This document is a Statement of Work (SOW) for a federal contract opportunity to provide barge crane services to remove and reinstall an Allied Marine Crane on a Coast Guard Barge.

The key details are:

  • The contractor must provide a barge crane capable of lifting 12,000 lbs and reaching a height of 80' and outreach of 70' to service the Coast Guard Barge USCGC OUACHITA located at the CG Schlimme Industrial Facility in St. Louis, MO.
  • The crane will be required for 5 hours on two specific dates: October 1, 2024 to remove the crane and October 22, 2024 to reinstall it.
  • The contractor must provide proof of a certified weight test of the crane within the last 12 months.
  • This is a small business set-aside acquisition with Solicitation Number 70Z02924QNEWO0168. The NAICS code is 811310 and the PSC code is M2BZ.
  • Quotes must be submitted via email to the Contracting Officer by the due date. The award will be based on the lowest price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1-Aug-24

BARGE CRANE SERVICE

This work item describes the requirements for the Contractor to provide a barge crane to remove and install equipment on a Coast Guard Barge.

Project Manager:

Mr. James Tepen Industrial Detachment Supervisor* Office (314) 771-6044 x 2103

Cell (314) 565-8893 Fax (314) 771-6269 *Visits for possible estimates must be scheduled with the Industrial Detachment Supervisor Project Location: CG Schlimme Industrial Facility

100 Arsenal Street Building 17

St. Louis, MO 63118 Location Work Hours:

0700 – 1500 (All work outside of these hours requires advanced approval from the Project Manager)

Vessel: USCGC OUACHITA (WLR 65501) Homeport: E. Chattanooga, TN

POC: MKC Dan Collard or Cutter Representative (423) 622-2214*

Remove Date: 1 Oct 2024 (8:00 am – 1:00 pm) Install Date:

22 Oct 2024 (8:00 am – 1:00 pm)

NOTE

Crane must be capable of mooring outboard of the USCG cutter, hoisting 12000 lbs and lowering it on the USCGC Ouachita. Approximately 80’ lift and 70’ outreach

1. SCOPE

1.1 This This work item describes the requirements for the Contractor to remove and reinstall the following equipment:

· 1ea Allied Marine Crane, TK20-50 Boom

12000lbs

2. REQUIREMENTS

2.1 General. The Contractor shall provide a barge crane with sufficient lifting capacity for the above listed equipment for a minimum period of five (5) hours on the date specified above. Positioning of the Barge crane shall be outboard of the Coast Guard Barge and the Allied Marine Crane boom shall be hoisted approximately 80’ height and 70’ outreach from the main pier to the cutter.

NOTE

Crane will be required to hold the load over the CGC Barge for an unspecified period while IPD St. Louis personnel position the boom onto the Allied Marine Crane pedestal.

SAFETY CAUTION!

A Coast Guard Deck Supervisor (Yellow Hard Hat) will direct all lifting and/or movement of the crane.

2.2 Equipment Removal. The Contractor shall lift equipment from the Coast Guard Barge to the main pier (approx. 80 feet above floating pier & 70 feet from centerline of the contracted floating crane) using lifting slings and straps provided by the Coast Guard. All equipment will be unfastened, unwired, and readied for removal by Coast Guard personnel.

2.3 Equipment Reinstall. The Contractor shall lift equipment from the main pier to the Coast Guard Barge for reinstallation by Coast Guard personnel using lifting slings and straps provided by the Coast Guard.

3. Quality Assurance

3.1 Certification. Contractor shall provided proof of Certified Weight Test of crane and weight handling equipment within the last twelve (12) months. Proof must be faxed to the project manager no later than one (1) week prior to start of project.

4. Notes

4.1 All persons conducting business with or at the U. S. Coast Guard Industrial Facility and onboard Coast Guard Cutters while moored at this facility are required to meet all applicable safety requirements including weather conditions set forth by the Coast Guard Industrial Facility and the Army Corps of Engineers.