About this file
This is a Bid Form Template document from the City of Scranton, Pennsylvania, for an as-needed requirements contract related to electrical services. The bid form requests pricing for multiple labor categories including Electrician Foreman, Journeyperson, and Apprentice positions across different shifts and schedules (weekday daytime hours, Saturday/outside hours, and Sunday/Federal holidays), as well as equipment rentals for service vans, bucket trucks, and line crew foreman services. The contract is structured on an as-needed basis with no guaranteed minimum hours or work volume, and the estimated annual hours for each category are provided as reference points only. Bidders must submit complete pricing for all line items in the form to be considered responsive.
All hourly rates must be inclusive of overhead and profit, with bidders explicitly prohibited from including charges for field supervision, supplemental benefits, emergency service overhead, or material costs in their hourly rates. The bid total represents the sum of all extended prices calculated by multiplying the proposed hourly rates by the estimated annual hours for each category. This pricing structure ensures transparency and allows the City of Scranton to evaluate bids on a standardized basis while maintaining flexibility to utilize services only as operational needs dictate throughout the contract period.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID FORM
[TITLE OF PROCUREMENT]
BIDDER: _____________________________________________
| Description |
| Hourly Rate |
Estimated # Hours Per Year
Extended Price
Electrician Foreman – 7am-3:30pm Weekdays
| x |
| 500 |
| = |
| 1. $ |
Electrician Journeyperson– 7am-3:30pm Weekdays
| x |
| 400 |
| = |
| 2. $ |
Electrician Apprentice– 7am-3:30pm Weekdays
| x |
| 250 |
| = |
| 3. $ |
Foreman– Saturdays and Outside Hours on Weekdays
| x |
| 250 |
| = |
| 4. $ |
Journeyperson– Saturdays and Outside Hours on Weekdays
| x |
| 200 |
| = |
| 5. $ |
Apprentice– Saturdays and Outside Hours on Weekdays
| x |
| 80 |
| = |
| 6. $ |
Foreman– Sundays and Federal Holidays
| x |
| 70 |
| = |
| 7. $ |
Journeyperson– Sundays and Federal Holidays
| x |
| 60 |
| = |
| 8. $ |
Apprentice– Sundays and Federal Holidays
| x |
| 60 |
| = |
| 9. $ |
Service Van
| x |
| 450 |
| = |
| 10. $ |
Bucket Truck
| x |
| 350 |
| = |
| 11. $ |
Line crew Foreman
| x |
| 200 |
| = |
| 12. $ |
| BID TOTAL |
| = |
| $ |
· This is a requirements contract for work on an as-needed basis.
· The City does not guarantee that any number of hours or that the estimated number of hours will be needed.
· Bidder shall provide figures for all spaces.
· Bidder shall not include charges for field supervision into the hourly rate.
· Bidder shall not charge City for additional supplemental benefits or overhead for Emergency Services.
· Bidder shall not include material costs in the hourly rate.
· All hourly rates shall be inclusive of overhead and profit.
| Signature: __________________________________________ | Date: ________________ |
| Name: ___________________________ | Title: ____________________ |
File details come from the government source that posted it. Updated .