B08_Statement_of_Work.docx

DOCX document 153 KB Posted

Attached to
APCO SEWER RELINE
Solicitation number
140P4224Q0068
Issued by

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to reline the gravity sewer piping at Appomattox Courthouse National Park in Appomattox, Virginia. The objective is to reline the sewer system, make repairs to manholes, install cleanouts, and reduce the cost of sewage pumped to the town of Appomattox.

The SOW includes details on the scope of work, project locations, duration, tasks and specifications, general guidance, warranty requirements, quality assurance, and submittal requirements. The contract opportunity has a Solicitation Number of 140P4224Q0068 and is being issued by the Department of the Interior National Park Service Northeast Region. An organized site visit is scheduled for July 9, 2024, and all questions are due by July 17, 2024. The contract has a period of performance of 90 days after the Notice to Proceed.

View the file

Other files

File Type Posted
B08_Attachment_4_-_Q_A_Document_0001.xlsx XLSX spreadsheet
Sol_140P4224Q0068_Amd_0001.pdf PDF
Site_Visit_Sign_In_0001.jpeg JPEG file
B08_Map_1.pdf PDF
B08_Map_2.pdf PDF
B08_APCO_Sewer_Reline_RFQ.docx DOCX document
Sol_140P4224Q0068.pdf PDF
B08_Wage_Determination_VA20240207.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Appomattox Courthouse National Park Appomattox, Virginia

STATEMENT OF WORK

Reline Gravity Sewer Piping

PMIS #: 341955

DATE

April 12, 2024 By John M. Mitchell February 6, 2017

NATIONAL PARK SERVICE

I. BACKGROUND / OBJECTIVES:

The original cast iron sewer line was replaced with 6” P.V.C. schedule 40 line between the years of 1978 and 1979. Over the past 45 years the gravity flow system has been compromised by tree roots. The objective of the project is to reline the sewer system to eliminate any possible water infiltration, make the necessary repairs to manholes, install cleanouts, and lower the cost of sewer that is pumped to the town of Appomattox.

II. SCOPE OF WORK:

Reline four sections of the piping and make needed repairs to the manholes within the gravity portion of the sanitary system. Reline five to six gravity lines from manholes to building structures.

III. PROJECT LOCATIONS:

Appomattox Court House National Historical Park 111 National Park Dr Appomattox VA 24522

IV. PROJECT DURATION:

· 90 Days after the Notice to Proceed has been issued.

· Hours of Operation: 7:00 A.M. to 5:00 P.M., Monday through Friday, excluding federal holidays.

· Overtime or weekend work will only be authorized with 48hrs notice.

V. TASKS / SPECIFICATIONS

1. Tasks:

The following tasks will be accomplished in compliance with all applicable governmental regulations and with all ordinances.

· Inspect the integrity of all manholes lined within the gravity system and make necessary repairs to prevent any possible water infiltration.

· Inspect 5 sewer lines from manhole to buildings and make necessary repairs to prevent any possible water infiltration.

2. Specifications:

· CCTV (Close-Circuit TV Inspection) approximately 360 LF of 6” sewer pipe between Peer’s House and Maintenance Complex.

· Reline Approximate 1153’ LF of 6” sewer pipe.

· Install 4 Cleanouts, 6-8’ deep, @ Maintenance Bld., Peer’s House, Meeks Store, and Isbell House.

· Raise 2 Frame and Manhole Coverings.

· Replace 8 Frame and Manhole Coverings.

· Install 9 Chimney Seals.

· Cap off existing sewer line at Clover Hill Kitchen and at manhole and add flowable fill to keep any infiltration out.

· Cap off existing sewer line at Clover Hill Guest House and at manhole and add flowable fill to keep out any infiltration.

VI. General Guidance:

· The Contractor shall be responsible for all site surveys, calculations, work plans, construction actions; equipment startups, and testing, repair, and/or training required for satisfactory completion of the work as required by each individual Task Order. This shall include, but not be limited to, providing labor, equipment, materials, applicable engineering documentation, and other necessary services and/or products for the construction, implementation, or testing that may be required by the individual Task Order.

· Obtain all necessary permits from DEQ and local municipality for the installation of this system.

· Archeological Monitoring will be coordinated by the park for any digging at buildings or along gravity lines.

VII. WARRANTY REQUIREMENTS:

· One year for the installation and Manufacturer’s warranty on all parts and equipment.

VIII. QUALITY ASSURANCE:

· Quality Control Plan: The Contractor shall provide a QASP (quality control and safety plan)

IX. SUBMITTALS

· The Contractor shall set up a Master Submittal List for items that will regularly be used throughout the contract. The submittal list provided for individual projects shall be submitted to the government within 7 calendar days of the project NTP.

· Project Schedule

· Complete as-built set of drawings upon completion and or provide copies of sewer line video.

X. BARRIERS & RESOURCE PROTECTION MEASURES

· Site Cleanup:

Although the government understands that a construction site is by nature not clean, the NPS desires to have work sites that are as clean, free of construction debris, and uncluttered as possible. For this reason, the Contractor shall clean work sites continuously to adhere to basic cleanliness and safety standards, and all FAR clauses for site cleanup. This shall include but is not limited to cleaning all haul routes and using covers for trucks hauling fill material. The Contractor shall respond to all government requests to clean the site within 1 hour. Ultimately it will be the contracting officer representative, and not the Contractor, who will determine what, constitutes a clean work site. The Contractor shall provide animal proof trash containers as directed by the COR.

· Construction Barriers & Fencing:

Construction fencing shall be included in the Contractor’s coefficient and shall be provided on all construction projects, unless specifically told otherwise. The fencing is intended not only for site safety and cleanliness, but also for aesthetic purposes. Dependent on specific requirements, worksite fencing may include government-approved screen material to hide the work site from visitors and Park Unit personnel. The Contractor shall determine the fencing requirement and area to be screened for the government’s review and approval. The Contractor shall respond to government requests to clean up or fix a downed fence at a job site within 1 hour. For the purposes of this contract, the definition of “construction fencing” shall be any barrier that the Contractor has to erect for site safety, cleanliness, screening, and/or protection of government- or Contractor-owned material inside or outside of any facility.

XI. GFP MATERIAL AND EQUIPMENT

N/A

XII. SPECIAL PRECAUTIONS / CONDITIONS

· Utility Shutdowns, Work Interruptions, and Street Closures:

The Contractor shall provide a minimum notice of 7 calendar days’ notice prior to any utility shutdowns and 10 calendar days for any road closures if it becomes necessary to interrupt the work activities of personnel at the project site, for construction purposes. The Contractor shall immediately notify the COR and/or contracting officer if underground utility lines are severed or damaged in anyway. Any utilities that are cut, damaged, or disrupted by the Contractor within three feet on either side of a staked or otherwise marked location, will be repaired at no cost to the government.

· Authorizations to Dig:

The Contractor shall be responsible for processing and obtaining all required authorizations and clearances to dig (digging permits) and obtaining blue stake location services. Once a construction site has been marked, it is the Contractor’s responsibility to maintain the markings. If work does not commence on-site within 30 calendar days of the blue stake approval and the Contractor has not maintained the blue stake markings, the Contractor shall request a re-stake prior to commencing actual site work. No extension of the task order performance period shall be approved due to a Contractor’s decision to not start contract work within 30 days of the blue stake approval. All costs of construction blue staking and potholing to verify utility locations shall be calculated as a part of the Contractor’s coefficient.

· Communication Systems:

The Contractor shall have a communications system (i.e., Cell Phones, Radios) that will allow the government to relay messages to or obtain answers/responses from Contractor personnel in the field. If cell phones are used for on-site communications, the Contractor shall provide the appropriate numbers to the contracting officer’s representative (COR). If radios are used for on-site communications, the Contractor shall provide use of a compatible radio unit to the COR. The Contractor shall also provide e- mail addresses for all key employees, which will allow electronic communications between the government and Contractor key personnel.

· Points of Contact:

The Contractor shall provide a primary and alternate point of contact (POC) that can be reached 24 hours a day, 7 days a week for emergencies. The individuals must have the authority to make binding decisions and commitments on behalf of the Contractor, in response to emergency / exigent situations and conditions. The government must be given POC names and phone number(s) in the event an urgent problem or situation is encountered with one of the Contractor’s projects, and the POC’s immediate response is required.