This is a Statement of Work (SOW) for fire pump repair services at the Easton Building located at 15 State Street, Boston, MA, issued by the National Park Service Interior Region 1.
The project scope involves repair of an existing Allis Chalmers fire pump gasket in the building's basement, including a minor rebuild, open lid interior inspection, and laser shaft alignment. The contractor must provide all labor, materials, equipment, and supervision to complete three primary work phases: (1) Demolition and Removal—isolating and locking out the motor and pump, removing the rotating assembly, removing old packing, and inspecting components; (2) Installation—repacking the pump with new gasket, replacing glands and fasteners, performing laser shaft alignment, running and adjusting the pump, and returning it to service; and (3) Testing and Commissioning—including Boston Fire Department (BFD) coordination, provision of fire watch staffing as required by BFD, and conducting a fire pump flow test during off-hours. The contractor shall also provide basic training to on-site staff for operation and troubleshooting. Deliverables include removal of obsolete components, installation of new components, documentation (as-built drawings, wiring diagrams, and O&M manuals), and minimum one-year warranty for parts and labor. The period of performance is 14 calendar days from Notice to Proceed, with all work occurring during regular business hours unless otherwise approved. Work must comply with Boston Fire Department standards and applicable safety requirements. The point of contact is Larry Seaboyer, Supervisory Facility Operations Specialist, at 617-223-5023 (office) or 978-427-5388 (cell). Any cost overruns require pre-approval from the Contracting Officer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P4326Q0029_Amd_0001.pdf | ||
| Sol_140P4326Q0029.pdf | ||
| B08_Solicitation_Attachment_2_DOL_Wage_Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Fire Pump Repair – BOSTON Easton Building
1. Project Overview
This project involves the repair of existing Fire Pump gasket in the basement of Easton Building located at 15 State Street, Boston MA. The scope includes a minor rebuild/repair of Allis Chalmer fire pump. Perform open lid inspection on the interior components of the fire pump and perform a laser shaft alignment.
2. Scope of Work
The contractor shall provide all labor, materials, equipment, and supervision necessary to perform the following:
2.1 Demolition and Removal
• Isolate the motor from the controller and lock out /tag out Isolate pump from system (Alarms by others).
• Set up and rig pump casing lid off pump.
• Remove rotating assembly from pump.
• Remove old packing and clean up and inspect shaft sleeves Inspect impeller and shoulder/lantern rings Install rotating assembly into pump.
2.2 Installation
• Re-pack pump and re-install pump casing lid with new gasket Replace glands, gland bolts, nuts and washers Inspect inboard and outboard bearings.
• Clean stuffing box area and clear packing box drain lines Perform laser shaft alignment.
• Run pump and adjust packing.
• Return pump to service.
2.3 Testing and Commissioning
*Include Fire Department Detail as required *** *Include BFD required Fire pump flow test done off hours ***
• Boston Fire Department (BFD) requires a fire watch while work is being preformed (staffing detail as required by BFD)
• Fire pump flow test as required.
2.4 Training
• Provide basic training to on-site staff for operation and troubleshooting of the new control system.
3. Deliverables
• Removal of all obsolete components.
• Installation of new components.
• Documentation, including as-built drawings, wiring diagrams, and O&M manuals.
• Warranty information for all installed equipment (minimum 1-year parts and labor).
4. Period of Performance
Work shall be completed within [14] calendar days from the Notice to Proceed (NTP).
5. Work Hours
All work shall occur during regular business hours unless otherwise approved.
6. Codes and Standards
All work shall comply with:
• Boston Fire Department
7. Safety and Protection
Contractor shall implement appropriate safety measures and ensure the protection of building occupants and property during all phases of work.
8. Budget & Funding
• Any cost overruns must be pre-approved by the Contracting Officer.
9. Point of Contact
Larry Seaboyer Supervisory Facility Operations Specialist National Park Service Interior Region 1
15 State Street Boston, MA 02109-3572
617-223-5023 (o) 978-427-5388 (c) laurence_seaboyer@nps.gov
10. Attachments (If Applicable)
• NONE
End of Statement of Work mailto:laurence_seaboyer@nps.gov
| 1. Project Overview |
| 2. Scope of Work |
| 2.1 Demolition and Removal |
| 2.2 Installation |
| 2.3 Testing and Commissioning |
| 2.4 Training |
| 3. Deliverables |
| 4. Period of Performance |
| 5. Work Hours |
| 6. Codes and Standards |
| 7. Safety and Protection |
| 8. Budget & Funding |
| 9. Point of Contact |
| 10. Attachments (If Applicable) |