B08_-_Statement_of_Work.pdf

PDF 75 KB Posted

Attached to
HVAC CONSERVATION ROOM-R4-LA-SELA-A4SE0
Solicitation number
140FC224Q0053
Issued by

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to replace the air conditioning system in the Conservation Room at the Big Branch Marsh National Wildlife Refuge in Lacombe, Louisiana.

The key details are:

  • Solicitation Number: 140FC224Q0053
  • Project Location: 61389 HIGHWAY 434, Lacombe, LA 70445
  • Period of Performance: Ninety (90) Calendar Days after receipt of Notice to Proceed
  • Requirement: Replace existing 25-ton packaged rooftop gas heating/electric cooling unit with a new 25-ton gas/electric rooftop package with a minimum IEER of 11.5. Contractor to provide all labor, equipment, and dispose of old equipment.
  • Warranties: 5 years on the compressor and 1 year on labor
  • Contracting Agency: Department of the Interior Fish and Wildlife Service

The SOW provides detailed specifications for the work, including recovering refrigerant, disconnecting utilities, removing the existing unit, installing the new unit, and reconnecting all components. Points of contact for the Contracting Officer's Representative and Coordinator are also included.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation# 140FC224Q0053 - PR 0040673570

STATEMENT OF WORK – Replace AC system in the Conservation Room at the Big Branch Marsh National Wildlife Refuge in Lacombe, Louisiana.

Project Location: FWS Southeast Louisiana Refuges, 61389 HIGHWAY 434, Lacombe, LA 70445.

Period of Performance: Ninety (90) Calendar Days after receipt of Notice to Proceed.

Replace existing 25-ton packaged rooftop gas heating/electric cooling unit. Contractor to provide all labor, equipment and dispose of old equipment at 61389 Hwy 434, Lacombe LA 70445. The current heat package cannot be repaired. The Contractor shall furnish all labor, materials, supervision, equipment, tools, and all other necessary resources to construct the project as detailed in the drawings and specifications, and according to the contract terms and conditions for the project.

Minimum specifications:

• Recover the refrigerant from the system and dispose of properly.

• Disconnect the electrical, natural gas, refrigerant piping, drain lines and ductwork from the existing roof top package.

• Remove the roof top package.

• Replace 25-ton gas/electric roof top package with a minimum of IEER of 11.5

• Set new roof top package, on new skid with new emergency drain.

• Reconnect the electrical, ductwork, drain lines and refrigerant piping.

• Re-install sheet metal supply air plenum (existing plenum is operable and can be reused).

• Leak check the systems, evacuate, and charge with new refrigerant 410A.

• Start up the system and check for proper operation.

New systems will be covered by a warranty: 5 years on the compressor and 1 year on labor.

Agree to furnish all labor and materials to complete the work as described above.

COR/Coordinator Point of Contact Info:

Name: Robert G Beech Email: robert_beech@fws.gov Cell: 404-226-1907

Coordinator Point of Contact Info:

Name: Craig Allarding Email: craig_allarding@fws.gov Cell: 478-618-3874