Bid Documents_Yampa River State Park Seasonal Housing-RV_IFB1_2027-047.pdf
PDF 8 MB Posted
- Solicitation number
- IFB1 PMAA 2027000047 1
- Issued by
- Mesa County, Colorado
About this file
This Invitation for Bid (IFB) document is issued by the Colorado Division of Parks and Wildlife under the Department of Natural Resources for the construction of seasonal housing RV sites at Yampa River State Park in Routt County, Colorado. The project involves construction of four full hookup spur RV sites with associated earthwork and utilities infrastructure. The scope of work includes site grading, earthwork, utility installation (electrical, water, sewer, and drainage), erosion control, clearing and grubbing, and site restoration. Sealed bids are due November 25, 2026 at 12:00 PM at Yampa River State Park Headquarters, with a non-mandatory pre-bid conference scheduled for November 4, 2026 at 12:00 PM. The Notice of Intent to Award is tentatively scheduled for December 2, 2026, with a Notice to Proceed anticipated January 1, 2027 and substantial completion required by May 30, 2027 (120 calendar days from Notice to Proceed). The project includes 19 bid items encompassing mobilization, erosion control, clearing, grading, imported fill, aggregate base course, electrical service, water and sewer infrastructure, lift station installation, culvert work, reseeding, and optional concrete and equipment rental items.
Payment will be made according to unit prices specified in the Bid Schedule on a lump sum or per-ton basis depending on the line item. A 5% bid bond, certified check, or cashier's check is required for bids of $50,000 or more. Performance and Labor and Material Bonds at 100% of contract price are required for contracts exceeding $150,000. The project exceeds $500,000, triggering requirements for Colorado resident bidder preference, 80% Colorado labor utilization (with written justification if not met), prevailing wage compliance under Colorado law (not Davis-Bacon), and final reporting on iron and steel content of manufactured goods. Liquidated damages are set at $267.58 per day for failure to complete within contract time. Contractors must obtain all required permits including State Electrical and Plumbing permits and a Routt County Septic permit as part of mobilization. The project is not federally funded and will be financed through state appropriations. Contractors must carry comprehensive insurance including Workers' Compensation, Commercial General Liability ($1,000,000 minimum), Automobile Liability ($1,000,000), Builder's Risk (project value), and Pollution Liability ($1,000,000), with the State named as additional insured.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Yampa River State Park - Seasonal Housing RV Sites
BIDDING AND CONTRACT INFORMATION
PROJECT NO. C25YA1
IFB1: 2027*047
NON-MANDATORY PRE-BID CONFERENCE: November 4, 2026 at 12:00pm
BID OPENING: November 25, 2026 at 12:00pm
TABLE OF CONTENTS
C25YA1
PART 1 - BIDDING AND CONTRACT INFORMATION
INVITATION FOR BID
BID SCHEDULE
MEASUREMENT AND PAYMENT
INSTRUCTIONS TO BIDDERS
PART 2 - SPECIFICATIONS
PART 3 - CONSTRUCTION DRAWINGS
PART 4 - APPENDICES
APPENDIX A .................................... PREVIOUS SUBSOIL AND FOUNDATION INVESTIGATION
APPENDIX B ................................................ STATE PREVAILING WAGE DETERMINATIONS
APPENDIX C ..................................... GENERAL CONDITIONS FOR CAPITAL CONSTRUCTION
APPENDIX D .......................................................... SAMPLE CONSTRUCTION CONTRACT
APPENDIX E .............................................................. PERFORMANCE BOND TEMPLATE
APPENDIX F ..................................................... LABOR AND MATERIAL BOND TEMPLATE
END OF TABLE OF CONTENTS
Bidding and Contract Information Page 1 of 18 C25YA1
INVITATION FOR BIDS
The Colorado Division of Parks and Wildlife is accepting sealed bids for the construction of four full hookup spur RV sites along with associated earthwork and utilities.
Sealed bids will be received by Colorado Parks and Wildlife, Yampa River State Park Headquarters, 6185 US-40, Hayden, CO 81639 until November 25, 2026 at 12:00pm, after which the bids will be made public. Bids shall be submitted using the form provided in the project specifications. Online bid submittals are not accepted.
A five-percent (5%) Bid Bond, certified check, or cashier’s check is required with bid proposals of $50,000.00 or more.
Non-Mandatory Pre-bid conference: November 4, 2026 at 12:00pm at the project site.
Project Address: Yampa River State Park
6185 US-40
Hayden, CO 81639 Routt County
Project Coordinates: Latitude: 40°29'29" N Longitude: 107°18'26" W
VIEW GOOGLE MAP LOCATION
Contractor Questions: All questions related to the project shall be submitted via e-mail to the Design Engineer, Hans Nielsen at hans.nielsen@state.co.us. The deadline for questions is November 11, 2026 at 12:00pm. Questions submitted after the deadline will not be addressed.
All questions and answers will be posted as solicitation amendments on the Vendor Self Service (VSS) website. Bidders may not automatically be notified of the existence of a modification or addendum. It is the responsibility of the bidder to check the VSS website periodically to see if any modifications have been issued. Failure to retrieve such modifications and include their provisions in your bid response may result in your bid being deemed non-responsive.
Plans and specifications are available for all bidders on the web at: www.colorado.gov/vss
The following is a tentative project schedule, which will be revised and expanded by the selected Contractor and submitted to the Project Manager for review:
NON-MANDATORY PRE-BID CONFERENCE November 4, 2026 at 12:00pm WRITTEN QUESTIONS DUE November 11, 2026 at 12:00pm BID OPENING November 25, 2026 at 12:00pm NOTICE OF INTENT TO AWARD December 2, 2026 (Tentative) NOTICE TO PROCEED January 1, 2027 (Tentative) SUBSTANTIAL COMPLETION May 30, 2027 (Tentative) https://maps.app.goo.gl/KxZQ8mrfWdCAvqYE6 mailto:hans.nielsen@state.co.us http://www.colorado.gov/vss
Bidding and Contract Information Page 2 of 18 C25YA1
BID SCHEDULE
DEPARTMENT OF NATURAL RESOURCES
COLORADO PARKS AND WILDLIFE
STATE OF COLORADO
Proposes to furnish all labor, equipment, materials, and incidentals needed to complete the Yampa River State Park - Seasonal Housing RV Sites. The work shall be completed in 120 calendar days from the date of the Notice to Proceed. We have read and made, the “Instructions to Bidders”, the “General Conditions for Capital Construction”, the Written Specifications, and the Construction Drawings part of this bid.
Technical Specifications related to construction materials and methods for work embraced under this Contract shall consist of references to, but not limited to, the Colorado Department of Transportation Most Current Standard Specifications for Roads and Bridge Construction.
Special attention should be given to these references and revisions noted within.
UNITS: ALLOW= allowance, CY= cubic yards, HRS= hours, LF= linear feet LS= lump sum, TON= tons
Service Disabled Veteran Owned Small Business Statement (SDVOSB): The undersigned bidder shall certify by checking below that the corporation, partnership, or sole proprietorship IS or IS NOT claiming a 5% bid preference in accordance with C.R.S. 24-103-211. SDVOSB certification must be included with your bid.
Is: Is Not:
Colorado Labor: The undersigned bidder shall certify by indicating the percentage of Colorado labor of the total workforce to be utilized for this project in accordance with C.R.S. 8-17-101.
Colorado Labor shall be employed to perform at least 80% of the work on a public works project greater that $500,000.00. A written justification for not meeting this percentage must be included with your bid.
% of Colorado Labor: ___________
Addendum Inclusion Statement: The undersigned bidder shall certify by listing below that all Addendums have been considered and included as part of the Contractor’s proposal. The Addendum numbers that the Contractor has included as part of his proposal shall be listed in the space provided.
Addendums: Initials:
Bidding and Contract Information Page 3 of 18 C25YA1
Bidding and Contract Information Page 4 of 18 C25YA1
Bidding and Contract Information Page 5 of 18 C25YA1
(A Corporate Signature Block)
Company Name
A Corporation
Date , 20
Colorado VSS Vendor ID# (if available) _____________________________________
By President Attested to by Secretary
(A Partnership Signature Block)
A limited partnership of , general partner;
doing business as (dba)
Company Name
Colorado VSS Vendor ID# (if available) _____________________________________ by General Partner
(A Sole Proprietorship Signature Block)
A Sole Proprietorship of (dba)
Colorado VSS Vendor ID# (if available) _____________________________________ by Owner
Bidding and Contract Information Page 6 of 18 C25YA1
MEASUREMENT AND PAYMENT
The following descriptions delineate the Work, materials, and how measurements of completed Work will be made and paid for, for each bid item in the Bid Schedule. The Bidder is to read these definitions and price their proposal accordingly.
Bid Item 1 – Mobilization Measurement and payment for mobilization will be in accordance with SECTION 02050 –
MOBILIZATION.
Bid Item 2 – Erosion and Sediment Control This bid item includes all labor, materials, equipment, and incidental costs associated with erosion and sediment control in accordance with these bid documents. This includes but is not limited to: the furnishing, placement and maintenance of erosion and sediment control devices, such as erosion control logs, concrete washout areas, vehicle tracking control, turf protection mats, and sediment removal from paved areas. Payment will be made at the lump sum bid price as noted in the Bid Schedule.
Bid Item 3 – Clearing, Grubbing, and Tree Removal This bid item includes all labor, materials, equipment, and incidental costs required to perform earthwork in accordance with these bid documents. This includes but is not limited to: any costs for the removal and disposal off site of trees, shrubs, brush, other wood vegetation and other objects that occur within the construction area. Individual items shall not be measured separately but shall be included in the total unit cost. Payment will be made at the lump sum bid price as reported on the Bid Schedule.
Bid Item 4 – Site Grading and Earthwork This bid item includes all labor, materials, equipment, independent testing services, and incidental costs required to perform earthwork in accordance with these bid documents. This includes but is not limited to: any costs for preparatory earthwork, clearing and grubbing, access road scarification, excavation, backfill, compaction, soil testing, and finish grading.
Individual items shall not be measured separately but shall be included in the total unit cost.
Payment will be made at the lump sum bid price as reported on the Bid Schedule.
Bid Item 5 – Imported Fill Material This bid item includes all labor, materials, equipment, independent testing services, and incidental costs required to furnish and place imported fill material at the locations indicated in the drawings in accordance with these bid documents. Imported fill shall be placed at optimum moisture content and compacted according to the specifications. The method to bring mixture to optimum moisture and density will not be measured or paid for separately, but shall be included in the unit price for this item. Measurement for this item will be according to load tickets delivered to the site and paid at the unit price per ton as reported on the Bid Schedule.
The load tickets shall be submitted by the Contractor with the pay application.
Bid Item 6 – Pit Run #1 This bid item includes all labor, materials, equipment, independent testing services, and incidental costs required to furnish and place Pit Run #1 material at the locations indicated in the drawings in accordance with these bid documents. Pit Run #1 shall be placed at optimum moisture content and compacted according to the specifications. The method to bring mixture to optimum moisture and density will not be measured or paid for separately, but shall be included in the unit price for this item. Measurement for this item will be according to load tickets delivered to the site, and paid at the unit price per ton as reported on the Bid Schedule.
The load tickets shall be submitted by the Contractor with the pay application.
Bidding and Contract Information Page 7 of 18 C25YA1
Bid Item 7 – Compacted Class 6 A.B.C.
This bid item includes all labor, materials, equipment, independent testing services, and incidental costs required to furnish and place CDOT Class 6 Aggregate Base Course (ABC) at the locations indicated in the drawings in accordance with these bid documents. This bid item does not include the High Use Pads (HUP). ABC shall be placed at optimum moisture content and compacted according to the specifications. The method to bring mixture to optimum moisture and density will not be measured or paid for separately but shall be included in the unit price for this item. Measurement for this item will be according to load tickets delivered to the site, and paid at the unit price per ton as reported on the Bid Schedule. The load tickets shall be submitted by the Contractor with the pay application.
Bid Item 8 – Compacted Class 6 A.B.C. for HUP This bid item includes all labor, materials, equipment, independent testing services, and incidental costs required to furnish and place CDOT Class 6 Aggregate Base Course (ABC) for the four High Use Pads (HUP) at the locations indicated in the drawings in accordance with these bid documents. ABC shall be placed at optimum moisture content and compacted according to the specifications. The method to bring mixture to optimum moisture and density will not be measured or paid for separately but shall be included in the unit price for this item.
Measurement for this item will be according to load tickets delivered to the site, and paid at the unit price per ton as reported on the Bid Schedule. The load tickets shall be submitted by the Contractor with the pay application.
Bid Item 9 – Electrical Service This bid item includes all labor, materials, equipment and incidental costs required to bring power from the transformer to the campsites and lift station and including but not limited to electrical pedestals in accordance with these bid documents. This also includes obtaining an Electrical Permit including all additional drawings and documentation as may be required. This item includes but is not limited to: service panels, transformer upgrades, C.T. cabinet, meter socket, disconnect panels, overhead wiring, ties, system grounding, connection testing and any other cost associated with the complete electrical system installation up to and including the service panel. Payment will be made at the lump sum price as reported on the Bid Schedule.
Bid Items 10-11 – HDPE Water Service This bid item includes all labor, materials, equipment, and incidental costs associated with the potable water supply installation to the seasonal housing unit in accordance with these bid documents. This includes but is not limited to: pipe, trenching, placement of pipe, backfill, connections, fittings, valves, pressure testing, sanitization and all other supplies necessary for the complete system installation. Individual items shall not be measured separately but shall be included in the total unit cost. Payment will be made according to the length of pipe placed and paid at the unit price per linear foot as reported on the Bid Schedule.
Bid Items 12 and 13 – PVC Sanitary Sewer and HDPE Force Main This bid item includes all labor, materials, equipment, and incidental costs associated with the sanitary sewer line installation in accordance with these bid documents. This includes but is not limited to: pipe, trenching, placement of pipe, backfill, connections, fittings, cleanouts, insulation and all other supplies necessary for the complete system installation. Individual items shall not be measured separately but shall be included in the total unit cost. Payment will be made according to the length of pipe placed and paid at the unit price per linear foot as reported on the Bid Schedule.
Bid Item 14 – Manhole with Lift Station Pump This bid item includes all labor, materials, equipment and incidental costs associated with the manhole with lift station pump installation in accordance with these bid documents. This includes but is not limited to: excavation, precast concrete manhole with cover, centrifugal
Bidding and Contract Information Page 8 of 18 C25YA1 grinder pump lift station, connecting hardware, electrical controls, backfill, system testing, and all additional accessories and supplies necessary for the complete system installation.
Individual items shall not be measured separately but shall be included in the total unit cost.
Payment will be made at the lump sum bid price as reported on the Bid Schedule.
Bid Item 15 – 18” HDPE Culvert with Riprap Outlet This bid item includes all labor, materials, equipment and incidental costs associated with the HDPE culvert with riprap outlet installation in accordance with these bid documents. This includes but is not limited to: excavation, placement of HDPE with flared end sections, furnishing and placement of riprap, backfill and compaction. Individual items shall not be measured separately but shall be included in the total unit cost. Payment will be made according to the length of pipe placed and paid at the unit price per linear foot as reported on the Bid Schedule.
Bid Item 16 – Site Restoration and Reseeding This bid item includes all labor, materials, equipment, and incidental costs required to restore the site to preconstruction conditions in accordance with these bid documents. This pay item includes but is not limited to: removal of all construction debris and materials, final grading, placement of reserved topsoil, and reseeding. Payment will be made at the lump sum bid price as reported on the Bid Schedule.
The following bid items are to be completed by the bidder and are alternate items which are NOT to be included in the Base Bid. They may be substituted for the appropriate base bid item and added to the contract to arrive at the selection of the lowest responsible bidder.
Alternate Bid Item Item 17 – Concrete at HUP This bid item includes all labor, materials, equipment, independent testing services, and incidental costs required to furnish and place 6” of concrete over 4” of CDOT Class 6 Aggregate Base Course (ABC) for the four High Use Pads (HUP) at the locations indicated in the drawings in accordance with these bid documents. ABC shall be placed at optimum moisture content and compacted according to the specifications. The method to bring mixture to optimum moisture and density will not be measured or paid for separately but shall be included in the unit price for this item. This includes but is not limited to: formwork, aggregate base course, reinforcement, concrete placement, finishing, control joint installation, and all other supplies necessary for the complete installation. Individual items shall not be measured separately but shall be included in the total unit cost. If selected, quantities will be measured according to the area of concrete placed, and paid at the unit price per cubic yard as reported on the Bid Schedule.
The following bid items are to be completed by the bidder and are additional items which are NOT to be included in the Base Bid. They may be added to the contract to arrive at the selection of the lowest responsible bidder.
Optional Bid Items 18-19: Time & Equipment These bid items will only apply to additional construction requests by the Project Manager that are not included in other bid items. Payment will be made at the Contract unit price for the number of hours operated or worked and includes operator, fuel, labor, tools and all support necessary for operation. A total of two hours for mobilization/demobilization will be paid on each piece of equipment requested not already located at the job site. The number of hours
Bidding and Contract Information Page 9 of 18 C25YA1 to be paid under these items will be discussed and agreed to in advance by the Contractor and the Project Manager. Bid Item pricing shall be based on the following types of equipment:
Bid Item 18: Mini Excavator – Cat 305 series or equivalent Bid Item 19: General Laborer
As a footnote to the bid items, the following items have NOT been included as specific pay items and ARE to be considered incidental to the construction for which they are required:
• Testing
• Water, watering, and dust control
• Temporary facilities and utilities
• Traffic control
• Barricades and other required safety provisions
This concludes the bid items listed in the proposal. The only payments made under this contract are for the bid items listed herein, and no additional payments will be made to the Contractor for work specified or shown in these Contract Documents. If any discrepancies exist, the Contractor shall notify the Project Manager in writing, requesting clarification.
END OF SECTION
Bidding and Contract Information Page 10 of 18 C25YA1
INSTRUCTIONS TO BIDDERS
PROJECT: Yampa River State Park - Seasonal Housing RV Sites
PROJECT NO: C25YA1
1. Bidders must review the plans and specifications, construction site and conditions in their entirety, and determine the problems that may be encountered in performing the work.
The bidder shall include any costs associated with his/her findings in the prices quoted in the proposal. Documents will be available on the State of Colorado VSS website www.colorado.gov/vss. No additional copies of the drawings and specifications will be provided by the Division of Parks and Wildlife at any time before or after the bid opening.
2. All work must conform to the requirements stated in the “General Conditions for Capital Construction”.
3. All questions concerning this project shall be in writing directed to the Design Engineer identified in the Invitation for Bids. The Invitation for Bids also identifies important dates and deadlines for this project.
4. BID SCHEDULE:
A. The bidder shall include on the signature page, their Vendor ID (if available) obtained from registration on the Colorado VSS website.
B. The bidder shall complete the Minority Business, Service Disabled Veteran Owned Small Business and Colorado Labor statements as well as acknowledge addendum(s) on the first page of the Bid Schedule.
C. All bid items shall include a unit and extended price or the bid will be disqualified. The bidder shall write in words and numerically the total base bid and add/alternate (if applicable) amounts on the included Bid Schedule. If conflicts exist between the written words and the numerical amount, the actual line item unit cost shall take precedence.
D. The Bid Schedule shall be signed manually in ink:
1) If the bidder is a corporation, use the corporate signature block, insert the name of the state in which the company was incorporated, and include the Employer Identification Number (E.I.N.) in the appropriate spaces. The bid must be signed by an officer (President or Vice President), and the title indicated. The signature of the officer shall be attested to by the Secretary and properly sealed. Cross out incorrect titles and insert correct ones, if necessary.
2) If the bidder is a partnership, use the partnership signature block. Cross out the word "Limited" if the partnership is a general one. Print each partner's name and note the proportion of the partnership that each partner has. The majority or general partner must sign the proposal. The same person must sign the contract, if awarded. Print the company name in the appropriate space.
3) If the bidder is a proprietorship, use the sole proprietorship signature block, print in the owner's name, Social Security number, and the business name in the blanks provided, and the owner signs the owner blank.
5. BID BOND: A bid bond is required for all competitive sealed bids when the price exceeds
$50,000. A bid guarantee in an amount not less than five percent (5%) of the total bid price must be submitted in the form of a firm commitment, such as a bid bond, bank money order, certified check or cashier's check. Checks or money orders should be made payable to the Treasurer, State of Colorado. An irrevocable letter of credit is not acceptable as a bid guarantee. Failure to furnish a bid guarantee in the proper form and amount by the time
Bidding and Contract Information Page 11 of 18 C25YA1 set for opening of bids may be cause for rejection of the bid.
6. PERFORMANCE BOND, LABOR AND MATERIAL BOND: The successful bidder shall furnish a bond in the amount of 100% of the contract price for performance and for material and labor payment when bid is equal to or exceeds $150,000. The bond shall be executed on the standard State of Colorado form. The State requests that the Surety and Contractor leave the date of the Contract found on the first page of each bond form, blank and we will ‘pen’ in the date after the Controller executes the Contract. These bonds will be submitted along with the standard State Agreement form within 10 days of the "Notice of Award."
7. VENDOR BOND ASSISTANCE: Any vendors that need support responding to solicitations may contact the Colorado Supplier Diversity Navigator at the Statewide Equity Office of Supplier Diversity dhr.colorado.gov/statewide-equity-office/supplier-diversity. Services provided include assistance with responding to solicitations, interpretation of solicitation documents, technical assistance referrals, availability of resources, and bond assistance under the Construction Statewide Bond Assistance Program dhr.colorado.gov/statewide-equity-office/supplier-diversity/construction-and-bond-assistance , through which eligible contractors can apply for assistance in securing the required bonding. The office can be reached during normal business hours by calling 303-866-5765 or emailing DPA_SupplierDiversityHelp@state.co.us.
8. RESIDENT BIDDER PREFERENCE: When a contract for commodities or services is to be awarded to a bidder (projects >$500,000), a resident bidder shall be allowed a preference against a nonresident bidder equal to the preference given or required by the state in which the nonresident bidder is a resident. (§24-103-906 C.R.S.) A resident bidder is authorized to transact business in the State of Colorado, maintains a place of business in Colorado and pays unemployment compensation taxes.
9. SERVICE DISABLED VETERAN OWNED SMALL BUSINESSES (SDVOSB’s): SDVOSB’s, who are incorporated or organized in Colorado or maintain a place of business or have an office in Colorado and who are officially registered and verified as a SDVOSB by the Center for Veteran Enterprise within the U.S. Department of Veterans Affairs. (www.vip.vetbiz.gov), may receive a 5% preference on their bid. This preference applies only to the price, and the SDVOSB’s must still meet all other qualifications required in the bid. SDVOSB’s claiming this preference shall submit documentation of SDVOSB certification Issued through the U.S. Department of Veterans Affairs in their response to the solicitation. Bid submissions without this documentation will not be given a preference.
10. COLORADO LABOR: Colorado Labor shall be employed to perform at least eighty percent (80%) of the work on a public works project (>$500,000) per CRS 8-17-101. BIDS/CORE notice to require bidder to indicate 80% Colorado labor in bid or proposal and provide written justification if the 80% Colorado labor is not included in the bid. The justification is a requirement of the bid or proposal submittal. State Agency shall waive the 80% requirement and post justification on its web site; if there is reasonable evidence to demonstrate insufficient Colorado labor to perform the work and, if compliance with the 80% would create an undue burden that would substantially prevent a project from proceeding to completion.
Posting of the agency’s written waiver should include but not be limited to contractor’s justification for insufficient available Colorado labor and the agency’s determination that there is an undue burden negatively impacting the project schedule, budget/appropriation, quality/standards of care or any other specific requirement of the project due to compliance with the 80% Colorado labor requirement. The posting of rational should be made on the date of the award and remain for not less than thirty (30) calendar days in a conspicuous web site https://dhr.colorado.gov/statewide-equity-office/supplier-diversity https://dhr.colorado.gov/statewide-equity-office/supplier-diversity/construction-and-bond-assistance https://dhr.colorado.gov/statewide-equity-office/supplier-diversity/construction-and-bond-assistance mailto:DPA_SupplierDiversityHelp@state.co.us http://www.vip.vetbiz.gov/
Bidding and Contract Information Page 12 of 18 C25YA1 location of the state agency under the title – “Reporting Requirements for Public Projects as per HB13-1292”.
11. FINAL REPORTING FOR IRON, STEEL, OR RELATED MANUFACTURED ITEMS: This requirement only applies when a contract for a public works project is to be awarded to a bidder (projects >$500,000), for a project that does not receive any federal moneys. At the completion of the project, the Contractor shall provide an accounting of the value and origin of the five most costly manufactured goods incorporated into the project. For the purposes of this reporting, “manufactured goods” contain over fifty percent iron or steel content when it is delivered to the job site for installation. If all the manufacturing processes for the final product take place in the United States, the product shall be considered as originating there.
12. SUBMITTAL OF BID: The completed Bid must be received by the deadline identified in the
Invitation for Bids. You must include as part of your bid the following items:
A. Provide completed Bid Schedule as described above.
B. Provide Bid Bond (if required) as described above.
C. SDVOSB certification is issued through the U.S Department of Veterans Affairs (if applicable).
D. Colorado Labor Justification if not using 80% Colorado Labor (if applicable).
This information is to be enclosed in a sealed envelope marked "SEALED BID". Include the bid opening date and time.
The envelope shall be addressed to:
ATTN: Tyler Jacox Colorado Parks and Wildlife
Yampa River State Park
6185 US-40
Hayden, CO 81639
Bidders Name and Address should appear in the Upper Left Corner of the envelope.
13. METHOD OF AWARD: The lowest responsible bid, taking into account the Colorado resident bidder preference provision of Colorado Law, will be determined by and the purchase order or contract will be issued, to the extent that the total dollar amount is within available funds to finance the construction. If all bids exceed such amount, the right is reserved to reject all bids. The Division of Parks and Wildlife reserves the right to reject any or all proposals, to waive informalities, and to accept any proposal deemed desirable.
Additive alternates will be used in determining the lowest responsible bidder within the amount available to finance the contract, added in the numeric order listed. An equal number of alternates shall be added to the base bid of each bidder within funds available to finance the contract for purposes of determining the lowest responsible bidder.
The bidder must be registered to do business in the State of Colorado with the Secretary of State www.sos.state.co.us. A Certificate of Good Standing will be required to process the Agreement.
14. UNIT COST: The price quoted in the proposal shall include the costs of labor, materials, equipment, and incidentals required to provide a fully complete and functioning unit as http://www.sos.state.co.us/
Bidding and Contract Information Page 13 of 18 C25YA1 shown and described in the plans and specifications. The price stated in the proposal shall be complete, and represent total payment for each item in the proposal. No additional payment will be made for the work presented in the proposal.
