B250 Remodel PER_JOFOC (1).pdf
PDF 225 KB Posted
- Solicitation number
- 80JSC024PA011
About this file
This document is a Justification for Other Than Full and Open Competition (JOFOC) prepared by NASA for a sole-source Purchase Order to Wright & Dalbin Architects, Inc. (WDA) to provide an addendum to the Preliminary Engineering Report (PER) for the new/remodel of the B250 Control Room at the NASA White Sands Test Facility (WSTF) in Las Cruces, New Mexico.
The addendum will include project management, architectural/engineering, and cost estimating services for an additional building option, with a total estimated value of $35,000. WDA is the only qualified source, as they completed the original 2019 PER and have exclusive knowledge of the facility requirements. The work is anticipated to be ongoing through September 2024. The new facility will address critical health and safety concerns and support NASA's mission-critical testing at WSTF, including spacecraft environmental systems, propulsion components, flight anomaly investigations, and fundamental space technology. NASA published a notice on SAM.gov but received no expressions of interest from other potential sources.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
Johnson Space Center (JSC)/White Sands Test Facility (WSTF)
JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION
(JOFOC)
For New/Remodel of B250 Control Room Preliminary Engineering Report (PER)
Addendum #1
1. Federal Acquisition Regulation (FAR) 6.303-2(b)(1) – Identification of the agency and the contracting activity, and specific identification of the document as a “Justification for other than full and open competition.”
This document is a justification for other than full and open competition prepared by the National Aeronautics and Space Administration (NASA) and the contracting activity will support JSC/WSTF, which is in Las Cruces, New Mexico.
2. FAR 6.303-2(b)(2) – The nature and/or description of the action being approved:
This justification provides the rationale for contracting by other than full and open competition to award a sole-source Purchase Order (PO) to Wright & Dalbin Architects, Inc.
(WDA) for preparing an addendum to the New/Remodel of B250 Control Room PER for the WSTF NASA. The original PER was completed by WDA in August of 2019.
3. FAR 6.303-2(b)(3) – A description of the supplies or services required, to meet the Agency’s needs (including the estimated value):
WDA will provide an addendum to the PER that they previously completed in 2019. Work will include project management, architectural/engineering, and cost estimating services for an additional building option. The total value of this PO is estimated at $35,000.00. The work will be ongoing through the summer of 2024 with a delivery date of the final report by no later than September 30, 2024.
The new facility will address critical human health and safety concerns for area personnel and provides a resilient and reliable facility with shelter in place capability and bathrooms.
The mission includes testing systems for Flight Acceptance Standard Test- (FAST), oxygen compatibility analysis, flammability analysis, particle impact testing, and high-pressure gas testing including hydrogen. WSTF conducts materials and component tests with oxygen in both gaseous and liquid states. Gaseous oxygen tests may be conducted at pressures up to 10,000 psi and at flow rates up to 2.5 pounds per second. Tests are conducted to determine compatibility with oxygen to enhance safe use or to determine life cycle issues including acceptance test and qualification of flight hardware. In addition, testing related to the evaluation of materials, components, and systems for developmental, qualification and acceptance testing under conditions reminiscent of spacecraft environments is performed.
The primary users of the future facility will include numerous NASA mission directorates, programs, and projects as follows: developers of space craft environmental control and life support systems, propulsion system component designers, investigations of mission critical flight anomalies, and systems supporting fundamental space technology, safety, and operations.
4. FAR 6.303-2(b)(4) – An identification of the statutory authority permitting other than full and open competition:
The statutory authority permitting other than full and open competition is 10 U.S.C.
3204(a)(1), as implemented by FAR 6.302-1(a)(2)(iii)(A), Only one responsible source and no other supplies or services will satisfy agency requirements without substantial duplication of cost to the Government.
5. FAR 6.303-2(b)(5) – A demonstration that the proposed contractor’s unique qualifications or the nature of the acquisition requires use of the authority cited:
The rationale supporting the use of 10 U.S.C. 3204(a) as described below.
WDA is the only responsible source to complete this effort as this Contractor completed the original PER for New/Remodel of B250 Control Room. The Contractor has exclusive knowledge of the base data related to many elements of the Facilities Requirements Document including site work, civil engineering, electrical requirements, mechanical requirements, energy management requirements, controls and instrumentation, ancillary test area monitoring, physical security, and information technology. If the Government selected another source, the Government would have to pay approximately $150,000 to recreate aspects of this work that has already been obtained from WDA. This would be a duplication of cost to the Government as WDA has already been paid for the initial award.
6. FAR 6.303-2(b)(6) – A description of the efforts made to ensure that offers are solicited from as many potential sources as practicable, including whether a notice was or will be publicized as required by Subpart 5.2 and, if not, which exception under 5.202 applies:
A notice to the Government Point of Entry (GPE) website (Sam.gov) was published on TBD, in accordance with FAR Subpart 5.2. This posting informed potential sources of NASA’s intent to award this sole-source contract to WDA. The results of this synopsis are summarized in Section 10 below.
7. FAR 6.303-2(b)(7) – A determination by the contracting officer that the anticipated cost to the Government will be fair and reasonable:
The Contracting Officer’s signature on this document indicates that the Contracting Officer has determined that the anticipated cost to the Government will be fair and reasonable. The Contractor shall be required to submit a proposal to be evaluated and negotiated by the Government. Prior to execution of the contractual instrument, a proposal analysis will be performed. The proposal analysis will ensure that the final agreed-to price for the contract action is fair and reasonable. Proposed pricing for this acquisition will be determined fair and reasonable through comparison of the proposed pricing to an Independent Government Estimate (IGE) completed by the technical team.
8. FAR 6.303-2(b)(8) – Description of the market research conducted, and the results, or a statement of the reasons market research was not conducted:
In an effort to determine potential capable vendors, multiple market research methods were conducted. For the predecessor acquisition, the TEST2 contractor at WSTF conducted market research in 2019 to obtain the services of WDA by conducting a qualification-based selection of Architect-Engineer Contractors to establish a blanket agreement. Award was then made to WDA under this established blanket agreement.
For this follow-on acquisition, a search was conducted online to identify companies in the local area that could possibly perform this effort. A total of four companies, including WDA, were identified and appear to have the resources to perform this work. However, utilizing these companies for this effort is not a feasible alternative for the reasons listed above in Section 5.
9. FAR 6.303-2(b)(9) – Any other facts supporting the use of other than full and open competition:
None.
10. FAR 6.303-2(b)(10) – A listing of the sources, if any, that expressed an interest in writing in the acquisition:
A notice of NASA’s intent to award this sole-source action was synopsized on the GPE website (Sam.gov) per FAR Subpart 5.2 (See Section 6 above). The synopsis was posted on June 4, 2024 and closed on June 7, 2024. No companies expressed any interest in performing this effort.
11. FAR 6.303-2(b)(11) – A statement of actions, if any, the agency may take to remove or overcome any barriers to competition before any subsequent acquisition for the supplies or services required:
The Agency will continue to examine the market in the future for alternative solutions or new sources before executing any subsequent acquisitions for the same requirements.