B8_Att_Def_of_Equitable_Adj.docx

DOCX document 26 KB Posted

Attached to
Bldg 82 Replace Overhead Coiling Grille and Security Grate Federal contract opportunity
Solicitation number
N0025325Q0008
Issued by
Department of the Navy Naval Sea Systems Command

About this file

The document is a data file tracking the definitization of equitable adjustments for the Department of the Navy's construction contracts. The data shows the time taken to definitize change order proposals, with a breakdown of the number of proposals resolved within different time frames: 2 proposals within 30 days, 3 proposals between 31-60 days, 3 proposals between 61-90 days, 5 proposals between 91-180 days, 5 proposals between 181-365 days, and 2 proposals taking over 365 days. Additionally, 9 proposals were addressed after contract completion through contract modifications.

The related federal contract opportunity is a pre-solicitation for replacing overhead coiling rollup doors and security grilles at Naval Undersea Warfare Center Division (NUWC) Keyport's Building 82. The solicitation (N0025325Q0008) is set for a single firm fixed-price construction contract, 100% set aside for small businesses, with an estimated value between $25,000 and $100,000. The target award date is July 16, 2025, with the solicitation expected to be issued around April 27, 2025, and a 30-day response period. The project will use NAICS code 238290 and is located in Keyport, WA, with evaluation based on Low Price Technically Acceptable factors.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Definitization of Equitable Adjustments.

Selected Agency:
DEPT OF THE NAVY
Time to definitize after receipt of an adequate Change Order Definitization Proposal under Construction Contracts
Number of Change Order Proposals definitized under Construction Contracts
30 days or less
2
31 to 60 days
3
61 to 90 days
3
91 to 180 days
5
181 to 365 days
5
Greater than 365 days
2

After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance