B9443 - SOW.pdf

PDF 524 KB Posted

Attached to
BLD 9443 CMU Block Paint Removal Federal contract opportunity
Solicitation number
FA500020Q0090
Issued by
Department of the Air Force Pacific Air Forces

View the file

Other files for this federal contract opportunity

Other files attached to BLD 9443 CMU Block Paint Removal, newest first.
File Type Posted
Wage Determinations DavisBacon Act WD AK20200001.pdf PDF
Wage Determination.pdf PDF
Solicitation - FA500020Q0090.pdf PDF
AF 3000.doc DOC document
B9443 - AF 66 Submittals.xlsx XLSX spreadsheet
GENERAL SPECIFICATIONS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Joint base elmendorf richardson

STATEMENT OF WORK

Remove Paint from CMU Block Wall, B9443

PROJECT NUMBER FXSB191251

Date 29 Jul 20 ii

TABLE OF CONTENTS

PARTS:……………………………………………………………………......………………..PAGE

PART I – PROJECT SPECIFIC GUIDANCE

1. SCOPE

1.1. PERIOD OF PERFORMANCE

1.2. OBJECTIVE…………………………………………………………………………………..1

1.3. LIMITATIONS

2. POINTS OF CONTACT

3. GOVERNMENT-FURNISHED INFORMATION

PART II – GENERIC REQUIREMENTS

1. GOVERNING DESIGN AND CONSTRUCTION DOCUMENTS

2. DESIGN REQUIREMENTS

3. CONSTRUCTION REQUIREMENTS

4. CONTRACT ADMINISTRATION REQUIREMENTS

5. SECURITY

6. APPENDIX A……………………………………………………………………………

PART I – PROJECT SPECIFIC GUIDANCE

1. SCOPE

1.1. PERIOD OF PERFORMANCE: 45days After NTP

1.2. OBJECTIVE: Remove chipped paint from CMU block and seal.

A BUILDING SITEWORK – B9443

1.3. LIMITATIONS:

The contractor shall notify the Government of HVAC system shutdowns no less than four (4) business days prior to system shutdown date.

The contractor shall be escorted into any areas they do not have the appropriate clearance to be in as determined by the government.

2. POINTS OF CONTACT (POC):

POC(s) will be provided at the time of contract award.

3. GOVERNMENT-FURNISHED INFORMATION, EQUIPMENT, MATERIAL,

AND PROPERTY

A. INFORMATION – None provided.

B. EQUIPMENT – None provided.

C. MATERIAL – None provided.

D. PROPERTY – None provided.

PART II – GENERIC REQUIREMENTS

1. GOVERNING DESIGN AND CONSTRUCTION DOCUMENTS

A. Department of Defense specifications and criteria are located at https://wbdg.org/ffc/dod.

B. Air Force specifications and criteria are located at https://wbdg.org/ffc/af-afcec.

C. JBER Installation Facilities Standards (IFS) is located at https://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/jber-elmendorf-ifs file:///C:/Users/1285687558A/Desktop/t%20https:/wbdg.org/ffc/dod file:///C:/Users/1285687558A/Desktop/t%20https:/wbdg.org/ffc/dod file:///C:/Users/1285687558A/Desktop/t%20https:/wbdg.org/ffc/af-afcec https://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/jber-elmendorf-ifs https://www.wbdg.org/ffc/af-afcec/installation-facilities-standards-ifs/jber-elmendorf-ifs

2. TABLE OF DELIVERABLES

Paint removal: remove paint from CMU block face and metal trim by dry blasting (sand, walnut shells, etc.). At no time will water be applied to the brick exacerbating the efflorescence.

Efflorescence is a crystalline deposit of salts that can form when water is present in or on brick, concrete, stone, stucco or other building surfaces. It has a white or greyish tint and consists of salt deposits left behind when water evaporates.

Figure 1: Existing paint to be removed

Once paint has been removed from block, cleared and removed from the site, it will be cleaned via acid wash in preparation for final sealant.

Sealant shall be placed on the block to mitigate further water intrusion and efflorescence from occurring. No paint will be reapplied to the block.

Figure 2: Desired end product

Remove approximately 2430SF of paint along a trim wall at B9443.

Contractor will supply their own equipment, no government equipment or assets will be used for project.

Building will be occupied, coordination with building occupants will be necessary to minimize impact on US Government mission.

All dimensions listed are approximate. Those submitting bids are required to base their estimates on their own measurements.

3. CONSTRUCTION REQUIREMENTS

i. In accordance with (IAW) United Facilities Guide Specifications

(UFGS) 01 33 00 Submittal Procedures shall govern construction submittals.

ii. PERMITS – The Contractor is responsible for all applicable permits, licenses, and certificates required to perform and execute this contract.

b. CONTRACT ADMINISTRATION REQUIREMENTS

i. PROGRESS SCHEDULE, AF FORM 3064 – The Contractor shall prepare and submit, for approval, by the Contracting Officer (CO), a work breakdown structure. The work breakdown structure shall be used to report the cost and schedule status for this project. All tasks required under this type of contract shall be included in the work breakdown structure.

ii. NOTIFICATION REQUIREMENT – The Contractor is required to notify the Contracting Officer and the Project Manager of critical issues that may affect life, health, safety, contract performance, or the environment. Verbal notification should be made immediately followed by written notification as soon as practical.

4. SECURITY:

i. SECURITY INSTRUCTIONS: All personnel employed by the contractor in the performance of this contract, or any representative of the contractor entering the Installation shall abide by all security instructions and directives of JBER.

1. At the close for each work period, government facilities, equipment and materials shall be secured, lights, heat and water turned off and all doors and window secured.

2. The contractor and, as applicable, subcontractor shall not employ persons for work on this contract if such employee is identified as a potential threat to the health, safety, security, general wellbeing or operational mission of the Installation and its population, nor shall the contractor or subcontractor employ persons under this contract who have an outstanding criminal warrant as identified during the Criminal Background

Check (CBI).

3. Contractors shall ensure their employees and those of their subcontracts have the proper credentials allowing them to work in the United States. Employees and subcontractors later found to be undocumented workers will be remanded to the proper authorities.

4. All contractors and subcontractors when working in a

Controlled, Restricted or other sensitive areas must be escorted at all times while. The military agency or unit responsible for the project is responsible for providing the escorts. The

Contractor shall follow existing procedures and instructions for obtaining entrance to restricted or controlled areas.

ii. CONTRACTOR BADGE POLICIES: All requests for contractor badges will be submitted through the 673th Contracting Squadron (673

CONS) and/or therequesting agencies base point of contact. 673 CONS or base point of contact will then complete an Operational Risk

Management Assessment Form (ORM) for the requesting agency and submit it to the 673 SFS Pass and Registrations section for approval in accordance with Operation Plan (OPlan) 31-101. As a minimum the

ORM will be submitted 10-days prior to the requested date of employment. At no time will a contractor contact 673 Security Forces

Squadron (673 SFS) directly regarding badge denial.

1. All contactor employees requesting unescorted access to the

Installation are required to consent to a Criminal Background

Investigation (CBI) prior to being granted entry to the

Installation. Continued employment is contingent upon successful completion and favorable reporting of the CBI.

2. Joint Base Elmendorf-Richardson (JBER) Contractor badges will be issued for a maximum period of one year. Prior to reissuing new badges, all old badges must be returned to 673

SFS, Pass and Registration for destruction. Prior to reissuing a badge an ORM must be resubmitted to the 673 SFS Pass and

Registration section for approval. In the event a badge is lost or stolen, immediately contact the 673 SFS, Pass and Registration office. The badge holder must accomplish the Loss/Theft of

Identification Worksheet and provide it to his/her supervisor.

The supervisor of the contractor will investigate the loss and report in writing the circumstances in which the badge was lost to the 673 CONS and 673 SFS, Pass and Registration office. A new request for a badge must be completed prior to a new badge being reissued.

3. The 673 CONS or base POC will immediately notify 673 SFS, Pass and Registration when a contractor’s employment has been terminated. The Site Supervisors are responsible for notifying and returning the contractor’s badge to 673 SFS Pass and Registration when this occurs.

C. INSTALLATION ACCESS: The contractor shall obtain personal contractor identification badge for all employees and vehicle passes for all contractor and personal vehicles requiring entry onto JBER from 673 SFS, Pass and Registration, for the duration of the contract.

(1) Employees are only permitted to enter the Installation during the date and time periods indicted on their contractor badge. Vehicle registration, proof of insurance and a valid driver’s license must be presented for all vehicles while operating on the Installation. All vehicles entering JBER are subject to search.

Any refusal or non-consent by an employee will result in termination of their base access and immediate confiscation of this access badge.

(2) During Force Protection Condition (FPCON) Normal and Alpha, personnel without base issued badges must be sponsored onto the installation.

(3) During FPCON Bravo, Charlie and Delta, personnel without base issued identification shall be physically escorted onto the installation.

(4) During Higher FPCONs (Charlie and Delta) the base will normally curtail non-essential operations/functions; access by non-essential Contract operations will be suspended as the direction of the Installation Commander.

(5) Department of Defense (DoD) contractors or subcontractors without a Common

Access Card (CAC) or who do not have access to a government Non-classified

Internet Protocol Router Network (NIPRNET) computer performing construction on the installation should consider completing Anti-Terrorism (AT)

Awareness Level I training IAW AFI 10-245, Antiterrorism, Standard 25, by completing the― Force Protection computer based training (CBT) course through the Joint Knowledge Online (JKO) Learning Management System

(LMS) at http://jko.jten.mil/courses/atl1/launch.html IMPORTANT: The standalone course MUST be completed on the computer in which it is started.

Course progress is not transferable between computers. The standalone course does provide a completion certificate but will not be tracked on JKO and no record will be maintained. AT Awareness Level I Training should be provided by the requiring unit after contract award or the sponsoring organization.

D. FLIGHTLINE DRIVING: Not applicable for this project.

http://jko.jten.mil/courses/atl1/launch.html

File details come from the government source that posted it. Updated .