Bid Notice-District 2 DMS Retrofit.pdf

PDF 12 MB Posted

Attached to
District 2 Dynamic Message Sign (DMS) Retrofit
Solicitation number
ITS-NH-D2(116)
Issued by
Sarpy County, North Platte City, Nebraska

About this file

This is a bid notice and proposal form issued by the Nebraska Department of Transportation (NDOT) for the District 2 Dynamic Message Sign (DMS) Retrofit project. The project involves retrofitting and modernizing existing Dynamic Message Signs located in Sarpy and Douglas Counties (Omaha metropolitan area) to upgrade Intelligent Transportation Systems (ITS) infrastructure. The work includes extensive coordination with major local telecommunication and energy providers including AT&T Communications, Cox Communications, Lumen, Metropolitan Utilities District, Omaha Public Power District, and others. The project is identified as Control Number 22921, Project Number ITS-NH-D2(116), with a letting date of August 27, 2026, at 1:30 PM and a tentative start date of January 4, 2027. The contract duration is 15 working days. Peak hours for construction are defined as 6:00 AM to 9:00 PM, Monday through Sunday, including holidays, with temporary lane closures restricted to non-peak hours and limited to one mile in length. The contractor is required to coordinate signing and construction activities with two concurrent projects: ITS-NH-D2(117) CN 22922 (District 2 DMS Replacement in Omaha) and related I-680 and N-50 projects.

Contractors must be prequalified under Class 8B (Electrical) and Class 10 (General) to bid on this project. All right-of-way has been acquired and is ready for contractor use. No utility conflicts are anticipated as work will occur within the footprint of existing DMS structures, though the contractor must coordinate with Nebraska One Call (811) for utility locating and flagging. The project is subject to federal requirements including Buy America provisions, Davis-Bacon wage determinations, and FHWA Form 1273 contract provisions. Environmental commitments include conservation conditions for threatened and endangered species, wetland protection, bald eagle nesting surveys if construction begins between February 1 and April 15, and restrictions on activities within Section 4(f) properties (Northwest Park). The contractor must maintain liability insurance with minimum limits of $1,000,000 per occurrence for general liability, $1,000,000 CSL for automobile liability, and statutory workers' compensation coverage. Additional requirements include federal immigration verification through E-Verify, submission of certified payrolls within seven days, and compliance with all applicable federal, state, and local environmental and safety regulations.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROPOSAL FORM

NEBRASKA DEPARTMENT OF TRANSPORTATION

LETTING DATE: August 27, 2026

LETTING TIME: 1:30 PM

CALL ORDER: 200

CONTROL NO. SEQ. NO.: 22921 000

TENTATIVE START DATE: 01/04/2027

LOCATION: DISTRICT 2 DMS RETROFIT

IN COUNTIES: SARPY, DOUGLAS

CONTRACT ID: 22921

PROJECT NO.: ITS-NH-D2(116)

CONTRACT TIME: 15 Working Days

DBE GOAL: N/A

PREQUALIFICATION CLASS: 8B,10 -

ELECTRICAL, GENERAL (ALL CLASSES)

COMBINED BID REQUIREMENTS: N/A

GROUP 8B

GROUP 10

ELECTRICAL

GENERAL ITEMS

-1-

P R

O F

E S

IO

NAL CIVIL

E

N G I N

E E

R

S T

A T

E

OF NEBRA

S

K A

S

E-9403

McCULLOUGH

STEVEN

Jul 14, 2026

District 2 DMS Retrofit Project No. D2(116)

Contract ID 22921

- 2 -

NOTICE TO ALL BIDDERS

To report bid rigging activities, call: 1-800-424-9071

The U.S. Department of Transportation (DOT) operates the above toll-free “hotline” Monday through Friday, 8:00 a.m. to 5:00 p.m. eastern time. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should use the “hotline” to report such activities.

The “hotline” is part of the DOT’s continuing effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT Inspector General. All information will be treated confidentially, and caller anonymity will be respected.

LETTING QUESTIONS

Prior to the letting, any questions pertaining to the Special Provisions or the Plans for this project should be submitted to NDOT in a written format through the Bid Express (BidX) website at https://www.bidx.com/ne/lettings. Likewise, NDOT will post answers exclusively to the BidX website. All official answers will be identified as “Authorized by NDOT.” Questions will not be answered verbally.

The NDOT answers posted in BidX are not a part of the contract documents, are provided for information only, and are subject to change. Only the contract documents, including any addenda thereto, should be relied upon by a potential bidder when submitting a bid.

- 3 -

TABLE OF CONTENTS

DIVISION 100 – GENERAL REQUIREMENTS

SPECIAL PROSECUTION AND PROGRESS

STATUS OF UTILITIES

STATUS OF RIGHT-OF-WAY

ENVIRONMENTAL COMMITMENTS

DIVISION 100 – GENERAL REQUIREMENTS AND COVENANTS

DIVISION 200 – EARTHWORK

DIVISION 400 – LIGHTING, SIGNS, AND TRAFFIC CONTROL

FHWA-1273 REQUIRED CONTRACT PROVISIONS FEDERAL-AID

CONSTRUCTION CONTRACTS

EXECUTIVE ORDER 11246

DAVIS-BACON WAGE DETERMINATION

TRAINING SPECIAL PROVISIONS

- 4 -

SPECIAL PROVISIONS

FOR

FEDERAL AID

PROJECT NO. D2(116)

GENERAL CONDITIONS

(1-1-0826)

Bids for the work contemplated in this proposal form will be received at the office of the Nebraska Department of Transportation in Room 109 of the Central Office Building at 1500 Nebraska Parkway at Lincoln, Nebraska, until the date and time shown on page 1 of the Proposal.

a. Bids submitted by mail should be addressed to the Nebraska Department of Transportation, c/o Contract Lettings Section, P.O. Box 94759, Lincoln, NE 68509-4759.

b. Bids submitted electronically over the internet, shall be submitted using www.bidx.com.

Contractors contemplating submitting a bid for this contract must submit a request to bid via the Department’s ‘Request for Bidding Document’ website at: https://dot.nebraska.gov/business-center/bid-request-planholder-registration/. An Authorization to Bid will only be issued to, and bids accepted from, Contractors who are prequalified for the Prequalification Class indicated on page 1 of the Proposal Form.

Bids will be opened, and the bid totals will be read via the Department’s designated online meeting platform immediately following the letting date and time indicated on page 1 of the Proposal. Access information for the online bid opening will be available on the BidX Letting webpage a minimum of 2 days prior to the opening, and can be found by selecting the applicable letting from: https://www.bidx.com/ne/lettings.

The 2017 Edition of the Standard Specifications for Highway Construction, including all amendments and additions thereto effective at the date of the contract, are made a part of these Special Provisions, through reference.

The Required Contract Provisions, Form FHWA 1273, (Rev. 10-23), and the Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity and Standard Federal Equal Employment Opportunity Construction Contract Specifications dated November 3, 1980, are attached to and are a part of this proposal form.

The General Wage Decision issued under the Davis-Bacon and Related Acts is attached to and is a part of this proposal form.

SPECIAL PROSECUTION AND PROGRESS

(General Requirements)

1. Peak hours for this project shall be from 6:00 am to 9:00 pm, Monday through Sunday, including holidays. All other hours are non-peak hours, and all temporary lane closures shall only be in place during non-peak hours.

- 5 -

During non-peak hours:

A. One lane may be closed beginning at 9:00 pm.

B. Two lanes may be closed beginning at 10:00 pm.

C. Peak hours may be modified at the discretion of the Engineer.

2. The Contractor may utilize one temporary lane closure in each direction. Temporary lane closures will be limited to the length required for that day's work, but no greater than 1 mile. The maximum lane closure length may vary dependent upon traffic operations, as directed by the Engineer. The Contractor shall schedule the placement of traffic control devices to accommodate each day’s closure. Accordingly, the Department will only pay for those traffic control devices considered reasonably necessary to protect the actual work area. When a lane closure is no longer required or is not necessary in the opinion of the Engineer, the Contractor shall have one hour, following notification by the Engineer, to open the closed lane(s) & shoulder(s) to traffic. After this one-hour period, the Contractor will incur an assessment.

3. The Contractor shall have a work crew at any closure site at all times during a lane closure, unless otherwise directed by the Engineer.

4. A lane closure will not be permitted during inclement weather conditions or during periods of time that atmospheric conditions may constitute a hazard to the traveling public, as determined by the Engineer.

5. Lane closures for emergency service situations will not incur an assessment for either peak or non-peak hours.

6. Temporary Shoulder Closures can be in place during peak and non-peak hours.

(Assessments)

A. General

The assessments described in this provision shall be in addition to other assessments described elsewhere in this proposal or in the NDOT Standard Specifications for Highway Construction.

B. Temporary Lane Closure Assessment

When a temporary lane(s) closure is no longer required or is not necessary in the opinion of the Engineer, the Contractor shall have one hour, following notification by the Engineer, to open the closed lane(s) to traffic. After this one-hour period, the Contractor will be assessed $500 per hour per lane per direction until the closed lane(s) is opened.

Any portion of an hour shall be considered as a full hour.

- 6 -

C. Peak Hour Temporary Lane Closure Assessment

The Contractor’s failure to have a closed lane(s) open to traffic during peak hours shall result in the assessment of a $500 per lane per hour per direction. This assessment shall begin at the beginning of the designated peak hour period and shall continue per hour until, and including, the hour the closed lane(s) is open to traffic. Any portion of an hour shall be considered as a full hour.

D. Ramp Closure Assessment

The Contractor will be allowed to close on/off-ramps at various locations as shown in the plans to perform construction during non-peak hours, unless otherwise directed by the Engineer. The Contractor’s failure to have all on/off-ramps open to traffic during peak hours shall result in the assessment of $500 per hour per lane. This assessment shall begin at the beginning of the designated peak hour period and shall continue per hour until, and including, the hour the closed lane is open to traffic. Any portion of an hour shall be considered as a full hour.

(Coordination With Others)

1. The Contractor for this project shall be required to coordinate signing and construction activities with the Contractor for Project ITS-NH-D2(117) CN 22922, District 2 DMS Replacement, Omaha. This project is scheduled to be let to contract in the August 27, 2026 letting. This project consists of replacing Dynamic Message Signs in Omaha.

2. The Contractor for this project shall be required to coordinate signing and construction activities with the Contractor for Project NH-MTIS-680-9(13), CN 22852, Pacific-Dodge, Omaha. This project was let to contract in the January 21, 2026 letting. This project consists of an additional lane on I-680, culvert work, lighting, and guardrail.

3. The Contractor for this project shall be required to coordinate signing and construction activities with the Contractor for Project NH-80-9(116), CN 22821, N-50 – 50th St, Omaha. This project was let to contract in the December 17, 2025 letting. This project consists of grinding, concrete repairs, and sealing.

STATUS OF UTILITIES

Project No.: ITS-NH-D2(116) Control No.: 22921 Location: District 2 DMS Retrofit

The following information is current as of June 15, 2026.

All utility work has been completed or the necessary arrangements have been made for the required utility work to be undertaken and completed as required for proper coordination with the physical construction schedules.

- 7 -

If any utility facilities are encountered and deemed to be in conflict during construction, the relocation work will be concurrent with construction.

The Contractor is directed to review Subsection 105.06 of the NDOT Standard Specifications for Highway Construction, 2017 Edition for additional information regarding cooperation with utilities.

The Contractor should request a utility status update at the project pre-construction conference, and/or prior to start of work. Any utility adjustments or interruption of service for the convenience of the Contractor shall be the sole responsibility of the Contractor.

To arrange for utilities to locate and flag their underground facilities, contact Nebraska One Call at 1-800-331-5666 or dial 811.

After review of the project, the following utility companies have facilities within the project limits:

AT&T Communications Are conflicts with this facility anticipated? NO Description of existing location(s) and facility type:

AT&T Communications facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Kevin Wingard, 508-931-7688, kwingard@sdt-1.com Rodney Haskins, 402-630-6529, rhaskins@sdt-1.com

City of Lincoln Are conflicts with this facility anticipated? NO Description of existing location(s) and facility type:

City of Lincoln facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Brion Perry, 402-480-8559, BPerry@lincoln.ne.gov Soulinnee Phan, 402-441-7411, sphan@lincoln.ne.gov

City of Omaha

Description of existing location(s) and facility type:

City of Omaha facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Mark Poland, 402-444-6539, mark.poland@cityofomaha.org Elizabeth Butler, 402-444-5550, cityclerk@cityofomaha.org

- 8 -

Cox Communications Are conflicts with this facility anticipated? NO Description of existing location(s) and facility type:

Cox Communications facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Pete Wilson, 402-934-0490; 402-510-0665 (c), Pete.Wilson@cox.com Brian Renz, 402-306-5842, brian.renz@cox.com

Great Plains Communications

Description of existing location(s) and facility type:

Great Plains Communications facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Justin Suhr, c 402-237-7039, jsuhr@gpcom.com Ben Little, 402-237-7082, blittle@gpcom.com

Lumen(CenturyLink)

Description of existing location(s) and facility type:

Lumen facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Eric Wallace, (402) 306-1115, Eric.Wallace@lumen.com Kim Ruettgers, kim.ruettgers@lumen.com

Metropolitan Utilities District

Description of existing location(s) and facility type:

Metropolitan Utilities District facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Jarod Ponticello, D:402-504-7769 C:402-639-4806, Jarod_Ponticello@mudnebr.com Dennis Rinkol, 402-504-7906, dennis_rinkol@mudnebr.com

Omaha Public Power District

Description of existing location(s) and facility type:

Omaha Public Power District facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

- 9 -

Contact Information:

Michael Willey, 402-440-3504, mkwilley@oppd.com Ken Porter, 402-917-7792, kdporter@oppd.com

Segra (Unite Private Networks)

Description of existing location(s) and facility type:

Segra facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Jeremy Beck , 402-278-4891, Jeremy.Beck@segrafiber.com Ryan Tanner, 402-860-0869, ryan.tanner@segrafiber.com

Verizon/MCI Telecommunications

Description of existing location(s) and facility type:

Verizon facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Jason Dimmock, 402-213-5879, jason.dimmock@verizon.com

Windstream Communications

Description of existing location(s) and facility type:

Windstream Communications facilities exist near the project areas.

Description of conflict(s):

All work will occur in the footprint of existing DMS structures. No impacts to utilities are anticipated.

Contact Information:

Todd J. Williams, 531-510-8528, todd.j.williams@windstream.com Mark Hussman, 402-677-5874 C 402-827-6355 O, Mark.Hussman@Windstream.com Rex Roberts, 402-661-9362, rex.roberts@windstream.com

NDOT Owned Utilities There are existing NDOT Owned Utilities within the project limits, but no impacts are anticipated. DMS Structures to be upgraded per construction plans.

To arrange for location and flagging State of Nebraska underground facilities, see the “STATE OWNED UTILITIES LOCATE NOTIFICATION” Special Provision included in this contract.

NDOT Owned Utilities that are found to be in conflict during construction and are not previously required to be relocated as part of the contract, will be relocated by the contractor as extra work as detailed in Section 109.05 of the NDOT Standard Specifications for Highway Construction, 2017 Edition.

- 10 -

STATUS OF RIGHT OF WAY

August 12, 2025

The right of way for Project Number D2(116), Control Number 22921 has been acquired and physical possession is held by the State of Nebraska and ready for the contractor’s use, except tracts listed below.

Unacquired Right-of-Way Tracts as follows:

Tract Number Status of Tract Date of Hearing

None None None

Right-of-Way Tracts with Pay Items:

Tract Number Pay Item

None None

• No encroachments on the old right of way

• Acquisition of right of way is not required for this project

NOTICE TO BIDDERS

(Environmental Commitments)

1. Below are the Conservation Conditions that will be required for this project. All conditions and regulations of any permit obtained for this project shall be followed by the contractor.

CONSERVATION MEASURE FOR ENVIRONMENTALLY SENSITIVE AREAS

1. The Contractor shall not stage, store, waste or stockpile materials and equipment in undisturbed locations, or in known/potential wetlands and/or known/potential streams that exhibit a clear “bed and bank” channel. Potential wetland areas consist of any area that is known to pond water, swampy areas or areas supporting known wetland vegetation or areas where there is a distinct difference in vegetation (at lower elevations) from the surrounding upland areas.

a. Attachment 1 includes the NDOT Wetland Fact Sheet and map(s) of potential wetlands and/or other potential regulated waters features. These features were identified from a desktop review of published resources. The above condition pertains to the areas as listed on Attachment 1. If access to any of these areas is required to complete the project construction, the Engineer shall coordinate with the Technical Resources Unit to determine need for field verification and/or permitting requirements prior to disturbance of the area.

- 11 -

GENERAL THREATENED AND ENDANGERED SPECIES CONSERVATION CONDITIONS

CONSERVATION CONDITIONS

1. The Contractor shall fully implement conservation conditions within the project limits as shown on the plans.

EARLY CONSTRUCTION STARTS

1. Contractor requests for early construction starts shall be coordinated by the Engineer with the NDOT Environmental Section for approval to ensure avoidance of listed species sensitive lifecycle timeframes. Early start requests may require consultation with the USFWS and NGPC. Agency coordination time will vary depending on species and project location.

T&E SPECIES

1. If federal or state listed species are observed during construction, Contractor shall contact the Engineer who will contact the NDOT Environmental Section to determine if additional species conservation conditions would be required prior to continuing project construction activities. Contact NDOT Environmental for a reference of federal and state listed species. Coordination with the USFWS and NGPC may be required depending on the species identified and construction activities.

REFUELING

1. The contractor shall conduct refueling outside of those sensitive areas identified on the plans, in the contract, and/or marked in the field.

RESTRICTED ACTIVITIES

1. The following project activities shall, to the extent possible, be restricted to between the beginning and ending points (stationing, reference posts, mile markers, and/or section-township-range references) of the project, within the right-of-way designated on the project plans: borrow sites, burn sites, construction debris waste disposal areas, concrete and asphalt plants, haul roads, stockpiling areas, staging areas, and material storage sites.

2. For activities outside the project limits, the Contractor shall refer to the Nebraska Game and

Parks Commission website to determine which species ranges occur within the off-site area.

The Contractor shall plan accordingly for any species surveys that may be required to approve the use of a borrow site, or other off-site activities. The Contractor shall review the T&E Matrix agreement (on NDOT’s website), where species survey protocols can be found, to estimate the level of effort and timing requirements for surveys.

3. Any project related activities that occur outside of the project limits must be environmentally cleared/permitted with the Nebraska Game and Parks Commission as well as any other appropriate agencies by the contractor and those clearances/permits submitted to the Engineer prior to the start of the above listed project activities. The Contractor shall submit information such as an aerial photo showing the proposed activity site, a soil survey map with the location of the site, a plan-sheet or drawing showing the location and dimensions of the activity site, a minimum of 4 different ground photos showing the existing conditions at

- 12 -the proposed activity site, depth to ground water and depth of pit, and the “Platte River depletion status” of the site. The Contractor shall receive notice of acceptance from NDOT environmental, prior to starting the above listed project activities. These project activities cannot adversely affect state and/or federally listed species or designated critical habitat.

WASTE/DEBRIS

1. The Contractor shall dispose of construction waste/debris in areas or a manner that will not adversely affect state and/or federally listed species and/or designated critical habitat.

POST CONSTRUCTION EROSION CONTROL

1. Erosion control activities carried out by NDOT Maintenance or others after construction is complete, but prior to project close-out, shall adhere to any standard conservation conditions for species designated for the project limits during construction.

PLATTE RIVER DEPLETIONS

1. To the maximum extent practical, efforts will be made to design the project and select borrow sites to prevent depletions to the Platte River. If there is any potential to create a depletion, NDOT (during design) and the Contractor (for borrow sites) shall follow the current Platte River depletion protocols for coordination, minimization, and mitigation. In general, the following are considered de minimis depletions but may still require agency coordination; a project which:

a. Creates an annual depletion less than 0.1 acre feet,

b. Creates a detention basin that detains water for less than 72 hours,

c. Diverted water that will be returned to its natural basin within 30 days,

d. Creates a one-time depletion of less than 10 acre feet.

NORTHERN LONG-EARED BAT

1. The Contractor shall ensure all operators employees, and contractors working in areas of

Indiana bat, NLEB, or TCB suitable habitat are aware of all Transportation Agency environmental commitments, including all applicable AMMs.

BALD AND GOLDEN EAGLE PROTECTION ACT

1. Suitable Bald Eagle nesting and/or roosting habitat exists within 0.5 miles of the

Environmental Study Area. If construction will begin between February 1 and April 15, a nest survey shall be completed at least 1 but not more than 14 days prior to construction.

If construction will begin between April 15 and October 1, a nest survey completed in March is sufficient, as nests will likely already be constructed if nesting will occur that year.

However, a nest survey may be completed anytime during this timeframe, as long as it is completed prior to construction. If Bald Eagles are nesting in the area, consultation with NGPC and USFWS shall occur prior to beginning construction activities. Eagle roosting surveys shall be conducted if construction occurs between October 1 and January 31.

