Bid Notice.pdf

PDF 1 MB Posted

Attached to
Demolition of Connex Box Structures and Removal of Debris
Solicitation number
ACFD 26-03
Issued by
Alameda County, California

About this file

This Bid Notice and associated contract documents are issued by the Alameda County Fire Department (ACFD) for the demolition of Connex box structures and removal of debris located at 890 Lola Street in San Leandro, California. The project involves demolishing two metal shipping container structures, one with a concrete block foundation, a small bungalow constructed as an addition to one structure, a rail car, assorted crashed car remains, 11 metal shipping containers, and a 1-ton propane tank. Certain on-site items must be preserved, including a classroom building, concrete training tower, metal silo, box truck, burn trailer, confidence course, tiller ladder trailer, tanker truck trailer, pickup truck, parking structure, three fire apparatus, compressor, and various concrete blocks and slabs. The mandatory combined pre-bid conference and site visit is scheduled for November 12, 2026, at 11:00 AM at the project site, with attendance required for bid eligibility. Sealed bids are due by 2:00 PM on December 10, 2026, at 6363 Clark Avenue, Dublin, California, with public opening immediately following. The Notice of Intent to Award is scheduled for December 11, 2026, with the estimated Notice of Award on January 5, 2027. The contract duration is 120 calendar days, with an estimated start date in March 2027 and completion by June 2027.

The estimated contract value is $250,000, and bidders must submit bids on the ACFD-provided Bid Form with a bid bond, cash, or cashier's check equal to 10 percent of the total bid price. The successful bidder must furnish 100 percent performance and payment bonds and maintain active California contractor licensing (Class A, B, or C21) throughout contract performance. All work is subject to prevailing wage requirements under California Labor Code sections 1770 et seq., with rates available through the Department of Industrial Relations. Contractors and subcontractors must register with the Department of Industrial Relations and comply with the Alameda County Contract Compliance System, including the Elation Systems application for payroll and payment tracking. The contract requires compliance with hazardous materials procedures, workers' compensation insurance, and various certifications including non-collusion and debarment declarations. Liquidated damages are assessed at $1,500 per day for delays beyond the contract completion date. ACFD reserves the right to reject any and all bids and award the contract to the lowest responsive responsible bidder based on base bid amount only.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS AND OTHER BIDDING AND CONTRACT DOCUMENTS

ALAMEDA COUNTY FIRE DEPARTMENT PROJECT #ACFD 26-03

Demolition of Connex Box Structures and Removal of Debris

MANDATORY COMBINED PRE-BID CONFERENCE AND SITE VISIT

THURSDAY, NOVEMBER 12, 2026, AT 11 AM

890 Lola Street, San Leandro

ALAMEDA COUNTY FIRE DEPARTMENT

6363 CLARK AVE.

DUBLIN, CA

DOCUMENT 00 01 09

SUMMARY BIDDING CALENDAR

NOTICE – This summary is for informational purposes only and does not list all dates or times in the bidding documents. The dates and times listed may not be relied upon or enforced. This summary does not form a part of the contract documents and does not establish contractual obligations. All bidders and contractors must refer to the actual documents for all applicable dates and time periods.

Event Date Reference

Contract documents available October 27, 2026 00 11 16 Notice to Bidders

Combined mandatory in-person pre-bid conference

November 12, 2026, at 11

AM

00 11 16 Notice to Bidders

Combined mandatory site visit

November 12, 2026, at 11

AM

00 11 16 Notice to Bidders

Last day for receipt of requests for substitutions before receipt of bids

November 16, 2026 00 21 13 Instructions to Bidders

Last day for Receipt of questions

November 16, 2026 00 21 13 Instructions to Bidders

Receipt of bids and bid opening

December 10, 2026, at 2 PM at 6363 Clark Ave.

Dublin, CA 94568 Campaign Room

00 11 16 Notice to Bidders 00 21 13 Instructions to Bidders 00 22 19 Supplemental Instructions to Bidders

Notice of Intent to Award December 11, 2026 00 51 13 Notice of Intent to Award

Last day to submit a bid protest

December 18, 2026 00 21 13 Instructions to Bidders

Estimated date of Notice of Award

January 5, 2026 TBD by ACFD (Board Date)

Signing of Contract January 2026 00 11 16 Notice to Bidders 00 51 10 Notice of Award

Submit post-award documents

January 2026 00 21 13 Instructions to Bidders

Last day to submit escrow bid documentation

January 2026 00 61 30 Escrow Bid Documentation

Contract duration 120 days 00 52 13 Agreement Form – Stipulated Sum (single prime contract)

Contract duration begins Estimated March 2027 00 55 00 Notice to Proceed

Contract duration ends Estimated June 2027 00 55 00 Notice to Proceed

Last day to submit preliminary schedule and other documents as noted, per Notice to Proceed

February 2027 00 55 00 Notice to Proceed

DOCUMENT 00 01 10

TABLE OF CONTENTS

Volume 1

DIVISION 00 – PROCUREMENT AND CONTRACTING

REQUIREMENTS

Please note that headings in bold that end in 00 do not have corresponding division documents.

They are heading titles for division documents listed below.

PROCUREMENT AND CONTRACTING REQUIREMENTS

INTRODUCTORY INFORMATION

00 01 01 Project Title Page

00 01 09 Summary Bidding Calendar

00 01 10 Table of Contents

00 01 15 List of Drawings

00 01 20 List of Schedules

PROCUREMENT REQUIREMENTS

SOLICITATION

00 11 16 Notice to Bidders

INSTRUCTIONS FOR PROCUREMENT

00 21 13 Instructions to Bidders

00 22 19 Supplementary Instructions to Bidders

AVAILABLE INFORMATION

00 31 19 Existing Conditions Information

PROCUREMENT FORM AND SUPPLEMENTS

00 41 13 Bid Form – Stipulated Sum (Single-Prime Contract)

00 43 13 Bid Security Form

00 43 36 Designated Subcontractors List

00 45 01 Site-Visit Certification

00 45 13 Non-Collusion Declaration

00 45 26 Worker’s Compensation Certification

00 45 46.01 Prevailing Wage and Related Labor Requirements Certification

00 45 46.04 Hazardous Materials Certification

CONTRACTING REQUIREMENTS

CONTRACTING FORMS AND SUPPLEMENTS

00 51 00 Notice of Intent to Award

00 51 10 Notice of Award

00 52 13 Agreement Form – Stipulated Sum (Single-Prime Contract)

00 52 13.1 Debarment and Suspension Certification Form

00 55 00 Notice to Proceed

00 61 30 Escrow of Bid Documentation

00 61 40 Escrow Agreement for Security Deposits in Lieu of Retention

PROJECT FORMS

00 61 13.13 Performance Bond Form

00 61 13.16 Payment Bond Form

00 65 19.26 Final Settlement Certificate Form

00 65 36 Warranty Form (Intentionally omitted)

CONDITIONS OF CONTRACT

00 72 13 General Conditions – Stipulated Sum (Single-Prime Contract)

00 73 13 Special Conditions

00 73 56 Hazardous Materials Procedures and Requirements

DIVISION 01 – GENERAL REQUIREMENTS

GENERAL REQUIREMENTS

00 01 00 Summary of Work

PRICE AND PAYMENT PROCEDURES

00 22 00 Unit Prices and Alternates

01 26 00 Contract Modification Procedures

01 29 00 Payment Procedures

ADMINISTRATIVE REQUIREMENTS

00 31 19 Project Meetings (Intentionally omitted)

01 33 00 Submittal Procedures (Intentionally omitted)

QUALITY REQUIREMENTS

01 41 00 Regulatory Requirements

01 42 00 References

01 42 13 Abbreviations and Acronyms

01 42 16 Definitions and Reference Standards

01 43 00 Quality Assurance – Materials and Equipment

01 45 00 Quality Control (Intentionally omitted)

01 50 00 Temporary Facilities and Controls

PRODUCT REQUIREMENTS

01 62 00 Product Options and Substitutions (Intentionally omitted)

01 65 00 Delivery, Storage and Handling (Intentionally omitted)

EXECUTION AND CLOSEOUT REQUIREMENTS

01 71 23 Field Engineering

01 73 29 Cutting and Patching (Intentionally omitted)

01 74 19 Construction Waste Management

01 76 00 Protecting Installed Construction

01 77 00 Contract Closeout

01 78 23 Operation and Maintenance Instructions (Intentionally omitted)

01 78 36 Warranties (Intentionally omitted)

01 78 39 Project Record Documents

LIFE CYCLE ACTIVITIES

01 91 13 General Commissioning Requirements (Intentionally omitted)

BFK SPECIFICATIONS

31 00 00 Soil Dust Mitigation Specifications

Volume 2 (Architectural Specifications)

END OF DOCUMENT

DOCUMENT 00 01 16

LIST OF DRAWINGS

Sheet Number File Number Description

General

G-1.0 Map of Site

DOCUMENT 00 01 20

LIST OF SCHEDULES

SCHEDULES

Project Duration: 120 Days project duration

Milestones:

Kick-Off Meeting

Set Up

Equipment Delivery

Demolition

On-Site Sorting of Recyclable Materials

Off-Haul

Site Clearance

DOCUMENT 00 11 16

NOTICE TO BIDDERS

Notice is hereby given that the Alameda County Fire Department (“Owner”) will receive sealed bids for the following project, Bid No. ACFD 26-03 (“Project” or “Contract”): Demolition of Connex

Box Structures and Removal of Debris.

1. Sealed bids will be received until 2:00 pm, December 10, 2026 at 6363 Clark Ave., Dublin, California, at or after which time the bids will be opened and publicly read aloud in the

Campaign Room. Any claim by a bidder of error in its bid must be made in compliance with §5100 et seq. of the Public Contract Code. Any bid that is submitted after this time shall be considered nonresponsive and returned to the bidder.

2. The project is located at 890 Lola Street in San Leandro.

3. The Project consists of:

a. Two structures constructed primarily from metal shipping containers need to be demolished and disposed of.

b. One structure includes a concrete block foundation that also is to be demolished and removed.

c. One structure was constructed as an addition onto a small bungalow. The bungalow is to be demolished and removed.

d. Assorted additional debris must be removed, including:

i. A rail car

ii. Assorted remains of crashed cars

iii. 11 metal shipping containers

iv. 1-ton propane tank

e. NOTE certain on-site items must remain:

i. Classroom building

ii. Concrete training tower

iii. Metal silo

iv. Box truck

v. Burn trailer

vi. Confidence course

vii. Tiller ladder trailer wood prop

viii. Tanker truck trailer

ix. Pickup truck

x. Parking structure

xi. Fire apparatus x3

xii. Compressor

xiii. Various concrete blocks and slabs

4. The estimated value for this contract is $250,000.

5. All bids shall be in the Bid Form Document 00 41 13 provided by ACFD. Each bid must conform to and be responsive to all pertinent Contract Documents, including but not limited to, the Instructions to Bidders Document 00 21 13 and the Supplemental

Instructions to Bidders Document 00 22 19.

6. To bid on this Project, the bidder is required to possess the following State of California

Contractor license:

a. Class A or B or C21 license

The bidder’s licenses and certificates must remain active and in good standing throughout the term of the Contract.

