The document is a data summary of Equitable Adjustments Definitization for the Department of the Navy, tracking the time taken to definitize Change Order Proposals under Construction Contracts. The data reveals a distribution of definitization timelines: 12 proposals were definitized within 30 days, 6 between 31-60 days, 6 between 61-90 days, 15 between 91-180 days, 22 between 181-365 days, and 13 taking over 365 days. Additionally, 55 equitable adjustments were addressed via contract modification after contract performance completion.

The related federal contract opportunity is a pre-solicitation for the Naval Undersea Warfare Center Division (NUWC) Keyport, seeking a small business contractor to renovate Building 84's restroom and lunchroom. The project involves removing peeling paint, demolishing and installing plumbing fixtures, installing epoxy flooring, and repainting walls, ceiling, and window frames. The solicitation (N0025325Q0011) has a government estimated budget of $125,000-$175,000, targets a July 28, 2025 award date, and will be issued around May 19, 2025, with a 30-day response period. The contract will be a firm fixed-price construction type, 100% set aside for small businesses, using Low Price Technically Acceptable evaluation factors.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Definitization of Equitable Adjustments.

Selected Agency:
DEPT OF THE NAVY
Time to definitize after receipt of an adequate Change Order Definitization Proposal under Construction Contracts
Number of Change Order Proposals definitized under Construction Contracts
30 days or less
12
31 to 60 days
6
61 to 90 days
6
91 to 180 days
15
181 to 365 days
22
Greater than 365 days
13

After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance