B08_Solicitation_-_Attachment_3_Closeout_Deliverables.pdf
PDF 188 KB Posted
- Attached to
- Rehabilitate 44 Year old service freight elevators Federal contract opportunity
- Solicitation number
- 140P6222R0001
About this file
This document outlines closeout deliverables required for a contract to rehabilitate 44-year-old service freight elevators at the Gateway Arch National Park in St. Louis, Missouri. The contractor must submit training materials on emergency recall operations and communications equipment by November 21, 2023, along with any specialized diagnostic tools and spare replacement parts for printed circuit boards and controllers. Additional deliverables due by November 21, 2023 include keys for equipment, straightline wiring diagrams, instruction manuals for maintenance and lubrication, and operation and maintenance data for fuses, circuit breakers, switches, and interior lighting. The contractor must also conduct a system demonstration and training along with providing tools, spare parts, and project record drawings to close out the contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6222R0001_Amd_0004.pdf | ||
| Sol_140P6222R0001_Amd_0003.pdf | ||
| B08_Solicitation_Attachment_10_Drawings_0003.pdf | ||
| Sol_140P6222R0001_Amd_0002.pdf | ||
| Sol_140P6222R0001_Amd_0001.pdf | ||
| B08_Solicitation_-_Attachment_6_-_Technical_Questionnaire_Final.docx | DOCX document | |
| B08_Solicitation_-_Attachment_2_Specs.pdf | ||
| B08_Solicitation_Attachment_8_Vaccination_Certification_Notification.pdf | ||
| B08_Solicitation_Attachment_7_WD_DBA_11-09-2021.pdf | ||
| B08_Solicitation_Attachment_9_Vaccination_Certification.pdf | ||
| B08_Solicitation_-_Attachment_1_Bid_Schedule.xlsx | XLSX spreadsheet | |
| Sol_140P6222R0001.pdf | ||
| B08_Solicitation_-_Attachment_4_-_Past_Performance_Questionnaire.pdf | ||
| B08_Solicitation_-_Attachment_5_-_Past_Performance_Additional_Information.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Topic Specification Section Requirement Submittal
Date Completed Received by Park
14 21 43 Controll Features Training ie:
Emergency Fire Recall Operation - Phase I Emergency In-Car Recall Operation - Phase II Emergency Communications Equipment
14 21 43 Any Specialized Tools Required to Perform Diagnostic Evaluations
14 21 43
Spare Replacement for Each Printed Circuit Board Needed to Fully Operate Any One of the Following:
Elevator and the Group Dispatch/ Supervisory Controller where Applicable
14 21 43 Provide Spare Parts Required for Maintenance of the Elevator Equipment Installed Under This Contract ie:
One Set of Controller Boards Power Supply of Each Size One Set of Controller I/O Boards
14 21 43 (6) Keys for Each General Key-Operated Device
14 21 43 Controls, Bus Bar Hoistway Power Sytem 14 21 43 Car Switch Station, and Hall Security Station 14 21 43 "As Installed" Straightline Wire Diagrams
14 21 43 Instruction Manuals and Recommendations for Maintenance & Lubrication
26 28 13 O & M Fuses 26 28 17 O & M Enclosed Circuit Breakers 26 28 18 O & M Enclosed Switches 26 51 00 O & M Interior Lighting
Extra Stock
Reports
Keys and keying schedule
O&M Data Warranties Guarantees
CLOSEOUT AND OPERATION & MAINTENANCE REQUIREMENTS
Project Record Drawings
System Demonstration and Training
Tools Spare Parts Equipment
Attachment 3 11/9/2021