7. A bid bond by an admitted surety insurer on the form provided by ACFD, cash, or a cashier’s check or a certified check drawn to the order of the Alameda County Fire

Department, in the amount of ten percent (10%) of the total bid price, shall accompany the Bid Form, as a guarantee that the bidder will, within seven (7) calendar days after the date of the Notice of Award, enter into contract with ACFD for the performance of the services as stipulated in the bid.

8. The successful bidder shall be required to furnish a 100% Performance Bond and a 100%

Payment Bond if it is awarded the contract for the Work.

9. The successful bidder may substitute securities for any monies withheld by ACFD to ensure performance under the Contract, in accordance with the provisions of §22300 of the Public

Contract Code.

10. The Contractor and all Subcontractors under the Contractor shall pay all workers on all work performed pursuant to this Contract not less than the general prevailing rate of per diem wages and the general prevailing rate for holiday and overtime work as determined by the Director of the Department of Industrial Relations, State of California, for the type of work performed and the locality in which the work is to be performed within the boundaries of the ACFD property, pursuant to §§1770 et seq. of the California Labor Code.

Prevailing wage rates are also available from the County, the ACFD Administrative Offices, and online at: http://www.dir.ca.gov.

11. This project is subject to compliance monitoring and enforcement by the Department of

Industrial Relations. The following requirements apply to this bid and contract:

a. No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to the Labor Code §1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code §1771.1(q)].

12. Mandatory combined pre-bid conference site visit will be held on November 12, 2026 at

11 AM at the project site located at 890 Lola Street in San Leandro. All participants are required to sign in at the site. The site visit is expected to take approximately one hour.

Failure to attend or arrival after the material start of the meeting will render the bidder ineligible to bid and their bid will be considered not responsive.

13. Contract Documents and technical specifications were made available to Contractors as of

October 27, 2026.

http://www.dir.ca.gov/

14. It is County policy to minimize the expenditure of funds on goods and services produced by any entity which buys, sells, leases, or distributes commodities and/or professional services to (1) the government of Burma; or (2) any entity organized under the laws of

Burma; or (3) any entity which does business with ay private of public entity located in

Burma, or conducts operations in Burma. Contractors are urged to comply with the policy in making purchases and subcontracts. (Alameda County Administrative Code

§4.32.050(B), (F)). Burma is now known as Myanmar or, officially, the Republic of the

Union of Myanmar.

15. ACFD reserves the right to reject any and all bids and/or waive any irregularity in any bid received. If the ACFD awards the Contract, the security of the unsuccessful bidder(s) shall be returned within sixty (60) days from the time the award is made. Unless otherwise required by law, no bidder may withdraw its bid for ninety (90) days after the date of the bid opening.

16. The ACFD shall award the Contract, if it awards it at all, to the lowest responsive responsible bidder based on the base bid amount only.

DOCUMENT 00 21 13

INSTRUCTIONS TO BIDDERS

Bidders shall follow the instructions in this document, and shall submit all documents, forms, and information required for consideration of a bid.

ACFD will evaluate information submitted by the apparent low bidder and, if incomplete or unsatisfactory to ACFD, bidder’s bid may be rejected at the sole discretion of ACFD.

Bids are requested for a general construction contract, or work described in general for the following project (“Project” or “Contract”):

Demolition of Connex Box Structures and Removal of Debris

1. ACFD will receive sealed bids from bidders as stipulated in the Notice to Bidders Document

00 11 16.

2. Bidders must submit bids on Document 00 41 13 (Bid Form Stipulated Sum) and all other required ACFD forms. Bids not submitted on the ACFD’s required forms shall be deemed non-responsive and shall not be considered. Additional sheets required to fully respond to requested information are permissible.

3. Bidders must supply all information required by each Bid Document. Bids must be completed in full. ACFD reserves the right in its sole discretion to reject any bid as non-responsive as a result of any error or omission in the Bid. Bidders must complete and submit all of the following documents with Bid Form Document 00 41 13:

a. Document 00 43 13 Bid Security Form or other security

b. Document 00 43 36 Designated Subcontractors List

c. Document 00 45 01 Site-Visit Certification, if a site visit was required

d. Document 00 45 13 Non-Collusion Declaration

e. Document 00 52 13.1 Completed Debarment Form

4. Bidders must submit with their Bids cash, a cashier’s check or a certified check payable to

ACFD, or a Bid Bond of not less than ten percent (10%) of the amount of the base bid.

The required form of corporate surety, Bid Security Form Document 00 43 13, is provided by ACFD and must be used and fully completed by bidders choosing to provide a Bid Bond as security. The surety on bidder’s Bid Bond must be an insurer admitted in the State of

California and authorized to issue surety bonds in the State of California. Bids submitted without necessary bid security will be deemed non-responsive and will not be considered.

5. If bidder to whom Contract is awarded shall for SEVEN (7) calendar days after the date of the Notice of Award, fails or neglects to enter into Contract and to submit required bonds, insurance certificates, and all other required documents, ACFD may deposit Bid

Bond, cash, cashier’s check, or certified check for collection, and proceeds thereof may be retained by ACFD as liquidated damages for the failure of bidder to enter into the

Contract, in the sole discretion of ACFD. It is agreed that the calculation of liquidated damages ACFD may suffer as a result of bidder’s failure to enter into the Contract would be extremely difficult and impractical to determine and that the amount of the Bidder’s required bid security shall be the agreed and conclusively presumed amount of damages.

6. Bidders must submit with the Bid the Designated Subcontractors List for those subcontractors who will perform any portion of Work, including labor, rendering of service, or specially fabricating and installing a portion of the Work or improvement according to detailed drawings contained in the plans and specifications, in excess of one half of one percent (0.5%) of the total Base Bid. Failure to submit this list when requested shall result in Bid being deemed non-responsive and the Bid will not be considered.

7. If a mandatory pre-bid conference and site visit (“Site Visit”) is requested as referenced in the Instructions to Bidders, then Bidders must submit the Site-Visit Certification with their Bid. ACFD will transmit to all prospective Bidders of record such Addenda as ACFD in its discretion considers necessary in response to questions arising at the Site Visit. Oral statements shall not be relied upon and will not be binding or legally effective. Addenda issued by AFCD as a result of the Site Visit, if any, shall constitute the sole and exclusive record and statement of the results of the Site Visit.

8. Bidders shall submit the Non-Collusion Declaration Document 00 45 13 with their Bids.

Bids submitted without the Non-Collusion Declaration shall be deemed non-responsive and will not be considered.

9. Bids shall be clearly written without erasure or deletions. ACFD reserves the right to reject any Bid containing erasures or deletions.

10. Bidders shall not modify Document 00 41 13 (Bid Form-Stipulated Sum) or qualify their bids. Bidders shall not submit to the ACFD a scanned, re-typed, word-processed, or otherwise recreated version of Document 00 41 13 (Bid Form-Stipulated Sum) or other

ACFD-provided document.

11. The successful bidder and all its subcontractors shall pay all workers on all work performed pursuant to this Contract mot less than the general prevailing rate of per diem wages and the general prevailing rate for holiday and overtime work as determined by the Directo of the Department of Industrial Relations, State of California, for the type of work performed and the locality in which the work is to be performed within the boundaries of the County, pursuant to §§1770 et seq. of the California Labor Code.

12. Submission of a bid signifies careful examination of Contract Documents and complete understanding of the nature, extent, and location of the Work to be performed. Bidders must complete the tasks listed below as a condition to bidding, and submission of a bid shall constitute the bidder’s express representation to ACFD that bidder has fully completed the following:

a. Bidder has visited the site and has examined thoroughly and understood the nature and extent of the Contract Documents. Work, Site, locality, actual conditions, as-built conditions, and all local conditions and federal, state, and local laws, and regulations that in any manner may affect cost, progress, performance, or furnishing of Work or that relate to any aspect of the means, methods, techniques, sequences, or procedures of construction to be employed by bidder and safety precautions and programs incident thereto;

b. Bidder has conducted or obtained and has understood all examinations, investigations, explorations, tests, reports, and studies that pertain to the subsurface conditions, as-built conditions, underground facilities, and all other physical conditions at or contiguous to the Site or otherwise that may affect the cost, progress, performance, or furnishing of Work, as bidder considers necessary for the performance or furnishing of Work at the Contract Sum, within the Contract

Time, and in accordance with the other terms and conditions of Contract

Documents, including specifically the provisions of the General Conditions; and no additional examinations, investigations, explorations, tests, reports, studies, or similar information or data are or will be required by Bidder for such purposes;

c. Bidder has correlated its knowledge and the results of all such observations, examinations, investigations, explorations, tests, reports, and studies with the terms and conditions of the Contract Documents;

d. Bidder had given ACFD prompt written notice of all conflicts, errors, ambiguities, or discrepancies that it has discovered in or among the Contract Documents and the actual conditions, and the written resolution thereof by ACFD is acceptable to

Bidder;

e. Bidder has made a complete disclosure in writing to ACFD of all facts bearing upon any possible interest, direct or indirect, that Bidder believes any representative of

ACFD or other officer or employee of ACFD presently has or will have in this

Contract or in the performance thereof or in any portion of the profits thereof (see

Government Code §1090, et seq.);

f. Bidder must, prior to bidding, perform the work, investigations, research, and analysis required by this document and that Bidder represents in its Document 00

41 13 (Bid Form-Stipulated Sum) and the Agreement that it performed prior to bidding. Bidders are charged with all information and knowledge that a reasonable bidder would ascertain from having performed this required work, investigation, research, and analysis. Bid prices must include the entire cost of all work

“incidental” to completion of the Work.

g. Conditions Shown on the Contract Documents: Information as to underground conditions, as-built conditions, or other conditions or obstructions, indicated in the

Contract Documents (for example, on Drawings or in Specifications), has been obtained with reasonable care, and has been recorded in good faith. However, ACFD only warrants, and Bidder may only rely on, the accuracy of limited types of information.

i. As to above-ground conditions or as-built conditions shown or indicated in the Contract Documents, there is no warranty., express or implied, or any that such information is correctly shown or indicated. In submitting its Bid, Bidder shall rely on the results of its own independent investigation. In submitting its Bid, Bidder shall not rely on ACFD-supplied information regarding above-ground conditions or as-built conditions.

ii. As to any subsurface condition shown or indicated in the Contract

Documents, Bidder may rely only upon the general accuracy of actual reported depths, actual reported character of materials, actual reported soil types, actual reported water conditions, or actual obstructions shown or indicated. ACFD is not responsible for the completeness of such information for bidding or construction; nor is ACFD responsible in any way for any conclusions or opinions of Bidder drawn from such information; nor is ACFD responsible for subsurface conditions that are not specifically shown (for example, ACFD is not responsible for soil conditions in areas contiguous to areas where a subsurface condition is shown).

h. Conditions Shown in Reports and Drawings Supplied for Informational Purposes:

Reference is made to Document 00 31 19 Existing Conditions Information, for identification of:

i. Subsurface Conditions: Those reports of explorations and tests of subsurface conditions at or contiguous to the Site that have been utilized by Architect in preparing the Contact Documents; and

ii. Physical Conditions: Those drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site that has been utilized by Architect in preparing the Contract Documents.

iii. These reports and drawings are not Contract Documents and, except for any “technical” data regarding subsurface conditions specifically identified in Document 00 31 19 Existing Conditions Information, and underground facilities data, Bidder may not in any manner rely on the information in these reports and drawings. Subject to the foregoing and must not rely on information provided by ACFD.

13. Bidders may examine any available “as-built” drawings of previous work by giving ACFD reasonable advance notice. ACFD will not be responsible for accuracy of “as-built” drawings. The Document 0031 19 Existing Conditions Information applies to all supplied

“as-built” drawings.

14. Copies of the general prevailing rates of per diem wages for each craft, classification, or type of worker needed to execute the Contract, as determined by the Director of the State of California Department of Industrial Relations, are on file at ACFD’s principal office.

Prevailing wage rates are also available on the internet at www.dir.ca.gov.

15. All questions about the meaning or intent of the Contract Documents are to be directed in writing, including by email, to ACFD. Interpretations or clarifications considered necessary by ACFD in response to such questions will be issued in writing by Addenda faxed, mailed, or delivered to all parties recorded by ACFD as having received the Contract

Documents. Questions received less than TEN (10) business days prior to the date for opening bids may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

16. Addenda may also be issued to modify other parts of the Contract Documents as deemed advisable by ACFD.

http://www.dir.ca.gov/

17. Each Bidder must acknowledge each Addendum in its Document 00 41 13 (Bid Form-

Stipulated Sum (Single-Prime Contract)) by number, or its bid shall be considered non-responsive. Addenda shall be part of the Contract Documents. A complete listing of

Addenda may be secured from ACFD.

18. Bids shall be based on products and systems specified in Contract Documents or listed by name in Addenda. ACFD is not responsible or liable in any way for a Bidder’s damages and/or claims related, in any way, to that Bidder’s basing its bid on any requested substitution that ACFD has not approved. Bidders and materials suppliers who submit requests for substitutions prior to the award of the Contract must do so in writing and in compliance with Public Contract Code §3400. All requests must comply with the following:

a. ACFD must receive any request for substitution a minimum of TEN (10) business days prior to bid opening.

b. Requests for substitutions shall contain sufficient information to access acceptability of product or system and impact on Project, including, without limitation, the requirements specified in Document 00 73 13 (Special Conditions) and the Specifications. Insufficient information shall be grounds for rejection of the request for substitution.

c. Approved substitutions shall be listed in Addenda. ACFD reserves the right not to act upon submittals of substitutions until after bid opening.

d. Substitutions may be requested after Contract has been awarded only if indicated in and in accordance with requirements specified in the Document 00 73 13

(Special Conditions) and the Specifications’

19. All Bids must be sealed and marked with the name and address of the Bidder and the

Project Number, Bid number, Bid package, and time of bid opening. Bids will be received as indicated in the Notice to Bidders.

a. Mark envelopes with the name of the Project.

b. Bids must be submitted at the place and by the date and time shown in the

Instructions to Bidders.

c. Bids must contain all documents as required herein.

20. Bids will be opened publicly immediately after the time indicated for receipt of bids.

21. The Contract may include alternates. Alternates are defined as alternate products, materials, equipment, systems, methods, or major elements of the construction that may, at ACFD’s option and under terms established in the Contract and pursuant to §20103.8 of the Public Contract Code, be selected for the Work. ACFD shall award the Contract, if it awards at all, to the lowest responsive responsible bidder based on the criteria as indicated in these contract documents.

22. Time for Completion: ACFD may issue a Notice to Proceed within NINETY (90) calendar days from the date of the Notice of Award. Once Contractor has received the Notice to

Proceed, Contractor shall complete the Work within the period of time indicated in the

Contract Documents.

a. In the event that ACFD desires to postpone issuing the Notice to Proceed beyond the 90-day period above, it is expressly understood that with reasonable notice to the Contractor, ACFD may postpone issuing the Notice to Proceed.

b. It is further expressly understood by Bidder that Contractor shall not be entitled to any claim of additional compensation as a result of the postponement of the issuance of the Notice to Proceed beyond the 90-day period. If the Contractor believes that a postponement of issuance of the Notice to Proceed will cause a hardship to the Contractor, the Contractor may terminate the Contract.

Contractor’s termination due to a postponement beyond the 90-day period shall be by written notice to ACFD within TEN (10) calendar days after receipt by

Contractor of ACFD’s notice of postponement.

c. It is further understood by Bidder that in the event that Contractor terminates the

Contract as a result of postponement by ACFD, ACFD shall only be obligated to pay Contractor for the Work that Contractor had performed at the time of the notification of postponement and which ACFD had in writing authorized Contractor to perform prior to issuing the Notice to Proceed.

d. Should the Contractor terminate the Contract as a result of a notice of postponement, ACFD shall have the authority to award the Contract to the next lowest responsive responsible bidder.

23. The Bidder to whom Contract is awarded shall execute and submit the following documents by 5:00 pm of the SEVENTH (7TH) calendar day following the date of the

Notice of Award. Failure to properly and timely submit these documents entitles ACFD to reject the bid as non-responsive.

a. Document 00 52 13 Agreement: To be executed by successful Bidder. Submit four

(4) copies, each bearing an original signature.

b. Document 00 61 30 Escrow Bid Documentation: This must include all required documentation. See the document Escrow of Bid Documentation for more information.

c. Document 00 61 13.13 Performance Bond (100%): On the form provided n the

Contract Documents and fully executed as indicated on the form.

d. Document 00 61 13.16 Payment Bond (100%) (Contractor’s Labor and Material

Bond): On the form provided in the Contract Documents and fully executed as indicated in the form.

e. Insurance Certificates and Endorsements as required.

f. Document 00 45 26 Workers’ Compensation Certification.

g. Document 00 45 46.01 Prevailing Wage and Related Labor Requirements

Certification.

h. Document 00 45 46.04 Hazardous Materials Certification.

24. Any bid protest by any bidder regarding any other bid must be submitted in writing to

ACFD at bidprotests@alamedacountyfire.gov before 5:00 pm of the FIFTH (5TH) BUSINESS

DAY FOLLOWING THE DATE OF ISSUANCE OF THE Document 00 51 11 (Notice of Intent mailto:bidprotests@alamedacountyfire.gov to Award). A bid protest received after 5:00 pm is considered received as of the next business day.

a. The bid protest must contain a complete statement of the reason(s) and fact(s) for the protest.

b. The protest must refer to the specific portions of all documents that form the basis for the protest.

c. The protest must include the name, address, email address, fax number and telephone number of the person representing the protesting party.

d. ACFD will notify bidders of the protest as soon as possible.

e. Upon receipt of written protest, ACFD will review and evaluate the protest and issue a written decision. ACFD may, at its discretion, investigate the protest, obtain additional information, provide an opportunity to settle the protest by mutual agreement, and/or schedule a meeting(s) with the protesting bidder and others

(as appropriate) to discuss the protest. The decision on the bid protest will be issued at least ten (10) business days prior to the Board hearing or award date.

f. The decision will be communicated by e-mail, fax, or US Postal Service mail, and will inform the bidder whether the recommendation to the Board of Directors in the Notice of Intent to Award is going to change. A copy of the decision will be furnished to all bidders affected by the decision. As used in this paragraph, a bidder is affected by the decision on a bid protest if a decision in the protest could result in the bidder not being the apparent successful bidder on the bid.

g. The decision of the ACFD on the bid protest may be appealed to the Auditor-

Controller’s Office of Contract Compliance and Reporting (OCCR) located at 1221

Oak St., Room 249, Oakland, CA 94612, Fax: (510) 272-6502 unless the OCCR determines that it has a conflict of interest in which case an alternate will be identified to hear the appeal and all steps to be taken by OCCR will be performed by the alternate. The bidder whose bid is the subject of the protest, all bidders affected by ACFD’s decision on the protest, and the protestor have the right to appeal the ACFD’s decision. All appeals to the Auditor-Controller’s Office shall be in writing and submitted within five (5) business days following the issuance of the decision by ACFD. An appeal received after 5:00 pm is considered received as of the next business day. An appeal received after the FIFTH (5th) business day following the date of the issuance of the decision by ACFD shall not be considered by the OCCR.

h. The appeal shall specify the decision being appealed and all the facts and circumstances relied upon in support of the appeal.

i. In reviewing the appeals, the OCCR will not re-judge the proposal(s). The appeal to the OCCR shall be limited to review of the procurement process to determine if the contracting department materially erred in following the Bid process or, where appropriate, contracting policies or other laws and regulations.

j. The appeal to the OCCR also shall be limited to the grounds raised in the original protest and the decision by ACFD. As such, a Bidder is prohibited from stating new grounds for a Bid protest in its appeal. The OCCR shall only review the materials and conclusions reached by ACFD and will determine whether to uphold or overturn the protest decision.

k. The Auditor’s Office may overturn the results of a bid process for ethical violations by staff managing or participating in the competitive bid process, regardless of timing of the contents of the bid protest.

l. The decision of the OCCR is the final step of the appeal process. A copy of the decision of the OCCR will be furnished to the protestor, the Bidder whose bid is the subject of the protest, and all bidders affected by the decision.

m. ACFD will complete the bid protest/appeal procedures set forth in this paragraph before a recommendation to award the Contract is considered by the Board of

Directors.

n. The procedures and time limits set forth in this paragraph are mandatory and are each Bidder’s sole and exclusive remedy in the event of a Bid protest. A Bidder’s failure to timely complete both the Bid protest and appeal procedures shall be deemed a failure to exhaust administrative remedies. Failure to exhaust administrative remedies, or failure to comply otherwise with these procedures, shall constitute a waiver of any right to further pursue the Bid protest, including filing a Government Code Claim or legal proceedings.

25. A responsive bid is a solicited bid that has been determined to be in conformance with the conditions, completion, or delivery requirements, and specifications detailed in the solicitation for bid. Responsive bids are those submitted on time with complete information and required submittals and/or supporting documentation.

26. A responsible bidder by the California Public Contract Code §1103 as “a bidder who has demonstrated the attribute of trustworthiness, as well as quality, fitness, capacity, and experience to satisfactorily perform the public works contract.”

27. ACFD reserves the right to reject any or all bids, including without limitation the right to reject any or all nonconforming, non-responsive, unbalanced, or conditional bids, to re-bid, and to reject the bid of any bidder if ACFD believes that it would not be in the best interest of ACFD to make an award to that bidder, whether because the bid is not responsive or the bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by ACFD. ACFD also reserves the right to waive inconsequential deviations not involving price, time, or changes in the Work. For purposes of this paragraph, an “unbalanced bid” is one having nominal prices for some work items and/or enhanced prices for other work items.

28. Discrepancies between written words and figures, or words and numerals, will be resolved in favor of the figures or numerals.

29. Prior to the award of Contract, ACFD reserves the right to consider the responsibility of the Bidder. ACFD may conduct investigations as ACFD deems necessary to assist in the evaluation of any bid and to establish the responsibility, including, without limitation, qualifications and financial ability of Bidders, proposed subcontractors, suppliers, and other persons and organizations to perform and furnish the Work in accordance with the

Contract Documents to ACFD’s satisfaction within the prescribed time.

DOCUMENT 00 22 19

SUPPLEMENTAL INSTRUCTIONS TO BIDDERS

(ELATION APPLICATION)

SECTION I

GENERAL

1. PURPOSE

a. By submitting a bid, Bidders acknowledge and agree to all Document 00 22 19 provisions.

2. APPLICATION

a. The provisions outlined in Section 00 22 19 apply to this contract for the construction of the above referenced project.

3. HIRING OF LOCAL APPRENTICES, YOUTH, UNEMPLOYED AND UNDEREMPLOYED

RESIDENTS (FOR PROJECTS OVER $125k)

a. ACFD strongly encourages the hiring of local apprentices, youth, unemployed, and underemployed Alameda County residents to complete the work required to provide jobs required for this project. Those firms that can demonstrate the ability and willingness to provide jobs required to complete this project to local apprentices, youth, unemployed and underemployed County residents should include such evidence in their bid response.

4. NONDISCRIMINATION

a. The Contractor shall comply with the Americans with Disability Act and Title VII of the Civil Rights Act of 1964 and shall not, in regard to any position for which an employee or applicant for employment because of race, creed, color, religion, disability, sex (including pregnancy, sexual orientation, or gender identity), political affiliation, national origin, age (40 or older), and genetic information (including family medical history) or by any other non-merit factors be otherwise subjected to discrimination. The Contractor shall ensure applicants are employed and that employees are treated during employment without regard to their race, age, religion, Vietnam Era Veteran’s status, political affiliation, or any other non-merit factors. Such action shall include, but not be limited to, the following: employment, upgrading, demolition or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other terms of compensation; and selection for training, including apprenticeship. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause.

Contractor shall, in all solicitations or advertisements for employees placed on behalf of ACFD, state that all qualified applicants will receive consideration for employment without regard to race, creed, color, disability, sex (including pregnancy, sexual orientation, or gender identity), national origin, age, religion, Vietnam Era Veteran’s status, political affiliation, genetic information, or any other non-merit factors.

SECTION II

CONTRACT COMPLIANCE REQUIREMENTS

2. APPLICATION

a. The Following provisions shall apply to all contracts.

3. ALAMEDA COUNTY CONTRACT COMPLIANCE SYSTEM

a. Alameda Couty utilizes the Elation Systems contract compliance application as part of its commitment to assist contractors to comply with certain legal and contractual requirements. The Elation Systems, a secure web-based computer system, was implemented to monitor compliance and to track and report certified payroll and payment participation in ACFD contracts.

b. The prime contractor and all participating subcontractors awarded contracts as a result of the bid process for this project are required to use the Elation System to submit payroll and payment information including, but not limited to, weekly certified payrolls, monthly progress payment reports and other information related to project progress. Use of the Elation System, support and training are available at no charge to prime and subcontractors participating in ACFD contracts.

c. Upon contract award:

i. ACFD will provide contractors and subcontractors participating in any contract awarded as a result of this bid process, a code that will allow them to register and use the Elation System free of charge.

ii. Contractors should schedule a representative from their office/company, along with each of their subcontractors, to attend Elation Systems training.

1. Free Elation Systems training session videos are available online within the Elation Systems application.

d. It is the Contractor’s responsibility to ensure that they and their subcontractors are registered and trained as required to utilize Elation Systems.

i. For systems support visit Elation Systems online at http://www.elationsys.com/ or contact them at (925) 924-0340.

ii. If you have questions regarding the utilization of the Elation Systems, please contact the ACFD Project Manager or ACFD Contracts Administrator.

4. MEETINGS

a. After the award of the contract and prior to beginning work, ACFD may hold a pre-construction conference at which a representative of the Contractor and of each subcontractor must attend. As it becomes necessary during performance of the contract, ACFD may call meetings of the Contractor and pertinent subcontractors http://www.elationsys.com/ as needed for Project Stabilization Community Benefit Agreement (PSCBA) clarification and compliance, if applicable

5. INFORMATION AND RECORDS

a. For the purposes of determining compliance with the Elation application, the

Contractor shall provide ACFD with access to all records and documents that relate to Elation Payroll and Payment entries. To the extent permitted by applicable law, proprietary information will be safeguarded.

SECTION III

1. OUTREACH

a. To promote the contractors and subcontractors in their efforts to develop their bidding and/or contracting relationships ACFD will:

i. E-mail the Notice to Bidders to vendors in the County Vendor Database and other sources, advertise the project once a week for at least two consecutive weeks in a newspaper of general circulation in the county where the project is located, trade organizations and chambers of commerce, and plan rooms. Notice of this project will also be posted on the County Current Contracting Opportunities and Calendar of Events websites (see website URL addresses below).

ii. Incorporate a networking and informational component in the mandatory bid walk/site visit.

iii. E-mail the list of attendees from the mandatory bid walk to each attendee when issuing the first Addendum on the Current Contracting Opportunities website.

2. CONTRACTOR RESOURCES

The following sources may be contacted for assistance in soliciting sub-contractor participation:

Alameda County Contractor Technical Assistance Program (CTAP)

Jennifer Elmore, CTAP Program Manager (Merriwether and Williams Insurance Services)

(510) 740-6922 ext. 710 CTAP@imwis.com

Asian American Contractors Association

Juliana Choy Sommer and Strange Chiang, Executive Committee Members

(415) 928-5910 www.aaca-sf.com

Western Regional Minority Supplier Development Council (WRMSDC)-MBE Certifications only

(510) 686-2555 www.wrmsdc.org

Women’s Business Enterprise National Council (WBENC)-WBE certifications only www.wbenc.org mailto:CTAP@imwis.com http://www.aaca-sf.com/ http://www.wrmsdc.org/ http://www.wbenc.org/

California Public Utilities Commission (CPUC) The Supplier Clearinghouse

MBE and WBE vendors and certifications www.thesupplierclearinghouse.com

Alameda County Transportation Commission

LBE and SLBE vendors and certifications http://www.alamedactc.org/get-involved/contract-equity/

Visit the following County websites:

CERTIFIED SMALL LOCAL VENDORS SSQS - SLEB Supplier Query System

CURRENT CONTRACT OPPORTUNITIES Contracting Opportunities | General Services Agency - Alameda County

CALENDAR OF EVENTS Upcoming Events | General Services Agency - Alameda County

COUNTY OF ALAMEDA HOME PAGE Home | Alameda County Government

ALAMEDA COUNTY FIRE DEPARTMENT Alameda County Fire Department http://www.thesupplierclearinghouse.com/ http://www.alamedactc.org/get-involved/contract-equity/ https://sleb.acgov.org/#/find-a-supplier/ https://gsa.acgov.org/do-business-with-us/contracting-opportunities/ https://gsa.acgov.org/do-business-with-us/contracting-opportunities/ https://gsa.acgov.org/do-business-with-us/upcoming-contracting-events/ https://gsa.acgov.org/do-business-with-us/upcoming-contracting-events/ https://acgov.org/ https://alamedacountyfire.gov/

DOCUMENT 00 31 19

EXISITING CONDITIONS INFORMATION

1. Summary

This document describes existing conditions at or near the Project, and use of information available regarding existing conditions. This document is not part of the Contract

Documents. See General Conditions for definitions(s) of terms used herein,

2. Reports and Information on Existing Conditions

a. Documents providing a general description of the Site and conditions of the Work may have been collected by ACFD, its consultants, contractors and tenants. These documents may include previous contracts, contract specifications, tenant improvement contracts, as-built drawings, utility drawings, and information regarding underground facilities.

b. Information regarding existing conditions may be inspected at the Fire

Administration Office or the Construction Manager’s offices, if any, and copies may be obtained at cost of reproduction and handling upon Bidder’s agreement to pay for such copies. These reports, documents, and other information are not part of the Contract Documents.

c. Information regarding existing conditions may also be included in the Project

Manual but shall not be considered part of the Contract Documents.

d. The reports and other data or information regarding existing conditions and underground facilities at or contiguous to the Project are provided as non-contract documents for Bidder’s convenience:

i. Not applicable.

3. Use of Information

a. Information regarding existing conditions was obtained only for use of ACFD and its consultants, contractors, and tenants for planning and design and is not part of the Contract Documents.

b. ACFD does not warrant and makes no representations regarding the accuracy or thoroughness of any information regarding existing conditions. Bidder represents and agrees that in submitting a bid it is not relying on any information regarding existing conditions supplied by ACFD.

c. Under no circumstances shall ACFD be deemed to warrant or represent existing above-ground conditions, as-built conditions, or other actual conditions, verifiable by independent investigation.

d. Any information shown or indicated in the reports and other data supplied herein with respect to existing underground facilities at or contiguous to the Project may be based upon information and data furnished to ACFD by the ACFD’s employees and/or consultants or builders of such underground facilities or others. ACFD does not assume responsibility for the completeness of this information, and Bidder is solely responsible for any interpretation of conclusion drawn from this information.

e. ACFD shall be responsible only for the general accuracy in information regarding underground facilities, and only for those underground facilities that are owned by

ACFD, and only where Bidder has conducted the independent investigation required of it pursuant to the Instructions to Bidders, and discrepancies are not apparent.

4. Investigations/Site Examinations

a. Before submitting a Bid, each Bidder is responsible for conducting or obtaining any additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and underground facilities) at or contiguous to the Site or otherwise, that may affect cost, progress, performance, or furnishing of Work or that relate to any aspect of the means, methods, techniques, sequences, or procedures of construction to be employed by Bidder and safety precautions and programs incident thereto on that Bidder deems necessary to determine its Bid for performing and furnishing the Work in accordance with the time, price, and other terms and conditions of the Contract

Documents.

b. On request, ACFD will provide each Bidder access to the Site to conduct such examinations, and investigations as each Bidder deems necessary for submission of a Bid. Bidders must fill all holes and clean up and restore the Site to its former condition upon completion of its explorations, investigations, tests, and studies.

Such investigations and Site examinations may be performed during any and all

Site Visits indicated in the Notice to Bidders and only under the provisions of the

Contract Documents, including, but not limited to, proof of insurance and obligation to indemnify against claims arising from such work, and ACFD’s prior approval.

DOCUMENT 00 41 13

BID FORM – STIPULATED SUM (SINGLE-PRIME CONTRACT)

To: The Alameda County Fire Department

From:

(Proper Name of Bidder)

The undersigned declares that the Contract Documents including, without limitation, the Notice to Bidders Document 00 11 16 and the Instructions to Bidders Document 00 21 13 have been read and agrees and proposes to furnish all necessary labor, materials, and equipment to perform and furnish all work in accordance with the terms and conditions of the Contract Documents, including, without limitation, the Drawings and Specifications of Bid No. ACFD 26-03

PROJECT Demolition of Connex Box Structures and Removal of Debris

(“Project” or “Contract”) and will accept in full payment for that Work the following total lump sum amount, all taxes included:

__________________________________________________dollars

TOTAL BASE BID

1. Unit Prices: The Bidder’s Base Bid includes the following unit prices, which the Bidder must provide and ACFD may, at its discretion, utilize in valuing additive and/or deductive change orders:

a. Hourly rates for personnel by role

b. Equipment rental rates

c. Tipping fees

2. Other (itemize)The undersigned has reviewed the Work outlined in the Contract

Documents and fully understands the scope of Work required in this Bid, understands the construction and project management functions(s) as described in the Contract

Documents, and that the Bidder who is awarded a contract shall be a prime contractor, not a subcontractor, to ACFD, and agrees that its Bid, if accepted by ACFD, will be the basis for the Bidder to enter into a contract with ACFD in accordance with the intent of the Contract Documents.

3. The undersigned has notified ACFD in writing of any discrepancies or omissions or of any doubt, questions, or ambiguities about the meaning of any of the Contract Documents and has contacted the Construction manager before bid date to verify the issuance of any clarifying Addenda.

4. The…