This is a Construction Bid Clarification Addendum issued by the Michigan Department of Technology, Management and Budget, State Facilities Administration Design and Construction Division. The addendum addresses technical issues encountered by vendors when uploading bid attachments to the SIGMA VSS (Statewide Information Gateway for Michigan Awards Vendor Self-Service) platform. The bid opening date is scheduled for July 31, 2019, and bidders are advised that if a dropdown menu appears during the attachment upload process, they should select either "standard" or "proprietary" before attaching their bid documents. To ensure timely receipt of bid responses and attachments, all submissions must be emailed directly to Linda Feldpausch (FeldpauschL1@michigan.gov) with a copy to Anne Watros (watrosa@michigan.gov). The SIGMA team indicated that a system fix to eliminate the dropdown menu issue was scheduled for implementation and notification of successful resolution was anticipated later that week.
Bidders are required to acknowledge receipt of this addendum in the designated space on the Bid Summary and Bid Form; failure to provide such acknowledgement may result in bid rejection. The addendum becomes part of the contract documents and carries the same binding authority as the original bidding documents.
Text of this file
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION BID CLARIFICATION
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
| TO: |
| ALL BIDDERS |
| DATE ISSUED |
7/29/2019
PROJECT NAME
FILE NUMBER
PROFESSIONAL
PROJECT DIRECTOR
BID OPENING DATE:
7/31/2019
ADDENDUM ITEMS:
In the last few weeks, vendors have experienced difficulty in uploading attachments to their bids, in part due to a new drop down indicating numerous attachment selection options. SIGMA team is aware of this issue and a fix was scheduled to be implemented over this past weekend. At this time, we have not been notified whether or not this fix to eliminate the drop down menu has been successful, we are advising our vendors that should a drop down menu appear, to please select either standard or proprietary BEFORE attaching your attachments to your bid. Also to ensure that your bid attachments are received timely, we are also requesting that all bid responses and attachments be emailed to Linda Feldpausch (FeldpauschL1@michigan.gov) and a cc to Anne Watros (watrosa@michigan.gov). We thank you for your cooperation and anticipate notification of the fix later this week.
ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
PROFESSIONAL:
DATE:
APPROVED BY:
PROJECT DIRECTOR:
DATE:
image1.jpeg
Other files
| File | Type | Posted |
|---|---|---|
| 751-19361AGY D-3 D-4 ADD#1 site maps.docx | DOCX document | |
| 751-19361AGY D-3 Maps _3 sites.pdf | ||
| 751-19361 D-4_maps 2 sites.pdf | ||
| 751-19361 D3 D4 AGY DTMB-0415 (Advertisment)(R04-19).doc | DOC document | |
| FR2019 D4 Alpena list ACM Reports.pdf | ||
| FR2019-D3 CheboyganPresqueIsle Demo List - ACM Reports.pdf | ||
| Exhibit B seeding reqmts .pdf | ||
| 751-19361 AGY Spec D3-D4 (Rev02-19).docx | DOCX document | |
| DIVISION TWO Site Work spec.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .