Project Manual and Bidding Documents for Building 315 Renovation - Stockton Port District

This document package comprises the complete project manual and bidding requirements for the Stockton Port District's Building 315 Administration Offices Renovation project (Project No. 210007) located at 315 Fyffe Avenue, Stockton, California. The project involves the alteration and renovation of Building 315 to serve as Port administration offices, including selective demolition, concrete work, architectural casework, thermal insulation, fireproofing, door and window systems, glazing, gypsum board installation, tiling, acoustical ceilings, resilient flooring, painting, signage, plumbing, HVAC, electrical systems, fire detection and alarm systems, and site work including asphalt paving, concrete paving, water distribution, sanitary sewerage, and storm drainage facilities. Sealed bids are due by 3:00 PM PST on Tuesday, October 13, 2026, with a mandatory pre-bid conference and site visit scheduled for 10:00 AM on Wednesday, September 16, 2026, at the Port Administration Building. Contractors must attend the pre-bid meeting and sign an attendance roster to be eligible to bid. Work shall be completed within twelve (12) months from the commencement date. Bidders must hold a valid California Class B contractor's license, and all personnel must obtain a Transportation Worker Identification Credential (TWIC) from the Transportation Security Administration.

Bidders must submit sealed bids on the required Bid Form (Document 00400) accompanied by bid security of not less than 10% of the total bid price in the form of a cashier's check, certified check, or surety bond. The bid must include a completed Schedule of Values, Subcontractors List (for subcontractors performing work exceeding 0.5% of the total bid amount), Non-Collusion Affidavit, Bidder Certifications, and Bidder Registration Form with proof of insurance. Questions and requests for information must be submitted by 5:00 PM PST on September 22, 2026, with responses issued by Addenda no later than September 29, 2026. The Port will determine the Apparent Low Bidder based on the lowest Total Base Bid Amount and reserves the right to reject any or all bids and to waive inconsequential deviations. Successful bidders must execute the Agreement (Document 00520), provide Construction Performance Bond and Construction Labor and Material Payment Bond equal to the contract price, and submit required insurance certificates and endorsements within 7 days of receiving the Notice of Award. All contractors and subcontractors must comply with prevailing wage laws and provide workers' compensation insurance. Bid protests must be submitted in writing within 10 days following the posting of the Notice of Intent to Award (Document 00505).

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DOCUMENT 00001

00001- 1

PROJECT MANUAL

BUILDING 315

ADMINISTRATION OFFICES RENOVATION

PROJECT NO. 210007

STOCKTON PORT DISTRICT

315 FYFFE AVENUE

STOCKTON, CA

(209) 946-0246 www.portofstockton.com procurement@stocktonport.com

Bids due: October 13, 2026 by 3:00 PM PST

Project No. 210007

Stockton Port District Table of Contents

BUILDING 315 RENOVATION

00010- 1

DOCUMENT 00010

TABLE OF CONTENTS

DIVISION I

SECTION TITLE

INTRODUCTORY INFORMATION

00001 Title Page

00010 Table of Contents 00015 TWIC Required for Service Providers

BIDDING REQUIREMENTS

00100 Advertisement for Bid 00200 Instructions to Bidders 00320 Geotechnical Data and Existing Conditions 00335 Hazardous Materials Survey 00400 Bid Form 00411 Bond Accompanying Bid 00420 Bidder Registration Form 00430 Subcontractors List 00481 Non-Collusion Affidavit 00482 Bidder Certifications

CONTRACT FORMS

00505 Notice of Intent to Award for Construction 00510 Notice of Award 00520 Agreement 00550 Notice to Proceed 00610 Construction Performance Bond 00620 Construction Labor and Material Payment Bond 00630 Guaranty 00650 Agreement and Release of Any and All Claims 00660 Substitution Request Form 00680 Escrow Agreement for Security Deposits in Lieu of Retention

CONDITIONS OF THE CONTRACT

00700 General Conditions

00800 Supplementary General Conditions 00821 Insurance and Indemnification 00822 Apprenticeship Program 00910 Addenda

00010- 2

GENERAL REQUIREMENTS

01100 Summary Attachment A – Special Provisions Attachment B – Construction Management Fact Sheet

01200 Price and Payment Procedures 01250 Modification Procedures 01315 Project Meetings 01320 Progress Schedules and Reports 01330 Submittal Procedures 01340 Safety Submittals 01410 Regulatory Requirements 01420 References and Definitions 01500 Temporary Facilities and Controls

01540 Site Security and Safety 01600 Product Requirements 01740 Cleaning 01770 Contract Closeout 01780 Project Record Documents 12313 Phasing

DIVISION II - SPECIFICATIONS

024119 Selective Demolition 033000 Cast-in-Place Concrete 064100 Architectural Wood Casework 072100 Thermal Insulation 072719 Weather Barrier 076200 Sheet Metal Flashings and Trim 076526 Self-Adhering Sheet Flashing 078100 Applied Fireproofing 078413 Penetration Firestopping 079200 Joint Sealants 081113 Hollow Metal Doors and Frames

081113.13 Prefinished Metal Door Frames

081429 Prefinished Flush Wood Doors 084113 Aluminum Framed Storefront System

084229.23 Sliding Automatic Entrances

087100 Door Hardware 088000 Glazing 088013 Fire-Rated Glazing 092400 Portland Cement Plastering 092900 Gypsum Board 093000 Tiling 095113 Suspended Acoustical Ceilings 096513 Resilient Base and Accessories

00010- 3

096813 Tile Carpeting 099100 Painting Dunn Edwards 101400 Signage

102113.13 Plastic Laminate Toilet Compartments

102800 Toilet Accessories 104413 Fire Extinguishers and Cabinets 122413 Roller Window Shades 129300 Site Furnishings 220000 Plumbing – See Plumbing Plans 230000 Heating, Ventilating, and Air Conditioning – See HVAC Plans 260000 Electrical – See Electrical Plans 283000 Fire Detection and Alarm – See Electrical Plans 310513 Soils for Earthwork 311100 Site Clearing 312000 Earthwork 312005 Trenching 321216 Asphalt Paving 321313 Concrete Paving and Walks 321373 Concrete Paving Joint Sealants 321700 Paving Specialties 331000 Water Distribution 333000 Sanitary Sewerage 334000 Storm Drainage Facilities Appendix A Asbestos & Lead Survey Report

--------- Drawings: Port of Stockton Building 315 Alteration – Phase 2

END OF DOCUMENT

Project 210007

00015-1

Stockton Port District TWIC Required for Service Providers

What is TWIC? The Transportation Worker Identification Credential, also known as TWIC®, is required by the Maritime Transportation Security Act for workers who need access to secure areas of the nation’s maritime facilities and vessels. The Transportation Security Administration (TSA) conducts a background check to determine a person’s eligibility and issues the credential.

General information available at https://www.tsa.gov/twic

How to Apply

Pre-enroll using the online application at https://tsaenrollmentbyidemia.tsa.dhs.gov or complete the entire process in person at an application center https://tsaenrollmentbyidemia.tsa.dhs.gov/locator

Schedule an appointment online at https://www.tsa.gov/twic or call (855) 347-8371 weekdays, 8 a.m. to 10 p.m. ET.

Visit a TWIC application center to:

1. Provide required documentation, be fingerprinted and take a facial photo.

2. First-time applicants pay $124 non-refundable fee valid for five years with a credit card, money order, company check or certified/cashier’s check.

3. Your card can be mailed to your home address or picked up at the application center.

LOCAL TWIC OFFICE:

This sheet is provided as INFORMATION ONLY. Contractor shall visit www.tsa.gov/twic to verify eligibility and further information.

DOCUMENT 00015

TWIC REQUIRED FOR SERVICE PROVIDERS

Advertisement for Bids Stockton Port District

BUILDING 315 RENOVATION

00100 - 1

DOCUMENT 00100

ADVERTISEMENT FOR BIDS

1. NOTICE. The STOCKTON PORT DISTRICT, a municipal corporation of the State of California (“Port”) hereby gives notice that it will accept Bids for construction of the following public work:

BUILDING 315 ADMINISTRATION OFFICES RENOVATION

2. BID SUBMISSION. Port will receive sealed Bids no later than 3:00 p.m. on Tuesday, October 13, 2026. Port’s representative will call out the designated time in the Port Administration Building lobby, stating that the period for accepting Bids is closed. The Bid opening will be in accordance with procedures set forth in Document 00200 (Instructions to Bidders).

3. CONTACT INFORMATION.

Mailing Address:

Janice Dias P.O. Box 2089 Stockton, California 95201

Website address for more information:

www.portofstockton.com

Owner’s Representative:

Rod Iwashita Director of Engineering & Facilities Or Port Designated Representative

Telephone: (209) 946-0246

4. DESCRIPTION OF THE WORK. Alteration of Building 315 to be used as Port of Stockton Administration Offices

5. CONTRACT TIME. Work shall be finally completed within twelve (12) months from the date when Contract Time commences to run.

6. REQUIRED CONTRACTOR’S LICENSE(S). A valid State of California Class B contractor’s license is required to

Bid this Contract. Joint ventures must secure a joint venture license prior to award of this Contract.

7. DEPARTMENT OF HOMELAND SECURITY REQUIREMENTS. All Service Provider and contractor personnel who will at any time be present on the project site must obtain a Transportation Worker Identification Credential (TWIC) from the Transportation Security Administration. Service Provider will be responsible for processing and costs associated with obtaining the TWIC. Information can be obtained at https://www.tsa.gov/for-industry/twic.

8. PREVAILING WAGE LAWS. The successful Bidder must comply with all prevailing wage laws applicable to the Project, and related requirements contained in the Contract Documents.

9. INSTRUCTIONS. Bidders shall refer to Document 00200 (Instructions to Bidders) for required documents and items to be submitted in sealed envelopes for deposit at the Stockton Port District administration building lobby.

10. SUBSTITUTION OF SECURITIES. Port will permit successful Bidder to substitute securities for retention monies withheld to ensure performance of Contract, as set forth in Document 00680 (Escrow Agreement for Security Deposits in Lieu of Retention), in accordance with California Public Contract Code, Section 22300. By this reference, Document 00680 (Escrow Agreement for Security Deposits in Lieu of Retention) is incorporated in full in this Document 00100.

11. MANDATORY PRE-BID CONFERENCE AND SITE VISIT. Port will conduct a Mandatory Pre-Bid Conference and Site Visit at 10:00 a.m. on Wednesday, September 16, 2026, initially meeting at the Port Administration Building, Advertisement for Bids Stockton Port District

BUILDING 315 RENOVATION

00100 - 2

315 Fyffe Avenue, Stockton, California. Each Bidder must be represented at the meeting. To be eligible, each Bidder’s representative is required to sign an attendance sheet prior to 10:00 a.m. identifying the Bidder represented. Any Bidder arriving after that time will not be permitted to attend the meeting or Bid on the Work. Any Bidder wishing to investigate subsurface conditions at the Site must schedule such a visit with the Port in accordance with Document 00200 (Instructions to Bidders).

12. PROCUREMENT OF BIDDING DOCUMENTS. Bidders may examine the Bidding Documents, including the Instructions to Bidders and the plans and specifications for the work at the Port’s offices. Documents will be transmitted using a flash drive with documents expected to be available on or after September 1, 2026. The Bidders’ attention is drawn to the Instructions to Bidders for complete instructions regarding submission of a Bid.

13. BID PREPARATION COST. Bidders are solely responsible for the cost of preparing their Bids.

14. INELIGIBLE CONTRACTORS AND SUBCONTRACTORS: Port shall not accept a Bid from a Bidder who is ineligible to bid or work on, or be awarded, a public works project pursuant to California Labor Code Section 1777.1 or

1777.7. Bidder shall not include in its Bid any subcontractor who is ineligible to bid or work on, or be awarded, a public works project pursuant to California Labor Code Section 1777.1 or 1777.7. Federal ineligible listings are located on the System for Award Management (SAM) at https://sam.gov.

15. RESERVATION OF RIGHTS. Port specifically reserves the right, in its sole discretion, to reject any or all Bids, or rebid, or to waive inconsequential deviations from Bid requirements not involving time, price, or quality of the Work.

By order of the Board of Commissioners of the Stockton Port District.

Stockton Port District Instructions to Bidders

BUILDING 315 RENOVATION

00200- 1

DOCUMENT 00200

INSTRUCTIONS TO BIDDERS

Bids are requested by the Stockton Port District, a California Port District with municipal powers organized pursuant to Harbors and Navigations Code Sections 6200 et seq. (“Port”), for a general construction contract, or work described in general, as follows:

1. RECEIPT OF BIDS: Sealed Bids will be received by Port at Port’s office (see paragraph 2 below) on

Tuesday, October 13, 2026, by 3:00 PM. Port will accept Bids only from Bidders duly licensed in accordance with the California Business & Professions Code. Port will receive Bids in opaque sealed 10 inch x 13 inch envelope(s), containing the respective items described in Paragraph 6 below. All Bid envelopes will be time-stamped to reflect their submittal time. Envelope shall be due by 3:00 PM. Port shall reject all Bids received after the specified time and will return such Bids to Bidders unopened. Bidders must submit Bids in accordance with this Document 00200.

2. CONTACT INFORMATION: Sealed Bids shall be received at Port’s Administration Building lobby located at 315 Fyffe Avenue, Stockton, California 95203. The telephone number for Port is (209) 946-0246.

3. PROCUREMENT OF BID DOCUMENTS: Bidders may obtain Bidding Documents from the Port’s

Administration Building at 315 Fyffe Avenue, Stockton, CA 95203, from the Procurement & Contracts Officer. Documents may also be obtained from the Port’s website www.portofstockton.com, Business tab, Bids/Proposals section.

4. MANDATORY PRE-BID SITE VISIT AND CONFERENCE: Port will conduct Pre-Bid Conference and

Site Visit at 10:00 AM on Wednesday, September 16, 2026, initially meeting at the Port Administration Building, 315 Fyffe Avenue, Stockton, California, and then moving to the project site, to consider such matters as Bidders may request and a Site Visit immediately following, at the Site. Bidders must attend Pre-Bid Conference and Site Visit and sign an attendance roster as a condition to bidding. The Pre-Bid Conference and Site Visit will last approximately 1 hour.

4.1. Other Pre-Bid Site Visits may be scheduled at Port’s sole discretion, depending on staff availability.

4.2. Port will transmit to all parties recorded as having received Bidding Documents such Addenda as Port in its discretion considers necessary in response to questions arising at the Pre-Bid Conference. Bidders shall not rely on oral statements. Oral statements will not be binding or legally effective. Port will issue Minutes of the Pre-Bid Conference, which shall constitute the sole and exclusive record and statement of the results of the Pre-Bid Conference. The Minutes issued by Port are not Contract Documents.

4.3. While Bidders will be allowed to observe Site conditions, invasive testing will not be allowed.

5. BID SUBMISSION: Bidder shall mark its Bid envelope as BID FOR THE STOCKTON PORT DISTRICT, BUILDING 315 RENOVATION. Bids shall be deemed to include the written responses of the Bidder to any questions or requests for information of Port made as part of Bid evaluation process after submission of Bid.

Bidder’s failure to submit all required documents strictly as required entitles Port to reject the Bid as non-responsive.

5.1. The submission of a Bid does not commit Port to award a contract for the Project, to pay costs incurred in the preparation of a Bid, or to procure or contract for any goods or services.

6. REQUIRED CONTENTS OF BIDS: All Bidders must submit Bids containing each of the fully executed documents supplied in this Project Manual.

BUILDING 315 RENOVATION

00200- 2

6.1. Bidders must submit Bids on Document 00400 Bid Form in accordance with the provisions of Document 00400. Port will reject as non-responsive any Bid not submitted on the required form. Bids must be full and complete. Bidders must complete all Bid items and supply all information required by Bid documents and specifications. Port reserves the right in its sole discretion to reject any Bid as non-responsive as a result of any error or omission in the Bid. Bidders must submit clearly written Bids without erasure or interlineation.

Bidders must clearly make any changes in the Bid. Bidders shall make any change in the Bid by crossing out the original entry, entering and initialing the new entry. Port reserves the right to reject any Bid not clearly written. Bidders may not modify the Bid Form or qualify their Bids.

6.2. Bidders must submit Document 00411 (Bond Accompanying Bid) accompanied by a cashier’s check, certified check (certified without qualification and drawn on a solvent bank of the State of California or a National Bank doing business in the State of California) or surety bond of not less than 10% of the Total Bid Price payable to “Stockton Port District,” and completed in accordance with the provisions of Document 00411. (Port may retain Bid securities and Bid bonds of other than the Apparent Low Bidder for a period of 90 Days after award or full execution of the Contract, whichever first occurs.)

6.3. Bidders must submit Document 00420 (Bidder Registration) completed in accordance with the provisions of Document 00420. Bidder must complete this form and include comprehensive answers to all questions.

Port shall reject as non-responsive any Bid submitted without the Bidder Registration and Experience Form.

6.4. Bidders must submit Document 00430 (Subcontractors List) completed in accordance with the provisions of Document 00430. The Subcontractors List must include the names of all subcontractors and their respective Bid item sub-Bids for those subcontractors who will perform any portion of work, including labor, rendering of service, or specially fabricating and installing a portion of the work or improvement according to detailed drawings contained in the plans and specifications, in excess of one half of one percent (0.5%) of the total Bid amount. Any violation of this requirement may result in a Bid being deemed non-responsive and not being considered.

6.5. Bidders must submit Document 00481 (Non-Collusion Affidavit) completed in accordance with the provisions of Document 00481. Port shall reject as non-responsive any Bid submitted without the Non- Collusion Affidavit.

6.6. Bidders must submit Document 00482 (Bidder Certifications) completed in accordance with the provisions of Document 00482. Port shall reject as non-responsive any Bid submitted without the Bidder Certifications.

6.7. Bidders must submit a complete Preliminary Schedule of Values allocating the Total Bid Amount among the various portions of the Work. The Schedule of Values shall provide sufficient detail to identify major trades, systems, materials, equipment, General Conditions, overhead and profit, and other significant components of the Work. The sum of all items in the Schedule of Values shall equal the Total Bid Amount as provided on Document 00400 Bid Form.

6.8. Any item required by the Special Conditions.

7. OTHER REQUIREMENTS PRIOR TO BIDDING: Submission of Bid signifies Bidder’s careful examination of Bidding Documents and complete understanding of the nature, extent, and location of Work to be performed.

BUILDING 315 RENOVATION

00200- 3

8. EXISTING CONDITIONS INFORMATION AND GEOTECHNICAL DATA: Bidders may examine any available existing conditions information (e.g., record documents, specifications, studies, drawings of previous work), as well as applicable environmental assessment information (if any) regarding the Project, by giving Port reasonable advanced notice. Document 00320 (Geotechnical Data and Existing Conditions) applies to all supplied existing conditions information. Port will make copies available for a fee. A Bidder must give five (5) days advanced notice if copies are desired.

9. ADDENDA & QUESTION / RFI SUBMITTAL: Bidders may submit questions / requests for information

(RFI) regarding this bid by email to procurement@stocktonport.com no later than 5:00 PM PST, September 22, 2026. Port will not respond to questions regarding this bid received after the date and time noted above.

Responses to question and RFI submittals will be issued by Addenda posted to the Port’s website www.portofstockton.com no later than September 29, 2026. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. It is the responsibility of all potential bidders to monitor the Port’s website and ensure that all addenda have been retrieved by the bidder.

9.1. Addenda may also be issued to modify the Bidding Documents as deemed advisable by Port.

9.2. Addenda shall be acknowledged by number with signature in Document 00400 (Bid Form) and shall be part of the Contract Documents. A complete listing of Addenda may be secured from Port.

10. DEPARTMENT OF HOMELAND SECURITY REQUIREMENTS: All personnel assigned to the successful Bidder to the project must obtain a Transportation Worker Identification Credential (TWIC) from the Transportation Security Administration. Successful Bidder will be responsible for processing and costs associated with obtaining the TWIC. Information can be obtained at https://www.tsa.gov/for-industry/twic.

11. EQUAL EMPLOYMENT OPPORTUNITY: Contractor shall comply with all applicable federal, state, and local laws, rules, and regulations in regard to nondiscrimination in employment because of race, color, ancestry, national origin, religion, sex, marital status, age, medical conditions, disability, or any other reason.

12. WAGE RATES: The Contractor acknowledges that it has examined the prevailing rate of per diem wages as established by California Director of Industrial Relations. The Contractor agrees to pay workers not less than the applicable prevailing rate of per diem wages, as set forth in these requirements.

13. WITHDRAWAL OF BIDS: Bidders may withdraw their Bids at any time prior to the Bid opening time fixed in this Document 00200, only by written request for the withdrawal of Bid filed with the Port at the Port’s office. Bidder or its duly authorized representative shall execute request to withdraw Bid. The submission of a Bid does not commit the Port to award a contract for the Project, to pay costs incurred in the preparation of a Bid, or to procure or contract for any goods or services.

14. BID OPENING: Port will open all Bidders’ Envelopes immediately after the time on the date specified in

Paragraph 1 above, initially evaluate them for responsiveness, and determine an Apparent Low Bidder as specified herein.

15. DETERMINATION OF APPARENT LOW BIDDER: Apparent Low Bid will be determined as provided in

Document 00400 (Bid Form). All Bidders are required to submit Bids on all Bid items.

15.1 If any Apparent Low Bidder is determined to be non-responsive or non-responsible, Port may proceed to the next Apparent Low Bidder’s Bid pursuant to any procedures determined in its reasonable discretion, and proceed for all purposes as if this Apparent Low Bidder were the original Apparent Low Bidder.

BUILDING 315 RENOVATION

00200- 4

16. BID EVALUATION: Port may reject any or all Bids and waive any informalities or minor irregularities in the Bids. Port also reserves the right, in its discretion, to reject any or all Bids and to re-Bid the Project. Port reserves the right to reject any or all nonconforming, non-responsive, unbalanced, or conditional Bids, and to reject the Bid of any Bidder if Port believes that it would not be in the best interest of Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by Port. For purposes of this paragraph, an “unbalanced Bid” is one having nominal prices for some Bid items and enhanced prices for other Bid items.

a. In evaluating Bids, Port will consider Bidders’ qualifications, whether or not the Bids comply with the prescribed requirements, bid item prices, and other data, as may be requested in Document 00400 (Bid Form) or prior to the Notice of Award.

b. Port may conduct reasonable investigations and reference checks of Bidder and other persons and organizations as Port deems necessary to assist in the evaluation of any Bid and to establish Bidder’s responsibility, qualifications, financial ability and ability to perform the Work in accordance with the Contract Documents to Port’s satisfaction within the prescribed time.

Submission of a Bid constitutes Bidder’s consent to the foregoing. Port shall have the right to consider information provided by sources other than Bidder. Port shall also have the right to communicate directly with Bidder’s surety regarding Bidder’s bonds.

c. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between written words and figures will be resolved in favor of the words.

d. Port may determine whether a Bidder is qualified in its sole discretionary judgment.

17. BID PROTEST: Any Bid protest must be submitted in writing to the Port’s offices (Attention: Procurement &

Contracts Officer), before 5:00 p.m. of the tenth Day following posting in the front entrance of the Administration Building of Document 00505 (Notice of Intent to Award for Construction). Time will be determined by the clock in the Administration Building lobby. Port will use reasonable efforts to deliver by email a copy of Document 00505 to all Bidders who submitted Bids no later than the business Day after issuance, although any delay or failure to do so will not extend the Bid protest deadline described above.

a. The initial protest document must contain a complete statement of the basis for the protest.

b. The protest must refer to the specific portion of the document that forms the basis for the protest.

c. The protest must include the name, address, and telephone number of the person representing the protesting party.

d. Only Bidders who Port otherwise determines are responsive and responsible are eligible to protest a Bid; protests from any other Bidder will not be considered. In order to determine whether a protesting Bidder is responsive and responsible, Port may evaluate all information contained in any protesting Bidder’s Bid, and conduct the same investigation and evaluation as Port is entitled to take regarding an Apparent Low Bidder.

e. The party filing the protest must concurrently transmit a copy of the initial protest document and any attached documentation to all other parties with a direct financial interest that may be adversely affected by the outcome of the protest. Such parties shall include all other Bidders who appear to have a reasonable prospect of receiving an award depending upon the outcome of the protest.

f. The procedure and time limits set forth in this paragraph are mandatory and are Bidder’s sole and exclusive remedy in the event of Bid protest. Bidder’s failure to comply with these procedures

BUILDING 315 RENOVATION

00200- 5 shall constitute a waiver of any right to further pursue the Bid protest, including filing a Government Code Claim or legal proceedings. A Bidder may not rely on a protest submitted by another Bidder, but must timely pursue its own protest.

18. AWARD: It is the intent of the Port to award a contract to accomplish the Work described in the Contract

Documents. If a Contract is awarded, it will be awarded to the lowest responsible responsive Bidder within ninety (90) days after the opening of the Bids.

19. PERMITS: It is the bidder’s responsibility to furnish prior to the start of work any and all applicable permits to this project. Actual costs of permits will be reimbursed upon receipt of appropriate documentation.

20. SUBSTITUTIONS: Bidders must base their Bids on products and systems specified in Contract Documents or listed by name in Addenda.

a. Except as provided in Paragraph 20.4 below, Port will consider substitution requests only for “or equal items.” Bidders wanting to use “or equal” item(s) may submit Document 00660 (Substitution Request Form) no later than 5 Days before the Bid Date. After that date, Port will not accept “or equal” substitution requests. To assess “or equal” acceptability of product or system, submittals of substitutions shall contain the information required in Document 00660 (Substitution Request Form). Insufficient information will be grounds for rejection of substitution. Port shall, within a reasonable period of time after having received a Request for Substitution, issue in writing its decision as to whether the proposed substitute item is an Equal item. Port’s decision shall be conclusive on all Bidders.

b. Approved substitutions shall be listed in Addenda and become part of Contract Documents.

c. Substitutions may be requested after submitting Bids and Award of Contract only in accordance with requirements specified in the Contract Documents.

d. As a limitation on Bidder's privilege to substitute “or equal” items, Port has found that certain items are designated as Port standards and certain items are designated to match existing items in use on a particular public improvement either completed or in the course of completion or are available from one source. As to such items, Port will not permit substitution. Such items are:

i. N/A

21. POST NOTICE OF AWARD REQUIREMENTS: Successful Bidder must execute and submit the documents set forth in this Document to Port by 5:00 p.m. of the 7th Day following the Notice of Award.

Execution of Contract by Port depends upon approval of these documents.

a. Document 00520 (Agreement) must be executed by successful Bidder. Submit two originals, each bearing an original signature and initials on each page.

b. Document 00610 (Construction Performance Bond) must be executed by successful Bidder and surety, in the amount set forth in Document 00610 (Construction Performance Bond). Submit one original.

c. Document 00620 (Construction Labor and Material Payment Bond) must be executed by successful Bidder and surety, in the amount set forth in Document 00620 (Construction Labor and Material Payment Bond). Submit one original.

d. Document 00630 (Guaranty) must be executed by successful Bidder.

e. Insurance certificates and endorsements required by Document 00821 (Insurance and

Indemnification) must be submitted by successful Bidder. Submit one original set

BUILDING 315 RENOVATION

00200- 6

f. Port shall have the right to communicate directly with Apparent Low Bidder’s proposed performance bond surety, to confirm the performance bond. Port may elect to extend the time to receive faithful performance and labor and material payment bonds.

g. Successful Bidder’s failure to submit the documents required herein, in a proper and timely manner, entitles Port to rescind its award, and to cause Bidder’s Bid security to be forfeited as provided herein.

22. FAILURE TO EXECUTE AND DELIVER DOCUMENTS: If Bidder to whom Contract is awarded shall, within the period described in Paragraph 19 of this Document 00200, fails or neglects to execute and deliver all required Contract Documents and file all required bonds, insurance certificates, and other documents, Port may, in its sole discretion, foreclose on Bidder’s surety bond, or deposit Bidder’s cashier’s check or certified check for collection, and retain the proceeds thereof as liquidated damages for Bidder’s failure to enter into the Contract Documents. Bidder agrees that calculating the damages Port may suffer as a result of Bidder’s failure to execute and deliver all required Contract Documents would be extremely difficult and impractical and that the amount of Bidder’s required Bid security shall be the agreed and presumed amount of Port’s damages.

a. Upon such failure to timely deliver all required Contract Documents as set forth in Paragraph 21 through Paragraph 21.8 of this Document 00200, Port may determine the next Apparent Low Bidder and proceed accordingly. Such Award, if made, will be made within the time described in paragraph 19 above.

23. MODIFICATION OF COMMENCEMENT OF WORK: Port expressly reserves the right to modify the date for the Commencement of Work under the Contract and to independently perform and complete work related to the Project. Port accepts no responsibility to Contractor for any delays attributed to its need to complete independent work at the Site.

24. CONFORMED PROJECT MANUAL: Following Award of Contract, Port may prepare a conformed Project

Manual reflecting Addenda issued during bidding, which will, failing objection, constitute the approved Project Manual.

25. INELIGIBLE CONTRACTORS AND SUBCONTRACTORS: Port shall not accept a Bid from a Bidder who is ineligible to bid or work on, or be awarded, a public works project pursuant to California Labor Code section 1777.1 or 1777.7. Bidders and the Contractor who is awarded the project contract shall not utilize, or allow work by, any subcontractor who is ineligible to bid or work on, or be awarded, a public works project pursuant to California Labor Code Section 1777.1 or 1777.7. (See California Public Contract Code Section 6109.) The California Division of Labor Standards Enforcement publishes a list of debarred contractors and subcontractors on the Internet at https://www.dir.ca.gov/DLSE/debar.html. Federal government listings are located at https://www.sam.gov/SAM/.

26. DEFINITIONS: All abbreviations and definitions of terms used in this Document 00200 are set forth in

Document 00700 (General Conditions) and Section 01420 (References and Definitions).

Stockton Port District Geotechnical Data and Existing Conditions

00320- 1

DOCUMENT 00320

GEOTECHNICAL DATA AND EXISTING CONDITIONS

1. REPORT AND INFORMATION

1.1 Existence of Reports: The Port, its consultants, and prior contractors may have collected documents providing a general description of the Site and conditions of the Work. These documents may consist of geotechnical reports for and around the Site, contracts, contract specifications, tenant improvement contracts, as-built drawings, utility drawings, and information regarding Underground Facilities. These reports, documents and other information are not part of the Contract Documents.

1.2 Inspection of Reports: Bidders may inspect geotechnical reports and information regarding existing conditions at the Site. These documents are available for review at the Port located at 315 Fyffe Avenue, Stockton, California 95203 and copies may be obtained for the cost of reproduction and handling upon Bidder’s payment for the costs. These reports, documents and other information are not part of the Contract Documents. Nevertheless, by submitting a Bid, Bidder accepts full responsibility for reviewing, knowing and understanding the contents of all of these materials.

1.3 Inclusion in Project Manual: Geotechnical reports may be included in the Project Manual and information regarding existing conditions may also be included in the Project Manual, but neither shall be considered part of the Contract Documents.

1.4 Alternative Documentation Location: Documentation for this project referred to at paragraph

1.2 above is also available for review at the following website:

http://geotracker.waterboards.ca.gov/

2. USE OF INFORMATION ON EXISTING CONDITIONS

2.1 Aboveground Existing Conditions: Under no circumstances shall Port be deemed to make a warranty or representation of existing aboveground conditions, as-built conditions, or other aboveground actual conditions verifiable by reasonable independent investigation. These conditions are verifiable by Bidder by the performance of its own independent investigation that Bidder must perform prior to bidding and Bidder must not rely on the information supplied by Port regarding existing conditions. Bidder represents and agrees that in submitting its Bid, it is not relying on any information regarding existing conditions supplied by Port.

2.2 Underground Facilities: Information supplied regarding existing Underground Facilities at or contiguous to the Site is based on information furnished to Port by others (e.g., the builders of such Underground Facilities or others). Except as expressly set forth in this Document 00320, Port does not assume responsibility for the accuracy, completeness or thoroughness of this information, and Bidder is solely responsible for any interpretation or conclusion drawn from this information. Except as expressly set forth in this Document 00320, Port will be responsible only for the general accuracy of information regarding Underground Facilities, and only for those Underground Facilities that are owned by Port. This express assumption of responsibility applies only if Bidder has conducted the independent investigation required of it and discrepancies were not apparent.

3. LIMITED RELIANCE PERMITTED ON CERTAIN GEOTECHNICAL INFORMATION

3.1 Geotechnical Data: Except as expressly set forth in this Document 00320, Port does not warrant, and makes no representation regarding, the accuracy or thoroughness of any geotechnical data.

Bidder represents and agrees that in submitting its Bid, it is not relying on any geotechnical data supplied by Port, except as specifically set forth herein.

Stockton Port District Geotechnical Data and Existing Conditions

00320- 2

A. Bidder may rely upon the general accuracy of the “technical data” contained in the geotechnical reports and drawings identified above, but only insofar as it relates to subsurface conditions, provided Bidder has conducted the independent investigation required of it and discrepancies were not apparent. The term “technical data” in the referenced reports and drawings shall be limited as follows:

1. The term “technical data” shall include actual reported depths, reported quantities, reported soil types, reported soil conditions, and reported material, equipment, or structures that were encountered during subsurface exploration.

2. The term “technical data” does not include, and Bidder may not rely upon, any other data, interpretations, opinions or information shown or indicated in such drawings or reports that otherwise relate to subsurface conditions or described structures.

3. The term “technical data” shall not include the location of Underground Facilities.

4. Bidder may not rely on the completeness of reports and drawings for the purposes of bidding or construction. Bidder may rely upon the general accuracy of the “technical data” contained in such reports or drawings.

5. Bidder is solely responsible for any interpretation or conclusion drawn from any “technical data” or any other data, interpretations, opinions, or information contained in supplied geotechnical data.

4. INVESTIGATIONS

4.1 Before submitting a Bid, each Bidder shall be responsible to obtain such additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Site or otherwise, which may affect cost, progress, performance or furnishing of Work or which relate to any aspect of the means, methods, techniques, sequences or procedures of construction to be employed by Bidder and safety precautions and programs incident thereto or which Bidder deems necessary to determine its Bid for performing and furnishing the Work in accordance with the time, price and other terms and conditions of Contract Documents. Bidders shall advise Port in writing during the Bid period of any questions, suppositions, inferences or deductions Bidders may have for Port’s review and response.

4.2 Port has provided time in the period prior to bidding for Bidder to perform these investigations.

5. ACCESS TO SITE FOR INVESTIGATIONS

5.1 During the Pre-Bid Site Visit(s), Port will provide each Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies, as each Bidder deems necessary for submission of a Bid. Bidders must fill all holes and clean up and restore the Site to its former conditions upon completion of such explorations, investigations, tests, and studies. Such investigations may be performed only under the provisions of Document 00200 (Instructions to Bidders) and Document 00700 (General Conditions) including, but not limited to, proof of insurance and obligation to indemnify against claims arising from such investigation work. Each Bidder shall supply all equipment required to perform any investigations as each Bidder deems necessary. Port has the right to limit the number of pieces of machinery operating at one time due to safety concerns.

Stockton Port District Building 315 Renovation 00335 - 1 Hazardous Materials Survey

SECTION 00335 - HAZARDOUS MATERIALS SURVEY

1. SUMMARY

1.1 This Document 00335 describes hazardous material surveys included with the Contract Documents and use of data therein.

2 REPORTS AND INFORMATION

2.1 The Stockton Port District, its consultants, contractors and tenants have prepared documents providing a general description of the Site and locations of hazardous materials subject of the Work. These documents are made available for review and copying. The documents are the following:

2.1.1 No known hazardous materials are present in the area of the proposed improvements.

2.2 Bidders may inspect such documents at Port’s offices, and copies may be obtained at cost of reproduction and handling upon Bidder’s payment for the costs. These documents are not part of the Contract Documents.

3. USE OF DATA AND INFORMATION

3.1 Data and information regarding the locations of hazardous materials are not part of Contract Documents.

Bidders may rely on this data and information for general accuracy regarding the locations of potentially hazardous materials subject of the Work.

3.2 The Port does not warrant and makes no representation regarding the completeness or thoroughness of any data or information regarding existing conditions or hazardous materials, including, but not limited to, quantities, characteristics, volumes, or associated structural features. Bidder represents and agrees that in submitting a Bid it is not relying on any such data, information or deductions.

4. INVESTIGATIONS

4.1 See Document 00320 (Geotechnical Data and Existing Conditions) regarding access to the Site for investigation. Additionally, any investigation performed by Bidder to verify hazardous materials/waste conditions must comply with the provisions of Document 00700 (General Conditions), including but not limited to the requirements regarding compliance with all laws, permits, giving of all notices, and indemnification. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests and studies.

Bidders shall also present proof of any additionally required insurance satisfactory to Port.

END OF DOCUMENT 00335

Building 315 Renovation Bid Form

00400-1

DOCUMENT 00400

BID FORM

TO THE STOCKTON PORT DISTRICT

THIS BID IS SUBMITTED BY:

(Firm/Company Name)

Re: STOCKTON PORT DISTRICT, BUILDING 315 RENOVATION – Project No. 210007

1. The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an agreement with the

Stockton Port District, (“Port”) in the form included in the Contract Documents, Document 00520 (Agreement), to perform and furnish all Work as specified or indicated in the Contract Documents for the Contract Sum and within the Contract Time indicated in this Bid and in accordance with all other terms and conditions of the Contract Documents.

2. Bidder accepts all of the terms and conditions of the Contract Documents, Document 00100

(Advertisement for Bids), and Document 00200 (Instructions to Bidders), including, without limitation, those dealing with the disposition of Bid Security. This Bid will remain subject to acceptance for 90 Days after the day of Bid opening.

3. In submitting this Bid, Bidder represents:

(a) Bidder has examined all of the Contract Documents and the following Addenda (receipt of all of which is hereby acknowledged).

Addendum Number Addendum Date Signature of Bidder

(b) Bidder acknowledges receipt of Pre-Bid Conference minutes, if any.

(c) Bidder has visited the Site and performed all tasks, research, investigation, reviews, examinations, and analysis and given notices, regarding the Project and the Site, as set forth in Document 00520 (Agreement), Article 5.

(d) Bidder has given Port prompt written notice of all conflicts, errors, ambiguities, or discrepancies that it has discovered in or among the Contract Documents and as-built drawings and actual conditions and the written resolution thereof through Addenda issued by Port is acceptable to Contractor.

Based on the foregoing, Bidder proposes and agrees to fully perform the Work within the time stated and in strict accordance with the Contract Documents for the: Total Bid Amount stated below:

00400-2

SCHEDULE OF VALUES

Bidder shall submit with the Bidders Bid a complete Preliminary Schedule of Values allocating the Total Base Bid Amount and separate Optional Bid Items amount among the various portions of the Work. The Schedule of Values shall provide sufficient detail to identify major trades, systems, materials, equipment, General Conditions, overhead and profit, and other significant components of the Work. The sum of all items in the Schedule of Values shall equal the Total Bid Amount.

TOTAL BASE BID AMOUNT: $________________________

OPTIONAL BID ITEMS:

OPTIONAL ITEM DESCRIPTION PRICE EACH ITEM TOTAL

Replacement of existing Air Conditioning (AC) units shown in Mechanical Drawings Sheets DM3.1 and M3.1 $ $

4. The Apparent Low Bidder will be the responsive and responsible Bidder submitting the lowest Total Base Bid Amount.

5. Subcontractors performing Work under this Contract are listed on the attached Document 00430 (Subcontractors List).

6. The undersigned Bidder understands that Port reserves the right to reject this Bid.

7. If written notice of the acceptance of this Bid, hereinafter referred to as Notice of Award, is mailed or delivered to the undersigned Bidder within the time described in Paragraph 2 of this Document 00400 or at any other time thereafter before it is withdrawn, the undersigned Bidder will execute and deliver the documents required by Document 00200 (Instructions to Bidders) within the times specified therein.

These documents include, but are not limited to, Document 00520 (Agreement), Document 00610

Total BASE BID Amount in Words:

(Words)

This amount shall constitute full compensation for furnishing all labor, materials, apparatus, facilities, transportation, tools, equipment, bonds and insurance for performance of all the work contemplated and embraced in this contract, and for all risks of every description connected with the work, and for well and faithful completion of the work and the whole thereof in the manner and according to the Contract Documents and the requirements of designated Port Project representative.

Discrepancies between the words and numbers will be resolved in favor of the words.

Total OPTIONAL BID ITEMS Amount in Words:

(Words)

00400-3

(Construction Performance Bond), and Document 00620 (Construction Labor and Material Payment Bond) and Insurance.

8. Notice of Award or request for additional information may be addressed to the undersigned Bidder at the address set forth below.

9. The undersigned Bidder herewith encloses cash, a cashier’s check, or certified check of or on a responsible bank in the United States, or a corporate surety bond furnished by a surety authorized to do a surety business in the State of California, in form specified in Document 00200 (Instructions to Bidders), in the amount of ten percent (10%) of the Total Bid Price and made payable to “Stockton Port District.”

10. The undersigned Bidder agrees to commence Work under the Contract Documents on the date established in Document 00700 (General Conditions) and to complete all Work within the time specified in Document 00520 (Agreement). The undersigned Bidder acknowledges that Port has reserved the right to delay or modify the commencement date. The undersigned Bidder further acknowledges Port has reserved the right to perform independent work at the Site, the extent of such work may not be determined until after the opening of the Bids, and that the undersigned Bidder will be required to cooperate with such other work in accordance with the requirements of the Contract Documents.

11. The undersigned Bidder agrees that, in accordance with Document 00700 (General Conditions), liquidated damages for failure to complete all Work in the Contract within the time specified in Document 00520 (Agreement) shall be as set forth in Document 00520 (Agreement).

12. The names of all persons interested in the foregoing Bid as principals are:

IMPORTANT NOTICE: If Bidder or other interested person is a corporation, give the legal name of corporation, state where incorporated, and names of president and secretary thereof; if a partnership, give name of the firm and names of all individual co- partners composing the firm; if Bidder or other interested person is an individual, give first and last names in full.

NAME OF BIDDER:

Licensed in accordance with an act for the registration of Contractors, and with license number:

Expiration:

(Place of Incorporation, if Applicable) (Principal)

(Principal)

I certify (or declare) under penalty of perjury under the laws of the State of California that the foregoing is true and correct.

x (Signature of Bidder)

NOTE: If Bidder is a corporation, set forth the legal name of the corporation together with the signature of the officer or officers authorized to sign contracts on behalf of the corporation. If Bidder is a partnership, set forth the name of the firm together with the signature of the partner or partners authorized to sign contracts on behalf of the partnership.

Business Address: ________________________________________

Contractor’s Representative(s): ________________________________________ (Name / Title)

00400-4

Officers Authorized to Sign Contracts: _________________________________________ (Name/Title)

Telephone Number(s): _________________________________________ (Area Code) (Number)

Contact Email address: _________________________________________ (Email)

Date of Bid: _________________________________________ (Date)

Stockton Port District Bond Accompanying Bid Building 315 Renovation

00411- 1

DOCUMENT 00411

BOND ACCOMPANYING BID

KNOW ALL BY THESE PRESENTS:

That the undersigned ___________________________________________________________________ , (Name of Contractor) as Principal and the undersigned as Surety are held and firmly bound unto the Stockton Port District, (“Port”), as obligee, in the penal sum of _______________________________________ Dollars ($______________) lawful money of the United States of America being at least ten percent (10%) of the aggregate amount of said Principal ____________________________________________________________’s base Bid, for the payment of which, well and truly to be made, we bind ourselves, our successors, executors, administrators, and assigns, jointly and severally, firmly by these presents.

WHEREAS, the said Principal is submitting a Bid for Port Project Number 210007, BUILDING 315

ADMINISTRATION OFFICES RENOVATION.

THE CONDITION OF THIS OBLIGATION IS SUCH that if the Bid submitted by the said Principal be accepted and the Contract be awarded to said Principal and said Principal shall within the required periods enter into the Contract so awarded and provide the required Construction Performance Bond, Construction Labor and Material Payment Bond, insurance certificates, and all other endorsements, forms, and documents required under Document 00200 (Instructions to Bidders), then this obligation shall be void, otherwise to remain in full force and effect.

IN WITNESS WHEREOF, the above bounden parties have executed this instrument this ______ day of (Month) (Year)

(Corporate Seal) By _______________________________________________

Principal

By _______________________________________________ Surety

(Corporate Seal) By _______________________________________________

Attorney in Fact

Stockton Port District Bidder Registration Form

DOCUMENT 00420

BIDDER…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .