Summary

This is a formal bid solicitation document issued by the Town of Brookhaven Department of Fire Prevention for the installation of generators at four municipal locations: Calabro Airport, Brookhaven Landfill, Holtsville Ecology Site, and Old Town Road Highway Yard. The bid was issued on October 23, 2026, with technical questions due by October 30, 2026, and sealed bids due November 13, 2026, by 11:00 AM at the Division of Purchasing in Farmingville, New York. The Town accepts both electronic submissions through BidNet Direct and sealed bids delivered in person. The project is classified as 100 percent capital funding and specifies a primary trade classification of Electrician, though the Town reserves the right to approve other applicable trades. Bidders must provide evidence of five years of prior experience directly related to generator installation, valid licenses for electrical and plumbing work, and an Underwriter's Certificate. The document includes comprehensive technical specifications covering concrete foundations, HVAC piping and equipment support, natural gas piping, electrical systems including low-voltage conductors, control cables, grounding and bonding, raceways, and equipment supports.

Prevailing wage compliance is mandatory per New York State Department of Labor Section 220-I regulations, and vendors must submit NYS DOL registration certification with their bid or be actively registered at the time of bid opening. The project also requires compliance with the Town of Brookhaven Apprenticeship Training Program. Bidders must demonstrate authorization to do business in New York State. The Town welcomes and encourages participation from minority-owned, women-owned, veteran-owned, and HUD Section 3 businesses. Questions should be directed to Amanda Boland (Lead Agent) at aboland@brookhavenny.gov or Patricia Mazzei (Support Agent) at pmazzei@brookhavenny.gov. The Town reserves the right to reject any or all bids and to waive informalities if deemed in its best interests. No award date, contract term, or renewal options are specified in this solicitation document.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Town of Brookhaven Department of Fire Prevention

Installation of Generators at

Various Town Locations

Town of Brookhaven Bid Number 26045

Issue Date: October 23, 2026

Technical Questions Due By: October 30, 2026

Due Date & Place:

November 13, 2026, by 11:00 AM

Division of Purchasing One Independence Hill

Farmingville, New York 11738

Prepared By:

Updated September 2026 – 100% (capital)

Intent: Generator installation at Calabro Airport, Brookhaven Landfill, Holtsville Ecology Site, and Old Town Road Highway Yard.

TABLE OF CONTENTS

• NOTICE TO BIDDER

• SPECIAL REQUIREMENTS

• PROPOSER INFORMATION

• SCOPE OF WORK

• BID SPECIFICATIONS DESCRIPTIONS (YELLOW PAGES)

• BID – LINE ITEMS

• BID SHEET – LUMP SUM COST

• BID SUBSTITUTIONS

• PRC NUMBER - Link to Prevailing Wage Rate Schedule and Debarred List

• INSTRUCTION TO BIDDERS

• GENERAL CONDITIONS

• CONDITIONS OF CONTRACT

• AFFIDAVIT COMPLIANCE FORMS - REQUIRES SIGNATURE

TOWN OF BROOKHAVEN

SUFFOLK COUNTY, NY

NOTICE TO BIDDERS

Electronic Bids received in BidNet and delivered Sealed Bids will be publicly opened and read aloud at the Brookhaven Town Hall Complex located at One Independence Hill, Farmingville, New York, 11738, for the following project on the date as indicated at 11:00 am:

BID #26045

INSTALLATION OF GENERATORS AT VARIOUS TOWN LOCATIONS

BID DUE DATE: NOVEMBER 13, 2026

Specifications for the above-referenced bid will be available beginning October 23, 2026.

Technical questions and concerns will be expected no later than close of business, October 30, 2026

The Town of Brookhaven is pleased to announce that it now accepts electronic bid submissions through its Website utilizing our new BidNet Direct portal by SOVRA, by the specified due date and time as outlined in the bid document. The website also can be accessed at www.bidnetdirect.com//townofbrookhaven.

Sealed bids also will be accepted if delivered to Town Hall in the prescribed format by the specified due date and time as outlined in the bid document.

Preferred Method

• Access website: www.bidnetdirect.com//townofbrookhaven

• Follow directions to register (if not already registered) and download Bid document.

• Follow directions of how to submit Bid response electronically if preferred to Sealed Bid delivery

Questions must be submitted in writing to Finance Department Purchasing Division to aboland@brookhavenny.gov and pmazzei@brookhavenny.gov .

The Town of Brookhaven reserves the right to reject and declare invalid any or all bids and to waive any informalities or irregularities in the proposals received, if in the best interests of the Town.

The Town of Brookhaven welcomes and encourages minorities and women-owned businesses; veteran owned businesses, HUD Section 3 businesses, etc., to participate in the bidding process.

Further information can be obtained by calling (631) 451-6252

Town of Brookhaven Purchasing Division Tamara Branson, Commissioner

(631) 451-6252 https://gcc02.safelinks.protection.outlook.com/?url=http%3A%2F%2Fwww.bidnetdirect.com%2Ftownofbrookhaven&data=05%7C02%7Cbhein%40brookhavenny.gov%7C58d660fb86944749ca5f08de966c4f45%7C856ec158f34b4b4f9850b009cdae49fe%7C0%7C0%7C639113589085819402%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=sbaq2iplqb4suyJiGA4joRHN8omBMhtsQ45E0z25hAs%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=http%3A%2F%2Fwww.bidnetdirect.com%2Ftownofbrookhaven&data=05%7C02%7Cbhein%40brookhavenny.gov%7C58d660fb86944749ca5f08de966c4f45%7C856ec158f34b4b4f9850b009cdae49fe%7C0%7C0%7C639113589085819402%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=sbaq2iplqb4suyJiGA4joRHN8omBMhtsQ45E0z25hAs%3D&reserved=0 mailto:aboland@brookhavenny.gov mailto:pmazzei@brookhavenny.gov

26045

Special Requirements

1. All questions should be submitted, in writing, to the following Town contacts:

o Lead agent: Amanda Boland aboland@brookhavenny.gov o Support agent: Patricia Mazzei pmazzei@brookhavenny.gov

2. This project is subject to compliance with Prevailing Wages per NYS Department of Labor (DOL) regulations.

o SECTION 220-I OF THE NYS LABOR LAW REQUIRES THAT THE VENDOR MUST

SUBMIT A COPY OF NYS DOL REGISTRATION CERTIFICATION WITH THEIR

BID OR BE ACTIVELY REGISTERED WITH THE NYS DOL AT THE TIME OF BID

OPENING.

o See page 122 for detail and PRC number (2026028973) and link. Please note the schedule is NOT attached: the information is available by accessing the link provided on page 122.

3. This project requires compliance with the Town of Brookhaven Apprenticeship Training Program. See page 133-139, and 172 for compliance requirements.

4. The primary trade classification for this contract is as follows: E l e c t r i c i a n . However, the Town reserves the right to approve any trade that it deems applicable and appropriate for the type and scope of work to be performed under the Contract(s).

5. This project requires the following:

a. License for: Electrical and Plumbing

b. Certificate of: Underwriter’s Certificate

6. This project requires 5 years of previous experience as it directly relates to the stated SOW.

Documentation must be provided in support of the cited experience.

7. Please provide proof of the firm’s authorization to do business in the State of New York.

Failure to meet these requirements or to submit the required documentation with your proposal may result in the disqualification of the submission mailto:aboland@brookhavenny.gov mailto:pmazzei@brookhavenny.gov

26045

Proposer Information

Firm:

Street Address:

Town, State, Zip

Telephone:

Fax:

Signature of person authorized to make this proposal and sign contracts as may be required

(Print name) Title

Signature

Contact Name:

Title:

Office Telephone:

Cell Number:

Email Address:

Alternate Contact Name:

Title:

Office Telephone:

Cell Number:

Email Address:

Acknowledgement Receipt of Addenda:

#1

#2

#3

SCOPE OF WORK:

Generator installation 135 Dawn Drive, Shirley, NY 11967 (Calabro Airport), 350 Horseblock Road, Brookhaven, NY 11980 (Brookhaven Landfill), 249 Buckley Road, Holtsville, NY 11742 (Holtsville Ecology), and 1140 Old Town Road, Coram, NY 11727 (Old Town Road Highway Yard).

21361 - Brookhaven Generators -

1- TABLE OF CONTENTS 02-10-2026

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

011000 SUMMARY

012100 ALLOWANCES

013300 SUBMITTAL PROCEDURES

DIVISION 03 - CONCRETE

033053 MISCELLANEOUS CAST-IN-PLACE CONCRETE

DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

231123 FACILITY NATURAL-GAS PIPING

DIVISION 26 - ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND

CABLES

260523 CONTROL-VOLTAGE ELECTRICAL POWER CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS

260543 UNDERGROUND DUCTS AND RACEWAYS FOR ELECTRICAL

SYSTEMS

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

262416 PANELBOARDS

262726 WIRING DEVICES

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

263213.13 DIESEL-ENGINE-DRIVEN GENERATOR SETS

263213.16 GAS-ENGINE-DRIVEN GENERATOR SETS

263600 TRANSFER SWITCHES

DIVISION 31 - EARTHWORK

312000 EARTH MOVING

DIVISION 32 - EXTERIOR IMPROVEMENTS

321216 ASPHALT PAVING

329120 TOPSOIL

329219 SEEDING

Generator Installation at:

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

Summary 011000 - 1

SECTION 011000

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: Town of Brookhaven Generator Installation at Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road.

B. Owner's Name: Town of Brookhaven.

C. The Project consists of the construction of new generators and transfer switches at four locations.

1.02 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price.

1.03 OWNER OCCUPANCY

A. Owner intends to occupy the Project throughout construction.

B. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

C. Schedule the Work to accommodate Owner occupancy.

1.04 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas noted on Drawings.

1. Locate and conduct construction activities in ways that will limit disturbance to site.

B. Arrange use of site and premises to allow:

1. Owner occupancy.

C. Utility Outages and Shutdown:

1. Limit shutdown of utility services to eight hours at a time, arranged at least 24 hours in advance with Owner.

2. Prevent accidental disruption of utility services to other facilities.

END OF SECTION 011000

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

Allowances 012100 - 1

SECTION 012100

ALLOWANCES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Contingency allowance.

B. Utility allowance.

1.02 CONTINGENCY ALLOWANCE

A. Contractor's costs for products, delivery, installation, labor, insurance, payroll, taxes, bonding, equipment rental, overhead and profit will be included in Change Orders authorizing expenditure of funds from this Contingency Allowance.

B. Funds will be drawn from the Contingency Allowance only by Change Order.

C. At closeout of Contract, funds remaining in Contingency Allowance will be credited to Owner by

Change Order.

1.03 UTILITY ALLOWANCE

A. Costs Included in Utility Allowance: Payment of utility service charges. No overhead and profit are to be charged for payment of utility service charges.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

END OF SECTION 012100

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

SUBMITTAL PROCEDURES 013300 - 1

SECTION 013300

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.01 SUMMARY

A. Section Includes:

1. Submittal schedule requirements.

2. Administrative and procedural requirements for submittals.

1.02 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require

Engineer's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Engineer's responsive action. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.03 SUBMITTAL SCHEDULE

A. Submittal Schedule: Engineer will provide a submittal schedule indicating the minimum submittals required. Contractor may add to the submittal schedule as required.

1.04 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Project name.

2. Date.

3. Name of Contractor.

4. Unique submittal number, including revision identifier. Include Specification Section number or Sheet number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals. For example, 013300-01.

5. Submittal purpose and description.

6. Drawing number and detail references, as appropriate.

7. Location(s) where product is to be installed, as appropriate.

B. Options: Identify options requiring selection by Engineer.

C. Electronic Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number and description. For example, 013300-01 SUBMITTAL LOG.

1.05 SUBMITTAL PROCEDURES

A. Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Email: Prepare submittals as PDF package, and transmit to Engineer by sending via email. Include PDF transmittal form as part of submittal file.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification

Section as separate packages under separate transmittals.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows.

Time for review shall commence on Engineer's receipt of submittal. No extension of the

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

SUBMITTAL PROCEDURES 013300 - 2

Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 10 business days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Engineer will advise Contractor when a submittal being processed must be delayed for coordination.

2. Resubmittal Review: Allow 10 business days for review of each resubmittal.

D. Resubmittals: Make resubmittals in same form as initial submittal.

E. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

F. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Engineer's action stamp.

1.06 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams that show factory-installed wiring.

b. Printed performance curves.

c. Operational range diagrams.

d. Clearances required to other construction, if not indicated on accompanying Shop

Drawings.

5. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data unless submittal based on Engineer's digital data drawing files is otherwise permitted.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

SUBMITTAL PROCEDURES 013300 - 3

2. Identification: Permanently attach label on unexposed side of Samples that includes the following:

a. Project name and submittal number.

b. Generic description of Sample.

c. Product name and name of manufacturer.

d. Sample source.

e. Number and title of applicable Specification Section.

f. Specification paragraph number and generic name of each item.

3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics, and identification information for record.

D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

E. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of Engineers and owners, and other information specified.

F. Design Data: Prepare and submit written and graphic information indicating compliance with indicated performance and design criteria in individual Specification Sections. Include list of assumptions and summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Number each page of submittal.

G. Certificates:

1. Certificates and Certifications Submittals: Submit a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

Provide a notarized signature where indicated.

2. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

3. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.

Include evidence of manufacturing experience where required.

4. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

5. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

6. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on AWS forms. Include names of firms and personnel certified.

H. Test and Research Reports:

1. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for substrate preparation and primers required.

2. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

3. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

4. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

SUBMITTAL PROCEDURES 013300 - 4

evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

1.07 DELEGATED-DESIGN SERVICES

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are insufficient to perform services or certification required, submit a written request for additional information to Engineer.

B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally signed PDF file and three paper copies of certificate, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the

Contract Documents. Include list of codes, loads, and other factors used in performing these services.

1.08 MATERIAL SUBMITTALS AND INSTALLATION REQUIREMENTS

A. Material submittals shall include a written description of their proposed application.

B. Approved materials are assumed to be for use in accordance with the Contract Documents only. Deviation from the specified application shall be submitted for review with material submittals.

C. Approval of specified materials does not permit the Contractor to deviate from the specified application of those materials.

D. Approval of alternate materials only permits the Contractor to install them in accordance with the written description of their proposed application.

1.09 ENGINEER'S REVIEW

A. Action Submittals: Engineer will review each submittal, indicate corrections or revisions required, and return it.

1. PDF Submittals: Engineer will indicate, via markup on each submittal, the appropriate action.

a. NO EXCEPTIONS TAKEN: Engineer takes no exceptions to the submittal as provided for review. No further action is required.

b. MAKE CORRECTIONS NOTED: Engineer takes no exceptions to the submittal as provided for review with the exception of minor comments and / or selections.

Contractor shall take note of Engineer’s comments and / or selections. No further action is required.

c. AMEND AND RESUBMIT: Contractor shall amend the submittal per the Engineer’s comments and resubmit for approval.

d. REJECTED – SEE REMARKS: Submittal is rejected. Contractor shall review

Engineer’s comments and resubmit for approval.

B. Informational Submittals: Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements. Engineer will forward each submittal to appropriate party.

C. Engineer will discard submittals received from sources other than Contractor.

D. Submittals not required by the Contract Documents will be returned by Engineer without action.

E. Submittals for substitutions will not be reviewed more than three times if not found acceptable by the Engineer.

1.10 MATERIAL SUBMITTALS AND INSTALLATION REQUIREMENTS

A. Material submittals shall include a written description of their proposed application.

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

SUBMITTAL PROCEDURES 013300 - 5

B. Approved materials are assumed to be for use in accordance with the Contract Documents only. Deviation from the specified application shall be submitted for review with material submittals.

C. Approval of specified materials does not permit the Contractor to deviate from the specified application of those materials.

D. Approval of alternate materials only permits the Contractor to install them in accordance with the written description of their proposed application.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

END OF SECTION 013300

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

MISCELLANEOUS CAST-IN-PLACE CONCRETE 033053 - 1

SECTION 033053

MISCELLANEOUS CAST-IN-PLACE CONCRETE

PART 1 GENERAL

1.01 SUMMARY

A. Section includes cast-in-place concrete, including reinforcement, concrete materials, mixture design, placement procedures, and finishes.

1.02 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Design Mixtures: For each concrete mixture.

C. Testing Lab Qualifications

1.03 INFORMATIONAL SUBMITTALS

A. Material Text Reports.

1.04 QUALITY ASSURANCE

A. Ready-Mix-Concrete Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C94/C94M requirements for production facilities and equipment.

1.05 FIELD CONDITIONS

A. Cold-Weather Placement: Comply with ACI 301 and ACI 306.1.

B. Hot-Weather Placement: Comply with ACI 301 and ACI 305.1.

PART 2 PRODUCTS

2.01 CONCRETE, GENERAL

A. Comply with ACI 301.

B. Comply with ACI 117.

2.02 STEEL REINFORCEMENT

A. Reinforcing Bars: ASTM A615/A615M, Grade 60, deformed.

B. Plain-Steel Welded-Wire Reinforcement: ASTM A1064/A1064M, plain, fabricated from as-drawn steel wire into flat sheets.

2.03 CONCRETE MIXTURE

A. Concrete shall be Concrete Class Type A as per Section 500 of the New York State Department of Transportation Specifications.

2.04 RELATED MATERIALS

A. Vapor Retarder: Polyethylene sheet, ASTM D4397, not less than 10 mils thick; or plastic sheet, ASTM E1745, Class C.

B. Joint-Filler Strips: ASTM D1751, asphalt-saturated cellulosic fiber.

2.05 CURING MATERIALS

A. Moisture-Retaining Cover: ASTM C171, polyethylene film or white burlap-polyethylene sheet.

B. Water: Potable.

2.06 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to

ASTM C94/C94M and ASTM C1116/C1116M, and furnish batch ticket information.

B. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete in accordance with ASTM C94/C94M. Mix concrete materials in appropriate drum-type batch machine mixer.

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

MISCELLANEOUS CAST-IN-PLACE CONCRETE 033053 - 2

1. For mixer capacity of 1 cu. yd. or smaller, continue mixing at least 1-1/2 minutes, but not more than five minutes after ingredients are in mixer, before any part of batch is released.

2. For mixer capacity larger than 1 cu. yd., increase mixing time by 15 seconds for each additional 1 cu. yd..

3. Provide batch ticket for each batch discharged and used in the Work, indicating Project identification name and number, date, mixture type, mixture time, quantity, and amount of water added. Record approximate location of final deposit in structure.

PART 3 EXECUTION

3.01 FORMWORK INSTALLATION

A. Design, construct, erect, brace, and maintain formwork according to ACI 301.

3.02 EMBEDDED ITEM INSTALLATION

A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

3.03 VAPOR-RETARDER INSTALLATION

A. Install, protect, and repair vapor retarders according to ASTM E1643; place sheets in position with longest dimension parallel with direction of pour. Place sheets under slabs on grade within structures or buildings.

1. Lap joints 6 inches and seal with manufacturer's recommended adhesive or joint tape.

3.04 STEEL REINFORCEMENT INSTALLATION

A. Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.

1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.

3.05 JOINTS

A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

B. Contraction Joints in Slabs-on-Grade: Form weakened-plane contraction joints, sectioning concrete into areas as indicated. Construct contraction joints for a depth equal to at least one-fourth of concrete thickness

C. Isolation Joints in Slabs-on-Grade: After removing formwork, install joint-filler strips at slab junctions with vertical surfaces, such as column pedestals, foundation walls, grade beams, and other locations, as indicated.

1. Extend joint-filler strips full width and depth of joint, terminating flush with finished concrete surface unless otherwise indicated.

3.06 CONCRETE PLACEMENT

A. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301.

B. Consolidate concrete with mechanical vibrating equipment according to ACI 301.

3.07 FINISHING FORMED SURFACES

A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie holes and defects repaired and patched. Remove fins and other projections exceeding 1/2 inch.

1. Apply to concrete surfaces not exposed to public view.

B. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defective areas. Remove fins and other projections exceeding 1/8 inch.

1. Apply to concrete surfaces exposed to public view or to receive a rubbed finish, be covered with a coating or covering material applied directly to concrete.

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

MISCELLANEOUS CAST-IN-PLACE CONCRETE 033053 - 3

C. Rubbed Finish: Apply the following rubbed finish, defined in ACI 301 to smooth-formed-finished as-cast concrete where indicated:

1. Smooth-rubbed finish.

D. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed surfaces, strike off smooth and finish with a texture matching adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent unformed surfaces unless otherwise indicated.

3.08 FINISHING UNFORMED SURFACES

A. General: Comply with ACI 302.1R for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

B. Screed surfaces with a straightedge and strike off. Begin initial floating using bull floats or darbies to form a uniform and open-textured surface plane before excess moisture or bleedwater appears on surface.

1. Do not further disturb surfaces before starting finishing operations.

C. Float Finish: Apply float finish to indoor housekeeping pads.

D. Trowel and Fine-Broom Finish: Apply a partial trowel finish, stopping after second troweling, to exterior slabs and housekeeping pads. Immediately after second troweling, and when concrete is still plastic, slightly scarify surface with a fine broom.

3.09 CONCRETE PROTECTING AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and with ACI 305.1for hot-weather protection during curing.

B. Begin curing after finishing concrete but not before free water has disappeared from concrete surface.

C. Curing Methods: Cure formed and unformed concrete for at least seven days by one or a combination of the following methods:

1. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive. Cure for not less than seven days.

Immediately repair any holes or tears during curing period, using cover material and waterproof tape.

3.10 FIELD QUALITY CONTROL

A. Testing Agency: Contractor shall engage a qualified testing and inspecting agency to perform tests and inspections and to submit reports.

1. Testing agency shall be responsible for providing curing container for composite samples on Site and verifying that field-cured composite samples are cured in accordance with

ASTM C31/C31M.

2. Testing agency shall immediately report to Engineer, Contractor, and concrete manufacturer any failure of Work to comply with Contract Documents.

3. Testing agency shall report results of tests and inspections, in writing, to Owner, Engineer, Contractor, and concrete manufacturer within 48 hours of inspections and tests.

a. Test reports shall include reporting requirements of ASTM C31/C31M, ASTM C39/C39M, and ACI 301, including the following as applicable to each test and inspection:

1) Project name.

2) Name of testing agency.

3) Names and certification numbers of field and laboratory technicians performing inspections and testing.

4) Name of concrete manufacturer.

5) Date and time of inspection, sampling, and field testing.

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

MISCELLANEOUS CAST-IN-PLACE CONCRETE 033053 - 4

6) Date and time of concrete placement.

7) Location in Work of concrete represented by samples.

8) Date and time sample was obtained.

9) Truck and batch ticket numbers.

10) Design compressive strength at 28 days.

11) Concrete mixture designation, proportions, and materials.

12) Field test results.

13) Information on storage and curing of samples before testing, including curing method and maximum and minimum temperatures during initial curing period.

14) Type of fracture and compressive break strengths at seven days and 28 days.

B. Batch Tickets: For each load delivered, submit three copies of batch delivery ticket to testing agency, indicating quantity, mix identification, admixtures, design strength, aggregate size, design air content, design slump at time of batching, and amount of water that can be added at Project site.

C. Concrete Tests: Testing of composite samples of fresh concrete obtained in accordance with ASTM C 172/C 172M shall be performed in accordance with the following requirements:

1. Testing Frequency: Obtain one composite sample for each day's pour of each concrete mixture less than 25 cu. yd., plus one set for each additional 50 cu. yd. or fraction thereof.

2. Compression Test Specimens: ASTM C31/C31M:

a. Cast, initial cure, and field cure one set of two standard cylinder specimens for each composite sample.

3. Compressive-Strength Tests: ASTM C39/C39M.

a. Test one set of field-cured specimens at seven days and one set of specimens at 28 days.

4. Additional Tests:

a. Testing and inspecting agency shall make additional tests of concrete when test results indicate that compressive strengths or other requirements have not been met, as directed by Engineer.

b. Testing and inspecting agency may conduct tests to determine adequacy of concrete by cored cylinders complying with ASTM C42/C42M or by other methods as directed by Engineer.

1) Acceptance criteria for concrete strength shall be in accordance with ACI 301 section 1.6.6.3.

5. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.

6. Correct deficiencies in the Work that test reports and inspections indicate do not comply with the Contract Documents.

END OF SECTION 033053

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

HANGERS AND SUPPORTS FOR HVAC PIPING

AND EQUIPMENT 230529 - 1

SECTION 230529

HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

PART 1 GENERAL

1.01 SUMMARY

A. Section Includes:

1. Metal pipe hangers and supports.

2. Trapeze pipe hangers.

3. Thermal-hanger shield inserts.

4. Fastener systems.

5. Equipment supports.

1.02 PERFORMANCE REQUIREMENTS

A. Delegated Design: Design trapeze pipe hangers and equipment supports, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.

B. Structural Performance: Hangers and supports for HVAC piping and equipment shall withstand the effects of gravity loads and stresses within limits and under conditions indicated according to ASCE/SEI 7.

1. Design supports for multiple pipes capable of supporting combined weight of supported systems, system contents, and test water.

2. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems and components.

3. Design seismic-restraint hangers and supports for piping and equipment.

1.03 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: Show fabrication and installation details and include calculations for the following; include Product Data for components:

1. Trapeze pipe hangers.

2. Equipment supports.

C. Delegated-Design Submittal: For trapeze hangers indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.

1.04 INFORMATIONAL SUBMITTALS

A. Welding certificates.

1.05 QUALITY ASSURANCE

A. Structural Steel Welding Qualifications: Qualify procedures and personnel according to

AWS D1.1/D1.1M, "Structural Welding Code - Steel."

B. Pipe Welding Qualifications: Qualify procedures and operators according to ASME Boiler and

Pressure Vessel Code.

PART 2 PRODUCTS

2.01 METAL PIPE HANGERS AND SUPPORTS

A. Carbon-Steel Pipe Hangers and Supports:

1. Description: MSS SP-58, Types 1 through 58, factory-fabricated components.

2. Galvanized Metallic Coatings: Pregalvanized or hot dipped.

3. Nonmetallic Coatings: Plastic coating, jacket, or liner.

4. Padded Hangers: Hanger with fiberglass or other pipe insulation pad or cushion to support bearing surface of piping.

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

HANGERS AND SUPPORTS FOR HVAC PIPING

AND EQUIPMENT 230529 - 2

5. Hanger Rods: Continuous-thread rod, nuts, and washer made of materials indicated on the Plans.

B. Stainless-Steel Pipe Hangers and Supports:

1. Description: MSS SP-58, Types 1 through 58, factory-fabricated components.

2. Padded Hangers: Hanger with fiberglass or other pipe insulation pad or cushion to support bearing surface of piping.

3. Hanger Rods: Continuous-thread rod, nuts, and washer made of stainless steel.

C. Copper Pipe Hangers:

1. Description: MSS SP-58, Types 1 through 58, copper-coated-steel, factory-fabricated components.

2. Hanger Rods: Continuous-thread rod, nuts, and washer made of stainless steel.

2.02 TRAPEZE PIPE HANGERS

A. Description: MSS SP-69, Type 59, shop- or field-fabricated pipe-support assembly made from structural carbon-steel shapes with MSS SP-58 carbon-steel hanger rods, nuts, saddles, and U-bolts.

2.03 INSULATION CLAMPS FOR STRUT-MOUNTED VERTICAL AND HORIZONTAL PIPE

A. Klo-Shure insulation clamp, or approved equal.

2.04 FASTENER SYSTEMS

A. Mechanical-Expansion Anchors: Insert-wedge-type, zinc-coated steel anchors, for use in hardened portland cement concrete; with pull-out, tension, and shear capacities appropriate for supported loads and building materials where used.

2.05 EQUIPMENT SUPPORTS

A. Description: Welded, shop- or field-fabricated equipment support made from structural carbon-steel shapes.

2.06 MISCELLANEOUS MATERIALS

A. Structural Steel: ASTM A 36/A 36M, carbon-steel plates, shapes, and bars; black and galvanized.

B. Grout: ASTM C 1107, factory-mixed and -packaged, dry, hydraulic-cement, nonshrink and nonmetallic grout; suitable for interior and exterior applications.

1. Properties: Nonstaining, noncorrosive, and nongaseous.

2. Design Mix: 5000-psi, 28-day compressive strength.

PART 3 EXECUTION

3.01 HANGER AND SUPPORT INSTALLATION

A. Metal Pipe-Hanger Installation: Comply with MSS SP-69 and MSS SP-89. Install hangers, supports, clamps, and attachments as required to properly support piping from the building structure.

B. Metal Trapeze Pipe-Hanger Installation: Comply with MSS SP-69 and MSS SP-89. Arrange for grouping of parallel runs of horizontal piping, and support together on field-fabricated trapeze pipe hangers.

1. Pipes of Various Sizes: Support together and space trapezes for smallest pipe size or install intermediate supports for smaller diameter pipes as specified for individual pipe hangers.

2. Field fabricate from ASTM A 36/A 36M, carbon-steel shapes selected for loads being supported. Weld steel according to AWS D1.1/D1.1M.

C. Fastener System Installation:

1. Install mechanical-expansion anchors in concrete after concrete is placed and completely cured. Install fasteners according to manufacturer's written instructions.

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

HANGERS AND SUPPORTS FOR HVAC PIPING

AND EQUIPMENT 230529 - 3

D. Install hangers and supports complete with necessary attachments, inserts, bolts, rods, nuts, washers, and other accessories.

E. Equipment Support Installation: Fabricate from welded-structural-steel shapes.

F. Install hangers and supports to allow controlled thermal and seismic movement of piping systems, to permit freedom of movement between pipe anchors, and to facilitate action of expansion joints, expansion loops, expansion bends, and similar units.

G. Install lateral bracing with pipe hangers and supports to prevent swaying.

H. Install building attachments within concrete slabs or attach to structural steel. Install additional attachments at concentrated loads, including valves, flanges, and strainers, NPS 2-1/2 and larger and at changes in direction of piping. Install concrete inserts before concrete is placed;

fasten inserts to forms and install reinforcing bars through openings at top of inserts.

I. Load Distribution: Install hangers and supports so that piping live and dead loads and stresses from movement will not be transmitted to connected equipment.

J. Pipe Slopes: Install hangers and supports to provide indicated pipe slopes and to not exceed maximum pipe deflections allowed by ASME B31.9 for building services piping.

K. Insulated Piping:

1. Attach clamps around insulation.

a. Do not exceed pipe stress limits allowed by ASME B31.9 for building services piping.

2. Install insulation coupling for strut-mounted vertical and horizontal piping.

3. Install MSS SP-58, Type 39, protection saddles if insulation without vapor barrier is indicated. Fill interior voids with insulation that matches adjoining insulation.

4. Install MSS SP-58, Type 40, protective shields on cold piping with vapor barrier. Shields shall span an arc of 180 degrees.

5. Shield Dimensions for Pipe: Not less than the following:

a. NPS 1/4 to NPS 3-1/2: 12 inches long and 0.048 inch thick.

b. NPS 4: 12 inches long and 0.06 inch thick.

c. NPS 5 and NPS 6: 18 inches long and 0.06 inch thick.

d. NPS 8 to NPS 14: 24 inches long and 0.075 inch thick.

e. NPS 16 to NPS 24: 24 inches long and 0.105 inch thick.

6. Pipes NPS 8 and Larger: Include wood or reinforced calcium-silicate-insulation inserts of length at least as long as protective shield.

7. Thermal-Hanger Shields: Install with insulation same thickness as piping insulation.

3.02 EQUIPMENT SUPPORTS

A. Fabricate structural-steel stands to suspend equipment from structure overhead or to support equipment above floor.

B. Grouting: Place grout under supports for equipment and make bearing surface smooth.

C. Provide lateral bracing, to prevent swaying, for equipment supports.

3.03 METAL FABRICATIONS

A. Cut, drill, and fit miscellaneous metal fabrications for trapeze pipe hangers and equipment supports.

B. Fit exposed connections together to form hairline joints. Field weld connections that cannot be shop welded because of shipping size limitations.

C. Field Welding: Comply with AWS D1.1/D1.1M procedures for shielded, metal arc welding;

appearance and quality of welds; and methods used in correcting welding work; and with the following:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap.

3. Remove welding flux immediately.

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

HANGERS AND SUPPORTS FOR HVAC PIPING

AND EQUIPMENT 230529 - 4

4. Finish welds at exposed connections so no roughness shows after finishing and so contours of welded surfaces match adjacent contours.

3.04 ADJUSTING

A. Hanger Adjustments: Adjust hangers to distribute loads equally on attachments and to achieve indicated slope of pipe.

B. Trim excess length of continuous-thread hanger and support rods to 1-1/2 inches.

3.05 PAINTING

A. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces.

1. Apply paint by brush or spray to provide a minimum dry film thickness of 2.0 mils.

B. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780.

3.06 HANGER AND SUPPORT SCHEDULE

A. Specific hanger and support requirements are in Sections specifying piping systems and equipment.

B. Comply with MSS SP-69 for pipe-hanger selections and applications that are not specified in piping system Sections.

C. Use hangers and supports with galvanized metallic coatings for piping and equipment that will not have field-applied finish.

D. Use nonmetallic coatings on attachments for electrolytic protection where attachments are in direct contact with copper tubing.

E. Use padded hangers for piping that is subject to scratching.

F. Horizontal-Piping Hangers and Supports: Unless otherwise indicated and except as specified in piping system Sections, install the following types:

1. Adjustable, Steel Clevis Hangers (MSS Type 1): For suspension of noninsulated or insulated, stationary pipes NPS 1/2 to NPS 30.

2. Yoke-Type Pipe Clamps (MSS Type 2): For suspension of up to 1050 deg F, pipes NPS 4 to NPS 24, requiring up to 4 inches of insulation.

3. Carbon- or Alloy-Steel, Double-Bolt Pipe Clamps (MSS Type 3): For suspension of pipes

NPS 3/4 to NPS 36, requiring clamp flexibility and up to 4 inches of insulation.

4. Adjustable, Steel Band Hangers (MSS Type 7): For suspension of noninsulated, stationary pipes NPS 1/2 to NPS 8.

5. U-Bolts (MSS Type 24): For support of heavy pipes NPS 1/2 to NPS 30.

6. Pipe Saddle Supports (MSS Type 36): For support of pipes NPS 4 to NPS 36, with steel-pipe base stanchion support and cast-iron floor flange or carbon-steel plate.

7. Pipe Stanchion Saddles (MSS Type 37): For support of pipes NPS 4 to NPS 36, with steel-pipe base stanchion support and cast-iron floor flange or carbon-steel plate, and with U-bolt to retain pipe.

8. Single-Pipe Rolls (MSS Type 41): For suspension of pipes NPS 1 to NPS 30, from two rods if longitudinal movement caused by expansion and contraction might occur.

9. Complete Pipe Rolls (MSS Type 44): For support of pipes NPS 2 to NPS 42 if longitudinal movement caused by expansion and contraction might occur but vertical adjustment is not necessary.

G. Vertical-Piping Clamps: Unless otherwise indicated and except as specified in piping system Sections, install the following types:

1. Extension Pipe or Riser Clamps (MSS Type 8): For support of pipe risers NPS 3/4 to

NPS 24.

2. Carbon- or Alloy-Steel Riser Clamps (MSS Type 42): For support of pipe risers NPS 3/4 to

NPS 24 if longer ends are required for riser clamps.

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

HANGERS AND SUPPORTS FOR HVAC PIPING

AND EQUIPMENT 230529 - 5

H. Hanger-Rod Attachments: Unless otherwise indicated and except as specified in piping system Sections, install the following types:

1. Steel Turnbuckles (MSS Type 13): For adjustment up to 6 inches for heavy loads.

2. Steel Clevises (MSS Type 14): For 120 to 450 deg F piping installations.

I. Building Attachments: Unless otherwise indicated and except as specified in piping system Sections, install the following types:

1. Steel or Malleable Concrete Inserts (MSS Type 18): For upper attachment to suspend pipe hangers from concrete ceiling.

2. Top-Beam C-Clamps (MSS Type 19): For use under roof installations with bar-joist construction, to attach to top flange of structural shape.

3. Side-Beam or Channel Clamps (MSS Type 20): For attaching to bottom flange of beams, channels, or angles.

4. Center-Beam Clamps (MSS Type 21): For attaching to center of bottom flange of beams.

5. Welded Beam Attachments (MSS Type 22): For attaching to bottom of beams if loads are considerable and rod sizes are large.

6. C-Clamps (MSS Type 23): For structural shapes.

7. Welded-Steel Brackets: For support of pipes from below, or for suspending from above by using clip and rod. Use one of the following for indicated loads:

a. Light (MSS Type 31): 750 lb.

b. Medium (MSS Type 32): 1500 lb.

c. Heavy (MSS Type 33): 3000 lb.

8. Side-Beam Brackets (MSS Type 34): For sides of steel or wooden beams.

9. Plate Lugs (MSS Type 57): For attaching to steel beams if flexibility at beam is required.

J. Saddles and Shields: Unless otherwise indicated and except as specified in piping system Sections, install the following types:

1. Steel-Pipe-Covering Protection Saddles (MSS Type 39): To fill interior voids with insulation that matches adjoining insulation.

2. Protection Shields (MSS Type 40): Of length recommended in writing by manufacturer to prevent crushing insulation.

3. Thermal-Hanger Shield Inserts: For supporting insulated pipe.

K. Spring Hangers and Supports: Unless otherwise indicated and except as specified in piping system Sections, install the following types:

1. Spring Cushions (MSS Type 48): For light loads if vertical movement does not exceed 1-

1/4 inches.

2. Spring-Cushion Roll Hangers (MSS Type 49): For equipping Type 41, roll hanger with springs.

3. Variable-Spring Base Supports (MSS Type 52): Preset to indicated load and limit variability factor to 25 percent to allow expansion and contraction of piping system from base support.

L. Comply with MSS SP-69 for trapeze pipe-hanger selections and applications that are not specified in piping system Sections.

M. Use mechanical-expansion anchors instead of building attachments where required in concrete construction.

END OF SECTION 230529

Calabro Airport, Brookhaven Landfill, Holtsville Ecology, Old Town Road

FACILITY NATURAL-GAS PIPING 231123 - 1

SECTION 231123

FACILITY NATURAL-GAS PIPING

PART 1 GENERAL

1.01 SUMMARY

A. Section Includes:

1. Pipes, tubes, and fittings.

2. Piping specialties.

3. Piping and tubing joining materials.

4. Manual gas shutoff valves.

1.02 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

1.03 INFORMATIONAL SUBMITTALS

A. Welding certificates.

B. Field quality-control reports.

1.04 CLOSEOUT SUBMITTALS

A. Operation and maintenance data.

1.05 QUALITY ASSURANCE

A. Steel Support Welding Qualifications: Qualify procedures and personnel according to

AWS D1.1/D1.1M, "Structural Welding Code - Steel."

B. Pipe Welding Qualifications: Qualify procedures and operators…