Bid Notice-Construction of the Murphy_s Community Park Lighting Improvement Project.pdf
PDF 176 KB Posted
- Solicitation number
- 26-1200-10-912
- Issued by
- Calaveras County, San Francisco City, California
About this file
This is a Bid Notice for an Invitation to Bid (ITB) issued by the Calaveras County Department of Public Works for the construction of the Murphy's Community Park Lighting Improvement Project (County Project #CCL-05930(106), ITB #26-1200-10-912). The project consists of demolishing an existing lighting panel and sub panel, installing new lighting panel and sub panel, conduits, pullboxes, light poles and foundations with appurtenant work in accordance with Caltrans Standard Specifications. Work also includes Alternative 1 for Main Street Lighting Improvements, which involves removal of existing light poles, installation of new light poles, and installation of protective bollards on Main Street. The contractor must furnish all necessary labor, tools, materials, appliances, and equipment to complete the project. Bids are due by October 14, 2026, at 3:00 PM via the Public Purchase website, with bid opening and public reading conducted via Zoom. The last day to submit written questions is October 7, 2026, at 3:00 PM, with County responses posted by October 9, 2026. The apparent successful bidder will be notified on October 19, 2026, with anticipated contract award on November 24, 2026. The base contract term is forty (40) working days, plus ten (10) additional working days if awarded Alternative Bid Items.
The estimated cost is $530,000 for the Base Bid and $725,000 with Alternative Bid Items included. Bidders must submit bidder's security equal to at least 10 percent of their bid and may use either a bidder's bond or other acceptable security. The successful bidder must furnish a payment bond and performance bond each equal to at least 100 percent of the total bid. The contractor must possess a Class A general engineering contractor license or a combination of Class C licenses constituting a majority of the work and must be registered as a public works contractor pursuant to Section 1725.5 of the Public Contract Code. General prevailing wage rates apply as determined by the California Department of Industrial Relations. All subcontractors performing work exceeding one-half of one percent of the total bid or $10,000, whichever is greater, must be listed with their California contractor license numbers and public works contractor registration numbers. The project is subject to Buy America requirements under the Infrastructure Investment and Jobs Act and California Air Resources Board compliance requirements for vehicle fleets.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
CONSTRUCTION OF THE MURPHYS COMMUNITY
PARK LIGHTING IMPROVEMENT PROJECT
COUNTY PROJECT #CCL-05930(106)
ITB #26-1200-10-912
Bid Submission Deadline: October 14, 2026, at 3:00 PM
CALAVERAS COUNTY
DEPARTMENT OF PUBLIC WORKS
Micah Martin, Director 891 Mountain Ranch Road
San Andreas, CA 95249
TABLE OF CONTENTS
1. Scope of Work 3
2. Control of Work 3
3. Schedule 4
4. General Construction Specifications 4
5. Technical Specifications 4
6. Compensation 4
7. Bidders’ Questions 4
8. Instructions to Bidders 5
8.1. Estimated Timeframe for Bidding Process 5
8.2. Submission of Bids 5
8.3 Execution of Contract 6
8.4 Failure to Execute Contract 7
8.5 Bid Protests 7
8.6 Award of Contract 8
9. Non-Discrimination 8
10. General Conditions of Invitation to Bid 8
10.1 Job Site and Document Examination 8
10.2 Bid Ineligibility 9
10.3 Rejection of Bids 9
10.4 Submittal Failure History 9
10.5 Bid Withdrawal 9
10.6 Bid Relief 9
10.7 Disqualification of Bidders 9
10.8 Previous Disqualification, Removal, or Other Prevention of Bidding 10
10.9 Compliance with Order of the National Labor Relations Board 10
10.10 Ineligibility to Contract 10
10.11 Public Record 11
10.12 Bidder’s Securities 11
10.13 Bid Rigging 11
EXHIBITS:
A. Bid Book
B. Project Plans
C. Special Provisions
D. Sample Agreement, Progress Pay Form, Change Order Log
NOTICE TO BIDDERS
MURPHYS COMMUNITY PARK LIGHTING
IMPROVEMENT PROJECT
The County of Calaveras will receive sealed bids for Murphys Community Park Lighting Improvement
Project, County Project No. CCL-05930(106).
This project, generally described, consists of the following project description:
The work to be performed consists of demoing an existing lighting panel and sub panel, installing new lighting panel and sub panel, conduits, pullboxes, light poles and foundations and appurtenant work, in accordance with the project plans as specified hereinafter, to ensure compliance with Caltrans Standard
Specifications, these Special Provisions and other such items that are required by plans.
Work includes an Alternative 1 for Main St. Lighting Improvements which include the removal of existing light poles and installing new light poles, and installing protective bollards on Main St. in accordance with the project plans as specified hereinafter, to ensure compliance with Caltrans Standard Specifications, these Special Provisions and other such items that are required by plans. Contractor shall furnish all necessary labor, tools, materials, appliances, and equipment to complete the project.
The Invitation to Bid is available through www.publicpurchase.com within the section dedicated to this solicitation under the agency of the County of Calaveras.
Bidders shall present inquiries to the County through the Public Purchase website using the “Questions” feature. All responses, if any, from the County to bidder’s inquiries will be issued as answers within the
“Questions” feature.
Bid Opening Wednesday, October 14, 2026, at 3:00 PM
The County will open and publicly read bids via Zoom video. You can attend the meeting using the following:
https://teams.microsoft.com/meet/281506473074354?p=zz0ftpROVRJA787wwG
Bids will not be accepted after the time set for bid opening.
Questions based on alleged patent ambiguity of the plans, specifications, or estimate must be asked in writing before bid opening. After bid opening, the County does not consider these questions as bid protests.
The Contractor shall possess a Class A general engineering contractor license or any combination of Class
C licenses which constitutes a majority of the work.
Complete the work within a total of forty (40) working days (Base Bid), plus ten (10) additional working days for awarded Added Alternative Bid Items beginning from the date specified on the County’s Notice to
Proceed.
The estimated cost of contract work is $530,000 for Base Bid and $725,000 with Alternative Bid Items included.
Bids must be accompanied by bidder’s security equal to at least 10 percent of the bid.
The successful bidder shall furnish a payment bond and a performance bond.
The general prevailing wage rates in the county, or counties, in which the work is to be done have been determined by the Director of the California Department of Industrial Relations and are available from the
California Department of Industrial Relations’ website at http://www.dir.ca.gov.
A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code or engage in the performance of any contract for public work, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section
7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.
BUILD AMERICA BUY AMERICA
Buy America requirements have been modified by the passage of the Build America Buy America Act
(BABA) as part of the Infrastructure Investment and Jobs Act (IIJA) in November 2021. The new requirements will apply to all steel and iron products, and construction materials supplied and permanently incorporated into a federal-aid project regardless of the funding source used to purchase the product and regardless of how the products were procured (i.e., agency furnished materials, materials added by change order, etc.). On May 14, 2022, a 180-day temporary waiver of the new Buy America requirements was granted for the addition of construction materials, extending the effective date to November 10, 2022. Once the temporary waiver expires on November 9, 2022, the Buy America requirements will be extended to construction materials in addition to the current steel and iron products.
All projects authorized on or after November 10, 2022, must comply with the new Buy America requirements. The new Buy America requirements are downloadable in a pdf document:
https://www.whitehouse.gov/wp-content/uploads/2022/04/M-22-11.pdf
CALIFORNIA AIR RESOURCES BOARD COMPLIANCE
Contractor shall comply with all applicable requirements of Title 13, California Code of Regulations §2449(i),
et. seq. for projects involving the use of vehicles subject to the regulation.
Contractor shall provide to County a valid Certificate of Reported Compliance (Certificate) prior to contract execution. Contractor shall obtain and retain valid Certificate for all subcontractors.
Contractor shall only allow fleets with valid Certificates on the job site. Contractor shall prominently display a sign that provides key information about the regulation and how to report noncompliance. The sign must be posted where vehicles subject to this regulation will operate for eight or more calendar days; the sign must be posted by the eighth calendar day from when the first vehicle operates. Section 2449(j)(5) provides the exact language that must be on the signage, verbatim, along with other very specific directions about how and where to post it. The signage lettering must be larger than size 14-point type and must be displayed in a conspicuous place where employee notices are typically posted or where there is employee foot traffic.
CARB has provided an example sign for contractors to use or reference at the following link and attached it below. For more information, see section 2449(j)(5) of the regulation.
INVITATION TO BID
1. SCOPE OF WORK
This project, generally described, consists of the following project description:
The work to be performed consists of demoing an existing lighting panel and sub panel, installing new lighting panel and sub panel, conduits, pullboxes, light poles and foundations and appurtenant work, in accordance with the project plans as specified hereinafter, to ensure compliance with Caltrans Standard Specifications, these Special Provisions and other such items that are required by plans.
Work includes an Alternative 1 for Main St. Lighting Improvements which include the removal of existing light poles and installing new light poles, and installing protective bollards on Main St. in accordance with the project plans as specified hereinafter, to ensure compliance with Caltrans Standard Specifications, these Special Provisions and other such items that are required by plans. Contractor shall furnish all necessary labor, tools, materials, appliances, and equipment to complete the project.
The Special Provisions for the work to be done are dated February 5th, 2026, and titled:
SPECIAL PROVISIONS FOR
MURPHYS COMMUNITY PARK LIGHTING IMPROVEMENT
County Project No. CCL-05930(106)
Calaveras County, California
Department of Public Works
The Project Plans for the work to be done are dated January 30, 2026, and titled:
PROJECT PLANS FOR
MURPHYS COMMUNITY PARK LIGHTING IMPROVEMENT
County Project No. CCL-5930(106)
Calaveras County, California
Department of Public Works
See Section 4, “Scope of Work,” of the Standard Specifications of the California Department of
Transportation dated 2025 which can be found at:
2025 Standard Plans, Standard Specifications, and Contract Item Codes | Caltrans
2. CONTROL OF WORK
For control of work unique to this project, see Section 5 of the Special Provisions.
See Section 5, “Control of Work,” of the Standard Specifications dated 2025 of the California Department of Transportation.
3. SCHEDULE
For information regarding schedule required from contractor, see Section 8-1.02, “Schedule,” of the
Standard Specifications dated 2025 of the California Department of Transportation.
4. GENERAL CONSTRUCTION SPECIFICATIONS
For payment unique to this project, see section 9-1.03 of the Special Provisions.
For time constraints unique to this project, see section 10-1.03 of the Special Provisions.
For maintaining traffic unique to this project, see Section 12-1.01 of the Special Provisions.
For water pollution control unique to this project, see Section 13-7.02C of the Special Provisions.
For environment stewardship unique to this project, see Section 14-11.04 of the Special Provisions.
For existing facilities unique to this project, see Section 15-1.03D of the Special Provisions.
5. TECHNICAL SPECIFICATIONS
For technical specifications unique to this project, see Sections 36, “Surfacings and Pavements-General”, 39, “Asphalt Concrete”, 84, “Traffic Stripes and Pavement Markings,” and Section 86, “Electrical Work-
General” of the Special Provisions.
6. COMPENSATION
The agreement will require that the contractor awarded the contract to agree to receive and accept the prices listed in the Bid Book as full compensation for furnishing all labor, materials, and equipment and doing all the work contemplated and described by the agreement and for well and faithfully completing the work, and the whole therefor, according to the plans and specifications, and the requirements of the
Engineer.
7. BIDDERS’ QUESTIONS
Questions regarding this Invitation to Bid must be submitted in writing to the County’s procurement website by 3:00 PM on October 07, 2026. The County will not respond to questions that might render the award of this contract invalid, nor will the County respond to any questions submitted after the deadline for submitting questions. The County will post the questions received, along with written responses, no later than 3:00
PM on October 09, 2026 to the County’s procurement website:
http://www.publicpurchase.com/gems/calaverasco.ca/buyer/public/home
It is the responsibility of the bidders to check this website to review the questions and responses.
8. INSTRUCTIONS TO BIDDERS
8.1. Estimated Timeframe for Bidding Process
Invitation to Bid Released September 23, 2026
Last Day to Submit Written Questions October 07, 2026, 3:00 PM
Last Day County will Respond to Questions October 09, 2026, 3:00 PM
Bids Due / Apparent Low Bidder October 14, 2026, 3:00 PM
Notification of Apparent Successful Bidder October 19, 2026
Anticipated Contract Award November 24, 2026
8.2. Submission of Bids
Firms or individuals interested in performing the requested services should complete the following steps:
1. Review the ITB, including Exhibits A through D (Project Plans, Bid Book, Sample
Contract, and Special Provisions).
2. Regularly check the section of the Public Purchase website dedicated to this solicitation for any addenda, questions posted by bidders, and responses to questions posted by bidders.
3. Complete the entire Bid Book, signed in ink, and submit, under sealed cover, in accordance with all ITB instructions and with the following required items:
a) Statement of qualifications and experience;
b) Addendums signed by bidder; and
c) Bidder’s security equal to at least 10% of bid. If using a bidder’s bond, use Bid
Bond Form supplied in Bid Book.
The Bid Book includes certifications, statements, disclosure and questionnaire that follow the signature page and must be completed. Please complete certifications, statements, disclosure and questionnaire as directed in Bid Book.
On the Subcontractor Listing form in Bid Book, list each subcontractor that will perform work in an amount in excess of 1/2 of 1 percent of the total bid or $10,000, whichever is greater
(Pub Cont Code § 4100 et seq.).
For each subcontractor listed, the Subcontractor Listing form must show:
1. Business name and the location of its place of business.
2. California contractor license number for a non-federal-aid contract.
3. Public works contractor registration number.
4. Portion of work it will perform. Show the portion of the work by:
a) Bid item numbers for the subcontracted work;
b) Percentage of the subcontracted work for each bid item listed; and
c) Description of the subcontracted work if the percentage of the bid item listed is less than 100 percent.
Bid documents must be submitted via the Public Purchase website under the ITB described in the Notice to Bidders. Submissions must be received no later than October
14, 2026 at 3:00 pm.
The County will open and publicly read bids via Zoom video. You can attend the meeting using the following:
https://teams.microsoft.com/meet/281506473074354?p=zz0ftpROVRJA787wwG
8.3 Execution of Contract
All bids will be evaluated for responsiveness to the requirements of the Invitation to Bid and compared on the basis of the Engineer's Estimate of the quantities of work to be done.
The County reserves the right to waive any minor irregularities in bids submitted.
Bidders shall be notified of the apparent successful bid at least 18 calendar days prior to the
Board of Supervisors meeting set for award.
The apparent successful bidder will be required to furnish proof of insurance as described in
Section 24, “Insurance Requirements,” of the sample contract, Exhibit C of this Invitation to Bid.
The apparent successful bidder must furnish 2 contract bonds:
1. Payment bond to secure the claim payments of laborers, workers, mechanics, or materialmen providing goods, labor, or services under the Contract. This bond must be equal to at least 100 percent of the total bid.
2. Performance bond to guarantee the faithful performance of the Contract. This bond must be equal to at least 100 percent of the total bid.
The County will present the contract to the apparent successful bidder for execution. The contract shall be signed by the apparent successful bidder and shall be returned, together with the contract bonds, to the County so that they are received within 10 days by the Calaveras
County Public Works Department, not including Saturdays, Sundays, and legal holidays, after the apparent successful bidder has received the contract for execution. The executed contract and contract bonds shall be delivered to the following address:
Calaveras County
Department of Public Works
Reference: ITB #26-1200-10-912 - Murphys Community Park Lighting
891 Mountain Ranch Road
San Andreas, CA 95249
8.4 Failure to Execute Contract
Failure of the apparent successful bidder to execute the contract and file acceptable bonds, as described herein, within 10 days, not including Saturdays, Sundays, and legal holidays, after that bidder has received the contract for execution shall be just cause for the forfeiture of the bid security. The successful bidder may file with the County a written notice, signed by the bidder or the bidder's authorized representative, specifying that the bidder will refuse to execute the contract if it is presented. The filing of this notice shall have the same force and effect as the failure of the bidder to execute the contract and furnish acceptable bonds within the time hereinbefore prescribed.
8.5 Bid Protests
Any bidder who wishes to protest contract award shall submit justification to the Director of the
Calaveras County Department of Public Works. Any protest must be received by the office of the Calaveras County Department of Public Works no more than 5 calendar days after publication of the notice of intent to award the construction contract.
Bid protests are to be delivered electronically to DPWProjects@calaverascounty.gov or to the following address:
Calaveras County
Department of Public Works
Attn: Director of Public Works
891 Mountain Ranch Road
San Andreas, CA 95249
Any protest shall be based on evidence that the apparent successful bidder misled or misrepresented themselves to the County. Economic considerations shall not be used as a basis for justification for a protest.
The Director of Public Works shall respond to the protester and all bidders in writing with the outcome of the protest evaluation prior to the Board of Supervisors meeting set for award. Any aggrieved bidder may bring final appeal to the Board of Supervisors at the meeting set for award.
8.6 Award of Contract
The award of the contract, if it is to be awarded, will be to the lowest responsible bidder for the sum of the base bid plus any additive alternates the County chooses to award.
To ensure impartiality when selecting the bid alternates, each bidder will be assigned an identification number by the Business Administrator or designee when turning in his/her bid. The bidder’s names will not be revealed to County staff selecting the bid alternates until the selection of which bid alternates to award has been made. The selection of the apparent low bidder may or may not be announced at the bid opening. All bid forms shall be retained by the Business
Administrator until after the award selection has been made.
The bid alternates will be awarded in the delineated order as funding allows, and the County reserves the right to amend the budget for any particular project if it deems it is in the best interest of the County to do so.
The award, if made, will be made within 60 days after the opening of bids. This period will be subject to extension for such further period as may be agreed upon in writing between the
County and the bidder concerned.
Should bid exceed funding made available by Caltrans, County shall award a contract, if any, within 30 days of approval by Caltrans of an adequate funding increase.
9. NON-DISCRIMINATION
The County will never exclude any person from participation in, deny any person the benefits of, or otherwise discriminate against anyone in connection with the award and performance of any contract on the basis of color, race, creed, national origin, religion, sex, age, sexual preferences, or physical or mental disability.
Should the contract be awarded, the contractor, sub-recipient or subcontractor shall not discriminate on the basis of color, race, creed, national origin, religion, sex, age, sexual preferences, or physical or mental disability in the performance of the contract.
10. GENERAL CONDITIONS OF INVITATION TO BID
10.1 Job Site and Document Examination
Examine the job site and bid documents. Notify the Department of apparent errors and patent ambiguities in the plans, specifications, and Bid Item List. Failure to do so may result in rejection of a bid or rescission of an award.
Bid submission is your acknowledgment that you have examined the job site and bid documents and are satisfied with:
A. General and local conditions to be encountered
B. Character, quality, and scope of work to be performed
C. Quantities of materials to be furnished
D. Character, quality, and quantity of surface and subsurface materials or obstacles
E. Requirements of the contract
10.2 Bid Ineligibility
No employee of the County shall be eligible to submit a proposal for, nor to subcontract for any portion of, nor to supply any materials for any contract administered by the County.
A firm that has provided architectural or engineering services to the Department for this contract before bid submittal for this contract is prohibited from any of the following:
A. Submitting a bid
B. Subcontracting for a part of the work
C. Supplying materials
10.3 Rejection of Bids
Proposals may be rejected if they have been transferred to another bidder, or if they show any alteration of form, additions not called for, conditional bids, incomplete bids, erasures, or irregularities of any kind.
When proposals are signed by an agent, other than the officer or officers of a corporation authorized to sign contracts on its behalf or a member of a partnership, a "Power of Attorney" must be on file with the County prior to opening bids or shall be submitted with the proposal;
otherwise, the proposal may be rejected as irregular and non-responsive.
10.4 Submittal Failure History
The County considers a bidder’s past failure to submit documents required after bid opening in determining a bidder’s responsibility.
10.5 Bid Withdrawal
An authorized agent may withdraw a bid before the bid opening date and time by submitting a written bid withdrawal request at the location where the bid was submitted. Withdrawing a bid does not prevent you from submitting a new bid.
After the bid opening time, a bidder cannot withdraw a bid.
10.6 Bid Relief
Attention is directed to the provisions of Public Contract Code Sections 5100 to 5110, inclusive, concerning relief of bidders and in particular to the requirement therein, that if the bidder claims a mistake was made in the bid presented, the bidder shall give the County written notice within
5 days after the opening of the bids of the alleged mistake, specifying in the notice in detail how the mistake occurred.
10.7 Disqualification of Bidders
More than one proposal from an individual, firm, partnership, corporation, or combination thereof under the same or different names will not be considered. Reasonable grounds for believing that any individual, firm, partnership, corporation or combination thereof is interested in more than one proposal for the work contemplated may cause the rejection of all proposals in which that individual, firm, partnership, corporation or combination thereof is interested. If there is reason for believing that collusion exists among the bidders, any or all proposals may be rejected. Proposals in which the prices obviously are unbalanced may be rejected.
10.8 Previous Disqualification, Removal or Other Prevention of Bidding
Pursuant to Section 10162 of the Public Contract Code, the bidder shall complete, under penalty of perjury, the questionnaire in the Bid Book relating to previous disqualification, removal or other prevention of bidding of the bidder, or officers or employees of the bidder because of violation of law or a safety regulation.
A bid may be rejected on the basis of a bidder, any officer of the bidder, or any employee of the bidder who has a proprietary interest in the bidder, having been disqualified, removed, or otherwise prevented from bidding on, or completing a federal, state or local project because of a violation of law or a safety regulation.
Communication of any kind by a firm with any County Board of Supervisors member for influencing selection before a contract is formally awarded will result in automatic disqualification.
10.9 Compliance with Order of the National Labor Relations Board
Pursuant to Public Contract Code Section 10232, the Contractor shall swear by a statement, under penalty of perjury, that no more than one final, unappealable finding of contempt of court by a Federal court has been issued against the Contractor within the immediately preceding two-year period because of the Contractor's failure to comply with an order of a Federal court which orders the Contractor to comply with an order of the National Labor Relations Board. For purposes of Section 10232, a finding of contempt does not include any finding which has been vacated, dismissed, or otherwise removed by the court because the Contractor has complied with the order which was the basis for the finding. The County may rescind any contract in which the Contractor falsely swears to the truth of the statement required by Section 10232.
The statement required by Public Contract Code Section 10232 is included in the Bid Book.
10.10 Ineligibility to Contract
Public Contract Code Section 10285.1 provides as follows:
Any state agency may suspend, for a period of up to three years from the date of conviction, any person from bidding upon, or being awarded, a public works or services contract with the agency under this part or from being a subcontractor at any tier upon the contract, if that person, or any partner, member, officer, director, responsible managing officer, or responsible managing employee thereof, has been convicted by a court of competent jurisdiction of any charge of fraud, bribery, collusion, conspiracy, or any other act in violation of any state or federal antitrust law in connection with the bidding upon, award of, or performance of any public works contract, as defined in Section 1101, with any public entity, as defined in Section 1100, including, for the purposes of this article, the Regents of the University of California or the Trustees of the
California State University. A state agency may determine the eligibility of any person to enter into a contract under this article by requiring the person to submit a statement under penalty of perjury declaring that neither the person nor any subcontractor to be engaged by the person has been convicted of any of the offenses referred to in this section within the preceding three years.
The bidder must complete the Public Contract Code Section 10285.1 Statement included in the
Bid Book.
10.11 Public Record
Bids are public upon opening; after being opened, tabulations shall be completed within seven days (Public Contract Code Section 10305).
10.12 Bidder’s Securities
The County keeps the securities of the 1st, 2nd, and 3rd low bidders until the contract has been executed. The other bidders’ securities, other than bidders’ bonds, are returned upon determination of the 1st, 2nd, and 3rd low bidders, and their bidders’ bonds are of no further effect
(Public Contract Code Section 10184).
10.13 Bid Rigging
The U.S. Department of Transportation (DOT) provides a toll-free hotline to report bid rigging activities. Use the hotline to report bid rigging, bidder collusion, and other fraudulent activities.
The hotline number is (800) 424-9071. The service is available 24 hours 7 days a week and is confidential and anonymous. The hotline is part of the DOT's effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the DOT
Inspector General.
File details come from the government source that posted it. Updated .