This document is an abstract of bids for a construction contract awarded by the U.S. Army Corps of Engineers Engineering District Alaska. The contract, numbered W911KB23C0008, was awarded to Alaska Marine Excavation LLC on January 19, 2023 for $4,003,500. The contract is for maintenance dredging of Homer Harbor and Ninilchik Harbor from 2023 through 2025. Work will include dredging and placement of material, hydrographic surveys, and mobilization and demobilization for each location annually. Locations include Homer Harbor, Ninilchik Harbor, and the Homer USCG Berth. Estimated quantities and unit pricing are provided for dredging and placement work items. The abstract of bids includes the government estimate and the bid from the awarded offeror, Alaska Marine Excavation LLC.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
8-Nov-2022 15-Dec-2022 1 of 1
DATE SIGNED
12-Jan-23
ITEM
NO. ITEM DESCRIPTION
EST.
QUANTI UNIT
UNIT
PRICE
ESTIMATED
AMOUNT
UNIT
PRICE AMOUNT
UNIT
PRICE AMOUNT
0001 Mobilization and Demobilization, Homer Harbor, 2023 complete. 1 Job $427,498.00 $427,498.00 $400,000.00 $400,000.00 $0.00 0002 Dredging and Placement, Homer Harbor, 2023 complete. $0.00 $0.00 $0.00 0002AA First 5,000 cubic yards. 5,000 CY $18.50 $92,500.00 $20.00 $100,000.00 $0.00 0002AB All Over 5,000 cubic yards. 2,000 CY $13.10 $26,200.00 $1.00 $2,000.00 $0.00 0003 Hydrographic Surveys, Homer Harbor, 2023 complete. 2 EA $32,230.00 $64,460.00 $40,000.00 $80,000.00 $0.00 0004 Mobilization and Demobilization, Ninilchik Harbor, 2023 complete. 1 Job $165,496.00 $165,496.00 $200,000.00 $200,000.00 $0.00 0005 Dredging and Placement, Ninilchik Harbor, 2023 complete. $0.00 $0.00 $0.00 0005AA First 7,500 cubic yards. 7,500 CY $16.60 $124,500.00 $20.00 $150,000.00 $0.00 0005AB All Over 7,500 cubic yards. 3,500 CY $15.20 $53,200.00 $1.00 $3,500.00 $0.00 0006 Hydrographic Surveys, Ninilchik Harbor, 2023 complete. 2 EA $26,496.00 $52,992.00 $32,000.00 $64,000.00 $0.00
Total of Base Items 0001 thru 0006 $1,006,846.00 $999,500.00 $0.00 0007 Mobilization and Demobilization, Homer USCG Berth, Spring 2023 complete. 1 Job $35,993.00 $35,993.00 $50,000.00 $50,000.00 $0.00 0008 Dredging and Placement, Homer USCG Berth, Spring 2023 complete. $0.00 $0.00 $0.00 0008AA First 5,500 cubic yards. 5500 CY $21.80 $119,900.00 $20.00 $110,000.00 $0.00 0008AB All Over 5,500 cubic yards. 2500 CY $17.30 $43,250.00 $20.00 $50,000.00 $0.00 0009 Hydrographic Surveys, Homer USCG Berth, Spring 2023 complete. 2 EA $17,995.00 $35,990.00 $30,000.00 $60,000.00 $0.00 0010 Mobilization and Demobilization, Homer USCG Berth, Fall 2023 complete. 1 Job $32,873.00 $32,873.00 $10,000.00 $10,000.00 $0.00 0011 Dredging and Placement, Homer USCG Berth, Fall 2023 complete. $0.00 $0.00 $0.00 0011AA First 1,500 cubic yards. 1500 CY $21.80 $32,700.00 $20.00 $30,000.00 $0.00 0011AB All Over 1,500 cubic yards. 500 CY $17.10 $8,550.00 $20.00 $10,000.00 $0.00 00012 Hydrographic Surveys, Homer USCG Berth, Fall 2023 complete. 2 EA $11,055.00 $22,110.00 $7,500.00 $15,000.00 $0.00
Total of Option Items 0007 thru 0012 $331,366.00 $335,000.00 $0.00
00013 Mobilization and Demobilization, Homer Harbor, 2024 complete. 1 Job $436,048.00 $436,048.00 $400,000.00 $400,000.00 $0.00 00014 Dredging and Placement, Homer Harbor, 2024 complete. $0.00 $0.00 $0.00 0014AA First 5,000 cubic yards. 5000 CY $19.00 $95,000.00 $20.00 $100,000.00 $0.00 0014AB All Over 5,000 cubic yards. 2000 CY $14.00 $28,000.00 $1.00 $2,000.00 $0.00 0015 Hydrographic Surveys, Homer Harbor, 2024 complete. 2 EA $32,875.00 $65,750.00 $40,000.00 $80,000.00 $0.00 0016 Mobilization and Demobilization, Ninilchik Harbor, 2024 complete. 1 Job $168,806.00 $168,806.00 $200,000.00 $200,000.00 $0.00 0017 Dredging and Placement, Ninilchik Harbor, 2024 complete. $0.00 $0.00 $0.00 0017AA First 7,500 cubic yards. 7500 CY $17.00 $127,500.00 $20.00 $150,000.00 $0.00 0017AB All Over 7,500 cubic yards. 3500 CY $16.00 $56,000.00 $1.00 $3,500.00 $0.00 0018 Hydrographic Surveys, Ninilchik Harbor, 2024 complete. 2 EA $27,026.00 $54,052.00 $32,000.00 $64,000.00 $0.00 0019 Mobilization and Demobilization, Homer USCG Berth, Spring 2024 complete. 1 Job $36,713.00 $36,713.00 $50,000.00 $50,000.00 $0.00 0020 Dredging and Placement, Homer USCG Berth, Spring 2024 complete. $0.00 $0.00 $0.00 0020AA First 5,500 cubic yards. 5500 CY $23.00 $126,500.00 $20.00 $110,000.00 $0.00 0020AB All Over 5,500 cubic yards. 2500 CY $18.00 $45,000.00 $20.00 $50,000.00 $0.00 0021 Hydrographic Surveys, Homer USCG Berth, Spring 2024 complete. 2 EA $18,355.00 $36,710.00 $30,000.00 $60,000.00 $0.00 0022 Mobilization and Demobilization, Homer USCG Berth, Fall 2024 complete. 1 Job $33,531.00 $33,531.00 $10,000.00 $10,000.00 $0.00 0023 Dredging and Placement, Homer USCG Berth, Fall 2024 complete. $0.00 $0.00 $0.00 0023AA First 1,500 cubic yards. 1500 CY $23.00 $34,500.00 $20.00 $30,000.00 $0.00 0023AB All Over 1,500 cubic yards. 500 CY $18.00 $9,000.00 $20.00 $10,000.00 $0.00 0024 Hydrographic Surveys, Homer USCG Berth, Fall 2024 complete. 2 EA $11,277.00 $22,554.00 $7,500.00 $15,000.00 $0.00
Total of Option Items 0013 thru 0024 $1,375,664.00 $1,334,500.00 $0.00
0025 Mobilization and Demobilization, Homer Harbor, 2025 complete. 1 Job $444,769.00 $444,769.00 $400,000.00 $400,000.00 $0.00 0026 Dredging and Placement, Homer Harbor, 2025 complete. $0.00 $0.00 $0.00 0026AA First 5,000 cubic yards. 5000 CY $20.00 $100,000.00 $20.00 $100,000.00 $0.00 0026AB All Over 5,000 cubic yards. 2,000 CY $15.00 $30,000.00 $1.00 $2,000.00 $0.00 0027 Hydrographic Surveys, Homer Harbor, 2025 complete. 2 EA $33,533.00 $67,066.00 $40,000.00 $80,000.00 $0.00 0028 Mobilization and Demobilization, Ninilchik Harbor, 2025 complete. 1 Job $172,183.00 $172,183.00 $200,000.00 $200,000.00 $0.00 0029 Dredging and Placement, Ninilchik Harbor, 2025 complete. $0.00 $0.00 $0.00 0029AA First 7,500 cubic yards. 7,500 CY $18.00 $135,000.00 $20.00 $150,000.00 $0.00 0029AB All Over 7,500 cubic yards. 3,500 CY $17.00 $59,500.00 $1.00 $3,500.00 $0.00 0030 Hydrographic Surveys, Ninilchik Harbor, 2025 complete. 2 EA $27,567.00 $55,134.00 $32,000.00 $64,000.00 $0.00 0031 Mobilization and Demobilization, Homer USCG Berth, Spring 2025 complete. 1 Job $37,448.00 $37,448.00 $50,000.00 $50,000.00 $0.00 0032 Dredging and Placement, Homer USCG Berth, Spring 2025 complete. $0.00 $0.00 $0.00 0032AA First 5,500 cubic yards. 5,500 CY $24.00 $132,000.00 $20.00 $110,000.00 $0.00 0032AB All Over 5,500 cubic yards. 2,500 CY $19.00 $47,500.00 $20.00 $50,000.00 $0.00 0033 Hydrographic Surveys, Homer USCG Berth, Spring 2025 complete. 2 EA $18,723.00 $37,446.00 $30,000.00 $60,000.00 $0.00 0034 Mobilization and Demobilization, Homer USCG Berth, Fall 2025 complete. 1 Job $34,202.00 $34,202.00 $10,000.00 $10,000.00 $0.00 0035 Dredging and Placement, Homer USCG Berth, Fall 2025 complete. $0.00 $0.00 $0.00 0035AA First 1,500 cubic yards. 1,500 CY $24.00 $36,000.00 $20.00 $30,000.00 $0.00 0035AB All Over 1,500 cubic yards. 500 CY $19.00 $9,500.00 $20.00 $10,000.00 $0.00 0036 Hydrographic Surveys, Homer USCG Berth, Fall 2025 complete. 2 EA $11,503.00 $23,006.00 $7,500.00 $15,000.00 $0.00
Total of Option Items 0025 thru 0036 $1,420,754.00 $1,334,500.00 $0.00
Total of Base and Option Items 0001 thru 0036 $4,134,630.00 $4,003,500.00 $0.00
5. PROJECT TITLE
8. GOVERNMENT ESTIMATE
(Check A, B, C and complete D, E, and F)
No. 01 No. 02
7. NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
U.S. Army Engineer District, Alaska PO Box 6898
JBER, AK 99506-6898
Christine A. Dale, Contracting Officer
SIGNATURE
9. OFFERS
2023-2025 HOMER HARBOR & NINILCHIK HARBOR MAINTENANCE DREDGING A. OFFEROR A. OFFEROR
Alaska Marine Excavation LLC
ABSTRACT OF BIDS - CONSTRUCTION
1. SOLICITATION NUMBER
W911KB23B0002
4. ISSUING OFFICE
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
Yes
B. BID SECURTIY (TYPE AND AMOUNT)
6. NUMBER OF AMENDMENTS ISSUED
B. BID SECURTIY (TYPE AND AMOUNT)
C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED
Yes