This document is a Statement of Work (SOW) for a federal contract opportunity to remove and replace approximately 480 linear feet of chain link fence at the El Portal Day Care facility in Yosemite National Park, California.
The key details are:
- The existing fence needs to be replaced to meet California Title 22 regulations, which require a 48-inch non-scalable fence with a mesh size no greater than 3 inches.
- The contractor will be responsible for providing a design, removing the existing fence, disposing of the materials, and installing a new fence that meets the specified requirements, including 48-inch height, 3-inch or smaller mesh, and 6-inch buried snake mesh.
- The contractor shall also install 4 walk-through gates and 2 vehicle gates with self-closing and self-latching mechanisms.
- The period of performance is from task order award to May 17, 2024, with all on-site work to be completed by that date.
- This procurement is set-aside for Small Businesses, with a NAICS code of 238990 and a size standard of $19.0 million.
- The construction magnitude is $25,000 to $100,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P8524Q0028_Amd_0002.pdf | ||
| Sol_140P8524Q0028_Amd_0001.pdf | ||
| Sol_140P8524Q0028.pdf | ||
| B08_Attachment_3_Wage_Determination_CA20240018.pdf | ||
| B08_EPB_717_Daycare_Fence.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Objective Yosemite National Park has a need for a fence contractor to remove and replace approximately 480 linear feet of chain link fence at the El Portal Day Care facility in El Portal, CA.
Background
The fence surrounds a residence that was converted into a day care facility. The fence needs to meet the regulations cited in California Title 22, which indicates that the fence must be 48” in height, the current fence averages 44” in height. The fence also needs to be non-scalable by children, so the mesh of the fencing must be no greater than 3 ½”. The inspection team from the CA licensing board has recommended the installation of snake fence, which has a mesh size of ¼” and requires the fence be embedded 6” in the ground to prevent snakes from entering the play area. The fence shall meet these requirements.
Location Information
EPB 0717 – 9752 River View Road – El Portal Day Care Facility – see map and photos attached Scope
The scope of the project is to remove the current fence and install a new fence meeting the CA Title 22, Caring for our Children regulations (CFOC 6.1.0.8) – Enclosures for Outdoor Play Areas, and the Consumer products Safety Commission’s Public Playground Safety Handbook (CPSC 2.2.2) – Age Separation. The contractor shall be responsible for providing a design for the fence that meets the specifications listed above.
The contractor shall provide all the labor, equipment, materials, and supervision to perform the tasks outlined in the scope of work.
The contractor shall field verify the measurements and site conditions.
The contractor shall provide a schedule for the work 1 week prior to beginning on-site construction, so that the NPS can give notice to the NPS and day care staff of the project.
· The contractor shall remove the existing fence
· The contractor shall dispose of removed fence materials and any additional debris outside of Yosemite National Park
· The contractor shall install a fence that is 48” in height – including posts, fence mesh, gates, and snake mesh
· The contractor shall install fence material with a mesh size of 3 ½” or less
· The contractor shall install fence material that will exclude snakes, mesh size ¼”, buried in the ground a minimum of 6”
· The contractor shall backfill trenching to provide a uniform and flat surface
· The contractor shall install 4 – 36” wide walk-thru gates with self-closing and self-latching mechanisms
· The contractor shall install 2 vehicle gates – 12’ wide with 2 – 6’ gates with latching mechanism, NPS to provide hasp lock
· The contractor shall clean-up the site and restore to operational condition
If welding work will happen as a part of the project, a hot work permit must be obtained by the contractor through NPS Structural Fire Protection office, Steve Lyon is the POC (steve_lyon@nps.gov) Period of Performance
The period of performance is from task order award to May 17, 2024. All on-site construction work and site remediation must be complete by this date.
Additional Information
HAULING RESTRICTIONS: Vehicles over 45 feet are prohibited and 1-way controlled traffic for all other vehicles 20 miles East of Mariposa (Mariposa County) 24 hours per day, seven days per week due to rockslide repairs.
ON-SITE WORK HOURS: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
BEAR/ ANIMAL SAFETY: Bears and other animals are active in Yosemite and surrounding areas. It is necessary for all visitors to practice bear and animal safety. Food items are not to be left in work trucks or anywhere else. The NPS provides bear boxes in campgrounds for food storage. Bear incidents are a ticketable offense in Yosemite.
Yosemite National Park
Carrie Toepper
Supervisory Facility Operations Specialist
Buildings and Grounds
Phone: 209-379-1089
National Park Service
U.S. Department of the Interior