The document is a table showing the Department of the Navy's data on the time required to definitize change order proposals under construction contracts. The table breaks down the number of change order proposals definitized across six time intervals, ranging from 30 days or less to greater than 365 days. A total of 56 change order proposals were definitized after the completion of contract performance through a contract modification addressing all undefinitized equitable adjustments received during contract performance. The data provides insight into the Navy's contract modification and definitization timelines, with the majority of change order proposals (22) taking between 181 to 365 days to definitize.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Selected Agency: DEPT OF THE NAVY

Time to definitize after receipt of an adequate Change Order Definitization Proposal under Construction Contracts

Number of Change Order Proposals definitized under Construction Contracts

30 days or less 12

31 to 60 days 6

61 to 90 days 6

91 to 180 days 15

181 to 365 days 22

Greater than 365 days 13

After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance