This document appears to be a report on the definitization of equitable adjustments for change orders under construction contracts for the Department of the Navy. It provides statistics on the time taken to definitize change order proposals, with 30 days or less for 2 proposals, 31 to 60 days for 3 proposals, 61 to 90 days for 3 proposals, 91 to 180 days for 5 proposals, 181 to 365 days for 5 proposals, and greater than 365 days for 2 proposals. An additional 9 proposals were definitized after completion of the contract via a contract modification.

The related federal contract opportunity is for installing bird deterrents at various buildings at the Naval Undersea Warfare Center Division in Keyport, Washington. The government estimates the requirement to be between $100,000 and $150,000, and the solicitation will be 100% set aside for small businesses. The target award date is November 1, 2024, and the solicitation will be issued on or about August 26, 2024 with a 30-day response time. The contracting office will not maintain a bidders list, and an organized site visit is expected to be included in the solicitation.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Definitization of Equitable Adjustments.

Selected Agency:
DEPT OF THE NAVY
Time to definitize after receipt of an adequate Change Order Definitization Proposal under Construction Contracts
Number of Change Order Proposals definitized under Construction Contracts
30 days or less
2
31 to 60 days
3
61 to 90 days
3
91 to 180 days
5
181 to 365 days
5
Greater than 365 days
2

After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance