Bid Abstract St.Paul Harbor.pdf
PDF 112 KB Posted
- Attached to
- St. Paul Harbor Repairs and Maintenance Dredging Federal contract opportunity
- Solicitation number
- W911KB24C0016
About this file
This document is a Bid Abstract for the St. Paul Harbor Repairs and Maintenance Dredging contract, Solicitation Number W911KB24B0003. The contract involves repairing the main breakwater dissipation reefs, constructing channel scour hole protection, performing maintenance dredging and placement of dredged materials at an upland placement site approximately 2.5 miles from the harbor, and completing pre- and post-work surveys at St. Paul Harbor in St. Paul Island, Alaska. The contract was awarded to Western Marine Construction, Inc. for $36,910,000.00 on August 30, 2024. The Bid Abstract provides pricing details for the base items as well as optional items, including mobilization/demobilization, dredging and placement quantities and unit prices, and survey requirements. Offerors included Western Marine Construction and CAM-Dutra JV-II LLC, with the contract awarded to the lowest bidder.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
17-Jun-2024 8-Aug-2024 1 of 2
DATE SIGNED
ITEM NO. ITEM DESCRIPTION
EST.
QUANTITY UNIT
UNIT
PRICE
ESTIMATED
AMOUNT
UNIT
PRICE AMOUNT
UNIT
PRICE AMOUNT
0001 Mobilization and Demobilization, complete 1 JOB $8,300,000.00 $8,300,000.00 $9,326,000.00 $9,326,000.00 $15,039,000.00 $15,039,000.00 0002 Dredge and Placement, Entrance Channel, Complete.
0002AA First 35,000 cubic yards 35,000 CY $68.00 $2,380,000.00 $160.00 $5,600,000.00 $150.00 $5,250,000.00 0002AB All Over 35,000 cubic yards 24,700 CY $68.00 $1,679,600.00 $40.00 $988,000.00 $105.00 $2,593,500.00
0003 Dredge and Placement, Maneuvering Area, Complete.
0003AA First 17,300 cubic 17,300 CY $72.00 $1,245,600.00 $150.00 $2,595,000.00 $150.00 $2,595,000.00 0003AB All Over 17,300 8,500 CY $72.00 $612,000.00 $40.00 $340,000.00 $105.00 $892,500.00
0004 Dredge and Placement, Small Boat Harbor Maneuvering Area, Complete. $0.00 $0.00 $0.00
0004AA First 9,800 cubic yards 9,800 CY $63.00 $617,400.00 $140.00 $1,372,000.00 $90.00 $882,000.00 0004AB All over 9,800 3,000 CY $63.00 $189,000.00 $30.00 $90,000.00 $80.00 $240,000.00
0005 Dredge and Placement, Sediment Mangement Area, complete 0005AA First 23,300 Cubic yards 23,300.00 CY $59.00 $1,374,700.00 $160.00 $3,728,000.00 $90.00 $2,097,000.00 0005AB All over 23,300 cubic yards 5,400.00 CY $59.00 $318,600.00 $60.00 $324,000.00 $80.00 $432,000.00
0006 Hydrographic Survey, Complete 2 EA $100,000.00 $200,000.00 $100,000.00 $200,000.00 $60,000.00 $120,000.00 Total of Base Items CLINS 0001 thru 0006 $16,916,900.00 $24,563,000.00 $30,141,000.00
0007 Mobilization and Demobilization for Option Items 0008 – 0011, complete 1 JOB $3,500,000.00 $3,500,000.00 $5,012,000.00 $5,012,000.00 $4,858,000.00 $4,858,000.00 0008 Repair Reef 2 and 3, Reef Rock, Complete
0008AA First 11,200 Cubic Yards 11,200 CY $520.00 $5,824,000.00 $350.00 $3,920,000.00 $500.00 $5,600,000.00 0008AB All Over 11,200 Cubic Yards 10,600 CY $520.00 $5,512,000.00 $100.00 $1,060,000.00 $460.00 $4,876,000.00
0009 Construct Entrance Channel Scour Protection, Scour Rock I, complete
0009AA First 2,700 Cubic Yards 2,700 CY $520.00 $1,404,000.00 $350.00 $945,000.00 $500.00 $1,350,000.00 0009AB All Over 3,700 Cubic Yards 2,200 CY $520.00 $1,144,000.00 $100.00 $220,000.00 $460.00 $1,012,000.00
0010 Construct Small Boat Harbor Entrance Channel Scour Protection, Scour Rock II, complete 3,000 CY $450.00 $1,350,000.00 $330.00 $990,000.00 $200.00 $600,000.00
0011 Hydrographic Survey, Complete 2 EA $100,000.00 $200,000.00 $100,000.00 $200,000.00 $40,000.00 $80,000.00 Total of Optional Items 0007 thru 0011 $18,934,000.00 $12,347,000.00 $18,376,000.00
Total of Base and Option Items $35,850,900.00 $36,910,000.00 $48,517,000.00
No. 01 No. 02 St. Paul Harbor Repairs and Maintenance Dredging, St. Paul Island, Alaska A. OFFEROR A. OFFEROR
Western Marine Construction CAM-Dutra JV-II LLC
5 Amendment
B. BID SECURTIY (TYPE AND AMOUNT)
6. NUMBER OF AMENDMENTS ISSUED
B. BID SECURTIY (TYPE AND AMOUNT)
C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED
ABSTRACT OF BIDS - CONSTRUCTION
1. SOLICITATION NUMBER
W911KB24B0003
4. ISSUING OFFICE
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
7. NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
U.S. Army Engineer District, Alaska PO Box 6898
JBER, AK 99506-6898
George Nasif, Contracting Officer
SIGNATURE
9. OFFERS
5. PROJECT TITLE 8. GOVERNMENT ESTIMATE
(Check A, B, C and complete D, E, and F)
IGE & Offeror 1-2
File details come from the government source that posted it. Updated .