- 13 -

SECTION 4(f)

1. The contractor shall not complete work, stage, stockpile, or store materials within the boundaries of the following Section 4(f) property as identified in attachment 2:

a. Northwest Park

2. If it is determined that temporary or permanent right-of-way is required from, or access is restricted to, a Section 4(f) property, coordination shall occur with NDOT Environmental.

TRAFFIC DISRUPTION

1. This project shall be constructed under traffic with lane closures controlled by approved temporary traffic control. The project shall not result in traffic disruptions requiring detours, temporary roads, or ramp closures that are greater than 30 working days.

ACCESS DISRUPTION

1. The Contractor shall maintain access to adjacent properties at all times during construction. Access may be disrupted temporarily at times due to construction activities but shall not be closed.

WELLHEAD PROTECTION AREA

1. A portion of the project has been identified as being located within the Douglas County

SID #258 - Carat Homes Wellhead Protection Area. NDOT’s Standard Specifications – Section 107 address the Contractor’s responsibility to keep fully informed of, observe, and comply with all federal, state, and local laws and ordinances that affect the conduct of the work.

UNEXPECTED WASTE

1. If contaminated soils/groundwater or unexpected wastes are discovered, the Contractor shall stop all work within the immediate area. The Contractor shall secure the area of the discovery and notify the Engineer. The Contractor shall not reenter the discovery area until notified by the Engineer. At the time of discovery, the Engineer and Contractor shall utilize the NDOT Unexpected Waste Action Plan (UWAP) to coordinate appropriate actions. The Contractor is required by NDOT's Standard Specification Section 107 (legal relations and responsibilities to the public) to handle and dispose of regulated material in accordance with applicable laws.

BORROW SITE

1. Any material needed shall be provided by the Contractor. The Contractor shall try to obtain borrow from an upland site to prevent depletion issues. If the borrow site is within a depletion area of concern, the Contractor shall coordinate with the appropriate agencies and NDOT to offset or minimize impacts. The Contractor shall obtain all environmental clearances and permits required for the borrow site prior to obtaining borrow material for the project.

- 14 -

2. The Contractor shall have a staging area for the project where material and equipment for the project is stored (e.g., re-steel, forms, etc.). The Contractor shall be required to dispose of material removed as part of the project described above and miscellaneous obstructions encountered and removed along the project. The disposal shall be the responsibility of the Contractor. A waste site may be needed. The Contractor shall be responsible to obtain all permits and clearances and all conditions of those permits shall be followed.

CONSTRUCTION STORMWATER

1. This project does not require a Construction Stormwater Permit or a Storm Water Pollution

Prevention Plan (SWPPP). Temporary water pollution prevention practices (including sediment and erosion control measures) are still required by Nebraska State Title 119. The Contractor shall exercise every reasonable precaution throughout the life of the contract to prevent sedimentation within rivers, streams, impoundments (lakes, reservoirs, etc.), the project site, and adjacent property.

- 15 -

STATUS OF ENVIRONMENTAL COMMITMENTS

- 16 -

ENVIRONMENTAL COMMITMENTS

Control No.: 22921 Project No.: ITS-NH-D2(116)

Project Name: District 2 DMS Retrofit

Below are the Conservation Conditions that will be required for this project. All conditions and regulations of any permit obtained for this project will be followed by the contractor.

(Responsible Party for the measure is found in parentheses)

Conservation Measure for Environmentally Sensitive Areas

The Contractor shall not stage, store, waste or stockpile materials and equipment in undisturbed locations, or in known/potential wetlands and/or known/potential streams that exhibit a clear “bed and bank” channel. Potential wetland areas consist of any area that is known to pond water, swampy areas or areas supporting known wetland vegetation or areas where there is a distinct difference in vegetation (at lower elevations) from the surrounding upland areas.

(Contractor, NDOT District)

• Attachment 1 includes the NDOT Wetland Fact Sheet and map(s) of potential wetlands and/or other potential regulated waters features. These features were identified from a desktop review of published resources. The above condition pertains to the areas as listed on Attachment 1. If access to any of these areas is required to complete the project construction, the NDOT construction project manager shall coordinate with the Technical Resources Unit to determine need for field verification and/or permitting requirements prior to disturbance of the area. (Contractor, District Construction)

Contact Person: Amy Utt, Ecologist, (402) 479-3879

General Threatened and Endangered Species Conservation Conditions

A-1 Changes in Project Scope. If there is a change in the project scope, the project limits, or environmental commitments, the Highway Project Manager shall coordinate with the NDOT Environmental Section to evaluate potential impacts prior to implementation.

Environmental commitments are not subject to change without prior written approval from the NDOT Environmental Section. (District Construction)

A-2 Conservation Conditions. Conservation conditions are to be fully implemented within the project limits as shown on the plans. (District Construction, Contractor)

A-3 Early Construction Starts. Contractor requests for early construction starts must be coordinated by the Project Construction Engineer with the NDOT Environmental Section for approval to ensure avoidance of listed species sensitive lifecycle timeframes. Early start requests may require consultation with the USFWS and NGPC. Agency coordination time will vary depending on species and project location. (District Construction, Contractor)

A-4 T&E Species. If federal or state listed species are observed during construction, the

Highway Project Manager will contact NDOT Environmental Section to determine if additional species conservation conditions would be required prior to continuing project

- 17 -construction activities. Contact NDOT Environmental for a reference of federal and state listed species. Coordination with the USFWS and NGPC may be required depending on the species identified and construction activities. (NDOT Environmental, District Construction, Contractor)

A-5 Refueling. Refueling will be conducted outside of those sensitive areas identified on the plans, in the contract, and/or marked in the field. (Contractor)

A-6 Restricted Activities. The following project activities shall, to the extent possible, be restricted to between the beginning and ending points (stationing, reference posts, mile markers, and/or section-township-range references) of the project, within the right-of-way designated on the project plans: borrow sites, burn sites, construction debris waste disposal areas, concrete and asphalt plants, haul roads, stockpiling areas, staging areas, and material storage sites.

For activities outside the project limits, the contractor should refer to the Nebraska Game and Parks Commission website to determine which species ranges occur within the off-site area. The contractor should plan accordingly for any species surveys that may be required to approve the use of a borrow site, or other off-site activities. The contractor should review the T&E Matrix agreement (on NDOT’s website), where species survey protocols can be found, to estimate the level of effort and timing requirements for surveys.

Any project related activities that occur outside of the project limits must be environmentally cleared/permitted with the Nebraska Game and Parks Commission as well as any other appropriate agencies by the contractor and those clearances/permits submitted to the District Construction Project Manager prior to the start of the above listed project activities. The contractor shall submit information such as an aerial photo showing the proposed activity site, a soil survey map with the location of the site, a plan-sheet or drawing showing the location and dimensions of the activity site, a minimum of 4 different ground photos showing the existing conditions at the proposed activity site, depth to ground water and depth of pit, and the “Platte River depletion status” of the site.

The contractor must receive notice of acceptance from NDOT environmental, prior to starting the above-listed project activities. These project activities cannot adversely affect state and/or federally listed species or designated critical habitat. (NDOT Environmental, District Construction, Contractor)

A-7 Waste/Debris. Construction waste/debris will be disposed of in areas or a manner that will not adversely affect state and/or federally listed species and/or designated critical habitat. (Contractor)

A-8 Post Construction Erosion Control. Erosion control activities carried out by NDOT

Maintenance or others after construction is complete, but prior to project close-out, shall adhere to any standard conservation conditions for species designated for the project limits during construction. (NDOT Maintenance, District Construction, Contractor)

S-2 Platte River Depletions. To the maximum extent practical, efforts will be made to design the project and select borrow sites to prevent depletions to the Platte River. If there is any potential to create a depletion, NDOT (during design) and the Contractor (for borrow sites) shall follow the current Platte River depletion protocols for coordination, minimization, and mitigation. In general, the following are considered de minimis

- 18 -depletions, but may still require agency coordination; a project which: a) creates an annual depletion less than 0.1 acre feet, b) creates a detention basin that detains water for less than 72 hours, c) diverted water that will be returned to its natural basin within 30 days, or d) creates a one-time depletion of less than 10 acre feet. (NDOT Roadway Design, Contractor)

S-3 Revegetation. All permanent seeding and plantings (excluding managed landscaped areas) shall use species and composition native to the project vicinity as shown in the Plan for the Roadside Environment. However, within the first 16 feet of the road shoulder or within high erosion prone locations, tall fescue or perennial ryegrass may be used at minimal rates to provide quick groundcover to prevent erosion, unless state or federally listed threatened or endangered plants were identified in the project area during surveys. If listed plants were identified, any seed mix requirements identified during resource agency consultations shall be used for the project. (NDOT Environmental)

S-4 Sensitive Areas. Environmentally Sensitive Areas will be marked on the plans, in the field, or in the contract by NDOT Environmental for avoidance. (NDOT Environmental, NDOT Roadway Design, District Construction)

S-5 Species Surveys. If species surveys are required during the construction phase of the project (including pre-construction surveys), results will be sent by NDOT Environmental Section to the USFWS, NGPC, and if applicable the USACE. (NDOT Environmental, District Construction)

Northern Long-eared Bat:

GAMM1 - Ensure all operators, employees, and contractors working in areas of

Indiana bat, NLEB, or TCB suitable habitat are aware of all Transportation

Agency environmental commitments, including all applicable AMMs. (NDOT

Environmental, District, Contractor)

LAMM1 - Direct temporary lighting away from suitable habitat during the active season (April 1st - November 15th). (District, Contractor)

Bald and Golden Eagle Protection Act

• Suitable Bald Eagle nesting and/or roosting habitat exists within 0.5 miles of the

Environmental Study Area. If construction will begin between February 1 and April

15, a nest survey must be completed at least 1 but not more than 14 days prior to construction. If construction will begin between April 15 and October 1, a nest survey completed in March is sufficient, as nests will likely already be constructed if nesting will occur that year. However, a nest survey may be completed anytime during this timeframe, as long as it is completed prior to construction. If bald eagles are nesting in the area, consultation with NGPC and USFWS will be required prior to beginning construction activities. Eagle roosting surveys will be conducted if construction occurs between October 1 and January 31. (NDOT

Environmental, Contractor)

- 19 -

NDOT Construction Project Managers should contact NDOT Environmental at 402-479-3546 or erika.hinz@nebraska.gov at least 30 days prior to construction start to schedule required surveys.

Contact Person: Erika Hinz, Ecologist, (402) 479-3546

Section 4(f)

The contractor shall not complete work, stage, stockpile or store materials within the boundaries of the following Section 4(f) properties, as identified in Attachment 2:

Northwest Park. If it is determined that temporary or permanent right-of-way is required from, or access is restricted to, a Section 4(f) property, coordination shall occur with

NDOT Environmental. (Contractor)

Utilities

Utility relocation or replacement is not anticipated for the project. If utility relocation or replacement is required in a later phase of the project, a re-evaluation shall be required if:

(1) federal funds will be used for the utility work; or (2) the project construction contractor will be responsible for the work. If this utility work is identified during final design, the project sponsor shall initiate the re-evaluation prior to project letting. If the work is identified during construction, the project sponsor shall initiate the re-evaluation prior to commencing utility work. (NDOT Environmental, NDOT District)

If either one of the above two conditions does not apply, later relocation or replacement of utilities shall be coordinated through NDOT and the Contractor per NDOTs Standard

Specifications for Highway Construction, Subsection 105.06. Any environmental permits required for these utility relocations or replacements shall be the responsibility of the Utility.

(NDOT District, Utility Provider (s))

Traffic Disruption

This project shall be constructed under traffic with lane closures controlled by approved temporary traffic control, with the exception of shoulder closures and rolling road blocks. The project shall not result in traffic disruptions requiring detours, temporary roads, or ramp closures that are greater than 30 working days. (Contractor)

Access Disruption

Access to adjacent properties shall be maintained at all times during construction. Access may be disrupted temporarily at times due to construction activities but shall not be closed.

(Contractor)

Public Involvement

A minimum of one news release shall go to all local and area media, and be posted on the

NDOT website, prior to the start of construction work. (NDOT District, NDOT

Communications)

- 20 -

Any written information that is dispersed to the public regarding this project must be translated into Spanish. Dispersed information does not include highway signs or electronic messaging boards, but does include, for example, public meeting invitations, mailers and postcards, legal notices, news releases, and project map/information handouts. Legal notices and news releases do not need to be translated if they are only to be placed in an English-language media source. Information that is distributed to businesses, public agencies, or to departments/representatives of public agencies, does not need to be translated. (NDOT District, NDOT Communications)

If a public meeting is held regarding this project, the written documents prepared for public dispersal (for example, project map/information handouts) at the meeting must be translated into Spanish. There must be a Spanish interpreter present. There must also be clear notice posted. (NDOT District, NDOT Communications)

Wellhead Protection Area

A portion of the project has been identified as being located within the Douglas County

SID #258 - Carat Homes Wellhead Protection Area. NDOT's Standard Specifications -

Section 107 address the Contractor's responsibility to keep fully informed of, observe, and comply with all federal, state, and local laws and ordinances that affect the conduct of the work. (Contractor)

Contact Person: Bre Lewis-Jones, NEPA Specialist, (402) 479-3567

Unexpected Waste

If contaminated soils/groundwater or unexpected wastes are discovered, the Contractor shall stop all work within the immediate area. The Contractor shall secure the area of the discovery and notify the Highway Project Manager (HPM). The Contractor shall not reenter the discovery area until notified by the HPM. At the time of discovery, the HPM and Contractor shall utilize the NDOT Unexpected Waste Action Plan (UWAP) to coordinate appropriate actions. The actions to be carried out by the HPM are (but not limited to): verification that the Contractor has suspended construction activities in the area of the discovery, contact the Roadside Development & Compliance Unit (RDCU) hazmat representative and make an entry into AASHTOware Project that an unexpected waste discovery was made. The HPM shall then utilize the UWAP Notification Form (NDOT Form 691) to properly document the extent and type of waste. The HPM will ensure that proper disposal of the waste and any required health and safety mitigation is implemented by the Contractor. The Contractor is required by NDOT's Standard Specification Section 107.11 (Hazardous Material Discoveries) to handle and dispose of regulated material in accordance with applicable laws.

Contractor Commitment. If contaminated soils/groundwater or unexpected wastes are discovered, the Contractor shall stop all work within the immediate area. The Contractor shall limit access to authorized personnel within the area of the discovery and notify the Highway Project Manager (HPM). The Contractor shall not reenter the discovery area until notified by the HPM. At the time of discovery, the HPM and Contractor shall utilize the NDOT Unexpected Waste Action Plan (UWAP) to coordinate appropriate actions. The Contractor is required by NDOT's Standard Specification Section 107.11 (Hazardous Material Discoveries) to handle and dispose of regulated material in accordance with applicable laws.

Contact Person: Aaron Bedea, Noise, Air Quality & Hazardous Materials Specialist, (402) 479-4312

- 21 -

Borrow Site. Any material needed shall be provided by the Contractor. The Contractor shall try to obtain borrow from an upland site to prevent depletion issues. If the borrow site is within a depletion area of concern, the Contractor shall coordinate with the appropriate agencies and NDOT to offset or minimize impacts. The Contractor shall obtain all environmental clearances and permits required for the borrow site prior to obtaining borrow material for the project. (Contractor)

The Contractor shall have a staging area for the project where material and equipment for the project is stored (e.g. re-steel, forms, etc.). The Contractor shall be required to dispose of material removed as part of the project described above and miscellaneous obstructions encountered and removed along the project. The disposal shall be the responsibility of the

Contractor. A waste site may be needed. The Contractor shall be responsible to obtain all permits and clearances, and all conditions of those permits shall be followed. (Contractor)

Contact Person: Carson Jones, Roadside Development Team Lead, (402) 479-3642

Construction Stormwater

This project does not require a Construction Stormwater Permit or a Storm Water Pollution Prevention Plan (SWPPP). Temporary water pollution prevention practices (including sediment and erosion control measures) are still required by Nebraska State Title 119. The Contractor shall exercise every reasonable precaution throughout the life of the contract to prevent sedimentation within rivers, streams, impoundments (lakes, reservoirs, etc.), the project site, and adjacent property. (Contractor)

Contact Person: Brian Anderson, Stormwater and Erosion Control Specialist, (402) 479-4538

NOTE:

In the event that paleontological remains, including but not limited to fossil bones or other fossilized material, preserved remains, impression, or trace of a once-living thing from a past geological age are discovered in the course of the work, work in the area of the discovery shall immediately cease and the Contractor shall immediately notify the Engineer and the UNL Highway Paleontologist. These fossils can be altered or unaltered remains, such as bones, teeth, and shells, or indirect traces like footprints, burrows, and fossilized dung (coprolites). The contact information for the Highway Paleontologist (Shane Tucker) is:

Nebraska Highway Paleontology Program University of Nebraska State Museum W436 Nebraska Hall, UNL Lincoln, NE 68588-0514

(402) 472-2657

- 22 -

- 23 -

- 24 -

- 26 - - 25 -

- 27 - - 26 -

- 28 - - 27 -

- 29 - - 28 -

- 30 -

- 29 -

- 31 -

- 30 -

- 32 - - 31 -

- 33 - - 32 -

- 34 - - 33 -

- 35 - - 34 -

- 36 -

FLOODPLAIN PERMIT

- 35 -

- 37 -

CERTIFICATION FOR FEDERAL-AID CONTRACTS

(1-9-1217)

The bidder certifies, by signing and submitting this bid, to the best of his or her knowledge and belief, that:

(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement.

(2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form-LLL, "Disclosure Form to Report Lobbying," in accordance with its instructions.

This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by Section 1352, Title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.

The bidder also agrees by submitting his or her bid that he or she shall require that the language of this certification be included in all lower tier subcontracts, which exceed $100,000 and that all such subrecipients shall certify and disclose accordingly.

REQUIRED SUBCONTRACTOR/SUPPLIER QUOTATIONS LIST

(1-43-1217)

All bidders must provide to the NDOT the identity of all firms who provided quotations on all projects, including both DBEs and non-DBEs. This information must be on a form provided by the NDOT Contracts Office.

If no quotations were received, the bidder must indicate this in the space provided.

Each bidder will be required to submit one list per letting to cover all projects bid.

- 36 -

- 38 -

GENERAL INFORMATION, DEFINITIONS, AND TERMS

(1-43-0120)

The last sentence of paragraph 1. of Subsection 101.0309 in the Standard Specifications is void and superseded by the following:

It includes all documents as set forth in Subsection 102.10.

Paragraph 1. of Subsection 101.0319 is void and superseded by the following:

1. The security executed by the bidder and the bidder’s surety, or sureties furnished to the Department to guarantee complete payment and performance of the contract.

PREQUALIFICATION OF BIDDERS

(1-43-0720)

Subsection 102.01 in the Standard Specifications is void and superseded by the following:

102.01 - - Prequalification of Bidders

1. All persons, (any individual, partnership, association, corporation or joint stock company) proposing to bid on a contract for the construction, reconstruction, improvement, maintenance, or repair of roads, bridges and their appurtenances to be let by the Department shall submit a statement showing his/her experience, equipment, and financial condition; except that such statement may not be required for contracts where the estimate of the Engineer is less than one hundred thousand dollars, or of an emergency nature. Such statement shall be under oath and on a form to be provided by the Department and shall be submitted not later than 5 calendar days before the letting of the Contract or Contracts. The statement shall develop fully the financial ability, adequacy of plant and equipment, organization, prior experience, and such other pertinent and material facts as may be desirable. The Department may require additional information at any time. The statements of bidder’s experience, equipment, and financial condition will not be retained in the active file of qualified bidders after the financial condition shown is of a date 15 months prior. Any person whose qualification will expire on or before the date of a letting must submit a new statement and request to be qualified at least 5 calendar days before the letting at which he/she desires to bid. Any person who desires a change in his/her qualification must submit a new statement or a request in writing at least 5 calendar days before the letting at which the change would be effective. Upon the compliance with all laws and rules and regulations relating thereto, such person will be qualified for the amount and class of work to which he/she is entitled. All information furnished the Department shall be confidential.

2. The financial showing required in such statement may be in the form of an audited financial statement certified by a public accountant holding a currently valid permit from the Nebraska Board of Public Accountancy or by any certified public accountant holding a currently valid permit.

- 37 -

- 39 -

3. The use of a Certification of Surety as a means of showing financial condition in such statement will be permitted. The applicant shall furnish a certified statement from a bonding agency licensed to do business in the state of Nebraska. The certification shall be made on bonding firm letterhead and indicate the total maximum bonding coverage the surety will issue on the applicant’s behalf.

4. The use of a “Letter of Credit” as an alternate means of showing financial condition may be permitted when the net amount of the “Letter of Credit” does not exceed $500,000.

The “Letter of Credit” must be from a licensed or chartered financial institution.

5. Each person will be qualified upon such statement for an amount of work…