B2506ADD1.pdf

PDF 126 KB Posted

Attached to
Generator for Lift Station #16
Solicitation number
B-25-06
Issued by
Volusia County, Florida

About this file

This document is Addendum #1 for the City of DeLand, Florida's Invitation to Bid (ITB) for a Generator for Lift Station #16, project number B-25-06, issued by the Finance Department on April 9, 2025. The addendum provides clarification on a bidder's question regarding payroll documentation and confirms that the proposal opening date and time remain unchanged, scheduled for April 24, 2025, at 3:00 P.M.

The addendum specifically addresses a contractor's inquiry about payroll document requirements, clarifying that if a vendor is providing only a product and not labor, the payroll form is not required with the bid submission. All other terms and conditions of the original bid package remain unaltered. The document is signed by Corey McMillen, the Purchasing Manager, and serves to provide official guidance to prospective contractors bidding on the generator project for Lift Station #16.

View the file

Other files

File Type Posted
B2506ADD2.pdf PDF
B2506ADD2.pdf PDF
B2506ADD1.pdf PDF
B2506Final.pdf PDF
B2506Final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Finance Department 120 S. Florida Ave.

2nd Floor

DeLand, FL 32720

Generator for Lift Station #16 B-25-06

April 9, 2025 Addendum #1

TO ALL PROSPECTIVE CONTRACTORS

This is an Addendum to and shall be considered as part of the original Proposal package for the abov e-mentioned Proposal. Contractors are requested to acknowledge receipt of this Addendum with their

Submission.

CLARIFICATION TO QUESTIONS ASKED & RECEIVED:

1. Q: Concerning payroll documents, if we are providing a product but not providing labor, is this form still required?

A: No, it is not required with bid submission.

Please note that the proposal opening date and time remains April 24, 2025 @ 3:00 P.M.

All other terms and conditions remain unchanged.

Sincerely, Corey McMillen, CPPB Purchasing Manager

END OF ADDENDUM #1

Generator for Lift Station #16
B-25-06
April 9, 2025
Addendum #1
TO ALL PROSPECTIVE CONTRACTORS
CLARIFICATION TO QUESTIONS ASKED RECEIVED: