Berwick Central Fire Station Roof scope of work - Google Search.pdf
PDF 92 KB Posted
- Attached to
- Berwick Central Fire Station Roof
- Solicitation number
- 26203973
- Issued by
- St. Martin Parish, Louisiana
About this file
This scope of work document outlines a roof conversion project for the Berwick Central Fire Station in Berwick, Louisiana, administered by the Town of Berwick. The project involves converting the existing flat roof system to a hip metal roof with new metal truss framing and standing seam metal roof panels. The work includes adjusting and modifying existing building vents and exhaust systems to accommodate the new roof configuration, as well as removing and properly disposing of the existing roofing system. The project is a single-phase construction effort expected to be completed within a few months of contract award. Bid submissions are managed by the Town of Berwick with a closing date of November 4, 2026.
Standard bonding requirements for this project include a 5% bid bond, certified check, performance bond, and payment bond. The project must be executed while maintaining compliance with active fire station operational requirements to ensure the facility continues to function during construction activities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Central Bidding - town of berwick Berwick Central Fire Station Roof (26203973).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The scope of work for the Berwick Central Fire Station roof project in Berwick, Louisiana, involves converting the existing flat roof into a hip metal roof .
Key Scope of Work Details
Roof Conversion Type: Converting the existing flat roof system to a hip metal roof.
Framing & Panels: Installing a new metal truss frame along with standing seam metal roof panels.
Vents & Exhausts: Adjusting and modifying existing building vents and exhaust systems to accommodate the new roof configuration.
Removal & Disposal: Removing the existing roofing system and properly disposing of old materials.
Compliance & Operations: Executing the project while maintaining compliance with active fire-station operational requirements.
Bonds & Requirements: Standard bonding requirements include a 5% bid bond, certified check, performance bond, and payment bond.
Timeline & Bidding: Bids are managed by the Town of Berwick (closing November 4, 2026), with the single-phase construction project expected to be completed within a few months of contract award.