Bid 6202: Roosevelt and Central Parking Lot Improvements

This is a construction bid document issued by the Port Huron Area School District for parking lot improvements at two facilities: Roosevelt Elementary School (1112 20th Street) and Central Middle School (200 32nd Street) in Port Huron, Michigan. The work consists of approximately 4,000 square yards of pavement and sidewalk removal, 3,500 square yards of aggregate base installation, 2,100 tons of hot mix asphalt, 2,000 square feet of concrete sidewalk, 360 square yards of concrete driveway/pavement, traffic control, pavement markings, permanent signage, and lawn restoration. Sealed bids were due April 1, 2026 at 10:00 AM at the Port Huron Area School District Administrative Offices. The contract period runs from a tentative start date of June 16, 2026 through substantial completion by August 14, 2026 and final completion by August 21, 2026. Bidders were required to register as plan holders on the State of Michigan Sigma Vendor Self Service website to have their bids accepted. Hard copies of bidding documents were available for a $35 nonrefundable fee plus $20 for shipping from BMJ Engineers & Surveyors, Inc.

Bids are on a unit price basis for separately identified work items. A bid security of five percent of the base bid amount, in the form of a certified check, cashier's check, or bid bond, was required with each bid submission. The successful bidder must furnish performance, labor and material payment bonds, and maintenance bonds equal to the contract price. Contractor's insurance requirements include workers' compensation, commercial general liability with minimum limits of $1,000,000 per occurrence, automobile liability, umbrella/excess liability of $2,000,000 per occurrence, and pollution liability insurance. Liquidated damages are assessed at $850 per day for failure to achieve substantial completion and $850 per day for failure to achieve final completion. Progress payments are made at 90 percent of completed work with 10 percent retainage, increasing to 95 percent upon substantial completion. The contract is governed by MDOT 2020 Standard Specifications for Construction with supplementary and special provisions addressing traffic maintenance, aggregate base specifications, and minor traffic devices.

View the file

Other files

File Type Posted
Bid 6202 Construction Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2026 PARKING LOT IMPROVEMENTS

ROOSEVELT ELEMENTARY SCHOOL

CENTRAL MIDDLE SCHOOL

BID #6202

ISSUE DATE: MARCH 6, 2026

DUE DATE: APRIL 1, 2026 AT 10:00AM

BID DOCUMENTS

ADVERTISEMENT FOR BIDS

PROJECT: Roosevelt Elementary and Central Middle School Parking Lot Improvements 1112 20th Street and 200 32nd Street, Port Huron MI 48060

OWNER: PORT HURON AREA SCHOOL DISTRICT

2720 Riverside Drive Port Huron, Michigan 48060 Telephone: (810) 984-3101

PROJECT DESCRIPTION

Port Huron Area School District will accept sealed proposals for parking lot improvements at 1112 20th Street and 200 32nd Street, Port Huron MI 48060

The work consists of furnishing all labor, material, and equipment required for approximately 4000 syd of pavement/sidewalk removal, 3500 syd of aggregate base, 2100 tons of hot mix asphalt, 2000 sq ft of concrete sidewalk 360 syd of concrete driveway/pavement, traffic control pavement markings, permanent traffic signage, lawn restoration and other incidental items related thereto.

PROPOSALS

The Port Huron Area School District will receive sealed proposals until: 10:00 a.m., local time, Wednesday, April 1st, 2026 at the Administrative Offices of the Port Huron Area School District, 2720 Riverside Drive, Port Huron, Michigan 48060, Attention: Kate Peternel, Chief Financial Officer. Label outside of envelopes “Parking Lot Improvements.” Faxed proposals will not be accepted. The District will not consider or accept a bid received after this date and time. All proposals will be publicly opened and read aloud. All interested parties are invited to attend.

Evaluation of the proposal and awards by Port Huron Schools will be available at a later date.

BIDDING DOCUMENTS

Contract Documents, including Construction Drawings, Instruction to Bidders, Proposal Forms, Contract Form, Bond Forms and Contract Specifications may be examined after 1:00 pm on Friday, March 6, 2026, on the Port Huron Area School District website www.phasd.us. Digital files of plans and Contract Documents in pdf format may be viewed and downloaded from the State of Michigan Sigma Vendor Self Service website:

https://sigma.michigan.gov/PRDVSS1X1/Advantage4.

Bidders must register as a plan holder on the State of Michigan Sigma Vendor Self Service website in order to have their bids accepted by the Port Huron Area School District. Hard copies (for an additional nonrefundable fee of $35.00) may be obtained after 1:00am on Friday, March 6, 2026, from BMJ Engineers & Surveyors, Inc., 519 Huron Avenue, Port Huron, Michigan 48060, 810-984-5596. Contract Documents will be shipped for an additional $20.00.

BID PROPOSAL GUARANTEE

Each proposal must be accompanied by an acceptable bid security in the form of a certified check, cashier’s check or standard form bid bond, made payable to the Port Huron Area School District in an amount of not less than five percent (5%) of the base bid submitted. Failure of any accepted Bidder to enter into contract for the work will cause forfeit of his bid security. After contracts for the work have been signed, all bid securities will be returned.

The winning bidder will have to furnish performance and labor & material payment bonds, the cost of which should be included in the project bid.

DISCLOSURES

As required by State Law (P.A. 232 of 2004) all proposals/bids must be accompanied by a sworn and notarized statement disclosing any familial relationship that exists between the Owner or any employee of the bidder and any member of the Port Huron Area School District Board or the Superintendent of the School District. Additionally, as required by State Law (P.A. 517 of 2012), the bidder must certify that it is not an Iran linked business as defined by P.A. 517 and that it will comply with the district's criminal background check requirements. The Board will not accept a bid that does not include thes sworn and notarized statements.

RIGHTS RESERVED BY THE OWNER:

The Owner reserves the right to waive any irregularity or informality in bids, to reject any and/or all bids, in whole or in part, or to award any Contract to other than the low bidder, should it be deemed in the Owner’s best interest to do so.

Bids may not be withdrawn for 60 days after receipt. All bids must be submitted on the Proposal Forms provided by the Engineer.

Signed: Kate Peternel, Chief Financial Officer, Port Huron Area School District

END OF ADVERTISEMENT FOR BIDS

https://sigma.michigan.gov/PRDVSS1X1/Advantage4

Roosevelt Elementary School and Central Middle

School Parking Lot Improvements

Roosevelt Elementary School

1112 20th Street and

Central Middle School

200 32nd Street

Owner:

Port Huron Area School District

2720 Riverside Drive

Port Huron, MI 48060

CONTRACT DOCUMENTS

Prepared By:

BMJ ENGINEERS & SURVEYORS, INC.

519 Huron Avenue

Port Huron, Michigan 48060

Telephone: (810) 984-5596

Fax: (810) 984-8760

Email: mail@bmjinc.com

BMJ Job No.: 2510.24

March 2026 pporte Placed Image

SECTION 00010

TABLE OF CONTENTS

TABLE OF CONTENTS 00010-1

Roosevelt Elementary School and Central Middle School

Parking Lot Improvements

Title Section

List of Drawings

Advertisement for Bids

Instructions to Bidders

Preliminary Schedules

Geotechnical Data

Bid Form

Unit Price Table

Bid Bond

Bidder’s Qualifications

Sworn and Notarized Affidavit of Compliance - Iran Economic Sanctions Act

Sworn and Notarized Familial Disclosure Statement

Non-Collusion Affidavit

Notice of Award

Agreement Form

Notice to Proceed

Performance Bond

Maintenance Bond

Payment Bond

Application for Payment

Certificate of Substantial Completion

General Conditions

Supplementary Conditions

Special Conditions

Special Provisions - General

END OF SECTION 00010

SECTION 001015

LIST OF DRAWINGS

LIST OF DRAWINGS 00015-1

Roosevelt Elementary School and Central Middle School Parking Lot

Improvements

LIST OF DRAWINGS

Title Sheet No.

Cover Legend and Notes Central Middle School Removal Plan

Central Middle School Layout Plan Roosevelt Elementary School Removal, Layout and Grading Plan

Roosevelt Elementary School Removal, Layout and Grading Plan

Roosevelt Elementary School Removal, Layout and Grading Plan

Details

END OF SECTION 00015

SECTION 00100

ADVERTISEMENT FOR BIDS

ADVERTISEMENT FOR BIDS 00100-1

Roosevelt Elementary School and Central Middle School Parking Lot Improvements and

Sealed bids for the Roosevelt Elementary School and Central Middle School Parking Lot

Improvements will be received by the Port Huron Area School District, at the office of the Port

Huron Area School District, 2720 Riverside Drive, Port Huron, Michigan 48060 until 10:00 am, prevailing local time on Wednesday, April 1, 2026. The bids will be publicly opened and read aloud immediately thereafter for the construction of Roosevelt Elementary School and Central Middle

School Parking Lot Improvements.

The work consists of furnishing all labor, material, and equipment required for approximately 4000 syd of pavement/sidewalk removal, 3500 syd of aggregate base, 2100 tons of hot mix asphalt, 2000 sft of concrete sidewalk 360 syd of concrete driveway/pavement, traffic control pavement markings, permanent traffic signage, lawn restoration and other incidental items related thereto.

Contract Documents, including Construction Drawings, Instruction to Bidders, Proposal Forms, Contract Form, Bond Forms and Contract Specifications may be examined after 1:00pm on Friday, March 6, 2026, on the Port Huron Area School District website www.phasd.us. Digital files of plans and Contract Documents in pdf format may be viewed and downloaded from the State of

Michigan Sigma Vendor Self Service website:

https://sigma.michigan.gov/PRDVSS1X1/Advantage4.

Bidders must register as a plan holder on the State of Michigan Sigma Vendor Self Service website in order to have their bids accepted by the Port Huron Area School District. Hard copies (for an additional nonrefundable fee of $35.00) may be obtained after 1:00am on Friday, March 6, 2026, from BMJ Engineers & Surveyors, Inc., 519 Huron Avenue, Port Huron, Michigan 48060, 810-

984-5596. Contract Documents will be shipped for an additional $20.00.

Bids shall be on a unit price basis for items of work, as specified. Bids shall be submitted on the proposal forms provided by the Engineer.

A Bid Bond in the form of a certified check, money order or a Bid Bond for a sum not less than five percent (5 percent) of the amount of the bid payable to Port Huron Area School District will be required with each bid.

The right is reserved by OWNER to accept any Bid, to reject any Bid, and to waive irregularities in Bids. The successful bidder will be required to furnish satisfactory Performance, Labor and

Materials bonds, Maintenance and Guarantee bonds, and insurance certificates.

Bids may not be withdrawn for 60 days after receipt. All bids must be submitted on the Proposal

Forms provided by the Engineer.

Published: Port Huron Times Herald, State of Michigan SIGMA website

\\BMJFS01W\Active_Files\(1)Projects\2510-24\09Bid Documents\www.phasd.us https://sigma.michigan.gov/PRDVSS1X1/Advantage4

EJCDC® C-200 (Rev. 1), Suggested Instructions to Bidders for Construction Contracts.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page i

SECTION 00200

INSTRUCTIONS TO BIDDERS

Page

Article 1 – Defined Terms

Article 2 – Copies of Bidding Documents

Article 3 – Qualifications of Bidders

Article 4 – Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 5 – Bidder’s Representations

Article 6 – Pre-Bid Conference

Article 7 – Interpretations and Addenda

Article 8 – Bid Security

Article 9 – Contract Times

Article 10 – Liquidated Damages

Article 11 – Substitute and “Or-Equal” Items

Article 12 – Subcontractors, Suppliers, and Others

Article 13 – Preparation of Bid

Article 14 – Basis of Bid

Article 15 – Submittal of Bid

Article 16 – Modification and Withdrawal of Bid

Article 17 – Opening of Bids

Article 18 – Bids to Remain Subject to Acceptance

Article 19 – Evaluation of Bids and Award of Contract

Article 20 – Bonds and Insurance

Article 21 – Signing of Agreement

Article 22 – Sales and Use Taxes

Article 23 – Contracts to be Assigned

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office – The office from which the Bidding Documents are to be issued.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents may be obtained from the Issuing Office in the number and format stated in the advertisement or invitation to bid.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within [5] days of Owner’s request, Bidder shall submit (a) written evidence establishing its qualifications such as financial data, previous experience, and present commitments, and (b) the following additional information:

A. Evidence of Bidder’s authority to do business in the state where the Project is located.

B. Bidder’s state or other contractor license number, if applicable.

C. Other required information regarding qualifications

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

4.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

4.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2

1. The Supplementary Conditions identify:

a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.

b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

c. reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

4. Geotechnical Baseline Report: The Bidding Documents contain a Geotechnical Baseline Report (GBR). The GBR describes certain select subsurface conditions that are anticipated to be encountered by Contractor during construction in specified locations (“Baseline Conditions”). The GBR is a Contract Document.

The Baseline Conditions in the GBR are intended to reduce uncertainty and the degree of contingency in submitted Bids. However, Bidders cannot rely solely on the Baseline Conditions. Bids should be based on a comprehensive approach that includes an independent review and analysis of the GBR, all other Contract Documents, Technical Data, other available information, and observable surface conditions. Not all potential subsurface conditions are baselined.

Nothing in the GBR is intended to relieve Bidders of the responsibility to make their own determinations regarding construction costs, bidding strategies, and Bid prices, nor of the responsibility to select and be responsible for the means, methods, techniques, sequences, and procedures of construction, and for safety precautions and programs incident thereto.

B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or adjacent to the Site are set forth in the Contract Documents and are based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.

C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 3 indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.

4.03 Site Visit and Testing by Bidders

A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.

B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

C. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.

D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

4.04 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. As the General Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary Conditions.

4.05 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 5 – BIDDER’S REPRESENTATIONS

5.01 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;

B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;

C. become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 4

D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings;

E. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;

F. agree, based on the information and observations referred to in the preceding paragraph, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;

G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;

H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;

I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work;

and

J. agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

ARTICLE 6 – PRE-BID CONFERENCE

6.01 A pre-Bid conference will be held at the time and location stated in the invitation or advertisement to bid. Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference. Engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.

ARTICLE 7 – INTERPRETATIONS AND ADDENDA

7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer in writing. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all parties recorded as having received the Bidding Documents. Questions received less than seven days prior to the date for

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 5 opening of Bids may not be answered. Only questions answered by Addenda will be binding.

Oral and other interpretations or clarifications will be without legal effect.

7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.

ARTICLE 8 – BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of [5] percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a certified check, bank money order, or a Bid bond (on the form included in the Bidding Documents) issued by a surety meeting the requirements of Paragraphs 6.01 and 6.02 of the General Conditions.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within seven days after the Bid opening.

ARTICLE 9 – CONTRACT TIMES

9.01 The number of days within which, or the dates by which the Work is to be substantially completed, and completed and ready for final payment, are set forth in the Agreement.

ARTICLE 10 – LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS

11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer at least 15 days prior to the date for receipt of Bids. Each such request shall comply with the requirements of Paragraphs 7.04 and 7.05 of the General Conditions. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 6 such proposed item, such approval will be set forth in an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals made in any other manner.

11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS

12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals or entities for the performance of the Work if required by the Bidding Documents (most commonly in the Specifications) to do so. If a prospective Bidder objects to retaining any such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or Contractor to retain any Subcontractor, Supplier, or other individual or entity against which Contractor has reasonable objection.

12.03 The apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work: Pavement Milling, Site Grading, HMA Paving, Concrete, Pavement Markings, Lawn Restoration.

If requested by Owner, such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder shall submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

12.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.

ARTICLE 13 – PREPARATION OF BID

13.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink.

Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 7

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation shall be shown.

13.03 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign.

The partnership’s address for receiving notices shall be shown.

13.04 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the firm’s address for receiving notices shall be shown.

13.05 A Bid by an individual shall show the Bidder’s name and address for receiving notices.

13.06 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture’s address for receiving notices shall be shown.

13.07 All names shall be printed in ink below the signatures.

13.08 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

13.09 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.

13.10 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.

ARTICLE 14 – BASIS OF BID

14.01 Unit Price

A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

14.02 Allowances

A. For cash allowances the Bid price shall include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 8 if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.

ARTICLE 15 – SUBMITTAL OF BID

15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound copy of the Bid Form, and, if required, the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the other documents required to be submitted under the terms of Article 7 of the Bid Form.

15.02 A Bid shall be received no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid and shall be enclosed in a plainly marked package with the Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted), the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid shall be addressed to the Port Huron Area School District, 2720 Riverside Drive, Port Huron, Michigan 48060.

15.03 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID

16.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.

16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.

ARTICLE 17 – OPENING OF BIDS

17.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 9

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive; provided that Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.

19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.

19.03 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. For the determination of the apparent low Bidder when unit price bids are submitted, Bids will be compared on the basis of the total of the products of the estimated quantity of each item and unit price Bid for that item, together with any lump sum items.

19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 20 – BONDS AND INSURANCE

20.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the Agreement (executed by Successful Bidder) to Owner, it shall be accompanied by required bonds and insurance documentation.

ARTICLE 21 – SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder shall execute and deliver the required number of counterparts of the Agreement (and any bonds and insurance documentation required to be delivered by the Contract Documents) to Owner. Within ten days thereafter, Owner shall deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 10

ARTICLE 22 – SALES AND USE TAXES

22.01 Owner is exempt from Michigan state sales and use taxes on materials and equipment to be incorporated in the Work. Said taxes shall not be included in the Bid. Refer to Paragraph SC-7.09 of the Supplementary Conditions for additional information.

ARTICLE 23 – CONTRACTS TO BE ASSIGNED

SECTION 00310

PRELIMINARY SCHEDULE

PRELIMINARY SCHEDULES 00310-1

This schedule is provided as a preliminary project schedule and is subject to revision by the Owner.

March 6, 2026 Contract Advertisement

April 1, 2026 Opening of Bids

April 20, 2026 Tentative Award of Contract

June 16, 2026 Tentative Start

August 14, 2026 Contract Substantial Completion

August 21, 2026 Contract Completion

END OF SECTION 00310

SECTION 00320

GEOTECHNICAL DATA

GEOTECHNICAL DATA 00320-1

SECTION 00320

GEOTECHNICAL DATA

GEOTECHNICAL DATA 00320-2

Pavement Core Log

February 2026

School Site/Core No.

Pavement

Material Type Pavement

Depth (Inch) Base Material Type and Estimated

Depth (inches) Sub-Base Material

Type Comments Central Middle School

1 Asphalt 5 Limestone - 4 Natural Stone - 2.5 Sand

2 Asphalt 4 Limestone - 10 Undetermined

3 Asphalt 4.5 Limestone - 7 Sand Water table at 9 inches

4 Asphalt 3.5 Limestone - 5.5 Sand

5 Asphalt 2.5 Limestone -7 Clay

6 Asphalt 5 Limestone - 9.5 Clay

7 Asphalt 5.75 Limestone - 10.25 Clay

8 Asphalt 5.5 Limestone - 10.5 Undetermined Roosevelt Elementary School

1 Asphalt 3.5 Limestone - 6 Clay Clay and aggregate base soft, water table at 6.5 inches

2 Asphalt 4 Limestone - 8.5 Clay Clay and aggregate base soft, water table at 6.5 inches

3 Asphalt 2.25 Limestone unknown

4 Asphalt 3.5 Limestone unknown

5 Asphalt 3.25 Clay/Topsoil/Stone unknown

6 Asphalt 4 Limestone unknown

PHASD Parking Lot Improvements 2026 Pavement Cores Table

Central Middle School

Pavement Cores

7 8

Roosevelt Elementary School – North Lot

Roosevelt Elementary School – South Lot and Court Yard

EJCDC® C-410, Bid Form for Construction Contracts.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page i

SECTION 00410

BID FORM

Roosevelt Elementary School and Central Middle School Parking Lot Improvements and

Owner:

Port Huron Area School District

2720 Riverside Drive

Port Huron, MI 48060

Project Number 2510.24

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page ii

Page

Article 1 – Bid Recipient

Article 2 – Bidder’s Acknowledgements

Article 3 – Bidder’s Representations

Article 4 – Bidder’s Certification

Article 5 – Basis of Bid

Article 6 – Time of Completion

Article 7 – Attachments to this Bid

Article 8 – Defined Terms

Article 9 – Bid Submittal

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1

ARTICLE 1 – BID RECIPIENT

1.01 This Bid is submitted to:

Port Huron Area School District, 2720 Riverside Drive, Port Huron, Michigan 48060

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS

2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

ARTICLE 3 – BIDDER’S REPRESENTATIONS

3.01 In submitting this Bid, Bidder represents that:

A. Bidder has examined and carefully studied the Bidding Documents, and any data and reference items identified in the Bidding Documents, and hereby acknowledges receipt of the following Addenda:

Addendum No. Addendum, Date

B. Bidder has visited the Site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfied itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

C. Bidder is familiar with and has satisfied itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work.

D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings.

E. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and any Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2 of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs.

F. Bidder agrees, based on the information and observations referred to in the preceding paragraph, that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents.

G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

H. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and confirms that the written resolution thereof by Engineer is acceptable to Bidder.

I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work.

J. The submission of this Bid constitutes an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, and that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

ARTICLE 4 – BIDDER’S CERTIFICATION

4.01 Bidder certifies that:

A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;

B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;

C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and

D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.D:

1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and

4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the e execution of the Contract.

Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 3

ARTICLE 5 – BASIS OF BID

5.01 Bidder will complete the Work in accordance with the Contract Documents for the following price(s):

See Attached Section 00415 Unit Price Table

Bidder acknowledges that (1) each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and (2) estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all unit price Bid items will be based on actual quantities, determined as provided in the Contract Documents.

ARTICLE 6 – TIME OF COMPLETION

6.01 Bidder agrees that the Work will be substantially complete on or before August 14, 2026 and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before August 21, 2026.

6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 7 – ATTACHMENTS TO THIS BID

7.01 The following documents are submitted with and made a condition of this Bid:

A. Unit Price Table – Section 00415

B. Required Bid Security – Section 00430

C. Required Bidder Qualification Statement with Supporting Data – Section 00450

D. Sworn and Notarized Affidavit of Compliance – Iran Economic Sanctions Act – Section 00460

E. Sworn and…