15. INSURANCE: The successful bidder will be required to submit proof of insurance at the time of executing the agreement. Proof of insurance must be submitted on certificates showing the minimum coverage amounts.
A. The Contractor is required to procure and maintain at all times during the term of this contract the insurance coverage listed below:
1) Workers’ Compensation and Employer’s Liability Insurance, as required by state statute, including occupational disease, covering all of contractor or subcontractor employees acting within the course and scope of their employment.
2) Commercial General Liability Insurance written on ISO occurrence form CG 00 01 10/93 or equivalent, covering premises operations, fire damage, independent contractors, products and completed operations, blanket contractual liability, personal injury, and advertising liability with minimum limits as follows:
a. $1,000,000 combined single limit written on an occurrence basis;
b. $1,000,000 general aggregate;
c. $1,000,000 products and completed operations aggregate; and
d. $50,000 any one fire.
e. If any aggregate limit is reduced below $1,000,000 because of claims made or paid, the contractor shall immediately obtain additional insurance to restore the full aggregate limit and furnish to the State a certificate or other document satisfactory to the State showing compliance with this provision.
3) Automobile Liability Insurance covering any auto (including owned, hired and non-owned autos) with a minimum limit as follows: $1,000,000 each accident combined single limit.
4) Builder’s Risk Insurance.
5) Pollution liability policy with minimum limits of $1,000,000 each occurrence and
$1,000,000 Annual Aggregate covering any environmental damage caused by the contractor or subcontractor during the Work with the State included as an additionally insured party.
B. The State of Colorado shall be named as an Additional Insured on the Commercial General Liability, Automobile Liability, and Builder’s Risk policy insurance certificates and Colorado Parks and Wildlife must be named as the certificate holder for all coverages 1-4 noted above (leases and construction contracts will require the additional insured coverage for completed operations on endorsements CG 2010 11/85, CG 2037, or equivalent). Coverage required of the contract will be primary over any insurance or self-insurance program carried by the State of Colorado.
C. The Insurance shall include provisions preventing cancellation or non-renewal without at least 45 days prior notice to the State by certified mail.
D. The Insurance shall include a waiver of subrogation for all coverages.
E. The contractor will require all insurance policies in any way related to the contract and secured and maintained by the contractor to include clauses stating that each carrier will waive all rights of recovery, under subrogation or otherwise, against the State of Colorado, its agencies, institutions, organizations, officers, agents, employees and volunteers.
F. All policies evidencing the insurance coverage required hereunder shall be issued by insurance companies satisfactory to the State. No later than 15 days prior to the expiration date of any such coverage, the contractor shall deliver the State certificates of insurance evidencing renewals thereof.
Bidding and Contract Information Page 14 of 18 C25YA1
16. BUILDER’S RISK INSURANCE: The Contractor shall effect and maintain, at their own expense, during the life of the contract, All Risk Builder’s Risk Completed Value Insurance if the work is for an entirely new structure, or All Risk Insurance if the work is for an existing structure.
The coverage shall be in the dollar amount of the total project for the contract.
The insurance shall remain in effect until all contract work has been completed and a Notice of Final Acceptance has been issued, whether or not the building or some part thereof is occupied in any manner prior to final acceptance of the project. Such insurance shall be in an amount equal to the aggregate total insurable value of the construction contract entered in with permissible deductions of the cost of the excavations, foundations below the lowest basement floor, underground construction, underground pipes, underground wiring, sidewalks, driveways, curbs and gutters, street improvements, and fences.
Upon request, the amount of such fire insurance shall be increased to include the cost of any additional work to be done on the project, or materials or equipment to be incorporated in the project, under other independent contracts let or to be let. In such event, the Contractor shall be reimbursed for the cost of their share of the insurance in the same ratio of the insurance represented by such independent contracts let or to be let to the total insurance carried.
All such insurance shall insure the State of Colorado acting by and through the Division, the Contractor and their subcontractors as their interest may appear, but the loss, if any shall be payable to the State Controller, as Trustee. The certificate of insurance shall specifically state the inclusion of provisions herein above. The Division with the approval of the State Controller will have the power to adjust and settle any loss. Unless it is agreed otherwise, all moneys received will be applied on rebuilding or repairing the destroyed or injured work.
17. If the successful bidder, upon acceptance of his bid by the OWNER, fails to execute such further contractual documents, and give such bond(s) (including any necessary coinsurance or reinsurance agreements) as may be required within ten (10) days after receipt of the Notice of Award, the contract may be terminated for default. In such event the CONTRACTOR shall be liable for any cost of procuring the work which exceeds the amount of his bid, and the bid guarantee shall be available toward offsetting such difference.
18. The bidder is not to give any information concerning his proposal to any other bidder or receive any information concerning another proposal.
19. SALES TAX: The Division of Parks and Wildlife is exempt from paying Colorado sales tax.
Any materials and supplies purchased for this contract are exempt. The Contractor will need to obtain an exemption number from the Department of Revenue for this project and each subcontractor is required to obtain one under the general contractor.
20. QUANTITIES: Quantities stated in the bid schedule and construction documents are estimates only and may increase or decrease during construction. The contractor will perform the required quantity of work based on the unit prices stated in the Bid Schedule except as provided in Section 4.2 of the "General Conditions for Capital Construction."
21. WORK STOPPAGE: Work stoppage is a possibility. The contractor must request all shutdowns or stoppages in writing. If a shutdown is granted, the Division will pay for only work that has been totally completed. No advanced payment of mobilization will be made.
22. CONSTRUCTION SCHEDULE: The Contractor shall submit a written project schedule and
Bidding and Contract Information Page 15 of 18 C25YA1 supporting data to the Project Manager as soon as possible after the receipt of the Notice of Award. The schedule shall describe key milestones and duration of project activities.
The supporting data for the schedule shall include a complete list of anticipated submittals and due dates, and the key ordering and delivery lead times. The Contractor shall schedule the sequence of construction to consider the delivery of long lead-time items. It shall be the Contractor's responsibility to notify the Project Manager of any problem in conforming to the Contract Documents, Specifications, and Construction Drawings for any element of the proposed improvements prior to its construction.
23. SCHEDULE OF VALUES/WORK SCHEDULE: The Contractor shall provide the Project Manager for review and acceptance, and prior to the commencement of any Work, a breakdown of the Contract cost proposal into values representing the various distinct stages, or units of the whole project, as a basis for making partial and final payments. Stages or specialty items shall be described in terms of a percentage to the whole. The schedule of values shall be shown on a proposed timeline estimating the actual Work schedule. The schedule shall indicate starting and completion dates for the various stages of Work and shall be in a format acceptable to the Project Manager.
24. SCHEDULE OF SUBCONTRACTORS, MAJOR EQUIPMENT AND MATERIALS SUPPLIERS: The
Contractor shall provide the Owner, prior to the commencement of any Work, a detailed listing of subcontractors and major equipment and materials suppliers indicating their name, address, description of service or equipment and materials being provided, if they are a woman owned or minority owned business enterprise (WBE/MBE), and their vested monetary interest in the contract. The Contractor shall not award any Work to a subcontractor, transfer or assign any portion of the Contract Work, without the written approval of the Owner. Records shall be maintained throughout the duration of the Contract and periodically submitted at the time the Contractor submits progress payment applications. The Owner will use these records to verify the Contractor’s level of indebtedness prior to making final payment.
25. DIVISION APPROVAL OF INDEPENDENT TESTING LABORATORY: The Contractor shall submit the name and qualifications of the independent testing laboratory to the Project Manager as soon as possible after receipt of the Notice of Award. The Division may request personal interviews and retains the right to reject the proposed candidates without reservation. If a candidate is rejected, the Contractor shall provide an alternative that is acceptable, and work shall not begin until approval is obtained.
26. CONSTRUCTION CONTROL PLAN: A traffic, excavation, and construction access control plan shall be submitted by the Contractor and approved by the Owner prior to the commencement of work. The disruption to project area visitors shall be kept to a minimum.
The plan shall take into consideration all users, including motorists, cyclists, and pedestrians. The Contractor shall provide all lights, signs, barricades, flagmen, or other devices necessary to provide for public safety in accordance with the current United States Department of Transportation’s Manual of Uniform Traffic Control Devices.
27. STORMWATER MANAGEMENT PLAN: This project will not disturb more than 1 acre of ground, so a State stormwater control permit is not required.
28. Colorado Parks and Wildlife shall not be obligated or liable for any cost incurred by any company or individual reviewing this proposed project or prior to the issuance of a contract approved by the Controller of the State of Colorado or such assistant as he may designate.
Any and all costs, to review the project, inspect the proposed construction site, prepare
Bidding and Contract Information Page 16 of 18 C25YA1 and or submit bids will be the sole responsibility of the bidder.
29. A submission in response to the solicitation acknowledges acceptance by the proposer of all unaltered terms and conditions, as set forth herein. Any proposed exception taken to the State’s Terms and Conditions must be clearly and thoroughly identified and supported and acceptable alternatives must be proposed. Failure to do so shall be deemed a waiver of any rights to subsequently raise exception and/or request modification, except as outlined or specified in this solicitation. Submission of exceptions does not guarantee their acceptance, however, and such submittal will be taken into consideration during proposal review and scoring by the evaluation team. The state reserves the right to reject any changes suggested to PO or Contact terms and conditions and award to the next most advantageous qualified responsive vendor.
30. PROTESTED SOLICITATIONS AND AWARDS: An aggrieved party may file a protest concerning a material issue(s), at any phase of solicitation, including, but not limited to, specifications, award or a disclosure of information marked confidential in the bid. The protest shall be submitted via email to the DNR Procurement Official as noted below within ten (10) business days after such aggrieved person knows, or should have known, of the facts giving rise thereto. Reference CRS 24-109-102, as amended, and Procurement Rule R-24-109-102-01, et seq.
DNR Procurement Official: Ion Cotsapas, ion.cotsapas@state.co.us
The written protest shall include, as a minimum, the following:
A. The name and address of the protestor;
B. Appropriate identification of the procurement by bid or award number;
C. A statement of the reasons for the protest, and any available exhibits, evidence, or documents substantiating the protest.
31. ACH/EFT PAYMENTS: Contractors are highly encouraged to consider signing up for ACH/EFT payments. ACH/EFT payments provide the advantage of ensuring quick and secure payments for the goods and services that vendors provide to the State. ACH/EFT payments help avoid the unnecessary, and sometimes inevitable delays in mail, and the possibility of lost warrants which will further delay vendor payment. DNR’s goal is to pay vendors as soon as possible - signing up for the ACH/EFT is an important step in making this happen. For additional information about signing up for ACH/EFT payments, please contact the Project Manager identified in the Invitation for Bids.
32. In accordance with procurement code and CRS 24-103-904 titled “Purchasing Preference for
Environmentally Preferable Products”, bidders responding to this solicitation may seek to qualify for the preference and governmental bodies conducting this solicitation shall award a contract to a bidder who offers environmentally preferable products subject to the condition in the code and procurement rules.
33. ALTERNATIVE PRODUCTS: Certain materials and equipment have been specified by manufacturers’ trade names. This was done to establish the minimum quality and type of product desired. Alternatives to the manufacturers’ products may be used if the Project Manager determines they are equal. The Award will be based on the products identified in the plans.
34. DAVIS-BACON WAGE LAW:
mailto:ion.cotsapas@state.co.us
Bidding and Contract Information Page 17 of 18 C25YA1
The subject Project is not a Federal prevailing wage rate project so Davis-Bacon Wage Rates do not apply. The State of Colorado prevailing wage requirements do apply; see below.
35. PREVAILING WAGES: A public construction project in the amount of five hundred thousand dollars or more shall be subject to the State prevailing wage rate, of the regular, holiday, and overtime wages paid and the general prevailing payments on behalf of employees to lawful welfare, pension, vacation, apprentice training, and educational funds in the State, for each employee needed to execute the contract. Payments to the funds must constitute an ordinary business expense deduction for federal income tax purposes by contractors and subcontractors. Contractors are required to pay their employees at weekly intervals and shall comply with the enforcement provisions of C.R.S. §24-92-209. Contractors awarded a project of this size will be required to utilize the LCPTracker cloud-based labor compliance and certified payroll application. Upon award, the Contractor will need to return a completed copy of this form for LCPTracker enrollment:
https://drive.google.com/file/d/13Xvu5GttmOerEViwQsXlnbVI40YwsllD/view.
The applicable prevailing wages for this project are attached in Appendix F Please review the “Special Considerations for Public Projects” section of the Contract Sample for additional details regarding compliance with the prevailing wages statutes.
36. NOTICE OF CONTRACTOR’S SETTLEMENT: If the project exceeds $150,000.00, a Final Settlement will be advertised via electronic media on the Colorado VSS website at www.colorado.gov/vss.
37. CONTRACT CLOSE OUT: Final Payment Statement: In addition to submittals required by the conditions of the Contract, provide submittals required by governing authorities and submit a final statement of accounting giving total adjusted Contract Sum, previous payments and sum remaining due. Provide a final summary of the cost and origin of the five most costly manufactured items containing more than fifty percent iron or steel that were installed on the project. The Contractor shall submit lien waivers for all subcontractors and material suppliers as part of the final payment statement.
38. LIQUIDATED DAMAGES: The parties agree that time is of the essence of the Contract and of the Specifications wherever a definite and certain length of time is fixed for the performances of any act. A daily charge will be made against the Contractor for each calendar day that any work remains uncompleted after the elapse of contract time. This daily charge will be deducted from any money due to the Contractor. This deduction will not be considered a penalty, but as liquidated damages.
The liquidated damages set forth is an amount, agreed to by the Contractor and the Division, as reasonably representing additional project construction administration costs incurred by the Division and projected loss of revenue to the Park if the Contractor fails to complete performance within the contract time. For this project, the Liquidated Damages will be $267.58 per day.
Due account shall be taken of any adjustment of the contract time for completion of the work granted under the provisions of subsection 8.5 of the General Conditions for Capital Construction. Permitting the Contractor to continue and finish the work or any part thereof after elapse of contract time will not operate as a waiver on the part of the Division on any of its rights under the Contract.
https://drive.google.com/file/d/13Xvu5GttmOerEViwQsXlnbVI40YwsllD/view http://www.colorado.gov/vss
Bidding and Contract Information Page 18 of 18 C25YA1
Any deduction assessed as liquidated damages under this section shall not relieve the Contractor from liability for any damages or costs resulting from delays to other contractors on the project or other projects caused by a failure of the assessed Contractor to complete the work according to contract times.
39. WORK HOURS ON PROJECT SITE: All work on this project site will be allowed as follows:
8am to 6pm or otherwise approved by the Project Manager.
40. PERFORMANCE MONITORING CRS §§ 24-106-107:
A. PERFORMANCE MEASURES AND STANDARDS:
Performance measures and Standards as defined in the General Conditions for Capital Construction shall be the basis for this Contract. This includes but is not limited to the following:
1) The Contractor shall prepare a project schedule at project startup and continue to update the schedule throughout construction providing detailed justifications for construction delays and schedule changes.
2) The Contractor shall submit all required product information as defined in the Construction Drawings & Specifications. In turn, the State’s Project Manager shall review and comment within 10 days of receipt.
3) The State’s Project Manager and the Contractor shall conduct Construction Progress Meetings and Quantity Verification Inspections at least monthly or as otherwise determined necessary during Construction activities.
B. ACCOUNTABILITY:
Project and Contract administration will provide accountability by documenting and evaluating the progression of construction and the ability to follow the agreed upon construction schedule. The Contractor shall report regularly on achievement of the performance measures and standards specified above and failure to do so allows the governmental body to withhold payment until successful completion of all or part of the contract and the achievement of established performance standards. Payment by the State to the Contractor shall be made without delay upon successful completion of all or any part of the contract in accordance with the payment schedule specified in the contract or as otherwise agreed upon by the parties.
C. MONITORING REQUIREMENTS:
The State will evaluate the Contractor’s performance by preparing monthly progress reports and monthly construction schedule updates provided by the Contractor as well as performing site visits to verify quantities based on the Bid Schedule, inspections to verify quality of work, and reviews of performance data as construction…