Summary
This is an Invitation for Bid issued by Fort Bend County, Texas for BID 27-020, Traffic Signal Pole Inventory, associated with the Fort Bend County Mobility Bond Project No. 23402. The project entails the procurement, delivery, and installation of traffic signal poles and mast-arms in standardized lengths (36, 44, 55, and 65 feet) with luminaires, along with the development of an inventory system for Fort Bend County's traffic signal infrastructure. The scope includes fabrication and delivery of TxDOT standard galvanized traffic signal poles with single mast-arms to an approved County Road & Bridge facility. A pre-bid conference is scheduled for Tuesday, November 10, 2026 at 9:30 AM Central Time at the Fort Bend County Purchasing Department in Richmond, Texas, with a site visit to follow if necessary. Sealed bids must be submitted electronically via the Bonfire Portal or by hard copy to the Fort Bend County Purchasing Department no later than 2:00 PM Central Time on Tuesday, November 24, 2026. The contract award will be made by Fort Bend County Commissioners Court to the lowest and best bidder. Bidders must complete all work within a maximum of 140 calendar days after issuance of a purchase order and notice to proceed.
Pricing must be firm for the contract duration with all costs specified on the bid sheet; bidders must include a bid bond or certified check equal to five percent of the total bid price. A pre-bid question deadline of Tuesday, November 17, 2026 at 9:00 AM Central Time applies. If the total bid price exceeds $25,000, a payment bond equal to 100 percent of the contract sum is required; if it exceeds $100,000, a performance bond of 100 percent is also required. Contractor insurance requirements include Workers' Compensation, Employers' Liability with $1,000,000 limits per injury, Commercial General Liability with $1,000,000 per occurrence and $2,000,000 aggregate, and Business Automobile Liability with $1,000,000 combined limits. The project is subject to prevailing wage requirements under Texas Government Code Chapter 2258 with specified wage rates for various classifications. Progress payments will be made monthly with retainage of ten percent for projects under $5 million or five percent for projects of $5 million or more. Liquidated damages of $250 per day apply for delays beyond the completion deadline. The contract is subject to Texas law and arbitration provisions, and contractor must comply with stormwater management requirements and all applicable federal, state, and local regulations.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared: 10/23/2026
Issued: 11/1/2026
Fort Bend County, Texas
Invitation for Bid
Traffic Signal Pole Inventory for Fort Bend County Mobility Bond Project No. 23402
BID 27-020
SUBMIT BIDS TO: SUBMIT NO LATER THAN:
Electronically using the Bonfire Portal: Tuesday, November 24, 2026 https://fortbendcountytx.bonfirehub.com/portal/ 2:00 PM (Central)
Or LABEL ENVELOPE:
Fort Bend County Purchasing Department (if responding by hard copy)
Travis Annex
301 Jackson, Suite 201
Richmond, TX 77469
Note: All correspondence must include the term
“Purchasing Department” in address to assist in proper delivery
-IF SUBMITTING A HARD COPY SEALED RESPONSE,
ALL BIDS MUST BE RECEIVED IN AND TIME/DATE STAMPED BY THE PURCHASING OFFICE
OF FORT BEND COUNTY ON OR BEFORE THE SPECIFIED TIME/DATE STATED ABOVE.
BIDS RECEIVED AS REQUIRED WILL THEN BE OPENED AND PUBLICLY READ.
BIDS RECEIVED AFTER THE SPECIFIED TIME, WILL BE RETURNED UNOPENED.
-IF SUBMITTING AN ELECTRONIC SEALED RESPONSE,
USING THE “BONFIRE” ELECTRONIC BIDDING PORTAL,
USE LINK, https://fortbendcountytx.bonfirehub.com/portal/, CLICK THE HELP BUTTON PROVIDED IN THE BONFIRE WEBSITE AS NEEDED.
Requests for information must be in
Results will not be given by phone. writing through the Bonfire Portal and
Results will be provided to bidder in writing directed to:
after Commissioners Court awards. LeAnn Cernoch
Senior Buyer
LeAnn.Cernoch@fortbendcountytx.gov
Vendor Responsibilities:
➢ Download and complete any addendums. (Addendums will be posted on the Bonfire Portal no later than 48 hours prior to bid opening)
➢ Submit response in accordance with requirements stated on the cover of this document.
➢ DO NOT submit responses via email or fax.
BID 27-020
Traffic Signal Pole Inventory https://fortbendcountytx.bonfirehub.com/portal/ https://fortbendcountytx.bonfirehub.com/portal/ mailto:LeAnn.Cernoch@fortbendcountytx.gov
COUNTY PURCHASING AGENT
Vendor Information
Legal Company Name (top line of W9) Business Name (if different from legal name)
Type of Business
Federal ID # or S.S. #
Age in Business?Corporation/LLC Sole Proprietor/Individual
Partnership Tax Exempt
SAM.gov Unique Entity ID #
SAM.gov
CAGE / NCAGE
Remittance Address
City/State/Zip
Physical Address
City/State/Zip
Phone Number
Contact Person E-mail
Check all that apply to the company listed above and provide certification number.
DBE-Disadvantaged Business Enterprise ___ SBE-Small Business Enterprise ___ HUB-Texas Historically Underutilized Business __ WBE-Women’s Business Enterprise __
Certification # ___________ Certification # ___________ Certification # ___________ Certification # ___________
Cert Date Exp Date
Company’s gross annual receipts
<$500,000 _____
$5,000,000-$16,999,999 ___
$500,000-$4,999,999 _____ $17,000,000-$22,399,999 _____ >$22,400,000 _____
NAICs codes (Please enter all that apply) Signature of Authorized Representative
Printed Name
Title
Date
Brooke Lindemann Purchasing Agent Office (281) 341-8640
THIS FORM MUST BE SUBMITTED WITH THE SOLICITATION RESPONSE
Publicly Traded Business ___ Noo ___ Yes Ticker Symbol ________
Fort Bend County Bid 27-020
Initials of Bidder: __________
1.0 GENERAL REQUIREMENTS:
1.1 Read this entire document carefully. Follow all instructions. You are responsible for fulfilling all requirements and specifications. Be sure you understand them.
1.2 General Requirements apply to all advertised bids; however, these may be superseded, whole or in part, by the scope, special requirements, specifications, special specifications or other data contained herein.
1.3 Governing Law: Bidder is advised that these requirements shall be fully governed by the laws of the State of Texas and that Fort Bend County may request and rely on advice, decisions and opinions of the Attorney General of Texas and the
County Attorney concerning any portion of these requirements.
1.4 Bid Form Completion: Fill out, sign, and return to the Fort Bend County
Purchasing Department one (1) complete bid form. An authorized representative of the bidder must sign the Contract Sheet. The Contract will be binding only when signed by the County Judge, Fort Bend County and a purchase order authorizing the item(s) desired has been issued. The use of corrective fluid is not acceptable and may result in the disqualification of bid. If an error is made, the bidder must draw a line through error and initial each change.
If a pricing form in Excel is included and/or posted amongst this bid document, the Vendor must download, complete and save the Excel (not a PDF of the Excel file) file of the pricing form on a flash drive if responding by hard copy. The
Excel file on the flash drive must be downloadable by the Purchasing Department in order to copy and paste the vendor’s pricing to the County’s tabulation. The flash drive must be labeled and included in the same sealed envelope with the respondent’s completed bid document along with a printed copy of the pricing form completed by the vendor.
1.5 Bid Returns:
1.5.1 Electronic Sealed Submission Requirements: Use Bonfire Portal Link https://fortbendcountytx.bonfirehub.com/portal/?tab=openOpportunities
Click the help button provided in the Bonfire website as needed. Note that this is the preferred method of submission for all Fort Bend County
Solicitations. Responses are required by Bid opening time of 2:00 PM on the date specified. Late bids will not be accepted.
1.5.2 Hard Copy Sealed Submission Requirements: Bidders must return all completed bids to the Fort Bend County Purchasing Department at 301
Jackson, Suite 201, Richmond Texas no later than 2:00 P.M. on the date specified. Late bids will not be accepted. Bids must be submitted in a sealed envelope, addressed as follows: Fort Bend County Purchasing
Agent, Travis Annex, 301 Jackson, Suite 201 Richmond, Texas 77469.
https://fortbendcountytx.bonfirehub.com/portal/?tab=openOpportunities
1.6 Addenda: No interpretation of the meaning of the drawings, specifications or other bid documents will be made to any bidder orally. All requests for such interpretations must be made in writing, utilizing the Q&A feature in the Bonfire portal addressed to LeAnn Cernoch, Senior Buyer. Any and all interpretations and any supplemental instructions will be in the form of written addenda to the contract documents which will be posted on the Bonfire portal. Addenda will
ONLY be issued by the Fort Bend County Purchasing Agent. It is the sole responsibility of each bidder to insure receipt of any and all addenda. All addenda issued will become part of the contract documents. Bidders must sign and include it in the returned bid package. Deadline for submission of questions and/or clarification is no later than Tuesday, November 17, 2026 at 9:00AM
(central). Requests received after the deadline will not be responded to due to the time constraints of this bid process.
1.7 References: All bidders must submit, WITH BID, at least three (3) references from clients for whom a project similar to that specified herein has been successfully accomplished. References must include, clients’ name, contact person and telephone number.
1.8 Bid Bond: All bidders must submit, WITH BID, a cashier's check or certified check for at least five percent (5%) of the total bid price, payable to the order of
Fort Bend County, or a Bid Bond in the same amount issued by a surety, acceptable to Fort Bend County, authorized to do business in the State of Texas, as a guarantee that the Bidder will do the work described herein at the rates stated herein. Unsuccessful bidder’s Cashier's Check or Certified Check will be returned only after a written request to do so have been received in the Office of the Fort Bend County Purchasing Agent.
1.9 Material Safety Data Sheets: Under the "Hazardous Communication Act", commonly known as the "Texas Right to Know Act", a bidder must provide to
Fort Bend County and using departments, with each delivery, material safety data sheets, which are, applicable to hazardous substances defined in the Act. Bidders are obligated to maintain a current, updated file in the Fort Bend County
Purchasing Department. Failure of the bidder to maintain such a file will be cause to reject any bid applying thereto.
1.10 Pricing: Prices for all goods and/or services shall be firm for the duration of this
Contract and shall be stated on the bid sheet. Prices shall be all inclusive. No price changes, additions, or subsequent qualifications will be honored during the course of the Contract. All prices must be written in ink or typewritten. If there are any additional charges of any kind, other than those mentioned above, specified or unspecified, bidder MUST indicate the items required and attendant costs or forfeit the right to payment for such items.
1.11 Term Contracts: If the Contract is intended to cover a specific time period, said time will be given in the specifications under scope.
1.12 Recycled Materials: Fort Bend County encourages the use of products made of recycled materials and shall give preference in purchasing to products made of recycled materials if the products meet applicable specifications as to quantity and quality. Fort Bend County will be the sole judge in determining product preference application.
1.13 Evaluation: Evaluation shall be used as a determinant as to which bid items or services are the most efficient and/or most economical for Fort Bend County. It shall be based on all factors which have a bearing on price and performance of the items in the user environment. All bids are subject to tabulation by the Fort Bend
County Purchasing Department and recommendation to Fort Bend County
Commissioners Court. Compliance with all bid requirements, delivery and needs of the using department are considerations in evaluating bids. Pricing is NOT the only criteria for making a recommendation. The Fort Bend County Purchasing
Department reserves the right to contact any bidder, at any time, to clarify, verify or request information with regard to any bid.
1.14 Disqualification of Bidder: Upon signing this bid document, a bidder offering to sell supplies, materials, services, or equipment to Fort Bend County certifies that the bidder has not violated the antitrust laws of this state codified in section 15.01, et seq., Business & Commerce Code, or the federal antitrust laws, and has not communicated directly or indirectly the bid made to any competitor or any other person engaged in such line of business. Any or all bids may be rejected if Fort
Bend County believes that collusion exists among the bidders. Bids in which the prices are obviously unbalanced may be rejected. If multiple bids are submitted by a bidder and after the bids are opened, one of the bids is withdrawn, the result will be that all of the bids submitted by that bidder will be withdrawn; however, nothing herein prohibits a vendor from submitting multiple bids for different products or services.
1.15 Awards: Fort Bend County reserves the right to award this Contract on the basis of lowest and best bid in accordance with the laws of the State of Texas, to waive any formality or irregularity, to make awards to more than one bidder, to reject any or all bids. In the event the lowest dollar bidder meeting specifications is not awarded a contract, the bidder may appear before the Commissioners Court and present evidence concerning its responsibility.
1.16 Contract Obligation: Fort Bend County Commissioners Court must award the
Contract and the County Judge or other person authorized by the Fort Bend
County Commissioners Court must sign the Contract before it becomes binding on Fort Bend County or the bidders. Department heads are not authorized to sign agreements for Fort Bend County. Binding agreements shall remain in effect until all products and/or services covered by this purchase have been satisfactorily delivered and accepted.
2.0 SCOPE:
It is the intent of Fort Bend County to contract with one (1) vendor for all materials, supplies, equipment, tools, services, labor and supervision necessary to complete the Traffic Signal Pole
Inventory, hereinafter referred to as the “Project,” as specified herein.
2.1 Work means the procurement, delivery and proper construction and/or installation of all materials and facilities and associated appurtenances necessary to fulfill the winning bidder’s obligations (hereinafter the “Contractor”) under the Contract as awarded for the Project specified herein, including the coordination and administration of all services necessary for Contractor, and/or its agents and/or subcontractors, to fulfill Contractor’s obligations under the Contract.
3.0 PRE-BID CONFERENCE:
A pre-bid conference will be conducted on Tuesday, November 10, 2026 at 9:30 AM (CST).
The pre-bid conference will be held at the Fort Bend County Purchasing Department located in the Travis Annex at 301 Jackson, Suite 201, Richmond, Texas 77469. All bidders are encouraged to attend. A site visit will be conducted after the conference, if necessary.
4.0 LIQUIDATED DAMAGES:
The County and the Contractor recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by the County if the work is not complete on time. Accordingly, instead of requiring any such proof, the County and the
Contractor agree that as liquidated damages for delay (but not as a penalty) the Contractor shall pay the County $250.00 for each day that expires after the time specified herein for completion until the Work is complete, unless contract time has been adjusted by extension of time approved by Commissioner’s Court.
The Contractor will be placed on one (1) year probation if liquidated damages are accrued.
During the probation period, if the Contractor accrues liquidated damages on another project, they will be disqualified from being awarded any County work for two (2) years.
5.0 COMPLETION TIME & PAYMENT:
5.1 Fort Bend County shall pay the Contractor in current funds for the Contractor’s performance of the Contract the contract sum, as stated herein, after receipt of notice to proceed and a purchase order issued by the Fort Bend County
Purchasing Agent.
5.2 Based upon Applications for payment submitted to the County Auditor, Fort Bend
County shall make progress payments on account of the contract sum to the
Contractor as provided below and elsewhere in the contract documents.
5.2.1 The period covered by each application for payment shall be one calendar month ending on the last day of the month.
5.2.2 Provided a customary, accurate and complete application for payment is received by the County Auditor not later than the 15th day of a month, Fort Bend County shall make payment of all undisputed amounts to the
Contractor not later than the 15th day of the next month. If an application for payment is received by the County Auditor after the application deadline fixed above, payment shall be made by Fort Bend County not later than 30 days after the County Auditor receives the application for payment.
5.2.3 Application for payment shall indicate the percentage of completion of each portion of the Project as of the end of the period covered by the application for payment.
5.2.4 Subject to the provisions of the contract documents, the amount of each progress payment shall be computed as follows:
5.2.4.1 Take that portion of the contract sum properly allocable to completed project less retainage of ten percent (10%) if the total project value is less than $5 Million; OR less retainage of five percent (5%) if the total project value is $5 million or more, per
Texas Local Government Code, Section 2252.032(b).
5.2.4.2 Add that portion of the contract sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction (or, if approved by Fort Bend County, suitably stored off the site at a location agreed upon in writing), less the appropriate retainage of five percent (5%) or ten percent (10%) as indicated above in
Section 5.2.4.1.
5.2.4.3 Subtract the aggregate of previous payments made by Fort Bend
County.
5.2.4.4 The progress payment amount as determined in above shall be further modified under the following circumstances:
Upon substantial completion of the Project, add a sum sufficient to increase the total payments to one hundred percent (100%) of the contract sum, less such amounts as Fort Bend County shall determine should be deducted for incomplete work and unsettled claims.
5.2.4.5 Final payment, constituting the entire unpaid undisputed balance of the contract sum, shall be made by Fort Bend County to the
Contractor when Fort Bend County and the Contractor agree that the Contract has been fully performed by the Contractor.
5.3 Before the first application for payment, the Contractor shall submit to the
Engineering Department a schedule of values allocated to various portions of the work, prepared in such form and supported by such data to substantiate its accuracy as the Engineering Department may require. This schedule, unless objected to by the Engineering Department shall be used as a basis for reviewing the Contractor’s application for payment.
5.4 Contractor must provide with each application for payment a contractor’s affidavit certifying bills against the Contractor for labor, material and expendable equipment employed in the performance of Contractor have been paid in full prior to acceptance of final payment from Fort Bend County.
5.5 The Contractor will permit Fort Bend County, or any duly authorized agent of
Fort Bend County, to inspect and examine the books and records of the Contractor for the purpose of verifying the amount of work performed under the Contract.
Fort Bend County’s right to inspect survives the termination of the Contract for a period of five years.
6.0 LIMIT OF APPROPRIATION:
Prior to the execution of this Contract, Contractor has been advised by County, and Contractor clearly understands and agrees, such understanding and agreement being of the absolute essence to this Contract, that County shall have available only those funds specifically allocated in this
Contract to fully discharge any and all liabilities which may be incurred by County in bringing this Project to an absolute conclusion, resulting in a complete, fully furnished, fully equipped and fully usable facility, and that the total of any and all basic construction costs, costs of providing the required services and materials, all fees and compensation of any sort to the Contractor, and any and all costs for any and all things or purposes coming inuring under or out of this Contract, irrespective of the nature thereof, shall not exceed said specifically allocated sum, notwithstanding any word, statement or thing contained in or inferred from the preceding provision of this Contract which might in any light by any person be interpreted to the contrary.
7.0 RIGHT TO ASSURANCE:
Whenever Fort Bend County in good faith has reason to question the Contractor's intent or ability to perform, Fort Bend County may demand that the Contractor give written assurance of its intent to perform and its plan to properly continue performance, including a reasonably detailed timeline. In the event that a demand is made and no assurance is given within five (5) business days, Fort Bend County may treat this failure as an anticipatory repudiation of the
Contract.
8.0 PERFORMANCE & PAYMENT BONDS:
Performance and Payment Bonds: In the event the total accepted bid price exceeds $25,000 the
Contractor must provide a payment bond in the amount of 100% of the total contract sum, and in the event the total accepted bid price exceeds $100,000 the contractor must also provide a performance bond in the amount of 100% of the total contract sum. Bonds must be submitted to the Office of the County Purchasing Agent within ten (10) calendar days after receipt of notification of bid award. Such bonds shall be executed by a corporate surety duly authorized and admitted to do business in the State of Texas and licensed in the State of Texas to issue surety bonds with a Best Rating of "A" or better. Fort Bend County reserves the right to accept or reject any surety company proposed by the Contractor. In the event Fort Bend County rejects, the proposed surety company, the Contractor will be afforded five (5) additional days to submit the required bonds issued by a surety company acceptable to Fort Bend County.
9.0 POWER OF ATTORNEY:
An attorney-in-fact who signs a bid bond, performance bond or payment bond must file with each bond a certified and effectively dated copy of his or her power of attorney.
10.0 INSURANCE:
10.1 All respondents shall submit, with response, a current certificate of insurance indicating coverage in the amounts stated below. In lieu of submitting a certificate of insurance, respondents may submit, with response, a notarized statement from an Insurance company, authorized to conduct business in the State of Texas, and acceptable to Fort Bend County, guaranteeing the issuance of an insurance policy, with the coverage stated below, to the firm named therein, if successful, upon award of this Contract.
10.2 At contract execution, contractor shall furnish County with properly executed certificates of insurance which shall evidence all insurance required and provide that such insurance shall not be canceled, except on 30 days prior written notice to
County. Contractor shall provide certified copies of insurance endorsements and/or policies if requested by County. Contractor shall maintain such insurance coverage from the time Services commence until Services are completed and provide replacement certificates, policies and/or endorsements for any such insurance expiring prior to completion of Services. Contractor shall obtain such insurance written on an Occurrence form (or a Claims Made form for Professional
Liability insurance) from such companies having Best’s rating of A/VII or better, licensed or approved to transact business in the State of Texas, and shall obtain such insurance of the following types and minimum limits:
10.2.1 Workers’ Compensation insurance. Substitutes to genuine Workers’
Compensation Insurance will not be allowed.
10.2.2 Employers’ Liability insurance with limits of not less than $1,000,000 per injury by accident, $1,000,000 per injury by disease, and $1,000,000 per bodily injury by disease.
10.2.3 Commercial general liability insurance with a limit of not less than
$1,000,000 each occurrence and $2,000,000 in the annual aggregate.
Policy shall cover liability for bodily injury, personal injury, and property damage and products/completed operations arising out of the business operations of the policyholder.
10.2.4 Business Automobile Liability coverage with a combined Bodily
Injury/Property Damage limit of not less than $1,000,000 each accident.
The policy shall cover liability arising from the operation of licensed vehicles by policyholder.
10.3 County and the members of Commissioners Court shall be named as additional insured to all required coverage except for Workers’ Compensation and
Professional Liability (if required). All Liability policies including Workers’
Compensation written on behalf of contractor, excluding Professional Liability, shall contain a waiver of subrogation in favor of County and members of
Commissioners Court.
10.4 If required coverage is written on a claims-made basis, contractor warrants that any retroactive date applicable to coverage under the policy precedes the effective date of the contract; and that continuous coverage will be maintained or an extended discovery period will be exercised for a period of two (2) years beginning from the time that work under the agreement is completed.
10.5 Contractor shall not commence any portion of the work under this Contract until it has obtained the insurance required herein and certificates of such insurance have been filed with and approved by Fort Bend County.
10.6 No cancellation of or changes to the certificates, or the policies, may be made without sixty (60) days prior, written notification to Fort Bend County.
10.7 Approval of the insurance by Fort Bend County shall not relieve or decrease the liability of the Contractor.
10.8 Builder’s Risk Insurance: Contractor is required to provide proof before a
Purchase Order is issued for this project and keep in full force and effect until the
Transfer Date, Builders Risk Insurance, subject to policy terms and conditions, of direct physical loss or damage to property, materials, equipment and supplies which are to become an integral part of the Project, whether owned by Contractor, or subcontractors of every tier, and in which one or more of same has an insurable interest, while in transit, while at the Construction Site awaiting construction, during construction, and until the Transfer Date. Such insurance shall be maintained to cover, as nearly as practicable, the insurable value of such property, materials, equipment and supplies at risk, and shall contain a waiver of subrogation in favor of Contractor, Architect, subcontractors of any tier and
Owner for loss or damage occurring during the Work and shall name Contractor as the named insured and Owner as additional insureds. All Builder's Risk
Insurance proceeds shall be paid directly to the Contractor.
11.0 INDEMNIFICATION:
Respondent shall save harmless County from and against all claims, liability, and expenses, including reasonable attorney’s fees, arising from activities of respondent, its agents, servants or employees, performed under this agreement that result from the negligent act, error, or omission of respondent or any of respondent’s agents, servants or employees.
11.1 Respondent shall timely report all such matters to Fort Bend County and shall, upon the receipt of any such claim, demand, suit, action, proceeding, lien or judgment, not later than the fifteenth day of each month; provide Fort Bend
County with a written report on each such matter, setting forth the status of each matter, the schedule or planned proceedings with respect to each matter and the cooperation or assistance, if any, of Fort Bend County required by Respondent in the defense of each matter.
11.2 Respondent's duty to defend, indemnify and hold Fort Bend County harmless shall be absolute. It shall not abate or end by reason of the expiration or termination of any contract unless otherwise agreed by Fort Bend County in writing. The provisions of this section shall survive the termination of the contract and shall remain in full force and effect with respect to all such matters no matter when they arise.
11.3 In the event of any dispute between the parties as to whether a claim, demand, suit, action, proceeding, lien or judgment appears to have been caused by or appears to have arisen out of or in connection with acts or omissions of
Respondent, Respondent shall never-the-less fully defend such claim, demand, suit, action, proceeding, lien or judgment until and unless there is a determination by a court of competent jurisdiction that the acts and omissions of Respondent are not at issue in the matter.
11.4 Respondent's indemnification shall cover, and Respondent agrees to indemnify
Fort Bend County, in the event Fort Bend County is found to have been negligent for having selected Respondent to perform the work described in this request.
11.5 The provision by Respondent of insurance shall not limit the liability of
Respondent under an agreement.
11.6 Respondent shall cause all trade contractors and any other contractor who may have a contract to perform construction or installation work in the area where work will be performed under this request, to agree to indemnify Fort Bend
County and to hold it harmless from all claims for bodily injury and property damage that may arise from said Respondent's operations. Such provisions shall be in form satisfactory to Fort Bend County.
11.7 Loss Deduction Clause - Fort Bend County shall be exempt from, and in no way liable for, any sums of money which may represent a deductible in any insurance policy. The payment of deductibles shall be the sole responsibility of Respondent and/or trade contractor providing such insurance.
12.0 PREVAILING WAGES:
This project is subject to the prevailing wage rate requirements of Chapter 2258 of the
Government Code. All persons employed by Contractor shall be compensated at not less than the rates shown below. Contractor shall keep detailed records of each of its workers and said records shall be made available to County for inspection at all reasonable times. The Contractor shall pay Fort Bend County sixty dollars ($60.00) for each worker employed by the Contractor for the provision of services described herein for each calendar day or part of the day that the worker is paid less than the below stated rates. Contractors may also visit www.wdol.gov/dba.aspx.
General Decision Number: TX20260299 05/18/2026
State: Texas
Construction Type: Highway
Counties: Austin, Brazoria, Chambers, Fort Bend, Galveston, Hardin, Harris, Jefferson, Liberty, Montgomery, Orange, San Jacinto and Waller Counties in Texas.
HIGHWAY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
If the contract is entered into on or after January 30, 2022, or the contract is renewed or extended
(e.g., an option is exercised) on or after January 30, 2022, Executive Order 14026 generally applies to the contract. The contractor must pay all covered workers at least $17.75 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in 2025.
If the contract was awarded on or between January 1, 2015 and January 29, 2022, and the contract is not renewed or extended on or after January 30, 2022, Executive Order 13658 generally applies to the contract. The contractor must pay all covered workers at least $13.30 per http://www.wdol.gov/dba.aspx hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours performing on that contract in 2025.
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive
Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/02/2026
1 05/18/2026
SATX2025-013 11/15/2023
Rates Fringes
Asphalt Distributor Operator $ 23.26 0.00
Asphalt Paving Machine Operator $ 22.67 0.00
Asphalt Raker $ 20.41 0.00
Broom or Sweeper Operator $ 17.63 0.00
Concrete Finisher, Paving and Structures $ 20.79 0.00
Concrete Pavement Finishing Machine Operator $ 22.18 0.00
Concrete Paving, Curing, Float, Texturing Machine Operator $ 22.62 0.00
Concrete Saw Operator $ 21.57 0.00
Crane Operator, Hydraulic 80 tons or less $ 24.75 0.00
Crane Operator, Lattice Boom 80 Tons or Less $ 25.74 0.00
Crane Operator, Lattice Boom Over 80 Tons $ 23.85 0.00
Crawler Tractor Operator $ 20.33 0.00
Electrician $ 31.46 0.00
Excavator Operator, 50,000 pounds or less $ 21.53 0.00
Excavator Operator, Over 50,000 pounds $ 22.24 0.00
Flagger $ 16.63 0.00
Form Builder/Setter, Structures $ 19.93 0.00
Form Setter, Paving & Curb $ 19.32 0.00
Foundation Drill Operator, Crawler Mounted $ 22.25 0.00
Foundation Drill Operator, Truck Mounted $ 26.04 0.00
Front End Loader Operator, 3 CY or Less $ 19.72 0.00
Front End Loader Operator, Over 3 CY $ 20.34 0.00
Laborer, Common $ 17.12 0.00
Laborer, Utility $ 19.11 0.00
Loader/Backhoe Operator $ 21.37 0.00
Mechanic $ 23.38 0.00
Milling Machine Operator $ 21.65 0.00
Motor Grader Operator, Fine Grade $ 23.91 0.00
Motor Grader Operator, Rough $ 21.20 0.00
Off Road Hauler $ 17.12 0.00
Painter, Structures $ 26.40 0.00
Pavement Marking Machine Operator $ 17.12 0.00
Piledriver $ 21.48 0.00
Pipelayer $ 20.03 0.00
Reinforcing Steel Worker $ 22.34 0.00
Roller Operator, Asphalt $ 19.79 0.00
Roller Operator, Other $ 18.93 0.00
Servicer $ 20.33 0.00
Spreader Box Operator $ 17.84 0.00
Structural Steel Worker $ 22.64 0.00
Truck Driver Lowboy Float $ 25.94 0.00
Truck Driver, Single Axle $ 21.93 0.00
Truck Driver, Single or Tandem Axle Dump Truck $ 18.60 0.00
Truck Driver, Tandem Axle Tractor with Semi Trailer $ 20.17 0.00
Welder $ 20.97 0.00
Work Zone Barricade Servicer $ 17.37 0.00
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR
5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC?
denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers
Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to
WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that
100% of the data reported for the classifications reflected union rates. EXAMPLE: UAVG-OH-
0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio. The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29
CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007
01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour
Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator
U.S. Department of Labor
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
Washington, DC 20210.
13.0 PERMITS:
It shall be the sole responsibility of the successful bidder to obtain all required permits in the name of Fort Bend County.
14.0 CONTRACTOR'S RESPONSIBILITY FOR WORK:
14.1 Preconstruction Work. Contractor shall do (or cause to be done) the following as preconstruction work:
14.1.1 On written demand as requested by Fort Bend County, cause the
Contractor’s personnel to meet with Fort Bend County and the Engineer to discuss the status of the Project.
14.1.2 On written demand as requested by Fort Bend County, review drawings and specifications with the Engineer to permit the Contractor and the
Engineer to determine the compliance of the proposed facility with applicable building codes.
14.2 Construction Work. Contractor shall do (or cause to be done) the following as construction work:
14.2.1 Perform (or cause to be performed) all preparatory work at the construction site required herein, including (without limitation) soil and concrete testing and demolition of improvements existing at the construction site and all actions necessary for compliance with all laws and regulations as to actions to be taken by owners or contractors before construction begins, including without limitation those in regard to archaeological and environmental requirements.
14.2.2 Construct and install (or cause to be constructed and installed) the Project on the construction site in accordance with this Contract and the drawings and specifications approved by Fort Bend County.
14.2.3 Furnish (or cause to be furnished) all materials, supplies, equipment, tools, labor, supervision, utilities, transportation, and other materials and services necessary to complete the Project described herein.
14.2.4 Materials testing necessary for the Project and required by laws and regulations, construction industry standards as approved by Fort Bend
County and this Contract; the frequency of testing shall be approved by
Fort Bend County. It is the contractor’s responsibility to engage a material testing laboratory to perform testing on the structural concrete to be used for foundation work in this project. The cost of testing shall be incidental to bid item for drill shaft foundation.
Testing of concrete shall comply with current TXDOT criteria.
Contractor has to submit the name of the testing laboratory, intended to be used by the contractor for this project, for County’s approval.
14.3 Standards for Review and Approval. Fort Bend County acknowledges that in order to meet the deadlines for the completion of the Project, and in order to accomplish the efficient completion of the Project, the Contractor may submit matters to Fort Bend County in stages for approval or consent. Upon receipt of any matter submitted by the Contractor for review and approval, Fort Bend
County shall review the same and shall diligently and promptly (but in any event within 14 calendar days for any such matter, other than a proposed change order, and within 28 calendar days for a proposed change order) give the Contractor notice of Fort Bend County's approval or disapproval, setting forth in detail all reasons for any disapproval. Fort Bend County's right to disapprove any such matter submitted (other than a proposed change order) shall be limited to the elements thereof (a) which do not conform substantially to matters previously approved, (b) which are new elements not previously presented and approved and the Contractor is unable to demonstrate that such new element is reasonably necessary for completion of the Project, or (c) which depict matters that are violations of this Contract or applicable laws and regulations.
14.3.1 If Fort Bend County disapproves of a particular matter or Proposed
Change Order, the Contractor shall have the right to resubmit such matter or Proposed Change Order to Fort Bend County, altered to satisfy Fort
Bend County's basis for disapproval. Any resubmission shall be subject to review and approval by Fort Bend County.
14.3.2 Fort Bend County and the Contractor shall attempt in good faith to resolve any disputes concerning the approval of any aspect of the Project expeditiously, so as not to delay the completion of the Project in accordance with this Contract.
14.3.3 Expedited Approvals. Fort Bend County recognizes the importance of expeditious action upon all matters submitted to Fort Bend County for review and approval and of expeditious response to those aspects of the
Project requiring approval by governmental authorities having jurisdiction there over. Fort Bend County agrees to exercise its rights of review and approval hereunder with due diligence, reasonableness, and good faith.
Fort Bend County shall use its reasonable efforts to expedite any required review of the Project or other matters by any governmental authority.
14.4 Changes.
14.4.1 General. Fort Bend County may make changes to the Project by altering, adding to, or deducting from the Project. All changes in the Project which
(a) require an adjustment in the contract sum or an adjustment in the final completion date or (b) involve a material change in the overall scope or function of the Project shall be requested and authorized before commencing such changes by use of written change order notices, Proposed Change Orders and Change Orders, which change order procedure shall be the exclusive means to effect such changes in the
Project.
14.4.2 Change Order Procedure. If at any time Fort Bend County desires to make any change in the Project requiring the issuance of a Change Order, Fort
Bend County shall so advise the Contractor in writing by delivery to the
Contractor of a written notice describing the change. Upon receipt of such notice initiated by Fort Bend County, the Contractor shall within a reasonable period of time advise Fort Bend County of the Contractor's proposal for the adjustments, if any, in the contract sum, the schedule of values, and the final completion date attributable to such change by delivering a written notice thereof (the "Proposed Change Order") to Fort
Bend County. Such Proposed Change Order shall contain a description of the proposed change and shall set forth the Contractor's estimate of the increase or decrease, if any, in the contract sum and the change, if any, in the schedule of values and the final completion date attributable to such change. If the Contractor desires to make a change in the Project requiring the issuance of a change order, the Contractor shall deliver to Fort Bend
County a Proposed Change Order. Upon execution by Fort Bend County, a Proposed Change Order shall constitute (and be defined herein as) a
"Change Order" for purposes of this Contract. The Contractor shall forthwith perform the work as changed in accordance with such Change
Order. All work performed pursuant to a Change Order shall be performed in accordance with the terms of this Contract. All Proposed Change Orders shall be submitted for approval by Fort Bend County. No action, acquiescence or inaction by Fort Bend County or any representative of
Fort Bend County shall be construed to be a waiver of requirements set forth in this Contract in regard to Change Orders or ratification of a violation of such requirements, and all acts in violation of this provision shall be considered void.
14.4.3 Change Order Authorization. Each Change Order shall be signed by Fort
Bend County and an authorized representative of the Contractor.
14.4.4 Contract Sum Adjustments. The contract sum and the schedule of values shall be adjusted only as a result of a Change Order requiring such adjustment. Any extra work performed without a proper Change Order shall be considered voluntary and not subject to additional compensation.
The Contractor shall not be entitled to an adjustment in the contract sum
(or a Change Order permitting such adjustment) or to damages as a result of any delays in the Project caused by the acts or omissions of Fort Bend
County, provided that this sentence is not applicable to delays that constitute more than 90 days in any 365-day period or cause the Project to be interrupted for a continuous period of 45 days through no fault of the
Contractor.
14.4.5 When Fort Bend County and the Contractor agree upon the adjustments in the contract sum, the schedule of values, and the final completion date attributable to such adjustment, such agreement will be documented by preparation and if approved by the Fort Bend County Commissioners
Court, execution of an appropriate Change Order.
14.5 Site Access. Prior to the transfer date, Fort Bend County and the Contractor shall have uninterrupted access to the construction site. Subsequent to the transfer date, Fort Bend County will permit the Contractor, the Engineer, and their representatives and subcontractors to enter upon the Project at times reasonably necessary to complete the punch list items.
14.6 Applicable Laws and Regulations. Contractor shall in its performance of the
Project comply with all applicable laws and regulations. Any delays in the prosecution of the Project caused by any changes in the laws and regulations or the application or enforcement of the laws and regulations may entitle the
Contractor to an extension of time.