B8_Att_Def_of_Equitable_Adj.pdf

PDF 6 KB Posted

Attached to
Bldg 1003 UPS Head Unit Install Federal contract opportunity
Solicitation number
N0025325Q0014
Issued by
Department of the Navy Naval Sea Systems Command

About this file

The document is a data table from the Department of the Navy presenting time-to-definitization metrics for Change Order Proposals under Construction Contracts. The table breaks down the number of Change Order Proposals definitized across different time intervals, ranging from 30 days or less to greater than 365 days. A notable entry shows 56 Change Order Proposals were definitized after completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance. The most frequent definitization timeframe is 181 to 365 days, with 22 Change Order Proposals falling into this category, followed by 91 to 180 days with 15 Change Order Proposals.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Selected Agency: DEPT OF THE NAVY

Time to definitize after receipt of an adequate Change Order Definitization Proposal under Construction Contracts

Number of Change Order Proposals definitized under Construction Contracts

30 days or less 12

31 to 60 days 6

61 to 90 days 6

91 to 180 days 15

181 to 365 days 22

Greater than 365 days 13

After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance