service is completed via email, Tri City Engineering must be cc’d within the email and the email must be printed and provided with the bid protest.

D. The party filing the protest (protester) must have actually submitted a bid for the work. A subcontractor of a party submitting a bid for the work may not submit a bid protest.

E. A party may not rely on the bid protest submitted by another bidder but must timely pursue its own protest.

00200 - 17 -

F. The protest must refer to the specific portion of the Contract Documents which forms the basis for the protest.

G. The protest must include the name, address, and telephone number of the person representing the protesting party.

H. The party subject of the bid protest (protested bidder) must submit a response in writing and in person to the

City Engineer before 4:00 p.m. on the fifth (5th) working day following the filing of a bid protest.

I. The protested bidder must concurrently transmit a copy of the response document and any attached documentation to the party filing the protest and the City Engineer, and the response must contain proof of service. If Proof of Service is completed via email, Tri City Engineering must be cc’d within the email and the email must be printed and provided with the protest response.

J. The procedure and time limits set forth in this paragraph are mandatory and are the bidder’s sole and exclusive remedy in the event of the bid protest. The bidder’s failure to comply with these procedures shall constitute a waiver of any right to further pursue the bid protest, including filing a Government Code Claim or legal proceedings.

K. The City Engineer will evaluate all proper bid protest before the award of the contract to the lowest responsive and responsible bidder.

OFFER ACCEPTANCE/REJECTION

DURATION OF OFFER

Bids shall remain open to acceptance and shall be irrevocable for a period of Thirty (30) days after the bid closing date.

ACCEPTANCE OF OFFER

A. City reserves the right to accept or reject any or all offers.

1. Owner reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to be non-responsive.

2. Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids.

3. Owner reserves the right to waive all informalities not involving price, time, or changes in Work and to negotiate contract terms with the Successful Bidder.

4. More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.

5. The Owner reserves the right to modify the Contract Documents and rebid the project, if necessary, to meet Owner's budgetary requirements.

6. The City reserves the right, in its sole discretion, to disqualify bids, proposals, and/or affiliates as referred in the Ordinance Related to Disqualification of Contractors for Public Works Projects.

B. After acceptance by The City, The Owner’s Representative will issue to the Successful Bidder, a written letter of Notice of Recommendation to Award.

TIE BREAKER

In the event a tiebreaker is needed to establish the lowest responsive and responsible Bidder, the City shall, unless otherwise agreed upon by all participating parties, utilize a coin toss as a tiebreaker to be administered by a third party chosen by mutual consent of the participants. Such coin toss shall take place within Seven (7) working days from the date of bid opening. If the City determines that a tiebreaker is necessary, each applicable Bidder agrees to participate or to indemnify the City in any litigation resulting from the utilization of the tiebreaker. If a Bidder refuses to timely participate, the City shall conduct the coin toss in a manner determined by the City to be fair to all and the results of such coin toss shall be final.

00360 - 18 -

Permits Information

SECTION 00360 - PERMITS INFORMATION

PERMITS

GENERAL INFORMATION

A. This section provides information required to obtain permits necessary for construction of the project. Contractor shall obtain and pay for all construction permits and licenses.

B. The Contractor shall be bound by the permit, as it applies, during his work. The cost of all Contractor obligations under the permit shall be borne by the Contractor at no expense to the Owner.

C. CONTRACTOR shall submit permit applications with such promptness as to provide adequate time for review and case no delay to the project schedule.

CITY

A. Permit(s): More information can be found under the City of Coalinga, Community Development Department, https://www.coalinga.com/152/Community-Development

1. Contractor will be required to complete a City of Coalinga Construction Meter Application from the City for the work under this project.

B. Business License:

1. Contractor and all Subcontractors performing work under this project shall be required to secure and maintain a current City Business License during work on any part of the project.

2. Contact the following for information regarding obtaining a City Business License;

City of Coalinga Finance Department 155 W. Durian Ave Coalinga, CA 93210

(559) 935-1533

STATE OF CALIFORNIA, DEPARTMENT OF…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .