YOSE-CONNECT UTILITIES TO FIRE OFFICE Federal contract opportunity
Solicitation number
140P8524Q0058
Issued by
Department of the Interior National Park Service

About this file

This document is a Statement of Work (SOW) for the Yosemite Fire Office Trailer Fresh Water and Wastewater Utility Connection Project. The objective is to connect a newly placed Yosemite Fire Office Trailer to existing potable water and wastewater lines nearby. The contractor shall trench approximately 65 feet to install a new 1" PVC waterline and trench approximately 60 feet to install a new 4" ABS sewer line, adhering to AWWA standards. The work is to be completed by September 6, 2024 and is estimated to take approximately three days. This project occurs on National Park Service (NPS) property, and NPS Utility operators will need to be closely coordinated with.

The related federal contract opportunity is a Request for Quotes (RFQ) for the YOSE-CONNECT UTILITIES TO FIRE OFFICE project, with a Solicitation Number of 140P8524Q0058. The procurement is set-aside for Small Business concerns only, under NAICS code 237110 with a size standard of $45.0 million. The construction magnitude is $25,000 to $100,000. Quotes are due by 12:00 P.M. Pacific Standard Time on July 31, 2024.

View the file

Other files for this federal contract opportunity

Other files attached to YOSE-CONNECT UTILITIES TO FIRE OFFICE, newest first.
File Type Posted
B03_Wage_Determinateion_CA20240018.pdf PDF
Sol_140P8524Q0058.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YOSE Fire Office Trailer Fresh Water and Wastewater Utility Connection Project

Mike Trumm, Utilities Branch Chief, Yosemite National Park Ansley Singer, Management Analyst, Yosemite National Park

3/25/2024

Objective This project will connect a newly placed Yosemite Fire Office Trailer to existing potable water and wastewater lines nearby. The electrical connection will be performed under a separate contract and is not included in the work described here. This project occurs on National Park Service (NPS) property and close coordination with NPS Utility operators will be required.

Address of the worksite is 2219 Rail Road, El Portal CA 95318.

Background Yosemite Wildland Fire Module (Fire Crew) is moving from the Chinquapin house down to a newly installed office trailer behind the Motor Inn Cabins in El Portal, CA. The new trailer site is in a location that does not have trailer hook-ups so this project will add potable water and waste water connections. NEPA Compliance is complete for this project and on-site monitoring from NPS Archeologists and or Tribal members may be required.

Scope of Work Contractor shall call 811 (Diggers Hotline) to request utility locating prior to starting to dig.

Potable Water Connection

See Attached Conceptual Drawing for details listed below.

Contractor shall trench approx. 65 feet and install new 1” PVC waterline from the Trailer site south to the existing 6” line. Hot Tap into 6” line, install corp stop (valve), install meter box, meter, Pressure Reducing Valve (PRV). Meter will be supplied by NPS. NPS Utilities shall be notified by the contractor when line connections begin and end. NPS Utilities will inspect work prior to trenches being filled.

Contractor must adhere to American Water Works Association (AWWA) standards for drinking water connection.

Wastewater Connection

See Attached Conceptual Drawing for details listed below.

Contractor shall trench approx. 60 feet and install new 4” ABS sewer line from the trailer site east to tie into the existing 4” lateral servicing residential address 5542 Foresta Road. Notification to area residences need to be made 7 days in advance if service will be disrupted. Disruption to any residential shall be restored within the same day. Install two cleanouts as indicated in drawing. Contractor must adhere to American Water Works Association (AWWA) standards for wastewater connection.

Delivery:

A site visit is not required but highly encouraged. There will be no change order due to differing site conditions.

It's anticipated this work will take approx. three days and be completed no later than 6 September, 2024.

Safety Work area must be secured each day prior to contractor departure. All trenches shall be covered overnight. Emergencies should be reported by calling 9-1-1.

Trailer Connection Photos

Photo of potable water connection under the Office Trailer Photo of wastewater connection under the Office Trailer

Trenching Path Photos

WASTEWATER

Work area photo from Manhole 34 looking

West toward Office Trailer

WASTEWATER

Work area photo from the side of the Office

Trailer looking East toward Manhole 34

POTABLE WATER

Work area photo from the side of the Office

Trailer looking South toward Cabin 774

POTABLE WATER

Work area photo from outside Cabin 774 looking North toward Office Trailer